dgc 13 04_16-18_european gold forum
TRANSCRIPT
1
CANADA’S NEXT INTERMEDIATE GOLD PRODUCER
European Gold Forum 2013, Zurich April 16-18, 2013
2
Forward Looking Information This presentation contains certain forward-looking information as defined in applicable securities laws (referred to herein as “forward-looking statements”). Specifically, this presentation contains forward-looking statements regarding the commencement of commercial production at the Detour Lake mine, 2013 guidance for gold production and total cash costs, the completion of a pre-feasibility study on Block A, reserve and resource estimates, ore grade, expected mine life, average annual gold production, gold recovery, cash operating costs and other costs , sensitivity to metal prices and other sensitivities, ramp-up of operations, mining rates reaching approximately 200,000 tpd by year-end 2013, future operating plans, potential expansion opportunities, and plans for organic growth which includes growing mineral reserves to more than 20 million ounces. Forward-looking statements involve known and unknown risks, uncertainties and other factors which are beyond Detour Gold’s ability to predict or control and may cause Detour Gold’s actual results, performance or achievements to be materially different from any of its future results, performance or achievements expressed or implied by forward-looking statements. These risks, uncertainties and other factors include, but are not limited to, gold price volatility, changes in debt and equity markets, the uncertainties involved in interpreting geological data, increases in costs, environmental compliance and changes in environmental legislation and regulation, interest rate and exchange rate fluctuations, general economic conditions and other risks involved in the gold exploration and development industry, as well as those risk factors discussed in the section entitled “Description of Business - Risk Factors” in Detour Gold’s 2012 AIF and in the continuous disclosure documents filed by Detour Gold on and available on SEDAR at www.sedar.com. Such forward-looking statements are also based on a number of assumptions which may prove to be incorrect, including, but not limited to, assumptions about the following: the availability of financing for exploration and development activities; operating and capital costs; the Company’s ability to attract and retain skilled staff; the mine development schedule; sensitivity to metal prices and other sensitivities; the supply and demand for, and the level and volatility of the price of, gold; timing of the receipt of regulatory and governmental approvals for development projects and other operations; the supply and availability of consumables and services; the exchange rates of the Canadian dollar to the U.S. dollar; energy and fuel costs; the accuracy of reserve and resource estimates and the assumptions on which the reserve and resource estimates are based; market competition; ongoing relations with employees and impacted communities and general business and economic conditions. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements contained herein are made as of the date hereof, or such other date or dates specified in such statements. Detour Gold undertakes no obligation to update publicly or otherwise revise any forward-looking statements contained herein whether as a result of new information or future events or otherwise, except as may be required by law. If the Company does update one or more forward-looking statements, no inference should be drawn that it will make additional updates with respect to those or other forward-looking statements.
3
The mineral reserve and resource estimates reported in this presentation were prepared in accordance with Canadian National Instrument 43-101Standards of Disclosure for Mineral Projects (“NI 43-101”), as required by Canadian securities regulatory authorities. For United States reporting purposes, the United States Securities and Exchange Commission (“SEC”) applies different standards in order to classify mineralization as a reserve. In particular, while the terms “measured,” “indicated” and “inferred” mineral resources are required pursuant to NI 43-101, the SEC does not recognize such terms. Canadian standards differ significantly from the requirements of the SEC. Investors are cautioned not to assume that any part or all of the mineral deposits in these categories constitute or will ever be converted into reserves. In addition, “inferred” mineral resources have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian securities laws, issuers must not make any disclosure of results of an economic analysis that includes inferred mineral resources, except in rare cases. On September 4, 2012, Detour Gold announced an updated mine production plan for the Detour Lake project. The NI 43-101 compliant Technical Report for this update was filed on SEDAR on October 18, 2012. The following QPs participated in this update: BBA Inc., under the direction of André Allaire, Eng., Vice-President, Markets – Mining and Metals and Patrice Live, Eng., Mining Manager; SGS Canada Inc., under the direction of Michel Dagbert, Eng., Senior Geostatistician and Maxime Dupéré, P.Geo., Senior Geologist; and AMEC Environment & Infrastructure, a Division of AMEC Americas Limited, David G. Ritchie M.Eng., P.Eng, Senior Associate Geotechnical Engineer.
