dgc 13 01_20-21_cambridge house vric

38
1 CANADA’S NEXT INTERMEDIATE GOLD PRODUCER Cambridge House International Vancouver Resource Investment Conference January 20-21, 2013

Upload: detourgold

Post on 21-Jun-2015

791 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Dgc 13 01_20-21_cambridge house vric

1

CANADA’S NEXT INTERMEDIATE GOLD PRODUCER

Cambridge House International

Vancouver Resource Investment Conference

January 20-21, 2013

Page 2: Dgc 13 01_20-21_cambridge house vric

2

Forward Looking Information This presentation contains certain forward-looking information as defined in applicable securities laws (referred to herein as

“forward-looking statements”). Specifically, this presentation contains forward-looking statements regarding the reserve and

resource estimates, ore grade, expected mine life, anticipated gold production, gold recovery, cash operating costs and other

costs, capital costs, sensitivity to metal prices and other sensitivities, financial analysis of the project, commencement of

operations, potential expansion opportunities, and plans for organic growth. Forward-looking statements involve known and

unknown risks, uncertainties and other factors which are beyond Detour Gold’s ability to predict or control and may cause

Detour Gold’s actual results, performance or achievements to be materially different from any of its future results, performance

or achievements expressed or implied by forward-looking statements. These risks, uncertainties and other factors include, but

are not limited to, gold price volatility, changes in debt and equity markets, the uncertainties involved in interpreting geological

data, increases in costs, environmental compliance and changes in environmental legislation and regulation, interest rate and

exchange rate fluctuations, general economic conditions and other risks involved in the gold exploration and development

industry, as well as those risk factors discussed in the section entitled “Description of Business - Risk Factors” in Detour Gold’s

2011 AIF and in the continuous disclosure documents filed by Detour Gold on and available on SEDAR at www.sedar.com.

Such forward-looking statements are also based on a number of assumptions which may prove to be incorrect, including, but

not limited to, assumptions about the following: the supply and demand for gold, and the level and volatility of the price of gold;

the availability of financing for exploration and development activities; the estimated timeline for the development of the Detour

Lake gold project; the expected mine life; anticipated gold production; gold recovery; the development schedule; cash

operating costs and other costs; the financial analysis for the project; capital costs; sensitivity to metal prices and other

sensitivities; the accuracy of reserve and resource estimates and the assumptions on which the reserve and resource

estimates are based; the receipt of necessary permits; market competition; ongoing relations with employees and impacted

communities; and general business and economic conditions. Accordingly, readers should not place undue reliance on

forward-looking statements. The forward-looking statements contained herein are made as of the date hereof, or such other

date or dates specified in such statements. Detour Gold undertakes no obligation to update publicly or otherwise revise any

forward-looking statements contained herein whether as a result of new information or future events or otherwise, except as

may be required by law. If the Company does update one or more forward-looking statements, no inference should be drawn

that it will make additional updates with respect to those or other forward-looking statements.

Page 3: Dgc 13 01_20-21_cambridge house vric

3

The mineral reserve and resource estimates reported in this presentation were prepared in accordance with Canadian

National Instrument 43-101Standards of Disclosure for Mineral Projects (“NI 43-101”), as required by Canadian securities

regulatory authorities. For United States reporting purposes, the United States Securities and Exchange Commission (“SEC”)

applies different standards in order to classify mineralization as a reserve. In particular, while the terms “measured,” “indicated”

and “inferred” mineral resources are required pursuant to NI 43-101, the SEC does not recognize such terms. Canadian

standards differ significantly from the requirements of the SEC. Investors are cautioned not to assume that any part or all of

the mineral deposits in these categories constitute or will ever be converted into reserves. In addition, “inferred” mineral

resources have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal

feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category.

Under Canadian securities laws, issuers must not make any disclosure of results of an economic analysis that includes

inferred mineral resources, except in rare cases.

On September 4, 2012, Detour Gold announced an updated mine production plan for the Detour Lake project. The NI 43-101

compliant Technical Report for this update was filed on SEDAR on October 18, 2012. The following QPs participated in this

update: BBA Inc., under the direction of André Allaire, Eng., Vice-President, Markets – Mining and Metals and Patrice Live,

Eng., Mining Manager; SGS Canada Inc., under the direction of Michel Dagbert, Eng., Senior Geostatistician and Maxime

Dupéré, P.Geo., Senior Geologist; and AMEC Environment & Infrastructure, a Division of AMEC Americas Limited, David G.

