development of fast setting pumped foamed cement r.m. smart – minova rsa… · 2009. 10. 15. ·...
TRANSCRIPT
SAIMM, SANIRE and ISRM
6th
International Symposium on Ground Support in Mining and Civil Engineering Construction
R M Smart and A T Harrison
Page 159
DEVELOPMENT OF FAST SETTING PUMPED FOAMED CEMENT
PACKS
R.M. Smart – Minova RSA, Technical Director
A.T. Harrison – Minova RSA, Consultant
ABSTRACT
Foamed cement packs offer a viable alternative to conventional timber or other forms of
packs for permanent underground support. These packs comprise steel mesh and hoop
containment with an outer bag for the grout; woven, laminated polypropylene fabric being
ideal for the purpose. The grout is supplied in 25kg bags and fed into a purpose – designed
foam placer machine which delivers the foamed grout directly to the packs from 60 metre
long delivery hose. Foamed cement grout as a fill material offers attractive properties for
support packs. In summary these are:
Variable Grout Strength
Grout strength is controlled by the grout density being delivered from the placer machine.
This can be changed by the machine settings.
Strength Development
Fast rate of strength development is possible so that support is available quickly.
Pack yield
The foamed grouts are compressible so that yielding of the grout pack can be achieved
without loss of support.
Rate of Filling
Three sizes of placer machine are available. These use one, two, or three 25kg bags per
minute of grout. Pack filling time is therefore a matter of minutes, a typical 0.75m diameter
pack x 1.2m high taking some 17 minutes to fill.
Tests in a 1000 tonne press have confirmed that the above characteristics can be achieved
with foamed cement packs at acceptable cost.
INTRODUCTION
Grout packs filled with foamed cement may offer a viable alternative to conventional
timber, composite, or grout packs for permanent underground support. Foamed cement is
currently used in the form of low density blocks for the construction of packs, usually a
combination of foamed cement and internal reinforcing steel cage and fibre. A number of
proprietary products of this type are available. Cement-based packs offer the immediate
advantage of increased safety, removing the risk of underground fires, an ever – present
hazard with conventional timber.
SAIMM, SANIRE and ISRM
6th
International Symposium on Ground Support in Mining and Civil Engineering Construction
R M Smart and A T Harrison
Page 160
Progress towards a foamed cement pack system offering advantages over cement packs
constructed from discrete foamed cement blocks is being made at MINOVA RSA. A
system is being developed in which the cement material for the packs will be delivered
underground in 25kg bags to a foam generating machine which will deliver the foamed
cement through a delivery hose directly to the packs.
With any grout pack, containment design is critical to performance of the pack, this is
particularly the case with this pumped cement pack and this aspect is still undergoing
development.
Fig 1 Foamed cement pack containment
Foamed Cement Grout Packs
The foamed cement grout pack comprises the following components as in Fig 1 above.
- Containment / reinforcement
1) Bag : woven laminated seamless
polypropylene, 125g/m2
, 0.75m
diameter x 1.2m high.
2) Mesh : 3.15mm x 10cm galvanized mild steel
diamond mesh.
3) Reinforcement : 25mm x 5mm flat bar mild steel hoops
or cartwheels.
4) Top / bottom rings : 8mm square section mild steel
top ring
reinforcement loops
mesh
outer containment bag
bottom ring
cartwheels
SAIMM, SANIRE and ISRM
6th
International Symposium on Ground Support in Mining and Civil Engineering Construction
R M Smart and A T Harrison
Page 161
- Grout
A fast setting cement with an aerating additive is used, supplied in 25kg
bags, when fed into the machine, a pumpable fast setting foamed cement is
produced.
Foamed Cement Placing Machine
This is shown in Fig 2. The placing machine uses a fixed rate of feed, either one, two, or
three 25kg bags of cement product per minute. A flow valve and meter allows variable
water : cement ratio to be used thus allowing a range of cement foam densities and hence
foamed cement strength to be achieved.
Fig 2 Foamed Cement Placing Machine
Pack Support Requirements
These are summarized in Fig 3. At 10% closure (deflection) a load bearing capacity of 150
tonnes minimum is required, with yield characteristics on closure lying within the shaded
area. In some applications a minimum load capacity at 10% closure of 100 tonnes may be
acceptable.
SAIMM, SANIRE and ISRM
6th
International Symposium on Ground Support in Mining and Civil Engineering Construction
R M Smart and A T Harrison
Page 162
Fig 3 Pack support requirements
Results to date
Effect of hoop reinforcement – cartwheel pack
This is summarized in the following table and in Fig. 4.
Test No. Hoop Containment Water : Powder
Ratio
Relative
Density
Load at 50%
Displacement
Standard Reinforced
1: 5 - 0.5 1.25 80t
2: - 5 0.5 1.25 227t
Using a grout with a density of 1.25 in a pack comprising five unreinforced hoops, 2 hours
after filling the packs, significant step-wise load shedding occurs between 180mm and
350mm of closure. This is due to the consecutive rupturing of the 3 central steel hoops with
the loss of some 30 tonnes of load each time, (line 1 in fig 4).
SAIMM, SANIRE and ISRM
6th
International Symposium on Ground Support in Mining and Civil Engineering Construction
R M Smart and A T Harrison
Page 163
Fig 4 Effect of hoop reinforcement
In contrast, in the pack with five ‘cartwheel’ hoops, no such load shedding occurs,
(line 2 in Fig 4), allowing a more acceptable support performance to be achieved, some 150
tonnes load at 10% and 40% closure (480mm). The reason for the improved performance is
that when rupture of the circular hoops takes place, always at the central hoop first, tensile
stress is lost on only one quadrant of the hoop, the remaining quadrants of the hoop being
held in place by the ‘cartwheel’ reinforcement which is embedded in the grout.
Effect of Foamed Grout Density
By adjusting the relative density of the grout by control of the water : cement ratio, and
testing at 2 hours after placement, variable pack performance in terms of load bearing
capacity can be achieved as illustrated in Fig. 5.
SAIMM, SANIRE and ISRM
6th
International Symposium on Ground Support in Mining and Civil Engineering Construction
R M Smart and A T Harrison
Page 164
Fig 5 Pack load vs. cement foam density
Further Development
The concept of a pumped foamed cement pack is still under development, in particular
the following:
- Containment : this is still somewhat cumbersome and heavy, and
lighter materials are under investigation.
- Reinforcement : means of combining the cartwheel concept into the
containment presents problems of design and these
are being addressed as part of the containment
development.
SAIMM, SANIRE and ISRM
6th
International Symposium on Ground Support in Mining and Civil Engineering Construction
R M Smart and A T Harrison
Page 165
CONCLUSION
From work carried out to date, a foamed cement pack offers a viable alternative to
conventional timber packs provided identified limitations can be overcome effectively.
SAIMM, SANIRE and ISRM
6th
International Symposium on Ground Support in Mining and Civil Engineering Construction
R M Smart and A T Harrison
Page 166