developments in cost estimating and scheduling in bim ...835/fulltext.pdf · northeastern...
Embed Size (px)
TRANSCRIPT

NORTHEASTERN UNIVERSITY Thesis Title: Developments in Cost Estimating and Scheduling in BIM technology Author: Xinan Jiang Department: Civil & Environmental Engineering Approved for Thesis Requirement of the Master of Science Degree in Civil & Environmental Engineering Thesis Advisor (Professor Ali Touran) Date Thesis Reader (Professor Asli Pelin Gurgun) Date Department Chair (Professor Jerome F. Hajjar) Date Graduate School Notified of Acceptance Director of the Graduate School Date

Page 1 of 88
DEVELOPMENTS IN COST ESTIMATING AND SCHEDULING IN BIM
TECHNOLOGY
A Thesis Presented
by
Xinan Jiang
to
The Department of Civil & Environmental Engineering
in partial fulfillment of the requirements for the degree of
Master of Science
in
Civil & Environmental Engineering
in the field of
Construction Engineering & Management
Northeastern University Boston, Massachusetts
August 2011

Page 2 of 88
Table of Contents Abstract .......................................................................................................................... 3
List of Figures ................................................................................................................ 5
List of Tables .................................................................................................................. 5
Chapter 1 Introduction ................................................................................................... 7
1.1 What is BIM? ....................................................................................................... 8
1.2 Current and Projected Status of BIM ................................................................... 9
Chapter 2 Background ................................................................................................. 12
2.1 BIM Capabilities ................................................................................................ 12
2.2 BIM Tools ........................................................................................................... 25
2.3 BIM Application Areas ....................................................................................... 30
Chapter 3 BIM and Construction Management ........................................................... 33
3.1 Project Scheduling in BIM ................................................................................. 33
3.2 Cost Estimating in BIM ...................................................................................... 42
3.3 Dealing with Electronic and Paper-based CAD Drawings ................................. 47
Chapter 4: A Case Study using BIM ............................................................................ 50
4.1 Introduction ........................................................................................................ 50
4.2 Cost Estimating .................................................................................................. 53
4.3 Construction Scheduling .................................................................................... 58
4.3 Conclusions ........................................................................................................ 63
Chapter 5: Conclusions and Future Work .................................................................... 64
5.1 Conclusions ........................................................................................................ 64
5.2 Future Work ........................................................................................................ 64
References .................................................................................................................... 70
Appendices ................................................................................................................... 77
Appendix 1 Floor Plans of the Building Model ....................................................... 77
Appendix 2 RS Means .............................................................................................. 79
Appendix 3 Interface of Autodesk Quantity Takeoff™ 2011 ................................... 81
Appendix 4 Quantity Takeoff List ............................................................................ 82
Appendix 5 Interface of Autodesk Revit Architecture™ 2011 ................................ 84
Appendix 6 Interfaces of Autodesk Navisworks™ 2011 ......................................... 85

Page 3 of 88
Abstract
Building Information Modeling (BIM) is an emerging technology in Architecture,
Engineering, and Construction (AEC) industry. BIM is a computable representation of
building and its related information, which provides a virtual view of the objects in
the building with physical geometry (2D or 3D) and other functional parameters.
Compared to parametric models in CAD, the object-based parametric models in BIM
represent the objects by both physical and functional parameters. Diverse BIM tools
such as Autodesk Revit Architecture™, ArchiCAD™, Bentley Architecture™, etc.
have been widely adopted within AEC industry in design/modeling, construction
energy analysis, clash detection, construction scheduling and cost estimating.
In this thesis, diverse BIM tools and applications have been introduced with an
emphasis on construction scheduling and cost estimating. Two approaches for 4D
scheduling in BIM have been presented: i) BIM tools with 4D capacity, and ii) use of
4D BIM tool to link the 3D BIM model with the project schedule. For the cost
estimating capability, three types of available methods have been discussed: i) export
the Quantity Takeoff (QTO) list from the BIM tool to the estimating software such as
MS Excel, ii) link BIM components to estimating software, and iii) use QTO tool to
extract the QTO list from the model. Based on the available methods, a case study is
presented to illustrate the scheduling and cost estimating processes in BIM based on
the BIM model of a three-story training facility.

Page 4 of 88
The case study shows that BIM does enhance the traditional scheduling and cost
estimating methods with a more reliable and automated technology. Based on the
reviews on BIM and the case study, the thesis finds out that there are three areas of
potential development in the future: i) higher levels of detail (LOD) in BIM model
will be available as BIM technology develops, ii) linking time and cost parameters
concurrently to BIM components in the building model to deliver a scheduled
financial analysis, and iii) allocation of resources on 4D BIM model to analyze and
plan the resource usage based on the most updated design, and even simulate the
resource allocation.

Page 5 of 88
List of Figures
Figure 1 Lifecycle of a building ................................................................................................ 8
Figure 2 Market growth in BIM use on projects ..................................................................... 10
Figure 3 The elevation view of an office building in CAD ..................................................... 14
Figure 4 The elevation view of an office building in Revit Architecture™ 2011 ................... 16
Figure 5 The interface of Revitcity for downloading object models ....................................... 17
Figure 6 Percentages of market share of BIM tools which are used by construction firms .... 26
Figure 7 The phasing function in Revit Architecture 2011 ..................................................... 38
Figure 8 The objects are linked with the defined phases in Revit Architecture 2011 ............. 38
Figure 9 The flowchart of 4D scheduling process .................................................................. 40
Figure 10 Snapshot of a 4D software interface showing how schedule is connected to object
......................................................................................................................................... 42
Figure 11 Generation of BIM model from paper drawing using Dprofiler ............................. 49
Figure 12 The training facility model in Munich, Germany ................................................... 50
Figure 13 Export the building model from Revit Architecture into Autodesk™ QTO ........... 54
Figure 14 The QTO list has been generated by Autodesk™ QTO 2011 ................................. 55
Figure 15 The QTO list shown in excel with the cost data added ........................................... 56
Figure 16 Tasks are defined directly in Autodesk™ Navisworks 2011................................... 59
Figure 17 Tasks are shown in gantt view ................................................................................ 60
Figure 18 Three gantt chart views can be selected based on the user’s preference ................. 60
Figure 19 The interfaces of Autodesk Navisworks™ of 4D Scheduling in BIM .................... 62
Figure 20 Overall layout for the proposed financial analysis by integrating cost and schedule
......................................................................................................................................... 68

Page 6 of 88
List of Tables
Table 1 Common exchange formats in AEC applications ....................................................... 22
Table 2 LOD definitions .......................................................................................................... 24
Table 3 BIM software- scheduling tools ................................................................................. 40
Table 4 Plug-in tools for cost estimation ................................................................................. 45
Table 5 Software list—quantity takeoff tools .......................................................................... 46
Table 6 Software tools to convert CAD drawing to BIM model ............................................. 48
Table 7 Model cost calculated for a 2-4 story office building ............................................... 57
Table 8 Comparison between MS Project™ and Autodesk Navisworks™ ............................ 69

Page 7 of 88
Chapter 1 Introduction
Building Information Modeling (BIM) is an emerging technology throughout the
world in the Architecture, Engineering, and Construction (AEC) industries. BIM
technology provides users with accurate and consistent building data and information,
accommodates the functions needed to model the building and provides a virtual view
of the building model. Building Information models are also increasingly used by
diverse stakeholders during the project lifecycle such as Owners, Designers,
Contractors and Engineers (Fig. 1). As a key part in the project lifecycle, contractors
play an important role in making sure the project will be delivered on time and within
the budget. This thesis will show how BIM technology will benefit contractors for
schedule and cost controls. It begins with a general introduction of BIM technology
and the different ways it works compared with traditional CAD (Computer Aided
Design) method, and continues with evaluation of BIM tools. It then explains the uses
of Scheduling and Cost Estimating in BIM respectively and provides a case study to
show how BIM can work for cost estimating and project scheduling with the available
BIM model. In the last part, the thesis will provide areas of potential development
with BIM technology in the foreseen future.

Page 8 of 88
Figure 1 Lifecycle of a building (Adapted from: Autodesk Revit brochure 2010)
1.1 What is BIM?
According to National Institute of Building Sciences (NIBS), BIM is a computable
representation of all the physical and functional characteristics of a building and its
related project/lifecycle information, which is intended to be a repository of
information for the building owner/operator to use and maintain throughout the
lifecycle of a building (NIBS 2007). As a digital representation, BIM provides a
virtual view of the objects in the building with physical geometry (2D or 3D) and
other functional parameters, such as materials, spatial relationship, etc. Designers
compose these BIM objects together to define a building model, and this model
incorporates both physical and functional information stored in the BIM objects. Once

Page 9 of 88
the building model is completed, all the information can be generated by users for
fabricating, analyzing, construction scheduling (4D BIM) and cost estimating (5D
BIM), and eventually, for facility management during operation phase of the building
lifecycle.
1.2 Current and Projected Status of BIM
After years of development and experimentation in the marketplace, BIM is being
adopted broadly across the construction industry by different users. McGraw Hill
Construction published a SmartMarket Report named Building Information Modeling
(BIM): Transforming Design and Construction to Achieve Greater Industry
Productivity in 2008 (Young et al. 2008). The report is based on the comprehensive
interviews with hundreds of owners, architects, civil engineers, structural engineers,
MEP engineers, construction managers, general contractors and trade contractors.
The goal of the report was to determine the perceptions of BIM adoption,
implementation, value, impact and even the perspectives on developing elements of
BIM within the interviewers’ firms. Young et al. (2008) distributed a questionnaire
survey to 82 architects, 101 engineers, 80 contractors, and 39 owners in the United
States. The result of the survey was published in the report on BIM use in the AEC
industry in 2008 and projections for 2009. In the report, BIM users are divided into
four groups: very heavy users are using BIM technology in more than 60% of their
projects, heavy users are using BIM technology in more than 31% of their projects

Page 10 of 88
and so forth as the percentage gets smaller and smaller (See in Fig. 2). The results of
the survey show that in 2008 roughly one-third (35%) of BIM users were very heavy
users, one-third (27%) were medium to heavy users, and one-third (38%) were light
users. Compared to 2008, the projected growth of usage of BIM in 2009 is
rapid—nearly half of all current adopters (45%) will become heavy users of BIM in
2009, using it on at least 60% of their projects—a 10 point increase over the previous
year (Young et al. 2008). An architect from the American Institute of Architects (AIA),
Markku Allison, has witnessed this rapid adoption of BIM in recent years: "At our
2005 convention, the opening plenary session was about BIM, and of the nearly 4,000
architects in the room we got the impression that 85% had never even heard of BIM.
Now when we go on the road, everyone knows what BIM is and the audience can
offer up success stories about using BIM" (AIA n.d.).
Figure 2 Market growth in BIM use on projects (Adapted from Young et al. 2008)

Page 11 of 88
Sophisticated owners are beginning to demand BIM and to change traditional routines
to enable it. U.S. Army Corps Engineers (USACE), one of the largest landowners and
the largest building owner in the United States, has made a long-term system-wide
commitment to BIM. The general Services Administration (GSA), which is
responsible for the construction of federal buildings in the United States, demands the
use of BIM models in their program requirements (Eastman et al. 2008).
Manufacturers, suppliers, contractors and realtors need to embrace BIM approaches
and technologies in order to gain the opportunities to do business with these
institutions. Economic benefits of BIM attract all the stakeholders including owners to
adopt it for their buildings. As an example of application areas for BIM use, 424
construction firms were ask to choose a specific project in BIM and answer the
questions of a survey conducted by Burcin and Samara in 2010. The results showed
that among the selected projects, 76.6% are commercial building projects, 18.5% are
residential building projects and others are industrial facility, transportation, and
power station projects (Burcin and Samara 2010). Indeed, heavy engineering and
process industries also have relied on 3D BIM Modeling for over a decade (Eastman
et al. 2008).