Ritchie M.Eng., P.Eng, Senior Associate Geotechnical Engineer.

NI-43 101 Disclosure

Information Containing Estimates of Mineral Reserves and Resources

Page 4: Dgc 13 01_20-21_cambridge house vric

4

Focus on a world-class asset – Detour Lake

Canada’s largest pure gold play with 15.6 M oz in reserves

Gold processing initiated in January 2013

One of the best cash flow/share opportunities

Average annual gold production of 657,000 oz

Excellent organic growth potential (5 year plan)

Potential expansion of mill throughput

Invest in Detour Gold

Our Vision

Page 5: Dgc 13 01_20-21_cambridge house vric

5

Market cap: C$2.8 billion

Cash position: C$236 million

Major shareholders: Paulson & Co. 15%

Carmignac Gestion 5%

Detour Gold Mgmt <2%

Institutions total >90%

Note: Cash position and share data at December 31, 2012. An additional 0.3 M shares were issued in

January 2013 following partial exercise of the over-allotment option.

Share Capital

FULLY DILUTED

139.5 M

OPTIONS & FN SHARE

COMMITMENTS

8.9 M

CONVERTIBLE

NOTES

13.0 M

ISSUED AND

OUTSTANDING

117.6M

Page 6: Dgc 13 01_20-21_cambridge house vric

6

PRODUCTION 2013

Record Timing from “Discovery” to Projected Production

Detour Lake in 6 years

ACQUISITION /DISCOVERY

PRE-FEASIBILITY STUDY

FEASIBILITY STUDY & PERMITTING

DEVELOPMENT PRODUCTION

2007 2009 2010 2011-12 2013

Successful Focused Approach

Page 7: Dgc 13 01_20-21_cambridge house vric

7

H1 2013

First gold pour

Commissioning of second production line

Securing $90 million credit facility

20,000 m drilling program targeting high-grade gold mineralization

H2 2013

Declaring commercial production

Gold production target of +350,000 ounces for the year

Completing pre-feasibility study on Block A

Advancing evaluation of mine expansion scenarios

Revising block model for Detour Lake

2013 Objectives

Page 8: Dgc 13 01_20-21_cambridge house vric

8

1.0 g/t Au

0.5 - 1.0 g/t Au

<0.5 g/t Au

20,600E

16,500E

700 m

Open pit

@ 0.5 g/t cut-off

Detour Lake September 2012

Mine Plan(1)

Production Start Q1 2013

OP Reserves (M oz) 15.6

Mill throughput (tpd) 55,000

Strip Ratio (waste:ore) 3.7

Gold recoveries 91%

Average grade (g/t) 1.03

Estimated mine life (yrs) 21.5

Avg. Production (oz/yr) 657,000

Cash operating costs (C$/oz) $710

Total cash costs (C$/oz) $749

Initial Capex (C$ B)(2) 1.45

Detour Lake Profile

(1) Gold price assumptions: US$1,600/oz for 2013, US$1,500/oz for 2014, and US$1,400/oz for 2015.

(2) Revised to approx. C$1.5 B in news release dated November 8, 2012.

Page 9: Dgc 13 01_20-21_cambridge house vric

9

800

700

600

500

400

300

200

100

0

Gold Production (‘000 oz)

1.6

1.4

1.2

1.0

0.8

0.6

0.4

0.2

0

Grade (g/t Au)

Updated LOM Gold Production

Avg. 657,000 oz/yr

Page 10: Dgc 13 01_20-21_cambridge house vric

10

MAINTENANCE

LABOUR POWER

DIESEL

G&A

ROYALTY+

OTHER

(2% NSR)

CONSUMABLES

29%

22%

18% 12%

8%

5%

6%

Breakdown of 2013-14 TCC

Operating Costs (LOM) C$/t milled C$/t mined C$/oz

Mining costs 11.65 2.49 388

Processing cost 7.83 -- 260

G&A 1.86 -- 62

Cash operating costs 21.34 -- 710

Royalty (2%) and other 1.26 -- 42

Refining 0.12 -- 4

Silver credit (0.20) -- (7)

Total cash costs (TCC) 22.52 -- 749

A 10% change in:

Diesel or power costs = $9/oz change in TCC

Cdn$ FX rate = $63/oz in TCC

Updated LOM Operating Costs

Page 11: Dgc 13 01_20-21_cambridge house vric

11

Gold - US$1,200/oz (1)