NI-43 101 Disclosure Information Containing Estimates of Mineral Reserves and Resources
4
Focus and Discipline Leverage to gold price Optimize operation Organic growth Safe jurisdiction Per Share Value Creation Free cash flow growth Limit share dilution Return on capital
Invest in Detour Gold Our Vision
5
Note: Cash position and share data at March 31, 2013.
Share Capital
FULLY DILUTED 139.8 M
OPTIONS & FN SHARE COMMITMENTS
8.9 M CONVERTIBLE
NOTES 13.0 M
ISSUED AND OUTSTANDING
117.9M C$2.0 B
C$170 M
TOP SHAREHOLDERS
MARKET CAP
CASH POSITION
PAULSON & CO: 15% INSTITUTIONS TOTAL: >80%
6
Focused on One Core Asset Detour Lake - Ontario, Canada Low-risk, mining friendly
jurisdiction Large prospective land
package of 566 km2 on Abitibi Greenstone Belt In production: Detour Lake
open pit mine 15.6 M oz in reserves
In progress: Block A pre-feasibility study
Exploration: Targeting high-grade mineralization
7
PRODUCTION 2013
Record Timing from “Discovery” to Production
Detour Lake in 6 years
ACQUISITION /DISCOVERY
PRE-FEASIBILITY STUDY
FEASIBILITY STUDY & PERMITTING
DEVELOPMENT PRODUCTION
2007 2009 2010 2011-12 2013
From Core to Pour
8
Detour Lake Mine in 6 Years Consistently Delivered Results Focused on execution Built strong management team with track record of success Increased resource growth by 750% since acquisition at <$5/oz Completed positive economic studies over a 2-year period Raised over $2 billion while limiting share dilution Completed mine construction within time frame (27 months) Obtained strong community and Aboriginal support
9
H1 2013 First gold pour in February Securing $90 million credit facility Commissioning of second production line 25,000 m drilling program targeting high-grade gold mineralization H2 2013 Achieving commercial production Gold production target of max. 350,000 ounces for the year Completing pre-feasibility study on Block A Advancing evaluation of mine expansion scenarios Year-end mineral resources/reserves update
2013 Objectives
10
Focus on health and safety of our employees, the well-being of our community and the protection of the natural environment Hiring in the region, giving priority to local Aboriginal communities:
95% of workforce from region 28% are Aboriginals Scholarship and job training
Supporting local communities Business opportunities Participation in municipal development Corporate philanthropy
NORTHERN ONTARIO
44%
COCHRANE 25%
COCHRANE AREA
26% REST OF ONTARIO
3%
2% OTHER
Corporate Responsibility
WORKFORCE ORIGIN
11
Production Start 02/ 2013
OP reserves (M oz) 15.6
Mill throughput (tpd) 55,000
Strip ratio (waste:ore) 3.7
Gold recoveries 91%
Average grade (g/t) 1.03
Estimated mine life (yrs) 21.5
Avg. production (oz/yr) 657,000
Initial capex (C$ B) 1.5
Sustaining capex (C$ B) 1.2
Detour Lake Mine
12
MAINTENANCE
LABOUR POWER
DIESEL
G&A
ROYALTY+ OTHER
(2% NSR)
CONSUMABLES 29%
22%
18% 12%
8% 5%
6%
Breakdown of 2013-14 TCC Operating Costs (LOM) C$/t milled C$/t mined C$/oz
Mining costs 11.65 2.49 388
Processing cost 7.83 -- 260
G&A 1.86 -- 62
Cash operating costs 21.34 -- 710 Royalty (2%) and other 1.26 -- 42
Refining 0.12 -- 4
Silver credit (0.20) -- (7)
Total cash costs (TCC) 22.52 -- 749
A 10% change in: Diesel or power costs = $9/oz change in TCC Cdn$ FX rate = $63/oz in TCC
Projected LOM Operating Costs
13
2013 Ramp Up Mining Current stockpiles:
2.3 Mt grading 0.7 g/t 1.6 Mt grading 0.4 g/t
Mining rates to ~200,000 tpd by year-end
Mining fleet of 20 haul trucks & 4 shovels
Processing Plant 55,000 tpd conventional gravity and
CIP processing plant with two production lines
Line 1 & 2 in operation Optimize and improve efficiencies
14
Q1 2013
Ore tonnes mined (Mt) 1.29
Tonnes milled (Mt) 1.02
Mill grade (g/t Au) 0.64
Recovery (%) 80
Availability (%) (1) 66
Gold produced (oz) (2) 16,841
Q1 Operation Statistics
(1) Quarterly period starting on January 12 with first production line and on March 9 with second production line. Availability averaged 70% for both production lines in the last week of March.