Page 12 of 88
Chapter 2 Background
2.1 BIM Capabilities
BIM is the representation of the digital evolution from traditional 2D model to 3D
mode and even to 4D model (scheduling) and 5D model (cost estimating) with a
database through the building lifecycle. Special capabilities of parametric modeling
and interoperability facilitate this evolution process, which will be explained in detail
in this section.
3D model: mathematical representation of any three-dimensional surface such as
width, length and height of an object. In BIM, there are different kinds of 3D
Models: 1) Design models – architectural, structural, MEP (Mechanical Electrical
and Plumbing) and site/civil models, 2) Construction model – breaking the design
models down into construction sequences, etc.
4D model: 4D model is adding the fourth dimension--schedule to the 3D model.
A 4D BIM model links the 3D elements with the project delivery timeline to
provide users a virtual simulation of the project in the 4D environment.
5D model: 5D model is adding the 5th dimension—cost data to the 3D model. A
5D model links the cost data with the Quantity Takeoff (QTO) list, which is
generated from the 3D model, to deliver more accurate project cost estimation.

Page 13 of 88
2.1.1
PARAMETRIC MODELING—CAD OBJECTS VS. BIM OBJECTS
The 3D modeling capability in Computer Aided Design (CAD) was first developed in
early 1980s, and this 3D modeling capability is also recognized as one of the
fundamental principles of parametric modeling—solid shape with physical
dimensions. BIM is an enhanced parametric modeling technology which is called
object-based parametric modeling. Other than basic physical dimensions of the object,
BIM objects also incorporate functional parameters. This section provides a
comparison between these two different object-based models.
Computer Aided Design (CAD)1
As the starter in 3D modeling technology, CAD models are recognized as the digital
representations of well-understood drawings of building objects. Thus the models
depict the shapes and dimensions with specifications by assembling lines into solid
models. In other words, CAD objects are models with basic parameters—geometrical
information. As an example, Figure 3 gives the elevation view of an office building in
CAD. The objects can be clearly classified by different colors in the design—yellow
lines for exterior walls and blue lines for windows. The windows are defined in the
layer named “Window” and colored “Blue” in order to distinguish the “Window”
Objects
1 Computer Aided Design (CAD): also known as computer-aided design and drafting (CADD), is the use of
computer technology for the process of design and design-documentation.

Page 14 of 88
from other objects—users may use other colors to make the objects be more easily
identified. However, the color and the name only represent the shape and the category
of the window in the drawing.
Figure 3 The elevation view of an office building in CAD
It is well known that the drawings from the architects are the most basic documents in
the building lifecycle, and changes made in architectural drawings will always come
with the changes in the following activities. MEP (Mechanical, Electrical and
Plumbing) and Structural design, cost estimating and scheduling, and all the other
sub-sequential activities will be conducted based on the architectural drawings. In 3D
CAD, every aspect of element’s geometry must be edited manually, and it will take
substantial amount of time to conduct these changes, while some errors and omissions
may occur in this process. For example, a wall in CAD is defined by length, width and
height, and if any of these three parameters is changed, the other two should be
The lines of the windows are defined in “window” layer and in “blue” color.

Page 15 of 88
changed manually. In other words, once the parameter of the object needs to be
changed, all the other related parameters should be manually edited and reassembled
on demand.
BIM Objects
Compared to parametric models in CAD, the object-based parametric models in BIM
represent the objects by parameters and associated rules that describe the geometry
and specification, as well as some non-geometric properties and features such as
geographic information, materials, spatial relationship, code requirements, price,
manufacturer, vendor and any other related parameter associated with how the object
is actually being used. Compared to Figure 3, Figure 4 also shows an elevation view
of a building, but this building design is shown as a BIM model, and the differences
are clearly shown: 1st, the windows in the design are not formed by colored
lines—they are recognized as the objects named “window” in the design; 2nd, the
properties of the window information are also shown in the design such as materials,
specifications, etc. in addition to geometry information, and these properties can be
easily edited by changing the values in the “Properties” window (Fig. 4). In other
words, BIM objects are geometric models which will also tell how the objects can
work. Instead of assembling lines into a solid model, designer defines a model family
or element class according to Construction Specification Institute (CSI) Masterformat
or Uniformat with a set of associated rules and data to control the parameters. The
rules will be defined as attached to, parallel to, and distance from, which allow the

Page 16 of 88
objects to be automatically updated if design changes are entered into the related
objects models in the building model. BIM technology facilitates the design change
process, since the changes can be updated automatically and shared within the
building lifecycle (shown in Fig. 1). It reduces the errors and omissions which may
happen in the changes in the CAD design.
Figure 4 The elevation view of an office building in Revit Architecture™ 2011 (Adapted from Autodesk Revit Architecture)
BIM tools have object-based parametric models under the object families such as
doors, walls, components and others. These predefined models can be modified and
then applied to building designs directly. In addition to that, some websites such as
Revitcity (http://www.revitcity.com) have started to provide predesigned BIM object
models which are available for download. Figure 5 shows the interface of the
Revitcity. In the left column, BIM objects are categorized according to CSI
Properties
of the
window

Page 17 of 88
Masterformat 03. In Figure 5, the “03 50 00 Precast Concrete” is chosen and the
available objects are listed on the right side of the interface. The Precast Column,
Precast Concrete Splash Block, etc. are available for users to download. As BIM
technology develops, more predefined BIM object models will be available for
download in the future, and the website such as Revitcity.com will become a huge
BIM model database. Other than that, this open database encourages product
manufacturers to provide BIM models of their own products on the website;
manufacturers can utilize this public platform to show potential customers their own
products. Thus the designers can use more predefined BIM object models instead of
designing the BIM objects by themselves and this will save more time for designers;
also the website may work as a platform for BIM users to share the models they have.
Figure 5 The interface of Revitcity for downloading object models (Adapted from Revitcity)

Page 18 of 88
2.1.2 INTEROPERABILITY
The building lifecycle involves organizations with different responsibilities and
functions and no BIM tools can support all the functions needed at all stages of the
building lifecycle. Data exchange between applications is essential to the stakeholders,
since other than architectural design of the building, there are structural and
Mechanical, Electrical and Plumbing (MEP) design, energy analysis, fabrication, cost
estimation, scheduling and other related activities. Each activity requires a different
software application to support its function, thus data exchange at the software level is
quite essential. According to Eastman et al. (2008), four ways are defined in which
model information can be exchanged between two software tools:
(1) Direct links between specific BIM tools
(2) Proprietary Exchange File Format
(3) Public Level Exchange Formats
(4) XML-based exchange formats
Direct links between specific BIM tools utilize the middleware interfacing
capabilities to integrate BIM tools. These capabilities include Open Database
Connection (ODBC), Component Object Model (COM) and some proprietary
interfaces such as Geographic Description Language (GDL) and MicroStation
Development Language (MDL) (Autodesk 2005, Eastman et al. 2008). These
binary-interface programming languages link BIM tools accessible to each other for
sharing data and information in the building model. The exchanged information from
the building model is accessible for export, modification and deletion. The

Page 19 of 88
middleware interface often supports the software tool better and can exchange the
information between software tools more directly, thus software vendors prefer to
choose the direct link approach. However, this interface is often designed for two
software tools from different software vendors, and it will be robust for the functions
the interface is designed for; furthermore, the interface requires the agreements
between the software vendors. Once the agreements are broken, the interface will not
be maintained or exist anymore.
Proprietary exchange file format is a file-based data exchange method. The file
format is usually developed by the commercial organization to support its own
software product. For example, Data Exchange Format (DXF) is one of the best
known proprietary exchange file formats, which is introduced by Autodesk (Eastman
et al. 2008, Eastman et al. 2010, and Arayici et al. 2011). Other proprietary exchange
file formats such as SAT, ACIS, STL and 3DS are also developed by the commercial
organizations to address the functions of their software. The proprietary exchange file
formats are developed by the software company for specific purposes, and the
limitation of this exchange format is that it may only be compatible with its own
software tool. However, the development of this exchange format is more complicated,
since it requires this format to gain the interoperability of different systems.
Public level exchange formats are using open standard exchanging models which are
Industry Foundation Classes (IFC)—for building planning, design, and construction
management and CIMsteel Integration Standard Version 2(CIS/2)—for structure and
fabrication (Eastman et al. 2008, IFCwiki 2009, Edwin 2010, Lee et al. 2011).

Page 20 of 88
Currently, more than a dozen BIM software tools are supporting IFC models such as
Revit Architecture™, Bentley Architecture™, ArchiCAD™, etc. (IFCwiki 2009).
Similar to IFC, CIS/2 is also supporting many BIM software tools such as
SmartPlant4D Structural™, Structural Triforma™, Tekla Structure™ (CIS/2@GT
2008). The IFC and CIS/2 are developed based on the open formats and international
standards. According to NIBS (NIBS 2007), the IFC data model has become the
international standard for data exchange in the building construction industry. These
formats enhance the interoperability between diverse software tools and integrate the
BIM model standard. The limitation is that the BIM model must follow the same
standard as the exchange format.
Extensible Markup Language (XML) is a markup language which is designed to
transport and store data (Refsnes 2009). XML structure which is called schema can
support the data exchange between different applications, and most of them are
desktop applications. The XML Schema was developed as an alternative to full scale
IFC models to simplify data exchanges between various AEC applications and to
connect Building Information Models through Web Services. However, XML is
mostly used for small amounts of business data exchange between two applications
and is not powerful enough for complex information exchange (Eastman et al. 2008,
Refsnes 2009).
Using these open standards, BIM tools can export the intended file format which can
be imported and read by another software tool. In Table 1, the common exchange
formats in AEC applications, provides a summary of most commonly used exchange

Page 21 of 88
file formats with their main usage. These include Image formats for pixel data, 2D
Vector formats for line drawings, 3D Surface and Shape formats for 3D drawings, 3D
Object Exchange formats for 3D models, various Game formats for different
animation purposes, GIS formats for geographical information and XML format for
business data. For example, an estimator intends to use Autodesk Quantity Takeoff™
to generate the quantity takeoff list from a building model designed by Revit
Architecture. The default format of the design is RVT which is not one of the file
formats supported in Autodesk Quantity Takeoff (DWF or DWG). However, Revit
Architecture™ allows users to export the drawing with different file formats, such as
DWG, DXF, or DWF. Thus, the estimator can export the drawing with the intended
file format and then import the file into Autodesk Quantity Takeoff to generate the
accurate takeoff list. For supported file formats in different BIM software, more
details will be discussed in the following section.
The interoperability of BIM allows users to pass a more complete and accurate
building model from computer applications used by one organization to another with
less errors and omissions. Thus all the involved organizations can share the consistent
building model data at all stages during the building lifecycle.