F/X - $Cdn/$US = 1.00

Base Case (1)

US$ Billions Undiscounted (0%) 5.0%

Pre-tax cash flow 4.3 1.7

Net cash flow after tax 3.0 1.1

Pre-tax IRR 14.4%

49

Power Cdn $0.065/kwh

Diesel US$100/barrel (WTI)

Financial Analysis

Base Case Assumptions

1. Gold price US$1,600/oz for 2013, US$1,500/oz for 2014, and US$1,400/oz for 2015.

@ US$1,600/oz

US$ Billions Undiscounted (0%) 5.0%

Pre-tax cash flow 9.4 4.4

Net cash flow after tax 6.6 3.0

Pre-tax IRR 24.6%

12-12-23

Page 12: Dgc 13 01_20-21_cambridge house vric

12

DETOUR LAKE MINE START UP

Page 13: Dgc 13 01_20-21_cambridge house vric

13

2013 Forecast

Guidance

350,000 oz to 400,000 oz of gold

Total cash costs between C$800/oz and C$900/oz (on

commercial production of 200,000 oz to 250,000 oz sold)

Estimated LOM sustaining capital of C$1.2 B:

2013 = C$180 M (<$80 M in H1)

2014 = C$140 M

NOTE: Commercial production to be declared after 60

consecutive days of operating at >75% of throughput

(55,000 tpd x 75% = 41,250 tpd)

Page 14: Dgc 13 01_20-21_cambridge house vric

14

2012 Pre-Stripping Status

(Year-end 2012)

Overburden/Till 15.1 Mt

Waste 7.7 Mt

Low Grade (0.3-0.5 g/t) 1.1 Mt

Ore 2.2 Mt

Total 26.1 Mt

Mining Production

2.2 Mt ore inventory on ROMs and short-term stockpiles (reconciled

average grade of approx. 0.7 g/t) (till dilution on first bench)

Average mining rates of +115,000 tpd in December 2012

Mining operation on 24 hrs/day, 365 days/yr

Page 15: Dgc 13 01_20-21_cambridge house vric

15

PLANT SITE

CAMPBELL

PIT

APPROX. PIT SHELL

AT END OF LOM

CURRENT

PIT SHAPE

MINERALIZED

ZONE

Satellite image dated July 2012

NORTH WASTE

DUMP

Mining Production

Page 16: Dgc 13 01_20-21_cambridge house vric

16

12-10-22

Detour Lake Open Pit Mine

Page 17: Dgc 13 01_20-21_cambridge house vric

17

DETOUR LAKE SITE

Page 18: Dgc 13 01_20-21_cambridge house vric

18

Overview Detour Lake Facilities

SECONDARY

CRUSHERS

GEODESIC

DOME

STOCKPILE

RECLAIM

PRIMARY

CRUSHER

12-10-22

Page 19: Dgc 13 01_20-21_cambridge house vric

19

35 m to surface

Gyro is

9 m high 12-10-02

Primary Crusher (100,000 tpd capacity)

Page 20: Dgc 13 01_20-21_cambridge house vric

20

Stockpile Reclaim (2 days capacity)

12-12-02

12-12-23

12-12-23

Page 21: Dgc 13 01_20-21_cambridge house vric

21

Processing Plant

Conventional gravity and CIP plant

55,000 tpd (=92% availability of 60,000 tpd capacity)

2 parallel lines (each with 1 secondary cone crusher + 1 SAG & 1 ball mill)

Estimated gravity recovery: 30-40%

Estimated overall gold recovery: 91.0%

Leach time 29 hours; leach feed size 80% passing 95 μm

12-12-23

Page 22: Dgc 13 01_20-21_cambridge house vric

22

Gyratory

crusher:

60” x 113”

90,000 tpd

SAG mills:

2 X 36’ x 20’, 15MW

55,000 tpd To

leaching

circuit

To

gravity

circuit

Secondary crushers:

2 X XL-1100

67,000 tpd

Pebble crushers:

2 X XL-1100

73,000 tpd

Circ. load

28 % Circ. load

250 % From

gravity

circuit

Stockpile

12 h live capacity

Ball mills:

2 X 26’ x 40’6’’, 15MW

55,000 tpd

Leach circuit:

55,000 tpd + 15% contingency in piping capacity

Simple Process Plant @ 92% Availability

Page 23: Dgc 13 01_20-21_cambridge house vric

23

Tailings Management Area (TMA)

12-10-22

High environmental standard design

3-cell containment system for natural degradation

2013: Cell #1 ready for production

2014: Building additional capacity in Cell #1 and footprint for Cell #2

Page 24: Dgc 13 01_20-21_cambridge house vric

24

FRONT LINE

81%

PROFESSIONAL

19%

NORTHERN

ONTARIO

43%

COCHRANE

25%

COCHRANE

AREA

26%

REST OF

ONTARIO

3%

2%

OTHER

* Excludes Corporate office.