(2) 7,300 oz poured and 9,541 oz of plant inventory.
15
2013 Guidance Guidance to be revised in Q2 Total gold production: max. 350,000 oz Post commercial production (Q3):
Total cash costs of C$800/oz to C$900/oz based on 200,000 oz to 250,000 oz sold
Sustaining capital: C$180 M (<$80 M in H1)
Commercial production target in Q3
NOTE: Commercial production to be declared after 60 consecutive days of operating at >75% of throughput (55,000 tpd x 75% = 41,250 tpd)
16
PLANT SITE
CAMPBELL PIT
APPROX. PIT SHELL AT END OF LOM
CURRENT PIT SHAPE
MINERALIZED ZONE
Satellite image dated July 2012
NORTH WASTE DUMP
Mining Production
17
Bench 6252m
Bench 6240m
Grade Control DDH Block model 40x40m drill spacing RC GC 20X10m & 10X10m drill spacing
Block Gold Grade (g/t)
< 0.3 < 0.5 < 0.8 < 2.0 > = 2.0
18
Conventional Milling Process
Primary Crusher 90,000 tpd
Mine Trucks
Secondary Crushers (2) 67,000 tpd Pebble Crushers (2) 73,000 tpd
To Market
Gold Doré Bars
Gold Furnace
Gold Electrowinning
Carbon Stripping
To Gravity Circuit
To Gravity Circuit
Stockpile SAG Mills (2) 55,000 tpd
Ball Mills (2) 55,000 tpd
CIP
Leach
Tailings
19
Development Grow reserve base to +20 M oz
Complete Block A pre-feasibility study in 2013-14
Evaluate Detour Lake expansion Exploration Large prospective land position of
566 km2
Tested gold targets on structures south of Detour Lake: 25,000 m completed (results pending)
Inferred M&I P&P
10M oz
20M oz
30M oz
15.6 14.9
11.4
8.8
Organic Growth Opportunities
20
Development – Block A
Block A pre-feasibility study underway Evaluate potential expansion options
21 *Note: Excludes drilling around Detour Lake and M zone (Block A).
25,000 m in 2013
15.6 M oz in Reserves
Exploration – South Structure
22
Focus and Discipline Leverage to gold price Optimize operation Organic growth Safe jurisdiction Per Share Value Creation Free cash flow growth Limit share dilution Return on capital
Invest in Detour Gold Our Vision
23
ADDITIONAL INFORMATION
24
Source: Bloomberg, company filings and select Street Research Note: Market data updated to March 28, 2013 1. Shown based on gold only reserves on an attributable basis. 2. Calculated as US$1,000 divided by fully diluted market capitalization multiplied by total attributable gold only reserves.