Page 22 of 88
Table 1 Common exchange formats in AEC applications (Adapted from Eastman et al. 2008)
Image (Raster) formats Descriptions JPG, GIF, TIF, BMP, PIC, PNG, RAW, TGA, RLE
Raster formats vary in terms of compactness, number of possible colors per pixel, some compress with some data loss
2D Vector formats Descriptions DXF, DWG, AI, CGM, EMF, IGS, WMF, DGN
Vector formats vary regarding compactness, line widths and pattern control, color, layering and types of curves supported
3D Surface and Shape formats Descriptions 3DS, WRL, STL, IGS, SAT, DXF, DWG, OBJ, DGN, PDF(3D), XGL, EWF, U3D, IPT, PTS
3D surface and shape formats vary according to the types of surfaces and edges represented, whether they represent surfaces and/or solids, any material properties of the shape (color, image bitmap, texture map) or viewpoint information
3D Object Exchange formats Descriptions STP, EXP, CIS/2 Product data model formats represent geometry
according to the 2D or 3D types represents. They also carry object properties and relations between objects.
Game formats Descriptions RWQ, X, GOF, FACT Game file formats vary according to the types of
surfaces, whether they carry hierarchical structure, types of material properties, texture and bump map parameters, animation and skinning
GIS formats Descriptions SHP, SHX, DBF, DEM, NED Geographical information system formats XML formats Descriptions AexXML, Obix, AEX, bcXML, AGCxml, IFCxml
XML schemas developed for the exchange of building data. They vary according to the information exchanged and the workflows supported.

Page 23 of 88
2.1.3 LEVEL OF DETAIL
According to Bedrick (2008), Level of Detail (LOD) of BIM models are defined as
“the steps through which a BIM element can logically progress from the lowest level
of conceptual approximation to the highest level of representational precision”. Five
levels of detail are determined to describe the BIM models, which are named from
Level 100 to Level 500: Conceptual, Approximate Geometry, Precise Geometry,
Fabrication and As-built. Table 2 provides LOD definitions in different project phases
(Bedrick 2008, Leite et al. 2010). As the project progresses, the LOD of the models
will be going to a higher level and the richness of the information will also be
improved. It requires the cooperation among all parties involved in the project such as
architects, estimators and schedules. Each party will embed the information in the
model based on its own requirements.

Page 24 of 88
Table 2 LOD definitions (Adapted from Bedrick 2008, Leite et al. 2010)
Project Phase LOD 100 LOD 200 LOD 300 LOD 400 LOD 500 Design Non-
geometric line, areas or volume zones
Three dimension-generic elements
Specific elements with dimensions, capacities and space relationships
Shop drawing/fabrication with manufacture, installation and other specified information
As built
Scheduling Total project construction duration
Time-scaled, ordered appearance of major activities
Time-scaled ordered appearance of detailed assemblies
Fabrication and assembly detail including construction means and methods
Cost Estimation
Conceptual cost estimation
Estimated cost based on measurement of generic element
Estimated cost based on measurement of specific assembly
Committed purchase price of specific assembly at buyout
As-built cost
Energy Analysis
Strategy and performance criteria based on volumes and areas
Conceptual design based on geometry and assumed system types
Approximate simulation
Precise simulation based on specific information
Commissioning and recording of measured performance

Page 25 of 88
2.2 BIM Tools
As BIM evolves into one of the most advanced technologies in construction industry,
more software developers are applying their products into the prospective area in BIM.
A survey conducted by Burcin and Samara (2010) of 424 construction firms in United
States shows that various BIM tools have already been adopted in the construction
industry. Figure 6 shows the market share of various BIM tools which are used by
these 424 construction firms. Autodesk BIM tools are the most widely used BIM
solutions in U.S with 54% of those construction firms using them; Graphisoft
ArchiCAD™ follows with 10.7% and Bentley BIM tools with 8%. Tekla and Vico
BIM tools are utilized by 6.5% and 5.8% of the construction firms based on the survey.
The other software tools such as Innovaya™, Dprofiler™, Vectorworks™, etc. are
also being utilized by a small portion of the construction firms (Burcin et al. 2010).
The software tools have been used in different phases during the project lifecycle such
as Preliminary Design and Feasibility Study, Shop Drawing and Fabrication,
Estimating, Scheduling, and File Sharing & Collaboration. The purchase of the
software package is different from regular purchases, since the buyers need to
consider the capabilities of each software tool in the package. This section provides
general information about BIM software packages which are widely adopted by users.

Page 26 of 88
Figure 6 Percentages of market share of BIM tools which are used by construction firms
(Adapted from Burcin and Samara 2010)
Autodesk
According to Young et al. (2008), Autodesk™ BIM software package is the best
known and most popular among BIM users—93% of building stakeholders have
heard about it and 73% are using this package. According to Burcin and Samara
(2010), 54% of the respondents (contractors in the case of this survey) are using
Autodesk BIM products in their projects. Autodesk’s first BIM product—Revit
Architecture™ was introduced to the industry in 2002 for the architectural design
purpose and was quickly adopted by most architecture firms who were using BIM
technology. After years of development, the Revit package has evolved into a product

Page 27 of 88
which can support multiple functions during the construction process—Revit
Architecture™ for architectural design, Revit MEP™ for electrical engineering and
plumbing design and Revit Structure™ for structural design. For the schedule and
cost controls, Autodesk has Navisworks™ which allows users to simulate and manage
the construction process and Autodesk Quantity Takeoff Software that supports cost
estimating function. Other than these, Autodesk™ also developed software tools such
as Autodesk 3ds Max for model visualization and Autodesk™ Inventor for data
exchange to benefit the users from higher control level. Most of the software tools
from Autodesk™ can support multiple file formats which include: DGN, DWG, DWF,
DXF, IFC, SAT, SKP, AVI, ODBC, gbXML, BMP, JPG, TGA, and TIF. The multiple
file formats supporting function allows these software to be compatible with products
from other software developers. Autodesk™ also provides free trial versions of the
software and training webinars.
Graphisoft
Graphisoft is one of the earliest companies to market BIM capabilities. Its main
product ArchiCAD™ is marketed since 1980s and is the only object-model-oriented
architectural CAD system running on the Apple Macintosh (Eastman et al. 2008).
Today, ArchiCAD™ can serve both Apple Platform and Windows. One special feature
of ArchiCAD™ is the Virtual Building Explorer, a real-time 3D navigation which is
enhanced with gravity, layer control, fly-mode, egress recognition and pre-saved
walkthroughs. ArchiCAD™ also includes a built-in analysis tool to conduct the

Page 28 of 88
energy analysis function on its BIM model. ArchiCAD supports a range of direct
interfaces: Maxon for curved surface modeling and animation, ArchiFM™ for facility
management and Sketchup™ for 3D sketching. It also contains object libraries for
users with an Open Database Connection (ODBC) interface. MEP modeler™ is
another key product from Graphisoft, the extension to ArchiCAD™, which is used for
MEP modeling pipes, fittings, ducts, and others. Graphisoft embeds large object
libraries in its product. However, the software tools have some limitations in
parametric modeling capabilities. As an example, automatic update to related objects
is not supported. The company offers free trials and education opportunities to its
potential users.
Bentley
Bentley is another major software company that offers products for architecture,
engineering and construction. The architectural designing tool in BIM, Bentley
Architecture™, introduced in 2004, can be integrated with other software tools such
as: Bentley Structural Modeler, Bentley Building Mechanical Systems, Bentley
Building Electrical Systems, Bentley Facilities, Bentley Generative Components and
Project Wise Navigator. Bentley offers a broad range of BIM software tools which are
involved in almost all stages of building lifecycle. Its products can deal with almost
all aspects of AEC industries such as Bridge design and engineering, Building
analysis and design, Plant operations, Rail design and operations, Transportation
operations, Water and Wastewater Network analysis and design and others. Currently,

Page 29 of 88
Bentley products are in version V8i and according to Bentley, the “i" stands for five
key new capabilities and enhancements: more intuitive conceptual modeling
capabilities; interactive dynamic views; intrinsic geo-coordination capability;
incredible project performance and speed; and finally, a high degree of
interoperability. Its supported file formats include: DGN, DWG, DXF, PDF, STEP,
IGES, STL, and IFC. The supported file formats are not as diverse as Autodesk™
BIM software tools which limit the interoperability capabilities of Bentley software
tools. Bentley also provides product tours, training and online seminars for users to
educate them about its products.
Tekla
Tekla is a Finnish company founded in 1966 which has multiple divisions: Building
and Construction, Infrastructure and Energy. The main product of Tekla is Tekla
Structures™ which was formerly named Xsteel in mid 1990s. The basic functionality
of Tekla Structures is for structural design. It allows users to create a complete digital
model that depicts the structure combined with both physical model and analytical
model, and then this structural model can be used for different types of structural
analyses. Tekla Structures is also used by detailers, fabricator and manufacturers for
generating detailed information for steel, precast and rebar detailing. Tekla Structures
supports interfaces with: IFC, DWG, CIS/2, DTSV, SDNF, DGN, and DXF file
formats. It links with various systems through Tekla Open API™ (Application
Programming Interface) that is implemented using Microsoft .NET technology. Tekla

Page 30 of 88
Structures™ is capable of supporting large models, even with multiple users operating
concurrently by its Multiuser Server. This Multiuser Server is developed by Tekla
Corporation and can support a maximum of 40 users operating simultaneously.
However, since the concurrent operation from multiple users is more complicated than
a single user operation, these users need to be highly skilled to fully utilize the
complex functions of this software.
2.3 BIM Application Areas
As section 2.1 indicated, BIM model is parametric-object based and all the
information stored in the model can be shared and reused by different stakeholders
involved in the building lifecycle. By storing and exchanging the information of the
building automatically, BIM model can provide more accurate data and information of
the building. BIM technology can be utilized in different application areas such as
design/modeling, energy analysis, clash detection, cost estimation and construction
scheduling. These multiple application areas in BIM can help users to improve the
communication, reduce errors, and potentially save time and money. This section will
explore important BIM application areas in various phases of the building lifecycle.
Design/Modeling
The object-based parametric modeling feature in BIM allows architects, MEP
engineers, structural engineers and fabricators to leverage multiple functions on the

Page 31 of 88
same building model for their own use. With accurate building information and object
models, the design/modeling process is dramatically facilitated. The design accuracy
and information sharing enhancement span all the phases of the design/modeling
process which also benefit the subsequent activities such as accurate quantity takeoffs
that can be used in cost estimating and the construction phase can be automated for
the project control.
Energy Analysis
The capability to link the building model to energy analysis tool allows users to
conduct the energy analysis in the early design phase. Traditionally, a separate energy
analysis would be conducted at the end of the design process and it is not possible for
users to modify the design to improve the building’s energy performance. By using
BIM technology, the building model can be linked to energy analysis tools for the
energy evaluation during the early design phase. The analysis allows users to make
energy-conscious decisions and to test the energy-saving ideas without postponing the
design process (Stumpf et al. n.d.).
Clash Detection
The designs from all organizations can be brought together and compared, and the
geometric clashes between architectural, structural and MEP systems will be detected,
checked and modified. Coordination among different organizations is enhanced and
errors and omissions are significantly reduced, thus speeding up the construction

Page 32 of 88
process, reducing costs, minimizing the likelihood of legal disputes, and shortening
the construction period.
Construction Scheduling
The design and the construction schedule can be synchronized by linking the building
model to the project schedule. It allows users to simulate the construction process and
show the virtual view of the building and the site. More details about construction
scheduling will be provided in the following sections.
Cost Estimating
BIM users can generate accurate and reliable cost estimates through automatic
quantity takeoff from the building model and get a faster cost feedback on changes in
design. It is possible to make all the involved organizations aware of the cost
associated with the design before it progresses to a more detailed level. The following
sections will provide more detailed discussions about cost estimating in BIM.

