Page 1: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

Digital Survey Plans Review

Final Report 17 December 2019 (v4.0)

Page 2: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P2

Grosvenor Performance Group welcomes any feedback on the content or methodology of this

review as well as any suggestions for future improvement.

Page 3: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P3

Executive Summary

Almost half of the total outlay for a new house and land package in a greenfield estate in

Sydney is estimated to be due to regulatory costs and statutory taxes1. The process of land

development is also extremely complex and with limited transparency for end users.

Digitalisation throughout the development process presents many opportunities to address

these issues and improve outcomes for customers. Initiatives such as eConveyancing and

ePlanning have already shown the potential for increasing speed, efficiency and transparency.

Efforts have been made to digitise the process of survey plan creation through to registration

over the past decade, primarily through online lodgement of plans through the ePlan portal and

the introduction of the LandXML (LXML) smart digital file format. Uptake for this format has

remained low however, with only approximately 5% of plans lodged in LXML.

The NSW Department of Customer Service (DCS) engaged Grosvenor to conduct a review of

digital survey plans; the three main objectives of the review were to:

> explore and explain why uptake of digital plans has remained low

> identify what opportunities exist for digitalisation of plans

> provide recommendations on the best way to progress digital plans such that benefits to

surveyors, Government and other plan users are maximised.

It is recognised by most stakeholders that the initial attempt to introduce LXML did not

sufficiently consider the views of the surveying industry. The Government and NSW Land

Registry Services (LRS) are keen to ensure that any future changes have the input and support

of the industry and, therefore, a major part of this review was engaging closely with surveyors to

understand their sentiments relating to digitalisation. The review was primarily informed by

consultations with surveyors, as well as representatives from many other stakeholders involved

in the plan registration process, including councils and utilities, LRS, developers, software

vendors and NSW Government entities such as DCS Spatial Services, the Office of the

Registrar General, Transport for NSW and the Department of Planning, Industry and

Environment. Approaches in other jurisdictions and from eConveyancing were also examined to

identify applicable lessons for digital survey plans in NSW.

1 The CIE, Summary and methodology of the final research report: Taxation of the Housing Sector, available at: https://hia.com.au/-/media/HIA-Website/Files/IndustryBusiness/Economic/research/cie-taxation-of-the-housing-sector.ashx?la=en (accessed 10/12/2019)

Page 4: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P4

Engagement throughout the review from all stakeholder groups was high and there is a lot of

support for digitalisation in various forms. Ultimately however, in the absence of mandating it,

uptake of LXML has remained low for the following reasons:

> there are insufficient incentives for surveyors to adopt LXML as inherent benefits (such as

improved quality control or efficiency in plan preparation through utilising existing LXML

plans) are not readily available or apparent. Many surveyors reported that they do not know

how to access existing LXML files or who to request them from

> poor rendering of LXML files results in surveyors having to create both a TIFF image and a

LXML file; this requires additional effort in most software packages and clients are typically

unwilling to pay for this, except where it may speed up registration (particularly for larger

developments with high holding costs)

> there is a perception by some surveyors that LXML may be moving away from the current

monument-based approach and favours data over decisions; likewise, there is resistance to

the concept of the data being the source of truth instead of the representation on the plan

image

> benefits from digitalisation more broadly (such as approvals and associated documents) are

disaggregated across a complex array of stakeholders and insufficient for any single group

to act on in the absence of state-wide leadership and coordination.

Whilst the opportunities for digitalisation vary somewhat by user group, overall there are three

key consistent themes, namely: improving efficiency, accuracy and customer service. The most

salient prospects to achieve these include the following:

> pre-populated documents (with automated validation) and easily ingestible metadata

– this will reduce manual data entry requirements for all stakeholders and improve accuracy

through minimising typographic errors

> digital signatures and a portal for managing associated documents – this will reduce

time currently spent on administering physical ‘wet’ signatures and enable approvals to

occur in parallel, resulting in increased speed of registration and improved transparency of

process for customers

> smart plan data for automated validations and examination – this will facilitate improved

accuracy, more efficient examination and faster registration (through lower requisitions); in

turn reducing the risk of professional indemnity and Torrens Assurance Fund claims, as well

as improving the accuracy and usefulness of the NSW Spatial Cadastre. Smart plan data

may also enhance survey practice by including additional boundary evidence (such as

photos) and should be easily accessible for surveyors to assist in plan preparation.

Ultimately these will all contribute to faster land access and reduced costs for homebuyers.

Page 5: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P5

To pursue these prospects barriers need to be overcome, including residual industry resistance

from the initial roll out of LXML and a lack of clear ownership for solution design and

implementation. A four-step high-level roadmap for change will ensure that these issues are

resolved and help progress digitalisation; the four steps are as follows.

1 – Confirm outcomes: the overarching aim of the digital survey plans reform should be

agreed upon and articulated to guide design and implementation and inform communications

with stakeholders, particularly surveyors who need to be convinced of the benefit of digital

plans. This will also prevent the perception of digital for digitals sake and ensure efficiency,

accuracy and customer service (or other agreed outcomes) remain central tenets for any

change initiatives.

2 – Agree governance: clear roles, responsibilities and accountabilities should be established;

this would likely include LRS for solution design and implementation and DCS for governance

and policy as well as stakeholder engagement and communications.

3 – Design solutions: technical solutions should be designed for three main areas, deposited

plans, strata plans and approvals and associated documents. The designs should address the

current issues and opportunities raised by stakeholders and be cognisant of other programs

such as ‘Re-imagining plans’, ePlanning and Cadastre 2034. An assessment framework (which

considers impact alignment to user needs and ease of implementation) has been proposed

within this report to assist in solution design and evaluation. The final designs should be

compared and prioritised prior to implementation. This may include a multi-stream approach

where solutions for simpler elements are implemented while more complex design remains

ongoing – however it is likely that the interdependencies between elements will require a

somewhat unified approach. Consultation and continued engagement with surveyors and other

industry stakeholders should be maintained throughout the solution design phase.

4 – Implement solutions: Once the technical solutions have been proposed and the

assessment framework has been used to understand their impact and feasibility, changes

should be prioritised for implementation. Equity of change should be considered to ensure

disadvantages to stakeholder groups (e.g. rural vs metro, big vs small firms, large greenfield

development vs two-lot subdivision) are minimised where possible. Likewise, change

management elements must be adopted including continued stakeholder engagement, co-

design, pilot-testing and staged implementation, as well as support for users with high barriers

to uptake. Mandating and legislative changes may be required, depending on the technical

solution. In the case of mandating, an appropriate notice period should be given with the timing

designed with, and agreed upon, by industry representatives.

Page 6: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P6

Table of Contents

Executive Summary ............................................................................................................................... 3

1 Introduction ............................................................................................................................. 7 1.1 Objectives ................................................................................................................................. 7 1.2 Report structure ........................................................................................................................ 8 1.3 Background............................................................................................................................... 9 1.4 Approach ................................................................................................................................ 16

2 Findings................................................................................................................................. 18 2.1 Surveyors ............................................................................................................................... 19 2.2 Councils and utilities ............................................................................................................... 21 2.3 Land Registry Services (LRS) ................................................................................................. 22 2.4 DCS Spatial Services .............................................................................................................. 23 2.5 Developers ............................................................................................................................. 24 2.6 Office of the Registrar General (ORG) ..................................................................................... 25 2.7 Software vendors .................................................................................................................... 26 2.8 Benchmarking ......................................................................................................................... 27

3 Conclusions .......................................................................................................................... 29 3.1 Why has uptake of digital survey plans been low in NSW? ...................................................... 29 3.2 What opportunities exist for digital survey plans?..................................................................... 30 3.3 What needs to be overcome to increase uptake of digital survey plans? .................................. 34

4 Recommendations ................................................................................................................ 36 4.1 Step 1: Confirm outcomes ...................................................................................................... 37 4.2 Step 2: Agree governance ...................................................................................................... 38 4.3 Step 3: Design solutions ......................................................................................................... 40 4.4 Step 4: Implement solutions ................................................................................................... 48

5 Attachments .......................................................................................................................... 52 Attachment A – Consultee details .......................................................................................................... 53 Attachment B – Surveyor sentiment ....................................................................................................... 55 Attachment C – Councils and utilities sentiment ..................................................................................... 66 Attachment D – LRS sentiment .............................................................................................................. 71 Attachment E – DCS Spatial Services sentiment .................................................................................... 73 Attachment F – Developer sentiment ..................................................................................................... 76 Attachment G – ORG sentiment ............................................................................................................. 78 Attachment H – Software vendor sentiment ............................................................................................ 80 Attachment I – Benchmark finding details by jurisdiction ......................................................................... 83 Attachment J – Sample scenarios for solution design ............................................................................. 89 Attachment K – Sample application of Assessment Framework ............................................................ 106

Contact Us ......................................................................................................................................... 112

Page 7: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P7

1 Introduction

The New South Wales (NSW) land titling system is undergoing a significant period of digital

transformation. Currently, 96%2 of all possible dealings are lodged electronically with NSW Land

Registry Services (LRS).

In contrast, the lodgement of digital survey plans for registration at LRS is lagging. Despite the

Government introducing the LandXML (LXML) format for plan lodgement in 2010, only 5% of

plans are currently lodged using this intelligent data format.

The benefits of digital survey plans are substantial and may include cost savings for LRS,

Government and industry, improved customer services and risk reduction by protecting the

integrity of the Cadastre. However, several issues with LXML have largely prevented these from

being realised and there is a recognition that the attempt at digitalisation of plans did not

adequately consider the views of or impact on the surveying industry.