Current Valuation vs. Peers Consensus P/NAV Share of Au Reserves per
$1000(2) EV / Reserves(1)
1.3
1.8
3.9
4.2
4.4
4.6
6.8
7.9
8.0
13.8
Alamos
New Gold
Osisko
IAMGOLD
AuRico
Alacer
Detour
Centerra
Allied Nevada
African Barrick
0.37x
0.46x
0.48x
0.61x
0.62x
0.73x
0.79x
0.80x
0.89x
0.92x
Centerra
Allied Nevada
African Barrick
Detour
IAMGOLD
Osisko
AuRico
Alamos
New Gold
Alacer
$47
$100
$140
$149
$169
$198
$209
$276
$540
$585
African Barrick
Centerra
Allied Nevada
Alacer
Detour
IAMGOLD
AuRico
Osisko
Alamos
New Gold
25
Detour Lake Profile Detour Lake Sept. 2012
Mine Plan(3)
Gold price (US$/oz) (1) 1,200
Foreign exchange rate (US$/Cdn$) 1.00
Assumptions Fuel price (US$/barrel) 100
Income/mining tax rate (%) 25/10
Net Smelter Royalty (%) 2
Ore milled (Mt) 470.0
Waste mined (Mt) (4) 1,734
Mine Strip ratio (waste:ore) 3.7
Parameters Avg. gold grade (g/t) 1.03
Total contained gold (M oz) 15.6
Estimated gold recovery (%) 91.0
Total recovered gold (M oz) 14.1
Mine life (years) 21.5
Avg. annual gold production (oz) 657,000
1. US$1,600/oz for 2013, US$1,500/oz for 2014, and US$1,400/oz for 2015. 2. Press release Jan. 31, 2011 with Technical Report dated Mar. 15, 2011. 3. Press release Sept. 4, 2012 with Technical Report dated Oct. 18, 2012. 4. Includes low-grade stockpile.
1.0 g/t Au
0.5 - 1.0 g/t Au
<0.5 g/t Au
20,600E
16,500E
700 m
Open pit @ 0.5 g/t cut-off
26
800
700
600
500
400
300
200
100
0
Gold Production (‘000 oz)
900
850
800
750
700
650
600
550
500
Total Cash Costs (C$/oz)
Gold Production/Cost/Grade Profile
Note: Excludes stripping adjustments.
Avg. C$749/oz
1.6
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0
Grade (g/t Au) Avg. 657,000 oz/yr
27
@ US$850/oz Tonnes (millions)
Grade (g/t)
Contained Gold (‘000 oz)
Reserves (1)
Proven 101.6 1.29 4,222
Probable 368.4 0.96 11,351
P&P 470.0 1.03 15,573 Resources (2)
Measured 124.5 1.36 5,424
Indicated 554.3 1.00 17,836
M&I 678.8 1.07 23,261 Inferred 208.5 0.86 5,785
1. After a 95% mining recovery rate; Mining dilution factor of 15.5%. 2. Inclusive of mineral reserves.
Detour Lake Reserves & Resources As at December 31, 2011
28
2012 completed DH Historical DH
Block A near-surface resource
Detour Lake 2011 year-end reserves = 15.6 M oz DH included in 2011 year-end
reserves DH not included in 2011 year-end reserves
Detour Lake & Block A
29
Gerald Panneton Founder, President & CEO Director Michael Kenyon Executive Chairman Paul Martin CFO Pierre Beaudoin Chief Operating Officer Julie Galloway Sr VP General Counsel & Corporate Secretary Derek Teevan Sr VP External & Aboriginal Affairs
Pat Donovan VP Corporate Development James Mavor VP Finance Rachel Pineault VP HR & Northern Affairs James Robertson VP Environment & Sustainability Eric Josipovic Controller Drew Anwyll Director of Operations
Andrew Croal Director Technical Services Laurie Gaborit Director Investor Relations Jean-Francois Metail Director Reserves and Resources Greg Miazga Director Construction & Engineering Bill Snelling Director Corporate Systems & Controls Christian Brousseau Project Manager Patrik Gillerstedt Mine Manager
Peter Crossgrove Louis Dionne Robert E. Doyle Andre Falzon
Gerald Panneton Jonathan Rubenstein Graham Wozniak
Ingrid Hibbard Michael Kenyon Alex G. Morrison
Management & Directors Management
Directors
30
Gerald Panneton President & CEO Email: [email protected] Phone: 416.304.0800
Laurie Gaborit Director Investor Relations Email: [email protected] Phone: 416.304.0800
www.detourgold.com
Contact Information