Page 33 of 88
Chapter 3
BIM and Construction Management
It has been widely accepted that construction management skill of the contractor is the
hub of the construction process, and any activities and decisions made by contractors
during the construction phase will influence the productivity and cost of the whole
project. It has been reported that as much as 30% of the cost of construction is wasted
in the field due to coordination errors, wasted material, labor inefficiencies and other
problems in the current construction practice (CURT 2002).One of the benefits in
BIM is to limit the above inefficiencies, thus enhancing the productivity and reducing
the project cost. According to Gallaher et al. (2004), the estimated “cost of inadequate
interoperability in the U.S. capital facilities industry is $15.8 billion per year” and the
AEC industry are targeting to reduce this $15.8 billion losses by providing a more
integrated project life-cycle. In this chapter, the utilization of BIM in construction
management will be discussed with special emphasis on scheduling, cost estimating
and project controls.
3.1 Project Scheduling in BIM
Project scheduling (4D modeling) in BIM is to link a BIM model to a schedule to
visualize the schedule of the construction. The use of scheduling function in BIM (4D
Model) can help the users establish optimized schedule of the project in a 3D

Page 34 of 88
environment which also allows the users to have a virtual view of the whole project.
The concept of 4D Model was first mentioned by Egan John (1998) that “certain
principles and management techniques could successfully cross-over from other
industries like manufacturing to serve the project delivery demands of the
construction industry.” Koo and Fischer (2000) developed a 4D model for a
commercial construction project. They were able to find the incompleteness of the
original schedule, detected the inconsistencies in the level of detail among the
schedule activities and discover the impossible schedule sequence. They proved that
4D models are able to evaluate the effectiveness of the project schedule and
anticipated the future improvement in 4D tools. The experiment of Songer et al. (2001)
focused on the 3D/4D visualization on project schedule review and the results
provided quantitative evidence of the advantages of 3D/4D representations for
schedule review for improving construction projects. Kamat and Martinez (2001)
proved that visualized simulation could significantly improve the effectiveness in
construction operation; however, the supportive software tools were still not available
in the market. They also provided the first version of a general-purpose 3D
visualization software tool of construction operations. Clayton et al. (2002) showed
that “3D modeling and computer simulations provide new ways for architecture
students to study the relationship between the design and construction of buildings.”
Heesom and Mahdjoubi (2004) provided emerging research initiatives in 4D CAD by
“identifying three research areas: product modeling and visualization, process
modeling and analysis, and collaboration and communication.” Mallasi (2006)

Page 35 of 88
developed a new concept for “visualizing workspace competition” between the
progressing activities. The 4D simulation tool, which was named PECASO, provided
a dynamic 4D simulation environment to analyze workspace congestions among
progressing activities. De Vries and Harink (2007) described a method for automated
construction planning and provided an algorithm that derived the construction
sequences from a solid model of the building. Finally, a perspective view was
presented on a more advanced and automated planning method which includes
contractor’s professional knowledge for more accurate results. Jongeling and
Olofsson (2007) presented “a process method for the planning of work-flow by
combined use of location-based scheduling2
2 Location-Based Scheduling: Location-based Scheduling uses production lines in a linear scheduling method (LSM) to represent work performed by various construction crews that work on specific locations in a project (Jongeling et al. 2007).
and 4D CAD.” They also suggested that
a location-based scheduling could improve the usability of 4D models and 4D models
could enhance the value of location-based schedules. Kang et al. (2007) proposed a
web-based 4D CAD to enhance the collaboration during construction scheduling
process. Jongeling et al. (2008) presented that the application of 4D is a promising
approach to extract different types of quantitative information from 4D models for
time-space analyses of construction operations. The paper also showed how to extract
different types of 4D contents from 4D models for project planning purpose. Young et
al. (2009) delivered surveys of thousands of AEC participants such as Architects,
Engineers, Construction Managers, etc. in the U.S to evaluate the market value of
BIM technology. The report showed that almost 50% of the industry is now using

Page 36 of 88
BIM and some users currently experienced value from 4D scheduling of BIM, which
was also one of the main future development areas in BIM (Park et al. 2011).
In the following section, project scheduling process in BIM will be discussed. Users
can choose from a variety of software tools which can support the 4D model functions
of BIM. They are: i) Manual method using 3D or 2D tools, ii) Built-in 4D features in
a 3D or BIM tool and iii) Export 3D/BIM to 4D tool and import schedule. The main
focus in this section will be on the last two options of the methods.
BIM tools with 4D capability
As stated above, two main 4D scheduling methods will be discussed in this section—
i) Built-in 4D features in a 3D or BIM tool and ii) Export 3D/BIM to 4D tool and
import schedule. The first method is to assign the “phase” of a BIM object to the
object property or parameter—adding the “phase” parameter to the BIM object. In the
building design, architects may need to create multiple design phases—“existing” and
‘new construction” phases for renovation projects or “demolished” phase for
temporary construction, or define the basic timeline of the project during the design
phase. This will require the built-in 4D capability in BIM software tool which will
allow users to assign simple phases to the building model. For example, in Autodesk
Revit Architecture™, users can define the project phases such as Existing, New
Construction and Demolished (Fig.7) or by timeline such as March 1st or by the end
of March under the Project Phases Tab. The BIM objects in Revit Architecture™
could be assigned to these phases, and the phase works as the 4th parameter of the

Page 37 of 88
model—4D model. As an example, in Figure 8, the Curtain Wall in the building
design is selected and under the Properties dialog, the Phasing Category is shown. The
selected Curtain is assigned to the “New Construction” phase in this project. When
the building model is completed, users can get a straight-forward breakdown of
project phases generated by Revit Architecture™. Users can also apply filters to show
the objects in a specific period of time or in a specific phase. Under the Phase Filters
tab, users can manage how to show the related objects. For example, “show
demo+new” filter will show all objects that are demolished and the objects that are in
new construction phase (Fig.7). However, the built-in 4D capability in BIM tools is
for basic project phasing since the phases defined are not based on the “date” and
“time”. For users who need to track a more accurate project schedule such as the
Actual start date, Actual end date, Planned start date, Planned end date, etc., the
direct integration with schedules generated by professional software tools like
Primavera™ is more applicable.

Page 38 of 88
Figure 7 The phasing function in Revit Architecture 2011
Figure 8 The objects are linked with the defined phases in Revit Architecture 2011
Defined
Phases

Page 39 of 88
Export 3D BIM to 4D tool and import schedule
The limitations of previous BIM 4D method encouraged the software developers to
find out a way which can fully integrate the scheduling function with the 3D model
(see details of software tools in Table 3). Generally, the steps involves importing the
existing 3D BIM model into the BIM software tool, importing the schedule created by
another scheduling software tool (such as PrimaveraTM and Microsoft Project™) and
then linking the schedule with its relevant objects in the BIM model (Fig.9); some
BIM scheduling software tools may have the in-built function to define the schedule
itself. Autodesk Navisworks™, ProjectWise Navigator™, Visual Simulation™,
Synchro Professional™ and Tekla Structures™ are the object-based 4D tools, which
mean the imported schedule will be linked to the objects of the building model. Vico
Control™ is different from others; it is a quantity-based 4D scheduling tool. In order
to calculate the schedule, Vico Control™ links the quantities of the building objects to
a “recipe” that contains the description of materials, labor, resource, cost and even
location information.

Page 40 of 88
Table 3 BIM software- scheduling Tools
Product Name Manufacturer Primary Function Supplier Web Link
Navisworks Manage
Autodesk Linking 3D model to project schedule applications
(e.g. MS Project or Primavera) www.autodesk.com
ProjectWise Navigator
Bentley Linking 3D model to project schedule applications
(e.g. MS Project or Primavera) www.bentley.com
Visual Simulation Innovaya Linking 3D model to project schedule applications
(e.g. MS Project or Primavera) www.innovaya.com
Synchro Professional
Synchro Bi-directional linking to project schedule
applications (e.g. MS Project or Primavera) www.synchroltd.com
Tekla Structures Tekla Schedule driven by link between
model and project software www.tekla.com
Vico Control Vico Software Schedule is analytically derived
from the resource-loaded, cost-loaded, location-based BIM
www.vicosoftware.com
Figure 9 The flowchart of 4D scheduling process
BIM scheduling
tool
3D BIM model
4D schedule
Schedule from
Primavera or MS. Project

Page 41 of 88
Most of the 4D tools such as Autodesk Navisworks™ can provide users a virtual view
of the building and site. The 3D virtual view of an office building in Autodesk
Navisworks™ is shown in Figure 10. The schedule (shown at the bottom of Fig.10),
which is defined by the in-built scheduling function in Navisworks™, is linked to the
building components in the 3D building model, and this integration of 3D model and
project schedule is called 4D model. The benefits of this integration are:
The 4D model can produce a visual representation of time, show the project status,
provide the virtual simulation of the project and even provide views of physical
completion of building at various points in time.
Contractors can communicate with other stakeholders and coordinate the
expected time and space flow based on the simulated project process. By
providing the simulation in the 4D environment, contractors can ensure that the
plan is feasible and efficient (Eastman et al. 2008).
This integration allows the real-time project process to be updated more
frequently. The process of the project can be updated automatically according to
the change in the building design (Hwang et al. 2010).
Contractors can arrange the site logistics based on the virtual 4D simulation such
as arrange lay-down areas, location of equipment, etc.