1.1 Objectives

The NSW Department of Customer Service (DCS) engaged Grosvenor to work with industry

stakeholders to undertake a review of digital survey plans. The review has three key objectives,

namely to:

> explore and explain why uptake of digital plans has remained low

> identify what opportunities exist for digitalisation of plans

> provide the Government and LRS with recommendations on the best way to progress digital

plans such that benefits to surveyors, Government and other plan users are maximised.

Through delivering upon these objectives, the review will support the efforts of the DCS-led

Digital Survey Plans Program, which has the following objectives in transitioning to digital

survey plans:

> make it easier for industry to subdivide developable land while protecting the integrity of the

cadastre

> improve Government services to the property sector

> make new housing more affordable.

Critical to this review was strong engagement with the surveying industry, to avoid repeating the

mistakes of the past and ensure the sentiment of surveyors is clearly considered in any future

changes.

2 https://www.registrargeneral.nsw.gov.au/property-and-conveyancing/eConveyancing/eConveyancing-Statistics (accessed 02/12/2019)

Page 8: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P8

1.2 Report structure

This report is structured as follows.

Chapter Contents

Introduction Details of the objective of the review, contextual background information relating to the surveying industry and the history of digital plans, and a summary of the methodology and limitations of the review.

Findings Summaries of findings grouped by the key stakeholders involved in the plan registration process as well as the various benchmark jurisdictions reviewed. Detailed findings are contained within Attachments A to H.

Conclusions Answers to the key questions aligning with the three objectives:

why has uptake of digital survey plans been low?

what opportunities exist for digital survey plans?

what needs to be overcome to increase uptake of digital survey plans?

Recommendations A four-step roadmap recommended in order to pursue and progress opportunities for digital survey plans.

Attachments Detailed findings by stakeholder group and benchmark jurisdiction, as well as sample scenarios to support the recommendations.

Page 9: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P9

1.3 Background

Land Surveying is not an exact science. Establishing title boundaries, or re-establishing them,

is at least as much about the law, its interpretation and the gathering of evidence as it is about

measurement and position fixing.

Bell and Cleary, 20013

About the surveying industry

Surveyors play an integral role in the construction of roads, infrastructure and buildings, as well

as planning and designing land subdivisions; their tasks include:

> measuring distances, directions, and angles between points on, above, and below the

earth’s surface

> establishing official land and water boundaries

> preparing plots, maps, and reports

> working alongside developers, architects, and construction managers.

Registered surveyors are the only practitioners warranted with direct management of the land

boundary system. They interpret legal aspects of land ownership; providing an understanding of

land, water and air, as well as the surrounding environment, to protect development from

impediments and unlock latent value4. They often act as agents for developers and help with, or

administer, the plan approval and registration process.

As of 30 June 2019, there were 1,059 registered surveyors in NSW, of which 928 were land

surveyors, 116 were mining surveyors and 15 were both land and mining surveyors5.

Henceforth, throughout this report, the term ‘surveyors’ is taken to refer to land surveyors.

As of 2017, the average age of surveyors was 52, with the largest proportion aged 61. The

surveying industry is male dominated, with men representing approximately 97% of the industry.

The majority of enterprises within the industry are sole proprietors and partners, with 95.7% of

enterprises consisting of less than 20 employees. Registered companies consist of 12.8% of the

industry, and of those, 59% are private organisations.

3 Bell, K.C. & Cleary, M., 2001, Protecting the Integrity of Victoria’s Cadastre – Managing the Risks, Australian Surveyors Congress, Brisbane

4BIS Oxford Economics, 2019, Determining the Future Demand, Supply and Skills Gap for Surveying and Geospatial Professional,

available at: http://admin.acsnational.com.au/uploads/9/docs/Website%20Full%20report%20Determining%20the%20Future %20Demand,%20Supply%20and%20Skills%20Gap%20for%20Surveying%20and%20Geospatial%20Professionals%20-%202018-2028.pdf (accessed 11/10/2019)

5 Board of Surveying and Spatial Information (BOSSI), 2019, BOSSI Statistical Review 2018-2019, available at: https://www.bossi.nsw.gov.au/__data/assets/pdf_file/0010/222949/BOSSI_Statistical_Review_2019.pdf (accessed 11/10/2019)

Page 10: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P10

A significant proportion of the industry’s revenue is derived from cadastral and boundary

surveying work within the residential construction market. Of the surveyors engaged with as part

of this review, on average 36% of their total workload was preparing plans for registration. The

process for preparing plans for registration and the main user group involved at each phase is

summarised in the diagram and descriptions below.

Figure 1 - Survey plan registration journey

> Surveyors create – surveyors are responsible for plan preparation and administration,

including reviewing historic plans, conducting field work, producing plans and often

administering the process of obtaining all necessary approvals before lodgement with LRS.

> Councils and utilities approve – as part of a development application (DA) a series of

conditions of consent are stipulated by councils and utilities. These entities subsequently

review the plans to confirm their conditions have been met, then issue approvals, after

which the certifying authority can release the subdivision or strata certificate.

> LRS register – LRS conducts an examination of plans lodged to ensure they comply with

legislation and guidelines; it then facilitates the updating of the Titles Register. LRS are

contractually restricted from providing electronic survey plans to some third-party

consumers, including surveyors, councils, utilities and developers; this information is

provided exclusively through Information Brokers. Information Brokers have not been

considered independently of LRS in this review, however, would need to be when

progressing the recommendations outlined in this report.

> DCS Spatial Services (and others) use – DCS Spatial Services (DCS Spatial Services)

obtain registered plans from LRS and add these to the NSW Spatial Cadastre within ten

days for use by surveyors, planners and other stakeholders. Plans are also utilised by

multiple other ancillary stakeholders such as other Government agencies, lawyers, valuers

and banks; the outcomes sought by these groups are similar in nature to DCS Spatial

Services and the groups below.

> Developers sell – after the title has been created developers are able to finalise the sale of

individual lots to homeowners.

> Homeowners own – the title is used by homeowners to provide proof of ownership of the

parcel of land.

> The Office of the Registrar General (ORG) and the Surveyor General (SG) regulate –

ORG is the main regulator of land titling, including oversighting LRS; the SG has

responsibility for regulating survey practice; both have a strong focus on improving

outcomes for end users.

Page 11: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P11

Each of the main ‘customers’ that interact with the plan registration process have unique roles

and objectives. Nonetheless, among them all is a common overall desire for a secure, intuitive

process that ensures a reliable and cost-effective outcome.

Digital change agenda

The NSW Government has been proactive about pursuing a digital change agenda to make

Government more agile, responsive and accountable for the services delivered to and on behalf

of NSW citizens6. This has touched and will continue to touch, many areas of public life,

including the process of creating a new home. It has been recognised by the Government that

the experience of customers and NSW citizens, who are navigating the process of creating a

new home, needs to be significantly improved. For the eventual owners at the end of the

process, this means lower costs with greater efficiency and transparency.

A recent study by the Centre of International Economics (commissioned by the Housing Industry

Association of Australia) revealed there is a significant financial burden on Sydney house prices

associated with delays from regulatory red tape. The report suggested that the average sum of

regulatory costs and statutory taxes for a new house and land package in a greenfield estate in

Sydney is $400,000, almost half of the average total outlay ($841,000) and the highest ratio in

the country. The report noted that one of the most significant cost contributors is interest

charges incurred by developers due to unreasonable delays arising from Government policies

and decisions (mostly in the development approval stage). Besides directly adding to developer

costs, this impacts the GST collected and the stamp duty paid by the purchaser7. Whilst

quantifying the cost contribution of survey plan registration (or potential savings from

digitalisation) was beyond the scope of this engagement, it is undoubtedly a large amount in

aggregate.

More broadly, the Government is committed to improving customer experience and delivering

greater efficiency and transparency. It has recently introduced the following six customer service

commitments which will help communicate and prioritise service design8 and delivery.

6 https://www.digital.nsw.gov.au/beyond-digital/ministers-foreword (accessed 11/11/2019)

7 The CIE, Summary and methodology of the final research report: Taxation of the Housing Sector, available at: https://hia.com.au/-/media/HIA-Website/Files/IndustryBusiness/Economic/research/cie-taxation-of-the-housing-sector.ashx?la=en (accessed 10/12/2019)

8 https://www.dpc.nsw.gov.au/programs-and-services/nsw-customer-service-commissioner/customer-commitments (accessed 1/10/2019)

Page 12: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P12

A major part of the Government’s drive towards improving outcomes in the home ownership

domain has been through electronic conveyancing (eConveyancing). This is a more efficient,

accurate and secure way of conducting the settlement and lodgement stages of the

conveyancing process. A study by KPMG revealed significant benefits to industry from

eConveyancing, including:

> 75% time saved per transaction

> risks associated with human error almost eliminated

> settlement day can be more confidently set

> funds from sales available sooner.

Adoption of eConveyancing has been positive, with a steady increase since its introduction to

almost 100% usage as of July 2019 (as seen in Figure 2 on page 14).

Another related endeavour by the Government has been the creation of the ePlanning portal,

which provides an online environment where customers can access planning services and

information at any time. The ePlanning portal has improved application determination times,

increased transparency of the planning system and improved accountability of all stakeholders.

Linking these two digital initiatives is the Digital Survey Plans Program, which will help deliver

an end-to-end digital service for customers.

History of digital survey plans

The limitations of a paper or PDF based approach for plan lodgement and registration have long

been recognised as causing issues in the land development process – particularly stemming

from delays created by a linear process of review and approval9. For almost two decades,

various jurisdictions across Australia have pursued a shift towards digital cadastral data that can

be shareable, discoverable, retrievable and downloadable. This has largely been through the

Inter-Governmental Committee on Surveying and Mapping’s (ICSM) ePlan working group, who

were responsible for the introduction of LXML in states across the country, including NSW. A

timeline of the design and delivery of LXML in NSW is shown below and discussed in more

detail overleaf.