DGC Workforce: Hiring Local First

DIVISION OF LABOUR

WORKFORCE ORIGIN

• Professional includes: MGMT, Eng., Geo., Supt.

• Front Line includes:

Operators, Admin, Support

423 employees at year-end* (25% are Aboriginal)

Continuing focus on hiring local and regional

Work rotation: 1 week in/out

Modern camp facility with 400

en-suite rooms

Page 25: Dgc 13 01_20-21_cambridge house vric

25

PLANNING FOR ORGANIC GROWTH

Under-Explored Greenstone Belt

Page 26: Dgc 13 01_20-21_cambridge house vric

26

• Two main gold structures with total strike length of >80km

• Continue focus on Detour Lake deposit extension (northern

structure i.e. Block A)

• Test targets on structure south of Detour Lake

Grow reserve base to +20 M oz (@ US$850/oz)

Increase mill throughput to above 75,000 tpd for gold production

output of +800,000 oz/yr

Find high-grade ore near-surface within trucking distance to

supplement mill

Planning for Organic Growth

5 Year Plan for Successful Organic Growth

Large prospective land position of approx. 566 km2

Future objectives

Page 27: Dgc 13 01_20-21_cambridge house vric

27

Resource Growth Exceeding 750% Since IPO

Date Accumulative DGC Drilling

Resources/Reserves (M oz) Inferred

2007-12 50,000m

2008-06 123,000m

2012-01 523,000m $850/oz 15.6

2011-01 430,000m $850/oz 14.9

2010-06 334,000m $850/oz 11.4

2009-09 249,000m 8.8

2005-05 Estimated by Pelangio

2006-09 DGC due diligence

10M 20M 30M

M&I 2P

Successful Growth of Resources

Page 28: Dgc 13 01_20-21_cambridge house vric

28

*Not updated with TWD Dec. 30th PR. On Dec. 1, 2011, Detour Gold announced the acquisition of TWD.

Block A

Pre-feasibility

Priority #1 – Block A Target

Block A pre-feasibility study by year-end 2013

Evaluate potential expansion options

Page 29: Dgc 13 01_20-21_cambridge house vric

29

2012 DH

2012 extension DH

Historical DH

Block A near-surface resource

Detour Lake

2011 year-end reserves = 15.6 M oz

Priority #1 – Block A Target

DH included in 2011 year-end reserves

DH not included in 2011 year-end reserves

Page 30: Dgc 13 01_20-21_cambridge house vric

30

Existing DDH Gold occurrence (OGS)

DDH intersection >1g/2m DDH intersection >1g/10m

*Note: Excludes drilling around Detour Lake and M zone (Block A).

20,000 m in H1 2013

MMI Survey Coverage

MMI Au Anomaly

15.6 M oz in Reserves

Priority #2 – South Structure

Page 31: Dgc 13 01_20-21_cambridge house vric

31

Focus on a world-class asset – Detour Lake

Canada’s largest pure gold play with 15.6 M oz in reserves

Gold processing initiated in January 2013

One of the best cash flow/share opportunities

Average annual gold production of 657,000 oz

Excellent organic growth potential (5 year plan)

Potential expansion of mill throughput

Invest in Detour Gold

Our Vision

Page 32: Dgc 13 01_20-21_cambridge house vric

32

ADDITIONAL INFORMATION

Page 33: Dgc 13 01_20-21_cambridge house vric

33

Detour Lake Profile

Detour Lake January 2011

Update (2)

September 2012

Mine Plan(3)