Page 42 of 88
Figure 10 Snapshot of a 4D software interface showing how schedule is connected to objects
(Autodesk Navisworks)
3.2 Cost Estimating in BIM
The cost estimating process involves performing quantity takeoff (QTO)3
3 Quantity takeoff list (QTO): a list of item and material quantities needed for the project.
and adding
cost data to the QTO list. Traditional QTO process with CAD drawings involves
selecting individual elements in CAD drawings, using the software to automatically
determine the dimensions for the take-off, and inputting the quantities into the QTO
list (Khemlani 2006). This process requires estimators to spend substantial amount of
time on generating the QTO of the entire drawing. Since the selecting and measuring
processes are all based on manual operations, the errors and omissions happen during
the QTO process. The construction industry is a unique industry that contractors need
to guarantee a price to owners before they know the actual completion cost (AGC,
Schedule
3D Virtual View
Building Objects
Linked

Page 43 of 88
n.d.). The calculations must be conducted before the project actually starts and this
will require a higher level of accuracy during the estimating process for contractors.
Since BIM models are object-based with in-built parametric information, it is easier to
capture the quantities of the objects in BIM and the QTO with BIM drawing will be
more accurate with less errors and omissions. The QTO process is also expedited– it
can require 50% to 80% of a cost estimator’s time on a project (Rundell 2006). QTO
process can be enhanced with higher accuracy and less time using BIM technology.
Mapping the QTO list with cost databases, which can be built-in in BIM models or a
standalone external cost database, estimators can generate a more accurate and
reliable cost estimate of the building with minimal effort. There are three main options
to leverage BIM for quantity takeoff and to support cost estimation. They include:
- Export building object quantities to estimating software
- Link the BIM tool directly to the estimating software
- Use a BIM quantity takeoff tool
Export Quantities to Estimating Software
Most BIM software tools offered by software vendors include features for extracting
the QTO off the BIM Model. These tools also include features to export quantity
takeoff data to a spreadsheet or an external database. In the United States alone, there
are over 100 commercial estimating packages that secure these needs and many are
specific to buildings of certain occupancies (Eastman et al. 2008). Microsoft Excel™
is the most commonly used estimating tool which is also sufficient for most estimators

Page 44 of 88
to extract the QTO from the BIM Model (Christofferson 2000, Sawyer and Grogan
2002). For example, designers and architects can utilize Revit Architecture™ to easily
export the material information—initial bill of quantities and material takeoffs—into
MS Excel Spreadsheet, thus more accurate budget estimates will be available at the
early stages of the project lifecycle. However, this approach requires significant setup
and standardized modeling process—such as sufficient information on the object
model—in order to generate the intact QTO information from the model.
Directly link BIM Components to Estimating Software
The second alternative is to use a BIM tool that is capable of linking BIM model
directly to an estimating package in the plug-in or third-party tool. Many of the larger
estimating software packages now offer plug-ins to various BIM tools. See Table 4 for
a few examples which have the plug-in functions for BIM tools. As an example,
Innovaya™ (a BIM cost estimating tool) uses a plug-in tool to link to “Sage
Timberline.” This plug-in function allows the user to associate components in the
building model directly with assemblies, recipes, or items in the estimating package in
Sage Timberline™. The user will be able to use rules to calculate quantities for these
items based on the component properties or manually enter data that was not extracted
automatically from the building information model. The assemblies of building
components will follow the rules in Sage Timberline, thus all information required to
develop a complete cost estimate can be generated from the BIM Model directly and
the building information will be highly integrated and assembled. In addition to that,

Page 45 of 88
there is no need for users to manually map the cost data with the building components,
since the cost data will be mapped as soon as the quantities are generated and
assembled. However, contractors may need to cooperate with subcontractors when
they work on different estimating packages in this approach.
Table 4 Plug-in tools for cost estimation
Product Name Manufacturer BIM Use Supplier Web Link
Success Estimator U.S. Cost Estimating www.uscost.com
Graphisoft Estimator Graphisoft Estimating www.graphisoft.com
Innovaya Innovaya Estimating www.innovaya.com
Quantity Takeoff Tool
A third alternative is to use a specialized quantity takeoff tool that imports data from
various BIM tools. Users can choose a takeoff tool specially designed for their needs
without having to learn all of the features contained within a given BIM tool (see
Table 5 for a few examples). These takeoff tools typically include specific features
that link directly to items and assemblies, annotate the model for specific ‘object
information’, and create visual takeoff diagrams. These tools offer varying levels of
support for automated extraction and manual takeoff features. The user assembles the
objects in the model and dimensional data will be transferred from the model to QTO
list for further pricing. Visualizing all the items being taken off reduces the chance of
the estimator missing items. It also reduces the chance for transposition errors as the
design changes the linked model updates the estimated quantities (Khemlani, 2006).

Page 46 of 88
Example of this is: Autodesk QTO™ can automatically extract QTO from the
building model according to category information leveled on the object model and it
also allows manual modification of the takeoffs based on the users’ own preference.
After that, the QTO list can be exported to the MS Excel spreadsheet and users can
associate the quantities with any suitable cost database. The QTO process in this
approach can be finished automatically and categorize the objects based on the
“Category” information leveled on the object model. After the automatic takeoff,
users can also make some changes on the QTO list manually. One advantage of this
approach is that users may not have to apply to the assemblies based on the specific
cost estimating package; any suitable cost data can be mapped with the QTO list after
the quantities are generated. However, compared to linking components to estimating
software directly, this method may take more time on mapping the cost database.
Table 5 Software list—quantity takeoff tools
Product Name Manufacturer BIM Use Supplier Web Link
QTO Autodesk Quantity Takeoffs www.autodesk.com
Exactal Exactal Quantity Takeoffs www.exactal.com
Innovaya Innovaya Quantity Takeoffs www.innovaya.com
Takeoff Manager Vico Quantity Takeoffs www.vicosoftware.com
OnCenter OnCenter Quantity Takeoffs www.oncenter.com

Page 47 of 88
3.3
Dealing with Electronic and Paper-based CAD Drawings
Although BIM is a rapidly developing technology in construction industry, traditional
building drawing formats such as paper drawing and conventional CAD drawing are
still dominating the market of the existing buildings. As stated in previous section,
compared to these traditional drawings, the BIM design consist of object-based
parametric models which contain not only the parameters but also the associated rules,
specifications and some non-geometric properties and features such as materials,
special relationship, etc. In order to benefit from BIM technology, users may choose
to convert paper or conventional CAD into BIM drawings. The converting process
may take users substantial amount of time, but BIM technology may benefit users by
shortening project period and reducing project cost. For example, U.S. Department of
Energy (DOE) planned to build a new $100 million, 45,000 square-foot
high-explosives Pressing Complex System in Texas. When the conventional CAD
documents were 95% completed, DOE chose to convert existing CAD design into
BIM model. It took DOE four months to convert the design, but the project ended up
with $10 million in savings and a shorter expected finishing date after utilizing BIM
(Young et al. 2009) In this section, methods for converting conventional CAD
drawings and paper drawings into BIM will be discussed respectively.

Page 48 of 88
Converting Conventional CAD Drawing to BIM
There are software tools (See Table 6) such as Revit Architecture by Autodesk,
MicroStation by Bentley and ArchiCAD by Graphisoft, which are capable of
converting conventional CAD drawings into BIM files. For example Revit
Architecture 2011 can import or link CAD Files using the ‘Import CAD’ and ‘Link
CAD’ Tools with the geometry information in the CAD Files. By using the geometry
information as a starting point in BIM model, the users can also define the other
properties in this defined model. Once all the data is captured in the BIM model, users
can generate the QTO from the converted BIM model to conduct cost estimating of
the project.
Table 6 Software tools to convert CAD drawing to BIM model
Product Name Manufacturer BIM Use Supplier Web Link
Revit Architecture Autodesk Architecture and
Site Design www.autodesk.com
MicroStation Bentley Creating and Reviewing 3D models
www.bentley.com
Dprofiler Beck Technology
Conceptual Design And Cost estimation www.beck-technology.com
ArchiCAD Graphisoft Conceptual 3D Architectural model www.graphisoft.com

Page 49 of 88
Converting Paper-drawing to BIM
BIM users can use software tools such as Dprofiler from Beck Technology to generate
the BIM model from paper based drawings. Figure 11 shows a paper-drawing of a
building and its BIM model generated by Dprofiler. The users can first scan the
paper-drawing and then use this scanned sketch to start the building model in
Dprofiler as a starting point. The elevations, floor plans, and site plans in the paper
drawing can also be used to speed up modeling process. Once all the data is captured
in the BIM model, users can generate the QTO from the converted BIM model to
conduct cost estimating of the project.
Figure 11 Generation of BIM model from paper drawing using Dprofiler (Adapted from Dprofiler)

Page 50 of 88
Chapter 4: A Case Study using BIM
4.1 Introduction
In the previous section, the methods of scheduling and cost estimating in BIM were
introduced. In this chapter, a BIM model of a training facility will be utilized to
illustrate the process of scheduling and cost estimating in BIM. The training facility is
a three-story building in Munich Germany, designed using Autodesk Revit
Architecture™ 2010 (Fig. 12). The building is 19,673.52 sq ft and is equipped mainly
with curtain walls and masonry insulation with seven main rooms and five stairs on
each floor. The first step is to utilize this building model to generate the QTO list
and then level the cost data on the list to estimate the project cost. The second step is
to link the building model with the defined project schedule to simulate the project
process in the 4D environment. The main purpose of the case study is twofold: 1) The
case study will illustrate how BIM technology can work for cost and schedule controls
2) Based on the existing technology, what kind of improvements can be made in the
future.
Figure 12 The training facility model in Munich, Germany
(Source: model provided by Autodesk)

Page 51 of 88
Problem Statement
BIM as an emerging technology has developed very rapidly in the past decade, and
BIM technology has already started to benefit the designers with intelligent and
model-based design and owners with a more feasible and accessible project.
Contractors, as inter-media between designers and owners, also start to deliver the
project with BIM model. As stated in the previous section, the LOD will be increased
as the project progresses, which means each involved party in the project needs to add
information to the model based on its own preference. From a contractor’s perspective,
two dimensions—time and cost will be added by the contractors after the models are
completed. Since cost and schedule are two key parameters for the construction
management process, it is essential to know if the information in BIM model can help
contractors for the cost and schedule controls and the potential developments can be
made on BIM technology for contractors.
Research Questions
1. Can BIM model be fully utilized by contractors for cost and schedule controls?
2. What kind of improvements can be made from contractor’s perspective for cost
estimating, scheduling and project controls?
Delimitations
The following delimitations define the scope of this study:
1. The purpose of the case study is to illustrate the scheduling and cost estimating
processes with the available BIM model and find out the improvements that can
be made in the future.

Page 52 of 88
2. This research is limited to performing a quantity takeoff and schedule simulation
since the building model only contains the Shell, Interiors and Services Parts of
the building (Appendix 2).
3. The quantity takeoffs were performed on a building model which has lower LOD
and the total project will be adjusted based on RS Means (2009)(See in Appendix
2).
4. The 4D scheduling and simulation were performed on a building model which has
lower LOD and the schedule is created based on the existing building components,
so the project period developed in the case may not be the accurate period of the
project.
5. The BIM model and software tools used were all adapted from the Autodesk since
Autodesk provides full access of its products to students. The selection of the
software tool may have limitations.
6. The building shown in the model is a training facility in German and the cost
estimation will be adjusted according to “2-4 story office building” category in RS
Means (2009) (See in Appendix 2).
Assumptions
The assumptions of this research included the following:
1. The contractors will have full access to all the selected software tools.
2. The planned and actual dates of schedules are created hypothetically in this case.
3. The building model in the project is drawn correctly with no clashes and errors so
that the measurements and quantities of the objects in the model are reliable.

Page 53 of 88
Software Tools Selected
The software tools selected in this case study are stated as follows:
1. Autodesk Revit Architecture™ 2011: A BIM-enabled design tool for architects
and designers; Autodesk Revit Architecture™ can capture the design concept and
provide the virtual view of the building design.
2. Autodesk Quantity Takeoff™ 2011: A building cost estimating software for cost
estimators; Autodesk QTO™ can automatically measure areas and count building
components, export to Microsoft Excel, and publish to DWF™ format.
3. Autodesk Navisworks™ 2011: A project review software that supports intelligent
3D model-based designs with scheduling, visualization, and collaboration tools, as
well as advanced clash detection capabilities.
4.2 Cost Estimating
In this case, since the BIM model of the building is available for the quantity take-off,
it is easy to generate the QTO list directly from the building model. As mentioned
before, the BIM model of the building is on a lower LOD. In order to generate a more
accurate project cost, the following steps will be taken:
(1) Export the building model from Revit Architecture™ to Autodesk QTO™:
Transfer the available model to a readable file format for quantity takeoff tool.
(2) Generate the QTO list from the building model.
(3) Export the QTO list to MS Excel™ and map QTO list with RS Means (2009)
cost database.
(4) Adjust the cost according to RS Means (2009) and get the total project cost.