2003 ICSM ePlan working group convened

2004-05 ePlan model designed

Jul 2006 LXML 1.1 released which supported ePlan model

Mar 2009 Preliminary LXML scheme given to software vendors

Jun 2009 LXML used by LPI to register land title plans internally

Sep 2009 National ePlan model finalised following software vendor feedback

Nov 2009 Final national LXML scheme formally published

Dec 2009 Pilot testing by LPI using select surveyors lodging LXML files

Apr 2010 LXML opened to the public

9 Falzon, K., & Williamson, I. P. (2001). Digital lodgement of cadastral survey data in Australia - user needs. Trans-Tasman Surveyor

Page 13: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P13

ICSM is responsible for leadership, coordination and standards for surveying in Australia and

New Zealand10. ICSM has long been a strong advocate for digital plans. In 2003, after initial

investigations by Queensland, ICSM sponsored a working group to develop a digital cadastral

survey information transfer protocol to allow for consistent transfer of data between surveying

entities and the jurisdictions. Through 2004 and 2005 the working group developed a generic

logical model for a cadastral survey, then investigated suitable international standards to

implement the model. Finding that no existing standard fully supported the model and, with New

Zealand having adopted LXML 1.0, the working group partnered with the producers of LXML. In

2006 LXML 1.1 was released, fully supporting the ePlan model.

The ePlan LXML file is an intelligent digital file that contains cadastral plan and survey

information including:

> survey measurements

> dimensions of the parcels

> interests in land (e.g., easements and restrictions)

> land parcel descriptions

> administrative information (e.g., locality)

> owners’ corporation schedules

> survey marks

> traverses

> radiations

> connections to title

> annotations

> plan approval status

> stakeholders’ signatures10.

In March 2009 the ePlan working group11 provided a draft copy of the LXML schema to software

vendors to enable them to develop packages capable of producing LXML files suitable for

lodgement in each jurisdiction. The NSW Land and Property Information (LPI) started using

ePlan for the electronic lodgement and processing of land title plans in June 2009. On 29

September 2009 the National ePlan model for LXML was finalised following feedback from the

software vendors. The final version of the LXML schema was ratified by the ICSM on 19

November 2009 and then formally published. Through December 2009 and January 2010, LPI

ran a pilot program of ePlan by inviting a number of selected surveyors to lodge both a LXML

file and a TIFF image of the land tile plan, using the TIFF image as a backup in case of

problems. In April 2010, the LXML ePlan lodgement facility was made available to the public for

use online through the LPI SIX portal.

10 Olfat H., et al, (2018) Strategic Actions for Increasing the Submission of Digital Cadastral Data by the Surveying Industry Based on

Lessons Learned from Victoria, Australia, International Journal of Geo-Information

11 Which represents all Australian states and territories involved in the implementation of ePlan (including NSW).

Page 14: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P14

Current state

Surveyors are currently able to lodge plans through three different channels:

> manual lodgement of a printed plan (which is then scanned by LRS); these represent

approximately 20% of total plans lodged

> digital lodgement of a TIFF file (known as ‘ePlan’); these represent approximately 75% of

total plans lodged

> digital lodgement of a LXML file and a TIFF file (known as ‘Digital Plans’ or ‘EPlan’); these

represent approximately 5% of plans lodged.

Since its introduction the adoption rate of LXML has remained low. This varies significantly to

the adoption of eConveyancing (mandated for all mainstream documents from July 2019),

which, as visible below, has risen sharply since 2016.

Figure 2 - eConveyancing adoption versus LXML

Despite the low lodgement rate, LXML plans account for a large portion (34% in 2018) of all new

lots created from deposited plans; over 50% of LXML plans lodged are for 1-10 lots, but the

average number of lots per LXML plan is 19 (compared to an average of 2.5 lots per TIFF plan).

As shown in Figure 3 overleaf, the vast majority of LXML plans lodged are for subdivision

(79%); only one strata plan has been lodged with LXML to date (as a proof of concept).

0.0%

10.0%

20.0%

30.0%

40.0%

50.0%

60.0%

70.0%

80.0%

90.0%

100.0%

eConveyancing adoption versus LXML

eConveyancing (mainstream documents) LXML Lodgements (deposited plans)

Page 15: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P15

Figure 3 - LXML plan purposes

It was estimated through consultations that the creation of a typical TIFF survey plan for a

subdivision involves the following breakdown of effort:

> pre-calculations – approximately 10% of total effort; this involves obtaining existing DPs

and then conducting pre-calculations and preparations in a calculation software package

> field work – approximately 30% of total effort; this involves taking measurements and

records on site (typically utilising a total station with comprehensive digital capabilities

including gathering distance and angular information as well as photos)

> calculations, finalisation and drafting – approximately 60% of total effort; this involves

calculations and manual adjustments in a calculation software package, then exporting to

drafting package (e.g. AutoCAD or BricsCAD) for plan creation – draftspeople are often

used for drafting (they may or may not be trained in LXML, nor understand the surveying

process enough to use it).

How surveyors create LXML varies significantly based on the software package used.

Landmark dominates the software for LXML plans lodged, accounting for 42% of all LXML plans

lodged (the next closest is Magnet Office with 27%). One software package is purpose built for

surveying and the raw data is used to generate the TIFF and LXML, which are identical. Other

packages may not have the same level of LXML integration and after calculations are done in

the calculation packages one of two routes may occur:

> a DXF/DWG can be exported into a drafting package, which then creates the TIFF and the

LXML file (it has geometry and the data attached); or

> a LXML file is created from scratch based on the TIFF.

The current process is not what was envisaged at the time LXML was introduced. The initial

concept was to create a LXML file only, which could be rendered automatically to generate a

plan image suitable for lodgement. However, the quality of rendering has prevented this and

forced the surveyor to create a TIFF in addition to the LXML.

Page 16: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P16

1.4 Approach

Methodology

Grosvenor was engaged by DCS to conduct the Review of Digital Survey Plans in September

2019. To ensure the perspectives of relevant stakeholders were appropriately considered, the

review involved significant engagement with stakeholders across the end-to-end process to

develop, lodge and use survey plans. Insights gathered from stakeholders were supplemented

with a review of relevant existing documentation and data.

A comprehensive stakeholder engagement plan was developed, which detailed the objectives,

approach and key lines of questioning for each stakeholder group. This was reviewed and

approved by the Digital Survey Plans Steering Committee prior to Grosvenor contacting

stakeholders.

Stakeholder engagement involved the exploration of the following elements:

> lessons learnt; why adoption of digital survey plans has not been greater

> analysis of stakeholders’ perspectives and perceptions

> how previous/current initiatives align with the existing plan creation process within private

sector

> analysis of successful implementations of digital survey plans or other relevant digital

transformation initiatives (e.g. eConveyancing) interstate and overseas.

Consultations included:

> surveyors in Sydney and Newcastle (two focus groups with approximately 10 firms in

attendance at each, varying in size and scope)

> regional surveyors (phone consultations with 11 firms of varying size and location)

> utilities and councils (phone and face-to-face consultations with three councils and four

utilities, both regional and metropolitan)

> LRS (face-to-face consultations and demonstrations with various team members and

executives)

> developer representative (phone consultations)

> software vendors (phone consultations or face-to-face consultations with Position Partners,

12d, LISCAD)

> benchmark jurisdictions (phone consultations with representatives from relevant entities in

New Zealand, Western Australia, South Australia, Queensland and Victoria)

> Government entities (phone and face-to-face consultations and workshops with DCS Spatial

Services (including the SG), ORG, Department of Planning, Industry and Environment

(DPIE) ePlanning team, Transport for NSW (including Roads and Maritime)).

Page 17: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P17

Details of the consultees can be found in Attachment A – Consultee details. Most surveyors

responded to a small written survey and a number of consultees also provided additional

information via email. It was observed throughout the consultations that the industry is highly

engaged and keen to remain involved in designing any future changes. A 2018 survey of the

surveying industry conducted by LRS (distributed to 840 surveyors with 141 responses

received) supplemented the consultations to inform surveyor sentiment. Other documentation

and data was also reviewed, including implementation of similar initiatives in other jurisdictions

and details of LXML usage in NSW provided by LRS.

The ultimate outcome of the review has been to provide the Government with a way to progress

towards increased adoption of digital survey plans in NSW. This has been delivered through the

high-level roadmap (supported by detailed examples and an assessment framework) in the

recommendations.

Limitations

No significant limitations were encountered as part of this review. However, it should be noted

that the review deals with complex technical matters which have a number of interdependencies.

The findings, recommendations and conclusions are based primarily on anecdotal feedback from

stakeholders. We have not validated the technical feasibility of the current state nor the set of

sample scenarios. As such, it is recommended that continued engagement with experts in

surveying and software is maintained through solution design. In absence of a detailed solution

no cost-benefit analysis has been undertaken for the possible scenarios. This should be

conducted as part of the development of a business case for any material changes.

Page 18: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P18

2 Findings

A critical element of the review was exploring the sentiment of the stakeholders involved in the

creation, review, registration, use and regulation of survey plans; including:

> surveyors

> councils and utilities

> NSW Land Registry Services (LRS)

> DCS Spatial Services (DCS Spatial Services); including the Surveyor General (SG)

> NSW Office of the Registrar General (ORG)

> developers

> software vendors.

