DEX Publication ProjectOASIS PLCS TC Telecon

22 January 2008Trine Hansen

Page 2: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

2PLCS Inc. (c) 2002

Overall object

2 DEXs ready for publication 1 March 08 including Templates Reference data

Minimum sub-set of Info pages documents ready for publication by 1 March 08

Page 3: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

3PLCS Inc. (c) 2002

Project main activities

The following slides report status and progress for each main activity per 22 January 08

Page 4: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

4PLCS Inc. (c) 2002

Activity #1 - Management

Runs as planned Reminded OASIS (Mary McRae) about more feedback on our

publication format. Awaits final acceptance see next slide.

Page 5: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

5PLCS Inc. (c) 2002

Activity #1 – ManagementPublication format: Preliminary Feedback from OASIS

E-mail received 29 November 07 from Mary McRea The frame with the PLCS logo – that would need to go; basically the

“page” could just shift left The cover page information would need to be changed so that the title

has a real version number (Version 1.0, Version 6.3.2, whatever you like)

The stage (where you have “Developer Draft”) would need to be Committee Draft 01 (assuming this has been approved by the TC members). The date of approval would then appear below that.

The file name – OASIS_cover, while legal, is pretty nondescript – maybe dexlib-v1-index? (just a suggestion)

The appendices should most likely be on a separate page and just linked through the TOC so it doesn’t appear like an empty document.

I’ll send more details later, but I think you’re just about ready to go!

Page 6: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

6PLCS Inc. (c) 2002

Activity #2 - Core Team Activities

This activity runs according to plan High activity these days

Page 7: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

7PLCS Inc. (c) 2002

Activity #3 TOG Support Management

Identifies OASIS requirements for having the DEXs ready for publication: Completed (Ref. DEX Publication format)

Discuss procedures for handling request for external support such as training and consultancy services Not started. Low priority these days.

Requirements for tool support of future TOG management activities will also be identified Not started. Low priority these days.

Page 8: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

8PLCS Inc. (c) 2002

Activity #4 Check lists and Processes

Nothing new to report on Checklists: Completed checklists

Templates Checklists not completed:

Reference data – on-going DEX – on-going Capabilities (established, but has to be updated)

PLCS Information Pages in DEXLib Established but not completed

Critical for Aviation M DEX

Page 9: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

9PLCS Inc. (c) 2002

Activity #5 DEXLib infrastructure

• This activity runs according to plan• Consists of sub-activities

• Templates• Acceptance test plan• Longform generation• Part 28 generation• Business DEXs• Business Objects• Release environment• Usage reporting tool• General maintenance• Configuration change management• Configuration management of reference data• Publication as standards

Acceptance test 26 Nov 07

Page 10: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

10PLCS Inc. (c) 2002

Activity #6 - DEXlib Help section

All information required are available through DEXLib with a few exceptions (“How to read DEXLib”)

Need more systemising Need more quality assurance

Plan forward: Complete the structuring work Publication 1 March 08:

Additional budget for completion of Information pages was offered by FMV last week. Start date?

Page 11: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

11PLCS Inc. (c) 2002

Activity #7 – Develop, review and update templates

Funding for all template activities are identified A few templates still under development (for the Task

DEX) Still some templates under development – funding

available for completion. All these are related to the Task DEX

Most templates have been reviewed Updates according to review comments on-going

Page 12: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

12PLCS Inc. (c) 2002

Activity #8 – Develop, review and update capabilities

Phase 2 delivery

Page 13: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

13PLCS Inc. (c) 2002

Activity #9 - Develop and harmonize DEXs

Task DEXs Ready for publication 1 March 08 Harmonization of PLCS solutions finished Results

Aviation Maintenance DEX Awaits review checklist from Task DEX activities Ready for ballot 1 March 08

Page 14: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

14PLCS Inc. (c) 2002

Activity #10 - Review and update DEXs

Task DEXs Review – part of harmonization activities Formal review not performed – Checklist not completed

Aviation Maintenance DEX Business review performed Awaits checklist for formal OASIS review

Page 15: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

15PLCS Inc. (c) 2002

Activity #11 – Preparations for establishing Implementers Forum

Prepare a proposal for scope of Implementers Forum as input to next face-to-face meeting (action on Tor Arne Irgens, Torbjörn Holm and Nils Sandsmark )

Page 16: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

16PLCS Inc. (c) 2002

Activity #12 – Final report

Not started

Page 17: DEX Publication Project OASIS PLCS TC Telecon 22 January 2008 Trine Hansen

17PLCS Inc. (c) 2002

Summary: We are very close…..