Page 54 of 88
Step 1: Export the building model from Revit Architecture to QTO tool
Since the Autodesk QTO™ 2011 can only read BIM model in .DWF file format, the
first step is to export the building model from Autodesk™ Revit Architecture 2011
to .DWF file format and then import it into Autodesk™ QTO 2011.Figure 13 shows
the building model is transferred from Autodesk Revit Architecture™ to Autodesk
QTO™ 2011 and the building components are categorized and colored automatically
in Autodesk QTO™. For example, the curtains walls are categorized and colored in
yellow automatically by Autodesk QTO™ (Fig.13).
Figure 13 Export the building model from Revit Architecture into Autodesk™ QTO
Step 2: Generate the QTO list
In the .DWF file, multiple interfaces of the building model can be included, such as
the 3D view, the elevation view, the floor plan views, etc. Autodesk QTO™ 2011 can

Page 55 of 88
take only minutes to generate the QTO of the entire building and each generated
building components will be colored coded. Figure 14 shows the interface of
Autodesk QTO™ 2011 and three parts are shown: (1) the list of grouped building
components, (2) the 3D view of the building model and (3) the generated QTO list. In
the list of grouped building components, the building components are categorized into
different groups such as doors & windows, walls, ceilings, curtain panel, etc. In the
QTO list, each building component is designated to the same color as shown in the 3D
view. The curtain wall is categorized in the “Curtain Panel” group and colored in
yellow. The quantity of the curtain wall is 23,768.516 sq ft which can be read directly
from the QTO list. The entire process is only finished within 15 minutes and the QTO
process is finished automatically.
Figure 14 The QTO list has been generated by Autodesk™ QTO 2011
QTO List Grouped
Building
Components

Page 56 of 88
Step 3: Export the QTO list to Excel and calculate the cost
The third step is to export the QTO list to MS Excel™. Since the categories in QTO
list of BIM model is sufficiently clear, users do not need to categorize them manually;
the following work is only to map the cost data such as material cost, labor cost and
equipment cost with the QTO list. In this case, the source of cost data being used is
RS Means (2009). The QTO list in MS Excel™ with the quantity list circled in blue;
the cost data has been added on the list and circled in red (Fig 15). The total estimated
cost of the building is $1,849,766.88
Figure 15 The QTO list shown in Excel with the cost data added
Total Cost

Page 57 of 88
Step4: Adjust the cost to get the total project cost
The available building model only contains the Shell and Interiors parts of the
building, so the cost estimated in Step 3 cannot be considered as the total project cost
and the adjustments should be made according to RS Means (Appendix 2). Table 7
shows the building components with its percentage of sub-total cost for a 2-4 story
office building (RS Means, 2009). The two colored categories are the components
contained in the building model and it takes 52.3% (12.2% + 15.8% + 1.6% + 22.7%
= 52.3%) of the sub-total cost, so the total sub-total cost is $3,537,030.36. By adding
Contractor fees and Architect Fees, the total Project Cost is $4,668,880.08 and the
cost per square foot is $237.32:
Sub-total cost $3,536,89.16
Contractor Fees (25% of sub-total cost) $884,257.591
Architect Fees(7% of sub-total cost) $247,592.125
Total Project Cost $4,668,880.08
Cost Per sq ft of floor area $237.32/sq ft
Table 7 Model cost calculated for a 2-4 story office building (RS Means, 2009)
Building Components % of Sub-Total A. SUBSTRUCTURE 4.4% B. SHELL B10 Superstructure 12.2% B20 Exterior Enclosure 15.8% B30 Roofing 1.6% C. INTERIORS 22.7% D. Services D10 Conveying 8.9% D20 Plumbing 2.8% D30 HVAC 11.8% D40 Fire Protection 2.8% D50 Electrical 17.0% E. EQUIPMENT & FURNISHINGS 0.0% F. SPECIAL CONSTRUCTION 0.0% G. BUILDING SITEWORK NA

Page 58 of 88
4.3 Construction Scheduling
By using the same .DWF model, Autodesk Navisworks™2011 can simulate the
schedule of the project by adding the fourth dimension—time into the model. The
time frame we set up for this case is starting at Mar. 21st 2011 and the project would
approximately last 7 months and completing by Oct. 31st. As stated in Chapter 3, there
are two different ways to add/incorporate the schedule into the building model: (1)
Importing Primavera or MS Project schedule or (2) defining the tasks in the Autodesk
Navisworks directly. For this case study, the second approach was used; the tasks
were defined directly in the Autodesk Navisworks™ 2011 and the steps are stated as
follows:
(1) Define the tasks in Autodesk Navisworks™ 2011
(2) Get the Gantt View of the project schedule
(3) 4D simulation view
Step 1: Defining Tasks
Autodesk Navisworks™ 2011 allows users to define tasks directly in the software tool
itself and then link building components with these defined tasks. In Figure 16, under
the “Tasks” tab, each task is defined with Start date and End date, Planned Start date
and Planned End date. The limitation is that the precedence relationships between
tasks cannot be defined in the Autodesk Navisworks™. The Start date and End date
show the actual project start and end dates and the scheduled dates are shown under
“Planned Start” and “Planned End”. Each task also has its own Status identified by an

Page 59 of 88
icon, representing planned against actual relationships. Each icon shows two bars: the
top bar represents the Planned dates and the bottom bar represents the Actual dates. If
the Actual start and finish dates are the same as the Planned start and finish dates, the
bars are displayed in green. Any variations between Planned and Actual dates are
displayed in red. Missing Planned or Actual dates are shown in grey. The interface can
clearly show to the Contractor and the Owner the updated status of the project. In this
case study, 25 tasks are defined based on the available building model and as the
building design has changed, the tasks can be changed accordingly.
Figure 16 Tasks are defined directly in Autodesk™ Navisworks 2011
Step 2: Gantt View
Under the Gantt View tab, a Gantt chart view provides a graphical representation of
the project schedule based on the tasks defined in Step 1. In Figure 17, the tasks are
shown in multi-column table on the left and colored Gantt bars are shown on the right.
Each task takes up one row. Planned, Actual, and Planned vs. Actual Gantt charts can
be selected based on the users’ preference. In Figure 18, the bars of Actual and
Planned Gantt charts are shown as blue; in the Planned vs. Actual Gantt chart view,

Page 60 of 88
the planned dates are shown as grey bars and the actual dates are shown as red bars
(Note: the color of the red and grey bars are not representing the status of the project).
Figure 17 Tasks are shown in Gantt View
Figure 18 Three Gantt Chart views can be selected based on the user’s preference
Actual vs. Planned
Planned
Actual

Page 61 of 88
Step 3 4D Simulation
The third step is to simulate the project phases in the 4D environment. In step 1, the
tasks defined are linked to the relevant building components in the Autodesk
Navisworks™ 2011. Under the “simulate” tab, the tasks are simulated. In Figure 19,
the simulation of the project progress is shown on 12 weekly based interfaces. On the
upper left side of simulation interfaces, the date, on-going project sequence and its
finished percentage are shown. By showing project phases and site logistics in a
virtual environment, 4D simulation in BIM dynamically provides users with different
project statuses. It is also convenient for the project contractor to provide the owner
with a virtual and intuitive view of the project progress. The contractor, the owner and
even the designers can be on the same page at any time to share understanding of
project status, milestones, responsibilities, and construction plans. If the contractor
defines a date under the simulation tab, the simulation interface can also show the
on-going tasks with the percentage of finished tasks on the defined date. The 4D
simulation in BIM provides the contractor with a virtual view of the project status.
Moreover, it helps the contractor to adjust the project schedule according to any
design change since the simulated tasks are linked to building components of the
building model.

Page 62 of 88
Figure 19 The interfaces of Autodesk Navisworks™ of 4D Scheduling in BIM
Week 1 Week 3 Week 4
Week 7 Week 10 Week 13
Week 16 Week 17 Week 20
Week 22 Week 23 Week 25

Page 63 of 88
4.3 Conclusions
A careful review of the case study shows that BIM technology brings many advanced
construction management skills to cost estimating, project scheduling and even
project controls for contractors.
In this case study, the QTO process is automatic and reliable, which is finished within
15 minutes, since the quantities of the building components are “read” by Autodesk
QTO™ 2011 from the building model directly. This will save contractors substantial
amount of time on cost estimating. On the other hand, the change of the design in the
building model can be updated and reflected in the QTO list in minutes, which means
that the owner (and in case of contracts where contractors are part of the team during
design phase, contractors) can get a faster cost feedback on changes in design using
BIM technology.
The 4D BIM links the building components with tasks and simulate these tasks in the
4D environment—the design and the construction schedule are synchronized. In this
case study, the tasks defined with planned and actual dates are represented in Gantt
chart view. By comparing the planned and actual dates, the status bars can tell the
contractor the progress of the project in an intuitive and simple way. The simulation of
the progress can also help contractor to adjust the project schedule according to the
design change in building model.

Page 64 of 88
Chapter 5: Conclusions and Future Work
5.1 Conclusions
Building Information Modeling (BIM) is an emerging technology in AEC industry. It
provides users with more accurate and consistent project information throughout the
lifecycle. In this thesis, diverse BIM tools and BIM application areas have been
discussed with emphasis on scheduling and cost estimating. Two approaches for 4D
scheduling in BIM have been presented: i) BIM tools with 4D capacity ii) use of 4D
BIM tool to link the 3D BIM model with the project schedule. After that, three types
of cost estimation methods have been discussed: i) export the QTO list from the BIM
tool to the estimating software such as MS Excel ii) link BIM components to
estimating software iii) use QTO tool to extract the QTO list from the model. Based
on the available methods, a case study is presented to illustrate the scheduling and
cost estimating processes in BIM based on the BIM model of a 3-story training
facility. The case study shows the QTO process can be finished in a more automatic
and reliable way and the 4D scheduling function in BIM simulate the project schedule
in the 4D environment. Based on the literature review and the case study, some
developments might be foreseen in the future.
5.2 Future Work
Contractors are “responsible for providing all of the material, labor, equipment,
(engineering vehicles and tools) and services necessary for the construction of the

Page 65 of 88
project” (Wikipedia). In order to ensure the project is completed on time, there are
many functions that the building contractors need to be responsible for: (1) implement
a proper plan to deliver the project on time, (2) review the progress and implement
any changes in project delivery on the way to ensure on time completion, (3) establish
the budget and follow the budget as closely as possible, (4) make sure to have
sufficient financial resources to successfully complete the project (5) and develop a
proper plan for manpower and materials needed for the execution of the project. In the
case study, it was shown that the improved cost estimating approach reduces the
potential errors in quantity takeoff process and expedites the process of cost
estimating. The scheduling in BIM can synchronize the schedule with the construction
of various building components. Currently, BIM technology cannot support all
contractors’ responsibilities; however, the technology is under development for
potential improvement in the following fields in the future:
(1) Higher LOD of the Object Models
(2) Scheduled financial analysis
(3) Resource Allocation
These points will be discussed in more detail in the following sections.
5.2.1
HIGHER LOD OF OBJECT MODELS DURING DESIGN PHASE
Cost is the most essential consideration to the contractors, since every decision that
the contractors make in the project will eventually aim to keep the project cost within

Page 66 of 88
the budget. As we discussed before, some BIM tools have the functions to generate
the material information such as bill of quantities and material takeoffs, then it will be
easier to control the project cost at the early stages of the project. However, the
limitation of this approach is that BIM model might not have sufficient information
during the design phase. As stated before, the LOD of the BIM model will be
increased as the project progresses. It means that when the building is in the
conceptual design phase, the LOD of the BIM model will be at its lowest point and
other users will need to add more detail to the model as more information becomes
available and project scope is better defined. The building model used in the case
study is on a lower LOD and as the project progresses, more information will be
added, such as material information, HVAC information and MEP information. If the
design has higher LOD, the QTO list the contractor generates from the building model
will include information that is sufficient for cost estimation. Since BIM technology is
still under development, designers or architects may not provide sufficient
information such as material information on the BIM model during the design phase;
thus the generation of bill of quantities will also be insufficient. As the design
technique in BIM becomes mature and more predefined BIM models will become
available, the design in BIM might be able to conclude sufficient information at the
early stages of the building lifecycle. By then, owners and even contractors can track
a more accurate cost of the project at the early stages of the project lifecycle and
ensure the cost will be kept within the budget.