For each stakeholder group this typically included understanding:

> the fundamental outcomes sought from the lodgement of survey plans

> perceived opportunities from digitalisation

> potential barriers to achieving these.

Other state entities including the Department of Planning, Industry and Environment (DPIE) and

Transport for NSW (TfNSW) were consulted and the input of the representatives from these

organisations has been considered in the conclusions and recommendations that follow.

Additionally, other jurisdictions in Australia and New Zealand were examined, to ensure lessons

learned from their efforts to digitise survey plans are considered for future changes in NSW.

Page 19: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P19

2.1 Surveyors

Surveyors are pivotal stakeholders, not only do they produce plans themselves, they also often

act as the lodging party and coordinate the gathering of approvals and endorsements.

Understanding the sentiment of surveyors, particularly why the uptake of digital plans has been

low, is therefore vital to the design of any future solution.

The key findings from engagement with surveyors have been categorised into 12 themes and

summarised below. Expanded details of these can be found in Attachment B – Surveyor

sentiment.

An important observation underpinning all of these themes is the general willingness of the

industry to be involved, demonstrated by the high level of engagement from surveyors in this

review, regardless of location or size of their firm.

Theme Summary of findings for surveyors

Outcomes sought Surveyors’ primary objectives from the process of plan creation to registration are client satisfaction and professional integrity.

Attitude to digitalisation

Digital change is seen as important to remaining contemporary and it is recognised that there are opportunities for improvements, particularly in the approvals and associated documents space. However, it is felt that previous efforts have focused on benefits to Government and LRS only and there is some ambiguity over the problem that LXML is supposed to solve.

Issues with LXML

LXML has frustrated surveyors principally due to the additional effort (estimated to be 30% on average) required to produce both a TIFF and a LXML (a result of the low quality of rendering from LXML). It currently provides little intrinsic benefit to surveyors and, except where it enables faster registration for developments with large holding costs, has limited demand from clients. Additionally, there is a fear that the format favours data over decisions, which are seen to be vital to maintaining the integrity of the monument-based cadastre.

Benefits of LXML

Some surveyors utilise LXML to assist with quality assurance (QA), enabled both through the inherent requirements of the file and automated validation. LXML can also enable faster plan creation for staged division of greenfield sites.

Incentivising LXML

Prioritised lodgement was seen to be a compelling incentive for developers to pay additional costs to surveyors to create a LXML. Additionally, if the LXML was simpler and easier to create, as well as the only file required, then surveyors would be more likely to utilise it.

Attitude to mandating LXML

Surveyors consulted were pragmatic and believe that the industry will adapt to LXML if mandated, but that any additional costs will be passed on to clients.

Plan contents

The concept of a ‘lite’ LXML was raised by some surveyors who suggested that, whilst almost all currently depicted survey information is relevant to

Page 20: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P20

Theme Summary of findings for surveyors

other surveyors, there is an opportunity to simplify digital requirements. Digitised information on a lite LXML should, at a minimum include parcel information (boundaries, lot numbers, dimensions and area) and easements.

Alternative file types

The design and construction industries are dominated by CAD formats (DWG and DXF); most surveyors are highly familiar with these and create them to generate the lodged image. Some councils and utilities also request plans in CAD formats for review and ingesting into their databases.

Strata plans The relative simplicity of strata plans means that some surveyors believe they are an ideal candidate for digitalisation. There are, however, some concerns over data misuse given that linework in strata plans is often generalised.

Approvals and associated documents

Adopting digital signatures is seen to be the biggest opportunity to improve efficiency of the currently time-consuming approvals process (such as endorsements by councils and utilities). There are also opportunities for smart associated documents (such as Section 88B instruments and strata by-laws) to minimise manual data entry and errors.

Other opportunities Other opportunities for improvements to the current processes were identified, including:

automated notification upon registration by other surveyors of pre-allocated plan numbers (PPN) over parcels adjacent to their client’s

separation of spatial cadastre (including the NSW Spatial Cadastre) updates (as a proposed layer) to the registration process

improved boundary decision evidence (e.g. photos) in the metadata.

Other findings There are currently mixed feelings about the quality of requisitions and some frustration about the multiplicity of spatial cadastral datasets across the state.

Page 21: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P21

2.2 Councils and utilities

Councils and utilities provide approvals for plans and are the primary stakeholders that

surveyors engage with prior to lodgement with LRS. Councils are typically the certifying

authority and sign the subdivision certificate, confirming all conditions of consent for the

development have been met. The conditions of consent usually incorporate sign-off of

requirements from other relevant agencies (utilities in many cases). Within both councils and

utilities, the main teams which interact with plans are Property and Planning (known as

Development Services within some utilities). Understanding the sentiment of councils and

utilities is vital in two regards; firstly plans are with them for a significant duration of the survey

registration process and secondly, they are important consumers of plans.

The key findings from engagement with councils and utilities have been categorised into the

following themes and summarised. Expanded details of these can be found in Attachment C –

Councils and utilities sentiment.

Theme Summary of findings for councils and utilities

Property Property teams use information from plans to:

update property records to deliver services and determine rates

spatially assess planning conditions that apply to land parcels

record the location of assets (for maintenance and repair).

Many maintain their own spatial cadastral databases and update these with DXF/DWG files (though only minimal information is required compared to a full survey plan).

Planning Planning teams typically review and certify or endorse plans and associated documents. The administration and management of this is currently quite labour intensive and highly manual.

Opportunities for digitalisation

Both Property and Planning teams from councils and utilities strongly support enhanced digitalisation. The perceived opportunities related primarily to:

minimise manual data handling through ingestible metadata

provide faster turnaround of documents through electronic or digital signatures

provide transparency of status (for customer and approvers)

reduce errors through validation of smart documents.

Additionally, it was noted that there is a strong focus on improving customer experience within these organisations and an appetite for digital change.

Page 22: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P22

2.3 Land Registry Services (LRS)

LRS performs an important function in maintaining the integrity of the Titles Register. It acts as a

quality gatekeeper for plans, responsible for examining lodged plans to ensure only those which

meet legislative and regulatory requirements are registered. Understanding the sentiment of

LRS is vital given the significance of the examination and registration process.

The key findings from engagement with LRS have been categorised into the following themes

and summarised. These are expanded upon in Attachment D – LRS sentiment.

Theme Summary of findings for LRS

Outcomes sought

LRS exists to maintain the integrity of the Titles Register and desires to improve plan lodgement, examination and registration outcomes for customers and citizens of NSW. As a commercial entity it must also ensure short term costs deliver long term benefits to LRS and their customers.

Opportunities for digitalisation

LRS is very keen to see an increase in uptake of digital plans as they have the potential to enable more efficient examination, as well as an increase in the quality of plans, and therefore, the Titles Register

Barriers to change

LRS is mindful of the previous attempts to introduce LXML without due consideration being given to the views of surveyors and is reluctant to introduce any solution without close and ongoing consultation and co-design with all stakeholders.

Page 23: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P23

2.4 DCS Spatial Services

DCS Spatial Services is responsible for the provision of spatial and land information services for

NSW. Its primary objective is to utilise spatial products and services in support of the NSW

Government Digital Strategy to improve services to the community, Government and industry.

Understanding the sentiment of DCS Spatial Services helps to identify the necessary

functionality any digital solution must have to meet the needs of Government.

Additionally, the Surveyor General (SG) is a part of the DCS Spatial Services division and has

responsibility for regulating surveying practice within NSW. Whilst the SG is co-located with the

ORG in Figure 1 on page 10 to highlight its regulatory focus, the findings for the SG are

included below as part of DCS Spatial Services, in alignment with its organisational structure.

The key findings from engagement with DCS Spatial Services staff have been categorised into

the following themes and summarised. These are expanded upon in Attachment E – DCS

Spatial Services sentiment.

Theme Summary of findings for DCS Spatial Services

Outcomes sought

DCS Spatial Services seeks to maintain the currency, completeness and accuracy of the NSW Spatial Cadastre.

The SG in its regulatory role seeks to deliver improvements to surveying practice and ensure standards are maintained.

Opportunities for digitalisation

Multiple opportunities for digitalisation are perceived by DCS Spatial Services; these include:

improved quality of information in the spatial cadastre

faster ingestion into the spatial cadastre and related datasets by reducing manual entry requirements

improved interoperability with other datasets (e.g. Survey Control Information Management System, transport network, imagery)

the ability to propagate and improve the survey control network

the potential to increase use of the NSW Spatial Cadastre through better meeting the needs of users

progression towards the future visions of Cadastre 2034 and support for development of a digital twin (including 3D and 4D spatial cadastre).

With the SG’s regulatory focus, it is also felt that digitalisation can improve efficiency and accuracy of surveying practices; including through facilitating enhanced evidence for defensibility of decisions of boundaries.

Barriers to change

It is recognised by DCS Spatial Services that the previous approach to digitalisation of the plan registration process did not sufficiently consider the views of the industry and that this must be overcome.

Page 24: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P24

2.5 Developers

As the main client in the process of plan registration, developers have a clear set of interests

and objectives. Their role and engagement in the process varies depending on the scale of the

organisation, from high frequency users such as multi-billion-dollar developers with inhouse

surveying teams, to one-off ‘mum and dad’ developers. Regardless of the scale, the developers’

sentiment is critical to appreciate in order to ensure strong outcomes for the ultimate end user -

homeowners.

The key findings from engagement with developers have been categorised into the following

themes and summarised below; these are expanded upon in Attachment F – Developer

sentiment.

Theme Summary of findings for developers

Outcomes sought

Developers noted a desire to have plans registered as quickly as possible with the least complexity, in a cost-effective manner.