Gold price (US$/oz) (1) 850 1,200

Foreign exchange rate (US$/Cdn$) 1.10 1.00

Assumptions Fuel price (US$/barrel) 80 100

Income/mining tax rate (%) 25/10 25/10

Net Smelter Royalty (%) 2 2

Ore milled (Mt) 449.6 470.0

Waste mined (Mt) (4) 1,654 1,734

Mine Strip ratio (waste:ore) 3.9 3.7

Parameters Average gold grade (g/t) 1.03 1.03

Total contained gold (M oz) 14.9 15.6

Estimated gold recovery (%) 91.0 91.0

Total recovered gold (M oz) 13.5 14.1

Mine life (years) 21 21.5

Average annual gold production (oz) 657,000 657,000

1. US$1,600/oz for 2013, US$1,500/oz for 2014, and US$1,400/oz for 2015.

2. Press release Jan. 31, 2011 with Technical Report dated Mar. 15, 2011.

3. Press release Sept. 4, 2012 with Technical Report dated Oct. 18, 2012.

4. Includes low-grade stockpile.

Page 34: Dgc 13 01_20-21_cambridge house vric

34

800

700

600

500

400

300

200

100

0

Gold Production (‘000 oz)

900

850

800

750

700

650

600

550

500

Total Cash Costs (C$/oz)

Gold Production/Cost Profile

Note: Excludes stripping adjustments.

Avg. C$749/oz

Page 35: Dgc 13 01_20-21_cambridge house vric

35

@ US$850/oz Tonnes

(millions)

Grade

(g/t)

Contained Gold

(‘000 oz)

Reserves (1)

Proven 101.6 1.29 4,222

Probable 368.4 0.96 11,351

P&P 470.0 1.03 15,573

Resources (2)

Measured 124.5 1.36 5,424

Indicated 554.3 1.00 17,836

M&I 678.8 1.07 23,261

Inferred 208.5 0.86 5,785

1. After a 95% mining recovery rate; Mining dilution factor of 15.5%.

2. Inclusive of mineral reserves.

Detour Lake Reserves & Resources

As at December 31, 2011

Page 36: Dgc 13 01_20-21_cambridge house vric

36

Gerald Panneton Founder, President & CEO

Director

Michael Kenyon Executive Chairman

Paul Martin CFO

Pierre Beaudoin Sr VP Capital Projects

Julie Galloway Sr VP General Counsel &

Corporate Secretary

Derek Teevan Sr VP External &

Aboriginal Affairs

Pat Donovan VP Corporate Development

James Mavor VP Finance

Rachel Pineault VP HR & Northern Affairs

James Robertson VP Environment &

Sustainability

Eric Josipovic Controller

Drew Anwyll Director of Operations

Andrew Croal Director Technical Services

Laurie Gaborit Director Investor Relations

Jean-Francois Metail Director Reserves and Resources

Greg Miazga Director Construction & Engineering

Bill Snelling Director Corporate Systems & Controls

Christian Brousseau Project Manager

Patrik Gillerstedt Mine Manager

Peter Crossgrove

Louis Dionne

Robert E. Doyle

Ingrid Hibbard

Jonathan Rubenstein

Graham Wozniak

Michael Kenyon

Alex G. Morrison

Gerald Panneton

Management & Directors

Management

Directors

Page 37: Dgc 13 01_20-21_cambridge house vric

37

Analyst Coverage Initiating

Research (y/m/d)

Firm Analyst

Target

07.06.11 Haywood Kerry Smith $42.25

07.07.09 Paradigm Don Blyth/Don MacLean $38.00

07.08.07 Raymond James Brad Humphrey $38.00

07.11.26 National Bank Steve Parsons $38.00

07.12.20 Macquarie Mike Siperco $38.50

08.01.14 Canaccord Steven Butler $34.50

08.07.14 TD Dan Earle $39.00

08.09.04 RBC Dan Rollins $32.00

08.11.06 BMO NB John Hayes $37.00

09.06.01 NCP Northland Catherine Gignac* $40.00

09.06.17 Laurentian Eric Lemieux Under review

10.04.27 UBS Securities Chris Lichtenheldt $35.00

10.05.19 CIBC Asset Management Barry Cooper $40.00

10.06.22 Dahlman Rose Adam Graf Hold

10.07.22 Credit Suisse Anita Soni $42.00

11.07.15 Bank of America Merrill Lynch Mike Parkin $33.00

Updated 13.01.09

Page 38: Dgc 13 01_20-21_cambridge house vric

38

Gerald Panneton President & CEO

Email: [email protected]

Phone: 416.304.0800

Laurie Gaborit Director Investor Relations

Email: [email protected]

Phone: 416.304.0800

www.detourgold.com

Contact Information