Page 67 of 88
5.2.2
SCHEDULED FINANCIAL ANALYSIS — TIME AND COST
INTEGRATION
It is well known that the financial aspects are very important to contractors since more
often contractors cannot be paid by the end of the payment cycle. Contractors need to
make sure to have sufficient financial resources to complete the project by arranging a
solid financing schedule to meet their cash flow requirements and reduce the cost for
financing. In the case study, we saw that the time and cost parameters were considered
separately—adding the cost to QTO list for cost estimating and linking the schedule to
the 3D model. As shown in Figure 20, the QTO list is generated from the building
components 3D model and the cost data is mapped with the generated quantities;
meanwhile, the tasks in the schedule are also linked to relevant building components
in the 3D model. So, the cost and schedule are indirectly linked by the 3D model.
Thus another potential development in BIM is to integrate these two parameters with
3D building model. As seen in Figure 19, the cost data and 4D schedule can be linked
to get a scheduled financial analysis in BIM. This integration will (1) allow
contractors to see the cost distribution based on project schedule, (2) help contractors
to arrange financing activities in a more effective way, and (3) assist contractors to
make faster adjustments to the financial plan according to the design change. Since
the design changes will occur all the time throughout the project lifecycle, the
contractor’s financial plans will need adjustments accordingly. The integration of cost
and schedule together with the 3D model will allow the user to automatically adjust

Page 68 of 88
the budget and schedule if the design is changed. Contractor then can make faster
adjustments to the financial plan based on the changes in cost and schedule. This
integration can ensure that the contractor has enough financial resources even when
there is a change in the design.
Figure 20 Overall layout for the proposed financial analysis by integrating cost and schedule
5.2.3 RESOURCE ALLOCATION
Another important responsibility of the contractor is to make the proper plan for
manpower and materials requirements. As was shown in Table 3, most BIM
scheduling software tools can import MS Project™ or Primavera™ schedule. One
benefit of using MS Project or Primavera software is that they can level other
resources on the schedule, such as labor and equipment requirements, and then
analyze the resource usage based on the schedule. Contractors can make workload
3D MODEL
Cost Data
QTO LIST
4D BIM
Schedule
Scheduled
Financial
Analysis

Page 69 of 88
plans, procurement plans and even budget plans by using MS Project™ or
Primavera™. As is shown in Table 8, compared to MS Project™, the scheduling
function of Autodesk Navisworks™ is limited to the 4D scheduling only. Other useful
functions such as assigning resources to tasks, cost loading and analyzing budget
which MS Project™ supports, are missing in Autodesk Navisworks™. Thus, another
potential improvement in BIM is to develop mechanisms for assigning resource
information on the 4D schedule. By assigning the resources to the 4D model,
contractors can allocate the resources on the 4D model, analyze and plan the resource
usage based on the most updated design, and even simulate the resource allocation.
Table 8 Comparison between MS Project™ and Autodesk Navisworks™
Functions Microsoft Project™ Autodesk Navisworks™
Develop Schedule
Assign Resources to Tasks
Tracking Progress
Manage Budgets
Analyze Workloads
Gantt Chart
Clash Detection
Simulation

Page 70 of 88
References
1. Adrian, R., Doru, S., Edward, B., Benjamin, H., Kevin, M. and Robert, R. (2009).
"Dynamic Visualizations for Soccer Statistical Analysis." Proceedings, 2010 14th
International Conference Information Visualization, iv, 207-212.
2. Advancing HVAC&R to serve humanity and promote a sustainable world
(ASHRAE) (n.d.). “An Introduction to Building Information Modeling (BIM)—A
Guide for ASHRAE members.” ASHRAE.
<http://todaysfacilitymanager.com/facilityblog/wp-content/uploads/bim_guide.pdf>
3. Arayici, Y., Coates, P., Koskela, L., Kagioglou, M., Usher, C. and O'Reilly, K.
(2011). “Technology adoption in the BIM implementation for lean architectural
practice.” Automation in Construction, 20(2), 189–19.
4. Autodesk (2005). “Tapping BIM using ODBC.”
<http://www.ideateinc.com/whitepapers/bim/Revit%20BIM%20Tapping%20BIM
%20using%20ODBC.pdf>
5. Autodesk Revit Architecture [Computer software]. San Rafael, CA, Autodesk.
6. Autodesk Quantity Takeoff [Computer software]. San Rafael, CA, Autodesk.
7. Autodesk Navisworks [Computer software]. San Rafael, CA, Autodesk.
8. Azhar, S., Hein, M. and Sketo, B. (2008). “Building Information Modeling (BIM):
Benefits, Risks and Challenges.” Auburn University, Auburn, Alabama.
9. Bedrick, J. (2008). “Organizing the Development of a Building information Model”
AECbytes.

Page 71 of 88
<http://www.aecbytes.com/feature/2008/MPSforBIM.html>
10. Burcin, B.G. and Samara, R. (2010). “The perceived value of building information
modeling in the U.S building industries.” Journal of Information Technology in
Construction, 15,185-201.
11. Christofferson, J. P. (2000). “Unlocking the Power for Home Builders: Estimating
with Microsoft excel.” Home Builder Press, Washington DC.
12. CIS/2 @ Georgia Tech (2008). “Exchange Capabilities.”
<http://tempest.arch.gatech.edu/~aisc/index.php?cat1=1>
13. Clayton, J.M., Warden, B.R., and Parker, W.T. (2002). “Virtual construction of
architecture using 3D CAD and simulation.” Automation in Construction, 11(2),
227-235.
14. Construction Users Roundtable (2002). “Collaboration, Integrated Information
and the Project lifecycle in Building Design, Construction and Operation.”
<http://www.eua.com/pdf/resources/integrated_project/Construction_Users_Roun
d_Table.pdf>
15. De Vries, B. Harink, J. M. J. (2007). “Generation of a construction planning from
a 3D CAD model.” Automation in Construction,16(1), 13–18
16. Eastman, C., Teicholz, P., Sacks, R., and Liston, K. (2008). BIM handbook: A
Guide to Building Information Modeling for Owners, Managers, Designers,
Engineers and Contractors, Wiley, Hoboken, NJ.

Page 72 of 88
17. Eastman, C., Jeong, Y., Sacks, R., and Kaner, I. (2010). “Exchange model and
exchange object concepts for implementation of national BIM standards.” Journal
of Computing in Civil Engineering© ASCE, 24(1),25-34
18. Edwin T. D. (2010) “Interoperability and the Structural Domain.” Nishkian,
Portland, Oregon
19. Egan John (1998) “Rethinking Construction” Department of Trade and Industry.
London
<http://www.synchroltd.com/library/images/rethinkingconstruction.pdf>
20. Heesom, D. and Mahdjoubi, L. (2004). “Trends of 4D CAD applications for
construction planning.” Journal of Construction Management and Economics,
22(2), 171-182
21. Howell, I. and Batcheler, B. (2005). “Building Information Modeling Two Years
Later—Huge Potential, Some Success and Several Limitations.” The Laiserin
Letter, Manchester, NH
<http://cad.amsystems.com/products/docs/autodesk-revit-building-9-whitepaper-O
DBC_Jun05.pdf>
22. IFCwiki. (2009). “IFC-certified software.”
<http://www.ifcwiki.org/index.php/IFC_Certified_Software>
23. Jongeling, R. and Olofsson, T. (2007). “A method for planning of work-flow by
combined use of location-based scheduling and 4D CAD.” Automation in
Construction, 16(2), 189-198.

Page 73 of 88
24. Jongeling, R., Kim, J., Fischer, M., Mourgues, C. and Olofsson, T. (2008).
“Quantitative analysis of workflow, temporary structure usage, and productivity
using 4D models.” Automation in Construction, 17(6), 780-791.
25. Kamat, R.V., Martinez, C.J. (2001). “Visualizing simulated construction
operations in 3D.” Journal of Computing in Civil Engineering, 15(4), 329-337.
26. Kang, J. H., Anderson, S. D., and Clayton, M. J. (2007). “Empirical study on the
merit of web-based 4D visualization in collaborative construction planning and
scheduling.” Journal Construction Engineering and Management, 133(6),
447–461.
27. Khemlani, L. (2006). “Visual Estimating: Extending BIM to Construction.”
AECbytes,
<http://www.aecbytes.com/buildingthefuture/2006/VisualEstimating.html>
28. Koo, B., Fischer, M. (2000). “Feasibility study of 4D CAD in commercial
construction.” Journal of Construction Engineering and Management, 126(4),
251-260
29. Khemlani, L. (2006). “Building the future, Visual Estimating: Extending BIM to
Construction.” AECbytes
<http://www.aecbytes.com/buildingthefuture/2996/VisualEstimating.html>
30. Kymmell, M. (2008). “Building Information Modeling: Planning and Managing
Construction Projects with 4D CAD and Simulations.” McGraw Hill Construction,
New York

Page 74 of 88
31. Lee, G., Won, J.S., Ham, S. and Shin, Y. (2011). “Metrics for quantifying the
similarities and differences between IFC files.” Journal of Computing in Civil
Engineering©ASCE, 25(2),172-181.
32. Leite, F., Akcamete, A., Akinci, B., Atasoy, G. and Kizilta, S. (2010). “Analysis
of modeling effort and impact of different levels of detail in building information
models.” Automation in Construction, 20(5), 601-609.
33. Gallaher, M. P., O'Connor, A. C., Dettbarn, J. L., Jr. and Gilday, L. T. (2004).
“Cost Analysis of Inadequate Interoperability in the U.S. Capital Facilities
Industry” U.S. Department of Commerce, National Institute of Standards and
Technology, NIST GCR 04-867
34. Hwang, S. and Liu, L.Y. (2010). “BIM for Integration of Automated Real-Time
Project Control Systems.” Construction Research Congress 2010, 509-517
35. Mallasi, Z. (2006). “Dynamic quantification and analysis of the construction
workspace congestion utilizing 4D visualization” Automation in Construction,
15(5), 640 – 655
36. National Institute of Building Sciences (NIBS). (2007). “National Building
Information Modeling Standard.” NIBS, Version 1, Part 1
<http://www.wbdg.org/pdfs/NBIMSv1_p1.pdf>
37. Park, J.J., Kim, B., Kim, C.Y. and Kim, H.K. (2011). “3D/4D CAD application
for life-cycle facility management” Journal of Computing in Civil Engineering,
25(2), 129-138.
38. Refsnes Data. (2009). “XML Introduction: What is XML?”