Opportunities for digitalisation

Two significant opportunities for improved customer service through digitalisation were raised by developers:

speed of registration – through automated examination and registration as well as digital approvals and associated documents

transparency of the process – through a portal where the status of plans can be easily viewed.

Barriers to change

It is felt that there are some historic issues with LXML which need to be overcome to affect change in the market. This can be addressed through a high level of engagement including educating surveyors and developers of the benefits of any changes.

Page 25: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P25

2.6 Office of the Registrar General (ORG)

ORG is responsible for ensuring the integrity of the NSW land title system. It acts as a policy

and legal advisor, regulator, review body, litigator and driver of reforms in land titling. In all these

areas, particularly in its capacity as the regulator and driver of reforms, the sentiment of ORG

must be considered for any possible changes. ORG also has insights from the introduction of

eConveyancing that are highly relevant for digital plans.

The key findings from engagement with ORG have been categorised into the following themes

and summarised; these are expanded upon in Attachment G – ORG sentiment.

Theme Summary of findings for ORG

Outcomes sought

ORG is ultimately responsible for the integrity of the NSW land titles system and for overseeing LRS’s performance in maintaining the security, performance and availability of the system. It sees its customers, in the context of survey plans, as landowners, surveyors, conveyancers and developers. The ORG desires to increase efficiency, accessibility and availability to ensure better outcomes for these customers.

Opportunities for digitalisation

ORG is keen to progress digitalisation and sees the potential benefits that digital plans can bring to all customers involved, with the end result being:

faster registration of plans

enhanced accuracy of plans from automated examination and data control (minimising boundary errors and mistakes in documents) in turn reducing conflicts between surveys and the cost of resolving disputes and improving the integrity of titles

reduced Torrens Assurance Fund (TAF) claims from errors on registered plans

assistance in its regulatory role through rapid data insight extraction.

Lessons from eConveyancing

Through the introduction of eConveyancing ORG learnt some valuable lessons that can be applied to the digitalisation of plans, particularly relating to the change management required. These include the importance of:

clear benefits for industry from the change

clarity of roles and responsibilities (for governance and policy versus solution and business rules)

communication and engagement with stakeholders to encourage uptake before mandate

training for users to encourage uptake and provide confidence in the reform prior to the mandate

mandating with a suitable fixed notice period (through close consultation with stakeholders and strong partnerships with peak industry bodies)

staged implementation, which prioritises low difficulty high volume aspects first, so industry becomes familiar with changes before the final mandate

under a mandate regime, test and prevent launch day surge issues.

Page 26: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P26

2.7 Software vendors

As a result of the relatively small surveying industry in NSW, there are relatively few software

vendors that provide tailored survey calculation packages. The vendors interviewed as part of

the review were Position Partners/Topcon, Landmark, LISTECH and 12d. The software solution

is integral to the feasibility of digital plans and, as noted by surveyors, has had a major impact

on the low uptake of LXML by many surveyors.

The key findings from engagement with software vendors have been categorised into the

following themes and summarised, then expanded in Attachment H – Software vendor

sentiment.

Theme Summary of findings for software vendors

Business drivers The importance of the surveying software package (and the NSW market) as a revenue stream varies between software vendors; but is not insignificant for any. As such, all software vendors interviewed have invested in LXML to varying degrees.

Opportunities for digitalisation

Software vendors were big advocates for digitalisation and believed that digital plans can be faster and more accurate if implemented correctly.

Issues with LXML

While all software vendors were generally supportive of LXML they expressed a degree of frustration at the limitations of the format. This was mostly around the lack of suitability of the format for visual representation of a plan image and 3D capabilities. Issues with visualisation largely stem from the poor-quality rendering (external to their packages) which leads to additional work by surveyors to prepare the plan image and LXML file. However, one software vendor demonstrated an integrated approach where the plan image and LXML are prepared simultaneously.

Alternative formats

There was no consensus for a particular existing file format being ideal as an alternative to LXML; however, a few options were suggested for further examination, particularly IFC files. Another popular option was the creation of a new XML based format which could cater for the specifics of NSW and resolve some of the current issues of LXML. A strong warning against using DWG was indicated by one vendor based on its proprietary nature.

Page 27: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P27

2.8 Benchmarking

Across Australia and New Zealand, approaches to survey plan creation, approval, examination

and registration differ. This is a result of historic differences in the legislation and governance in

each jurisdiction. Despite this, there is a consistent appreciation of the benefits of digitalisation

and efforts have been undertaken in all jurisdictions to progress this. There are therefore

valuable insights gained through examining the current approaches and future intentions of the

various jurisdictions. A summary table is of these insights is presented below, while details for

each jurisdiction can be found in Attachment I – Benchmark finding details by jurisdiction.

Jurisdiction Summary of survey plan lodgement processes

New Zealand

100% digital survey lodgement in LXML since 2007, when mandated.

Surveys lodge in LXML format; pictures, text and PDF documents that support the data set are uploaded as a Cadastral Survey Dataset package.

The system provides an electronic workspace for surveyors. Automated business rules for pre-validation are provided and automated warnings are flagged to surveyors. The system facilitates supporting documentation with drop down menus and pre-populated templates. Approvals are processed digitally online in the system.

LXML was chosen as the format as no better alternatives were identified at the time. Standardisation of file format was important. The NZ cadastre is effectively one single LXML dataset, which surveyors can use to easily select existing survey data to use for their pre-calculations.

Western Australia

Surveyors lodge plans in a proprietary Cadastral Survey Data (CSD) file along with a plan graphic and field notes in PDF.

All files lodged electronically since 2013, now via the New Land Registry system.

Survey plans are relatively simple compared with NSW, with correspondingly light examination, resulting in a very low requisition rate (2%).

The WA Planning and Development Act 2005 allows most easements to be created just by spatial definition on a plan, especially in greenfield subdivisions.

All approvals are done as electronic signatures on PDF by authorities such as the WA Planning Commission.

Victoria Digital signatures are used for approvals within the Subdivision and Planning through Electronic Applications and Referrals (SPEAR) system.

SPEAR applications account for 98% of all plans lodged. From 01 January 2020, SPEAR will be compulsory for the creation and processing of all supported application types.

The majority of information uploaded in SPEAR is either in PDF or direct data input; it does allow surveyors to submit all 2D land subdivision plans in ePlan format (LXML) but only 1% are supplied as such.

By the end of 2020 the aim is to have a structured CAD file (co-designed with industry) and a CAD to LXML conversion tool to support the process.

Page 28: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P28

Jurisdiction Summary of survey plan lodgement processes

South Australia

Surveyors lodge TIFF image of the plan via online portal, and generate a textual sheet in the system that includes easements in short form and parcel details.

Approvals involve electronic signatures on the textual sheet.

Lodged survey plans are digitally captured in CEXML format using PCPlans software. PCPlans is also made available to surveyors to check closures before lodging. Connecting parcels to coordinated survey marks enables spatially accurate representation.

LXML has not been adopted. Currently piloting alternative formats.

Queensland All lodgement is with titles office, done at lodgement centres for paper plans with a bundled approach to registration and creation of title. Have recently begun accepting PDF from approved lodgers. Wet signatures are used for approvals.

While progressing with back-capture of registered plans in LXML, further investment in systems to support LXML lodgement have been paused due to cost and technology uncertainties and limitations, while awaiting a national consensus on a digital solution.

Page 29: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P29

3 Conclusions

3.1 Why has uptake of digital survey plans been low in NSW?

Ultimately, uptake of digital survey plans in NSW has remained low as there have been

insufficient incentives for surveyors to adopt LXML and it has not been mandated.

Surveyors are appreciative of the potential benefits of digitalisation and keen not to be seen as

averse to technology and change. However, in most cases, the benefits to surveyors and their

clients have not overcome the challenges of producing a LXML file. The challenges primarily

stem from the fact that, compared to the ‘traditional’ approach of producing a TIFF image,

producing a LXML often requires significant additional effort12. This can be largely explained by

the rendering inadequacies and the LXML creation process not fitting into the normal plan

preparation workflow (requiring duplication of effort). In addition, error reporting from the

validation service is difficult to understand and surveyors reported in some cases increased

frequency of requisitions when lodging a LXML, a result of minor inconsistencies between the

LXML and the TIFF.

The corollary of these issues is usually additional costs for surveyors to create a LXML. Not

wanting to reduce their profit margin, the additional costs to create a LXML are typically

forwarded to clients. Where the use of a LXML results in faster registration (such as previously

when LXML lodgements were prioritised) this can be a sufficient incentive for clients (particularly

those with high holding-costs) to pay the additional costs. However, with a large proportion of

plans being for small developments with relatively low holding costs, this demand does not exist

for most plans.

The perception of surveyors is that most of the benefits of LXML accrue to Government (and

LRS) and only firms who primarily work with greenfield subdivisions can realise efficiencies.

This is compounded by the fact that it is difficult for surveyors to access registered LXML files to

assist with their pre-calculations. Even when these are available, there is a lack of trust in the

data reflecting the plan (as it is not the legal source of truth) by some surveyors, as well as

resistance to moving from working with a plan image to a dataset. Surveyors are therefore

unwilling to invest in software and training for their staff where there is low demand and no

intrinsic benefits to themselves or their clients.

Lastly, the benefits from LXML are disaggregated across stakeholders and have not been

sufficient for any one group to act on. Likewise, broader digitalisation of other elements of plan

registration, such as associated documents and approvals, has lagged as there has not been

sufficient state-wide coordination or leadership.

12 It was reported that, if rendering was better, and an image suitable for registration could be generated straight from the LXML file, then the total time difference compared to the ‘traditional’ method would be negligible in many cases.

Page 30: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P30

3.2 What opportunities exist for digital survey plans?

Whilst not without its challenges, digitising plans present opportunities to multiple stakeholders.

Table 1 - Opportunities for digitalisation through the survey plan registration journey (page 33)

summarises the findings from each of the main stakeholder or ‘customer’ groups in the process

from plan creation to registration and the use of plans. Opportunities for other users, such as

lawyers, valuers and banks are not called out specifically as they are similar in nature to other

customer groups, particularly DCS Spatial Services, developers and homeowners. The table

includes:

> the Objective of each stakeholder group through their participation in the process

> Success factors that, if met, will contribute substantially to the achievement of objectives

> Enablers which digitalisation can help provide to support the success factors

> Outcomes that will result from meeting the success factors

> Opportunities that may be secondary to the main success factors but are possible through

digitalisation.

As apparent in the table, there are many benefits through digitalisation for customers. These

can be generally summarised into two main areas, faster registration and improved data for land

administration. These are driven by increased accuracy (enabled by enhanced validations and

minimised human error) which also contributes to increased speed (through fewer requisitions)

and is beneficial in and of itself for the integrity of the Titles Register. Digitalisation can also

achieve greater efficiency through increased automation, with subsequent reduction in costs for

surveyors, LRS and Government. The benefits also align tightly to four of the six NSW

Customer Commitments13 as shown in the table below.

13 https://www.dpc.nsw.gov.au/programs-and-services/nsw-customer-service-commissioner/customer-commitments/ (accessed 25/11/19)

Page 31: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P31

Faster registration

Reducing the time from plan preparation to registration will provide some benefits to almost all

parties. Developers and purchasers will benefit the most, as it will reduce holding costs and

therefore potentially also reduce purchase costs. Additionally, utility service providers would

benefit from a reduced delay between providing services (water, electricity, etc.) and formally

taking legal ownership of the infrastructure required to deliver those services.

Faster registration is achieved by shortening the duration of the ‘critical path’, particularly

obtaining approvals and then successful examination and registration by LRS. This can be

facilitated through the following means:

> simplified and pre-populated data in associated documents will save time for surveyors

in document creation, as well as reduce errors from incorrect details, leading to faster

approvals, fewer requisitions and faster examination.

> digital signatures which will save significant time as the current requirement for documents

to be physically mailed and signed by hand was seen to be one of the biggest sources of

delay.

> parallel approvals which can be enabled by digital signatures and will allow for concurrent

endorsements to be obtained, shortening the critical path. Digitising the approvals process

may also enable transparency for stakeholders to monitor the status of the plan throughout.

> structured data enabling enhanced workflow management (rather than physically

looking at a plan to transfer details into systems) which will enable automation and

efficiencies for administration and management of documents during approval and

examination.

> automated pre-validation of digital plan data by surveyors which should lead to reduced

requisitions as more errors are identified prior to lodgement, and some automated

examination checks by LRS may lead to faster registration.

Improved data for land administration

Capturing more detailed and accurate data will support land administration, primarily through

helping to enhance the quality and utility of the NSW Spatial Cadastre. The main beneficiaries

from this are planners, both Government and private. Additionally, surveyors will benefit from

being able to access more information earlier than they currently do. Improving data for land

administration is primarily facilitated by:

> smart plan data which allows for automatic ingestion into a variety of systems, particularly

the NSW Spatial Cadastre, allowing more information to be included and with lower risk of

data integrity degradation (as it is easier to import information from a LXML file and does not

introduce risk of human error). This may include automated quality checks which improve

the standard of plans that are registered and then incorporated into the NSW Spatial

Cadastre. It may also include additional evidence for boundary decisions made by

surveyors, such as photos, to assist in future boundary surveys.

Page 32: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P32

> lodgement of plans separated from registration which, whilst not purely a digital aspect,

can be enabled by digital plans. By incorporating plans into the NSW Spatial Cadastre as

close to the time of the actual survey, the currency of the information is enhanced, as other

surveyors can access and use the most relevant and recent information. This may include a

digital system flagging when a PPN is registered for any relevant adjacent parcels.

These opportunities will also promote interoperability, and ideally consolidation, of the disparate

cadastral databases being maintained by various entities, which is a source of minor frustration

for many stakeholders.

Lastly, there is a contemporary opportunity at an industry level for change, as other initiatives

like ePlanning and the shift to GDA2020 are encouraging stakeholders to think differently and

modify their processes.

Page 33: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

.

NSW DCS | Digital Survey Plans Review P33

Table 1 - Opportunities for digitalisation through the survey plan registration journey

Page 34: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P34

3.3 What needs to be overcome to increase uptake of digital survey plans?

With the benefits disaggregated, to achieve increased uptake of digital plans, a convincing

solution needs to be designed that provides tangible benefits back to industry without unfair

impost on any one group. The solution needs to overcome the majority of issues identified by

surveyors, most considerably so that digital plans do not take additional effort compared to the

current state, or that benefits to themselves or their clients are significant enough to warrant the

extra effort or cost.

To overcome current challenges and achieve increased uptake of digital plans, the technical

solution must be well designed and implemented. There are several interdependent factors that

must be considered to achieve the ideal design for file formats and processes. As shown below,

surveyors in their responses to the 2018 survey revealed the importance of effective software

solution(s) to overcome the barriers to utilisation of LXML. The relative difficulty of implementing

this depends on the file formats chosen (explored below in Recommendations – Step 3: Design

Solutions).

Figure 4 - Overcoming barriers to using LXML

Training will also be required for any changes, particularly software based. Other change

management processes, including continued stakeholder engagement (particularly to overcome

historic perceptions of under-valuing surveyor’s input), pilot testing and staged implementation,

will also help to overcome typical barriers to change such as inequity. These are discussed in

Recommendations – Step 4: Implement Solutions.

The multitude of stakeholders has also led to a lack of ownership for improvements, with no one

group the clear leader with oversight over the whole process that tie together other related

projects such as ‘Re-imagining Plans’, ePlanning, 3D Cadastre and ‘digital twin’. To drive

improvements across the whole customer journey clear accountability and direction is required.

As learned from implementing eConveyancing, whilst DCS and the ORG should retain a key

role in communications, policy setting and governance, LRS should be leading the technical

design and implementation of the solution.

0

10

20

30

40

50

60

70

80

LandXML interestgroup via social

media to share ideasand important

information

Other (please specify) More training /information sessions

Supportingapplications (e.g.rendering service)

Supporting services(e.g. TIFF/PDF to

LandXML conversionservice)

What would help you overcome this barrier (to using LXML)?(please tick all applicable) n=116

Page 35: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P35

Implementation of any changes are further complicated by the lack of consistency across

jurisdictions. Whilst various jurisdictions have been successful in certain areas, even NZ and

WA – considered by many to be leaders in this space – are looking to improve their approach to

digitalisation. That no jurisdiction believes their current position is ideal highlights the complexity

in designing a suitable solution. While pursuit of national consistency remains a common

aspiration, legacy differences in legislation and approach make this difficult.

Lastly, it was reported by other jurisdictions that the only way to achieve a high level of digital

adoption was through mandating use of LXML. Surveyors in NSW believe that, if digital plan

lodgement was mandated, the industry would adapt within 12-24 months but that costs would

be passed to clients. This must be done carefully, with suitable change management processes

and only after an effective solution has been designed.

Page 36: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P36

4 Recommendations

A number of recommendations have been prepared to assist DCS and LRS in increasing digital

survey plan uptake. These are based on an appreciation of the reasons for low uptake of digital

plans, the opportunities digitalisation presents and the barriers that must be overcome to realise

the benefits.

The recommendations are structured as a high-level roadmap with four steps designed to

efficiently progress digitalisation efforts from the current state. It should be noted that there may

be multiple solution streams which exist in parallel and some solutions, by virtue of their

complexity, will take longer than others to design and implement.

The four steps are outlined below then expanded upon in the following pages.

Page 37: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P37

4.1 Step 1: Confirm outcomes

There is seemingly tacit agreement on the purpose of the drive to digitise plans amongst

members of the Digital Survey Plan Steering Committee (henceforth ‘Steering Committee’).

These are based on the views of their organisations as well as the input of industry and other

related stakeholders. However, the specific outcomes sought should be defined, articulated and

agreed upon by the Steering Committee. These outcomes will then underpin all planning and

communication activities. The outcomes may be ‘faster, smarter surveying’ – which encompasses

speed for all parties along the customer journey, as well as improved survey integrity.

Labelling the push “towards 100% digitalisation” (or similar) risks conveying that the main

outcome is digitisation for the sake of it. Communications should focus on benefits to the

stakeholder groups and the problems that digitalisation solves. For surveyors, for example,

amongst other things, digital solutions will:

> enable effective automated validation of plans; reducing requisitions

> reduce time waiting for approvals through digital signatures and electronic associated

documents

> reduce professional indemnity claims by enhancing survey quality

> facilitate simplified sourcing of existing plans, giving surveyors access to search for

registered plans available in digital format, and linking to a downloadable source of plans

> support more efficient plan preparation by utilising existing registered digital plans

> allow integration of lodged/proposed plans into a layer in NSW Spatial Cadastre prior to

registration, again accessible to surveyors.

Surveyors should also be provided assurance that monument-based surveying will remain.

Surveyors have voiced concerns that digital processing of collected survey information will

ultimately lead to a coordinate-based cadastre. As part of any change and communication plan,

it will be important to address this concern and neutralise the presumption that a monumented

cadastre will be at risk as digitalisation of survey information is implemented.