Page 75 of 88
<http://www.w3schools.com/xml/xml_whatis.asp>
39. Rundell, R. (2006). “1-2-3 Revit: BIM and Cost Estimating.” Cadalyst,
<http://www.cadalyst.com/cad/building-design/1-2-3-revit-bim-and-cost-estimatin
g-part-1-3350>
40. Rundell, R. (2007). “BIM and Analysis for Sustainable Design (1-2-3 Revit
Tutorial.” Cadalyst,
<http://www.cadalyst.com/aec/bim-and-analysis-sustainable-design-1-2-3-revit-tu
torial-3549>
41. Rundell, R. (2008a). “BIM and Digital Fabrication (1-2-3 Revit Tutorial).”
Cadalyst,
<http://www.cadalyst.com/aec/bim-and-digital-fabrication-1-2-3-revit-tutorial-370
7>
42. Rundell, R. (2008b). “BIM and Searching for Product Content (1-2-3 Revit
Tutorial).” Cadalyst,
<http://www.cadalyst.com/aec/bim-and-searching-product-content-1-2-3-revit-tut
orial-3733>
43. Sabol, L. (2008). “Challenges in Cost Estimating with Building Information
Modeling.” Design+ConstructionStrategies,LLC, Washington, DC
<http://www.dcstrategies.net/files/2_sabol_cost_estimating.pdf>
44. Sawyer, T. and Grogan, T. (2002). “Finding the bottom line gets a gradual lift
from technology.” Engineering News Record (ENR),Aug 12, 2002

Page 76 of 88
45. Shen, Z. and Issa, R. (2010) “Quantitative evaluation of the BIM-assisted
construction detailed cost estimates.” Journal of Information Technology in
Construction, 15, 234-257.
46. Songer, A. D., Diekmann, J. E., Rasheed, K.A., and Hays, B. (2001).
"Construction schedule using 3-D CAD and walk-thru." Construction Innovation,
2001(1), 191-207.
47. Stumpf, A. and Brucker, B. (n.d.). “BIM Enables Early Design Energy Analysis”
<http://www.cecer.army.mil/td/tips/docs/BIM-EnergyAnalysis.pdf>
48. Tang, P. Huber, D., Akinci, B., Lipman, R. and Lytle, A. (2010). “Automatic
reconstruction of as-built building information models from laser-scanned point
clouds: A review of related techniques.” Automation in Construction, 19(7),
829-843.
49. Yong, N. W. Jr., Jones, S. A. and Berstein, H. M. (2008). “Building Information
Modeling (BIM): Transforming Design and Construction to Achieve Greater
Industry Productivity.” SmartMarket Report, McGraw-Hill Construction, New
York.
50. Young, N. W. Jr., Jones, S. A., Berstein, H. M., and Gudgel, J. E. (2009). “The
business value of BIM: Getting Building Information Modeling to the Bottom
Line Premier.” SmartMarket Report, McGraw-Hill Construction, New York.

Page 77 of 88
Appendices
Appendix 1 Floor plans of the Building Model
Entry Level Floor Plan

Page 78 of 88
Second & Third Floor Plans

Page 79 of 88
Appendix 2 RS Means

Page 80 of 88

Page 81 of 88
Appendix 3 Interface of Autodesk Quantity Takeoff™ 2011

Page 82 of 88
Appendix 4 Quantity Takeoff List
WBS Description Items Quantity1 Material Cost Labor Cost Equipment Cost Total Cost
Ceilings Compound Ceiling 600 x 600mm Grid 29,420.339 sq. ft $ 0.93 $ 0.53 $ - $ 1.46 $ 42,953.69 Compound Ceiling Furred Ceiling 9,924.188 sq. ft $ 1.97 $ 1.47 $ - $ 3.44 $ 34,139.21 Compound Ceiling Plain 330.144 sq. ft $ 1.37 $ 0.69 $ - $ 2.06 $ 680.10 Curtain Panels System Panel Glazed 23,768.516 sq. ft $ 29.00 $ 7.05 $ - $ 36.05 $ 856,855.01 System Panel Solid 3,759.340 sq. ft $ 20.50 $ 7.80 $ - $ 28.30 $ 106,389.34 Curtain Wall Mullions L Corner Mullion L Mullion 1 79.000 EA $ 20.00 $ 2.10 $ - $ 22.10 $ 1,745.90 Rectangular Mullion 30mm Square 120.000 EA $ 18.00 $ 2.20 $ - $ 20.20 $ 2,424.00 Rectangular Mullion 50 x 150mm 3,029.000 EA $ 19.00 $ 2.00 $ - $ 21.00 $ 63,609.00
Doors & Windows M_Curtain Wall Dbl Glass M_Curtain Wall Dbl Glass 6.000 EA $ 62.00 $ 8.05 $ - $ 70.05 $ 420.30
M_Curtain Wall Sgl Glass M_Curtain Wall Sgl Glass 11.000 EA $ 48.00 $ 7.45 $ - $ 55.45 $ 609.95
Doors\M_Double-Flush 1730 x 2134mm 1.000 EA $ 95.00 $ 43.00 $ - $ 138.00 $ 138.00
Doors\M_Double-Flush 1730 x 2134mm 20 Minute Rated 4.000 EA $ 95.00 $ 43.00 $ - $ 138.00 $ 552.00
Doors\M_Double-Flush 1830 x 2134mm 2.000 EA $ 95.00 $ 43.00 $ - $ 138.00 $ 276.00 Doors\M_Double-Glass 2 1830 x 2134mm 1.000 EA $ 885.00 $ 172.00 $ - $ 1,057.00 $ 1,057.00 Doors\M_Single-Flush 0915 x 2134mm 63.000 EA $ 65.00 $ 43.00 $ - $ 108.00 $ 6,804.00
Doors\M_Single-Flush 0915 x 2134mm 20 Minute Rated 6.000 EA $ 65.00 $ 43.00 $ - $ 108.00 $ 648.00
Doors\M_Single-Flush Vision 0915 x 2134mm 4.000 EA $ 65.00 $ 43.00 $ - $ 108.00 $ 432.00
Doors\M_Single-Flush-Dbl Acting 0915 x 2134mm 1.000 EA $ 65.00 $ 43.00 $ - $ 108.00 $ 108.00
Doors\M_Single-Glass 1 0915 x 2134mm 1.000 EA $ 65.00 $ 43.00 $ - $ 108.00 $ 108.00
Windows 0915 x 1220mm 24.000 EA $ 55.00 $ 45.00 $ - $ 100.00 $ 2,400.00
Floors Floor Metal Sunscreen 2,221.222 sq. ft $ 2.39 $ 0.45 $ 0.03 $ 2.87 $ 6,374.91
Floor Standard Timber-Wood Finish
2,576.873 sq. ft $ 3.74 $ 3.44 $ - $ 7.18 $ 18,501.94
Floor Concrete- 100mm 18,943.701 sq. ft $ 3.96 $ 4.28 $ - $ 8.24 $ 156,096.09
Floor Hollow Core Plank - Concrete Topping 33,436.501 sq. ft $ 2.95 $ 2.03 $ - $ 4.98 $ 166,513.77
Pads Pad Pad 1 1.000 EA $ 50.00 $ - $ - $ 50.00 $ 50.00 Railings Railing 900mm Pipe 207.221 ft $ 39.50 $ 9.80 $ 0.68 $ 49.98 $ 10,356.90

Page 83 of 88
WBS Description Items Quantity1 Material Cost Labor Cost Equipment
Cost Total Cost
Railing 900mm Pipe - Wall Monted 78.829 ft $ 44.00 $ 9.80 $ 0.68 $ 54.48 $ 4,294.58
Railing Guardrail - Pipe 406.468 ft $ 175.00 $ 13.10 $ - $ 188.10 $ 76,456.64
Roofs Basic Roof Concrete Deck - Tapered Insulation
20,158.938 cubic ft $ 1.16 $ 0.02 $ - $ 1.18 $ 23,787.55
Basic Roof Generic - 400mm 598.449 sq. ft $ 1.16 $ 3.50 $ - $ 4.66 $ 2,788.77
Basic Roof Generic - 75mm 765.249 sq. ft $ 1.16 $ 2.80 $ - $ 3.96 $ 3,030.39
Slab Edges Slab Edge Slab Edge 967.048 ft $ 0.41 $ 0.08 $ - $ 0.49 $ 473.85
Stairs Stair 150mm max riser 300mm tread 5.000 EA $ 700.00 $ 78.50 $ - $ 778.50 $ 3,892.50
Columns M_Concrete-Round-Column 300mm 1,530.999 cubic ft $ 17.40 $ 33.23 $ - $ 50.63 $ 77,514.49
M_Concrete-Round-Column 450mm 61.628 cubic ft $ 16.11 $ 13.33 $ - $ 29.44 $ 1,814.33
M_W-Wide Flange-Column W250X49.1 4.328 cubic ft $ 15.00 $ 15.00 $ - $ 30.00 $ 129.83
Structural Framing Curved Beam Curved Beam 3.611 cubic ft $ 2.02 $ 7.60 $ - $ 9.62 $ 34.74
M_K-Series Bar Joist-Angle Web 8K1 308.120 ft $ 3.20 $ 6.70 $ - $ 9.90 $ 3,050.39
M_Precast-Rectangular Beam
300 RB 600 963.111 ft $ 3.20 $ 6.80 $ - $ 10.00 $ 9,631.11
M_W-Wide Flange W310X28.3 54.056 ft $ 1.50 $ 6.80 $ - $ 8.30 $ 448.66
Walls Basic Wall Exterior - Insulation on Masonry 8,435.732 sq. ft $ 0.82 $ 0.62 $ - $ 1.44 $ 12,147.45
Basic Wall Generic - 200mm 4,087.402 sq. ft $ 2.62 $ 3.50 $ - $ 6.12 $ 25,014.90
Basic Wall Generic - 225mm Concrete
687.168 sq. ft $ 5.10 $ 4.68 $ - $ 9.78 $ 6,720.50
Basic Wall Interior - 138mm Partition (1-hr) 31,085.232 sq. ft $ 1.52 $ 1.91 $ - $ 3.43 $ 106,622.35
Basic Wall Parapet Wall 921.860 ft $ 4.56 $ 8.10 $ - $ 12.66 $ 11,670.75
Total Cost $ 1,849,766.88

Page 84 of 88
Appendix 5 Interface of Autodesk Revit Architecture™ 2011

Page 85 of 88
Appendix 6 Interfaces of Autodesk Navisworks™ 2011
Tasks are defined

Page 86 of 88
Gantt Chart View

Page 87 of 88
4D Simulation