For the wider users of plans, an aspirational goal could be to ultimately reduce number of

unique cadastral datasets being operated by Government, councils and utilities. Developing a

more accurate spatial cadastre in a format that can be shared with end users to manage their

assets, operations and obligations would remove extensive duplication of systems and effort

across NSW.

Page 38: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P38

4.2 Step 2: Agree governance

An absence of clearly articulated roles and responsibilities has led to inertia on progressing

digital solutions, as no individual party has a sense of ownership of the change process. All

stakeholders consulted acknowledged there are benefits to digitalisation of the survey

registration process. But while significant in the aggregate, the benefits are widely dispersed

across multiple varied stakeholders, with no single entity being strongly motivated enough to

make the change, nor holding a strong enough mandate to lead others in a collective change.

The current Steering Committee approach has created a platform where necessary actions for a

path forwards can be agreed between parties. Nonetheless, there is a need to have one

organisation ultimately responsible for each agreed action. Whilst the organisation responsible

for each action will drive the change, they will still need to coordinate with many stakeholders,

including Consultative Committee members, DPIE, surveyors, developers, software vendors,

councils and utilities. Key areas for defined accountabilities should include governance and

policy, solution design, and communications and engagement.

Governance and policy

DCS’ remit is to work across the NSW Government to provide a better customer experience for

citizens. It holds responsibility for policy and regulations, as well as driving reforms in land titling

through the ORG. Through the Surveyor General, DCS is also responsible for supporting the

quality of the surveying profession. As such, DCS should retain ownership of the overall

governance and policy setting for all changes related to surveying, including digitalisation. In

this capacity DCS would be responsible for setting timelines, approving proposed technical

solutions and implementing policy and legislative changes.

Technical solution design

As the concession holder responsible for the administration of the NSW Titles Register, LRS

has a strong incentive to increase digitalisation. It is therefore the most suitable organisation to

lead the design of future technical solutions for smart plans and associated documents, as well

as any new portal to support these (including possible integration with ePlanning). LRS is

somewhat agnostic to the file formats ultimately adopted, as long as they provide users with the

capabilities to achieve the stated outcomes and benefits of digitalisation.

The digital approvals processes for survey plan registration involves surveyors and LRS, as well

as many different council and utility entities across NSW. No individual entity is in a position to

take the lead on improving every aspect of approvals, but the majority of stakeholders would

benefit. The Consultative Committee needs to identify stakeholders across the varied parties to

champion digitalisation and work with LRS in designing a solution which will meet all parties’

needs.

Page 39: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P39

Communications and stakeholder engagement

Whilst engagement should involve all stakeholders from the Consultative Committee, a single

party should own responsibility for managing engagements and communications. DCS has a

strong profile and engagement capacity, and it was reported that its leadership for the

engagement for eConveyancing was highly effective. As such it should be considered by the

Steering Committee to lead the communications and stakeholder engagement efforts.

Page 40: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P40

4.3 Step 3: Design solutions

Once the desired outcomes and governance models have been decided, the next step is to

design the solutions for digital plans. Solutions should initially focus on the three main areas:

> deposited plans

> strata plans

> approvals and associated documents.

The solutions may be heavily influenced by the ‘Re-imagining Plans’ project and the outcomes of

this should inform any designs. Likewise, the impacts of related NSW and national endeavours,

such as ePlanning and Cadastre 2034, should continue to be considered as they evolve.

Solution design should be the responsibility of the party designated as part of Step 2 – Agree

Governance (likely LRS), but with the continued input of the surveying industry and other

stakeholders.

Considerations for each of the three main elements have been set out below. An Assessment

Framework (the Framework) to assist in solution design and evaluation has also been designed

and is explained after the considerations. Finally, sample scenarios for the deposited plans are

included to demonstrate the application of the Framework.

The final designs should be compared and reviewed to understand impact and ease of

implementation and then approved by DCS prior to implementation.

Considerations for deposited plans (DPs)

Defining and establishing boundaries is fundamental to the role of registered surveyors and any

change to the format or nature of DPs must ensure legally sound methodologies for this are

retained. Evidence for how the surveyor defined a boundary is currently contained on the plan

image, in a fashion that typically only registered surveyors can accurately interpret. If DPs

become lodged in a digital format, it will be important to consider how the evidence gathered in

the field will be captured, particularly if less information is required on a future legal source of

truth as part of the ‘re-imagining plans’ program. Options for providing this evidence include:

> embedded in smart data

> a digital survey report as part of lodgement

> annotations on the plan image.

Additionally, surveyor instrumentation typically has the functionality to collect digital photos in

the field, which could be included within the plan data where relevant as a method of

documenting evidence used to define the boundary, such as occupations.

The transition to digital survey plans may create an opportunity to enact a reduced content or

‘lite’ plan as part of the registration process; potentially simplifying rendering and improving

legibility while ensuring the data is the same as the ‘full’ plan. If any changes result in

Page 41: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P41

simplification of plans, or a reduction of information on a separate title plan (compared to the full

survey plan), the minimum content for what needs to be digitised may include:

> subject boundaries, lot number and areas

> easements

> reference and control marks

> bearings and distances for subject parcels and connections.

Lastly, consideration should be given to minimising changes to the current plan preparation

workflows used by surveyors, as this will mitigate resistance to adopting digital change.

Ideally, prior to lodgement, surveyors should be able to pre-validate their digital plans against

similar checks that will be run by LRS. The current validation service provided is not considered

effective by most surveyors and a future solution should be more comprehensive, up to date

and user friendly14. Automated validation tests could be run either in provided calculation

software packages or on an online portal. This would allow lodgement business rule violations

to be flagged, or potentially enforced, prior to lodgement, which would likely reduce requisitions

and increase the speed of plan registration.

A digital system could enable automated creation and collation of metadata, and provide pre-

population of key information, which could be tethered to associated documents, for example,

automating the same plan number on all documentation.

Ideally for examination, only a single version of the plan is needed (e.g. not a TIFF and LXML)

and a comparison of alignment between two files is not required. If two files are created then

workflows should ensure alignment between a full drafted plan and a lite digital boundary plan.

Several such processes are outlined in the scenarios below.

Any digital solution should facilitate access to registered digital plans. Plans should able to be

quickly searched for and available to surveyors and other entities, such as utilities, via a portal.

This will be a key benefit to surveyors (who mostly reported that finding LXML files is currently

difficult or impossible) by reducing effort in pre-field calculations through ingesting survey data

available as LXML files or other formats. It will also support the examination procedure by LRS,

where examiners currently have to locate plans via a manual process. Lastly it should also

assist utilities to easily obtain digital information, such as what is currently provided in the

Authority Registered Plan Report (the content of which could be enhanced through digital data).

Other users, such as utilities, would also benefit from having relevant information that can easily

be viewed, with metadata contained in a format that can be automatically read and ingested into

their systems.

Opportunities for enhanced presentation and functionality such as 3D plans and/or BIM

integration should be considered. LXML has received generally poor reviews from stakeholders

14 LRS representatives reported that this is currently being overhauled and an improvement to the current service will be released in early-2020

Page 42: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P42

consulted regarding its ability as a file format to capture 3D spatial information. Other formats

used in the engineering and design industries are better able to produce 3D representations.

Such formats include spatial data file (SDF), LandInfra and IFC, which are used to model

building and facilities designs. These formats have not been included in the lodged format

scenarios below as there was limited understanding or awareness of these across industry and

no consensus on what a suitable format would be. Nonetheless, it should be considered in

future. Likewise, a custom XML based format (essentially a modified LXML) should be explored.

Regardless of the format chosen the parameters should be clearly defined and, if it is a shift

from an image to a data-based plan, then the change management effort will likely be more

significant.

Considerations for strata plans

Strata plans are a good candidate for digitalisation as they are expected to be more easily

rendered from digital data to plan graphic, and are a large proportion of all plans lodged,

particularly in metro areas. The ability to represent components of strata lots (such as the main

apartment, carpark and storage cage) in 3D space on the NSW Spatial Cadastre would be

highly valued by strata owners to easily determine ownership (including of the body corporate)

within the building. In doing so, associated documents, particularly by-laws, could be uploaded

and clauses linked to spatial objects, in turn improving access to and comprehension of

obligations under the by-laws.

However, the benefits of digitally lodging strata plans is likely lower for surveyors than

Government and end users, as the current TIFF plans are already relatively simple in

presentation. As strata plans are primarily for metro locations, any change to the requirements

for strata lodgement would not impact regional surveyors as much as digitising DPs.

Surveyors did raise concerns about liabilities and reputational damage from misuse of digital

information, as strata plans generalise the location of boundaries and are not ‘survey accurate’.

This would need to be addressed with suitable protections in order to gain the support of

surveyors.

LXML may not be the ideal file format for digitising strata plans. An alternative file format that

better enables visual representation of 3D strata lots could be more suited.

Considerations for approvals and associated documents

Sequential wet signatures are seen to be a major delay to the approvals process by all

stakeholder groups. In many instances even if documents can be digitally uploaded,

prepopulated, and edited, they must still be printed in hard copy to be signed with ink, and then

either posted as hard copies (occasionally lost in the post) or scanned to a new PDF.

Implementing a digital signature approval system is highly recommended. Such a system would:

> shorten the end to end process for customers, reducing developer holding costs and

allowing plan approvals to be managed across all authorities, monitored in real-time with

push notifications for actions

Page 43: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P43

> enhance interoperability and consistency across stakeholders, with roles and responsibilities

for approvals controlled

> not unreasonably disadvantage any stakeholder group, and costs can be shared fairly and

transparently.

A digital approval system would provide greater transparency and enable approval processes to

occur in parallel. Approving stakeholders would require notification if a consenting authority

requires a change on a plan they have already approved, and they may need to reassess and

endorse the changed plan depending on the nature of the required change. An arbitration

process, and associated governance, would be needed to determine if a change impacts an

approver’s area of control.

In conjunction with a digital approval process, associated documents lodged with the plan should

be digitised. These should be implemented as a consistent state-wide set of documents, which

have embedded functionality to auto-populate with the correct information following enforced

business rules that can be readily kept up to date. These could be either downloadable smart

documents or completed in an online workspace. Whilst ePlanning is still being developed,

consideration should be given to potential integration and links to this platform.

The lodging party would select the document type, location and only the relevant consenting

authorities for that location would be able to be selected. Councils and utilities would be able to

more easily make available their standard text requirements, such as for the creation of

easements, to the lodging party via the portal. The document suite or system would enable

document content to be managed by the appropriate authorities. The lodging party would then

select the relevant standard text from a list or similar means.

NSW may also consider reducing duplication or simplification of information across a plan and

associated documents. As an example, in WA, simple easements can be automatically created

by spatial representation on the plan (without a Section 88B). These sort of adjustments will

likely require legislative changes which will take time to implement.

Assessment Framework

The Framework has been developed to understand which changes should be pursued to

improve uptake of digital plans. The Framework is based on the findings and conclusions of the

review. It also incorporates the pain points and success measures that arose from engagement

workshops with the Digital Survey Plans Consultative Committee in mid-201915.

The Framework assesses the likely contribution of changes towards achieving the key

outcomes for each customer and stage of the surveying lodgement process (as detailed in the

table in Conclusions – What opportunities exist for digital survey plans above). Contribution

towards each outcome is understood by considering the likelihood of achieving the relevant

success factors.

15 DCS, Digital Survey Plans Program Consultative Committee Workshop Outcomes, 9 August 2019

Page 44: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P44

Whilst the contribution for all stages of the survey plan journey are shown equally, it should be

noted that success factors for the final two stages (developers and ORG) effectively amount to

the net impact for the key outcome criteria (time from creation to registration, and quality,

respectively).

The impact of achieving the key outcomes is balanced by reviewing the ease of implementation,

to understand the practicality of each change across the following categories:

> technical feasibility – including the amount of disruption to current surveying practices, as

well as the likely complexity of any software solution required to support the change.

> cost of change – to each of the stakeholder groups to implement the change.

> legislative change – both the quantity and difficulty of any legislative change required to

support the change.

The Framework is presented overleaf, showing the criteria by which, each element is assessed.

Page 45: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

.

NSW DCS | Digital Survey Plans Review P45

Figure 5 - Assessment Framework

Page 46: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P46

There are multiple decisions that need to be made on the path to improving and digitalising

plans, each with interdependencies to other decisions. Even when reducing the scope of a

single decision to a binary choice, there still remains a significant number of permutations of all

the decisions and the order in which each can be made is complex. Example decisions to

consider include:

> mandate 100% vs mandate <100%

> metro or regional vs metro and regional

> mandate sooner vs mandate later

> lite LXML vs full LXML

> bearings and distances boundary only vs all surveyor information

> multi-lot greenfield development vs ‘mum and dad’ two lot

> online portal vs distributed software

> in-house software development vs market software development

> training for all for free vs training for some/none

> digital for DP only vs digital for DP and strata.

Using the Framework will help focus decision making on achievement of outcomes. It has been

developed to facilitate agreement on a technical solution that will achieve outcomes such as

increased speed of registration, improved data quality and greater efficiencies for stakeholders.

Sample scenarios

A series of five sample scenarios for deposited plans, as well as one for strata plans and one for

approvals and associated documents, have been devised. The five scenarios for deposited

plans revolve around the file created and lodged by surveyors; an overview of these scenarios

is presented in the summary table overleaf. The scenarios have all been conceived through

initial engagements with stakeholders as part of this review; however, these are not intended to

represent final design solutions.

Details of each of the seven sample scenarios (five sample scenarios for deposited plans, one

sample scenario for strata plans, one sample scenario for approvals and associated documents)

is provided at Attachment J – Sample scenarios for solution design.

The outcomes and implementation of the seven sample scenarios have been assessed against

the Framework, with findings summarised in two separate tables in Attachment K – Sample

application of Assessment Framework. Again, these sample scenarios have been assessed

without consultation and input from all stakeholder groups and serve to illustrate the use of the

Framework as well as prompt discussion on possible design solutions. Further, these sample

scenarios do not consider Information Brokers, who exclusively deliver some survey plan

products and information to third-party consumers including surveyors, councils and utilities, on

behalf of LRS. Where LRS intend to include any delivery mechanism of digital plan information

through Information Brokers, the impacts must be considered.

Page 47: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

.

NSW DCS | Digital Survey Plans Review P47

Summary of sample scenarios for deposited plans

Scenario Lodged by surveyor

LRS Processing Examined by LRS Legal source of truth

Digital capture Technical solution requirements

Roll back digital

TIFF TIFF back-captured to LXML

TIFF TIFF Back-captured LXML

LRS sources a back-capture service provider

Structured CAD

Structured DXF DXF conversion to lite LXML

Boundary image for title rendered from lite LXML

LXML (with DXF to support examination)

Rendered boundary image from converted lite LXML

Boundary LXML Tool for conversion from DXF to LXML needs to be developed for bearings and distances-based boundary information digitisation

Lite LXML TIFF + Lite LXML None Examination of TIFF and lite LXML

TIFF Boundary LXML Rendering tool for boundary information possibly required

Full LXML TIFF + LXML None Examination of TIFF and full LXML

TIFF Full LXML Rendering tool possibly required

Full LXML only

LXML Render boundary image for title from LXML

Full LXML file Rendered boundary from full LXML

Full LXML Rendering tool for boundary image for title required

Page 48: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P48

4.4 Step 4: Implement solutions

Once the technical solutions have been proposed and the Framework has been used to

understand their impact and feasibility, changes should be prioritised based on the benefits

versus the ease of implementation. A detailed roadmap describing the steps of change should

be presented by the responsible party and agreed upon by the endorsing party or parties, then

adhered to.

Key implementation principles of equity and change management must be considered

regardless of the technical solution agreed in order to achieve the aims and benefits that

digitalisation of survey information seeks to realise. Likewise, mandating and legislative

changes may be required, depending on the technical solution.

Equity

Decisions made regarding potential changes to the format and content of plans will impact all

surveyors. Depending on the nature or extent of some of these decisions, different surveyors

will be impacted to varying extents. An important consideration for any decision making as part

of the pathway to digital plan lodgement is mitigating issues of fairness, perceived or real,

across surveyors.

In particular, the size of impacted surveying firms, and by proportion, the number of plans

lodged by the surveying firm, will likely dictate considerations for how digital changes are

implemented.

Training may be required and as a result, pose an imposition, for all firms, however it is likely

that smaller firms will feel this burden most. Unlike smaller firms, larger firms are more likely to

be in a position to have select staff undertake formalised training and specialise in digital plans

initially. These staff can then subsequently pass on the skills to others in the firm over time,

thereby easing the cost burden and opportunity loss.

Software is a cost consideration to firms. Small firms, or those lodging relatively very few plans,

will be disproportionately affected if new software is required to produce plans in a new digital

format.

As such, if specific software solutions are necessary, consideration should be made as to

whether these should be provided to the surveying industry, particularly to smaller firms. This

requirement would be mitigated if the software to produce digital plans is hosted in an online

workspace. This would, however, require changes to the current workflow for how surveyors

and their drafting colleagues produce plan graphics.

Mandating digital plans

Mandating was a common characteristic across jurisdictions which have high digital adoption –

they all noted that without mandating it would never have been achieved. Most surveyors

consulted were open to the idea of mandating, with many noting that there would be ‘grumbling’

Page 49: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P49

but the industry would just adapt and ‘get on with it’. Equally, software vendors and LRS

indicated that mandating would provide clarity on the likely return on investment from creation of

associated tools or processes to support digitalisation.

If changes are to be mandated, it should be well understood who will make such a decision, the

extent to which changes will be mandated, and how the changes will be mandated, for example

using a staged approach similar to eConveyancing.

There needs to be a viable, preferably co-designed, solution agreed to, tested and established

prior to mandating, with considered and agreed timelines that are clearly communicated to all

impacted stakeholders. It is likely that a minimum of 12 to 24 months (depending on the change)

will be necessary to give time for the industry to prepare and transition.

Legislative changes

Depending on the technical solution agreed upon, the legal source of truth for survey plan

information may need to change. Any legislative changes are likely to take time to be passed

and readied for enactment. Other changes to regulations may require less time or fewer

decision makers to implement, but regardless, it should be clearly established who will be

accountable for ensuring decisions are endorsed in a timely fashion.

Change Management

Surveyors have demonstrated a strong desire to be actively engaged in any digitalisation

process. Clear communication must be provided to all surveyors (and other impacted

stakeholders) along each stage of the design and implementation process. From LRS’ 2018

survey it was reported that the most effective mechanism for increasing industry awareness is

through seminars or conferences (reported by 59.5% of all respondents - all other channels

were selected by less than 6%).

Close and active industry involvement was also common to the digitalisation efforts of all

jurisdictions. This has been considered by all benchmark consultees to be vitally important and

was achieved via working groups, partnership with representative bodies and/or employing

independent surveyor(s) to be part of the project team. Continual engagement should also be

maintained with other jurisdictions, as any practical solution that works for NSW is likely to be

beneficial across Australia.

The industry will require time to adopt change and should be appropriately supported. A

measured approach, with an initial pilot test phase followed by gradual roll out of changes

(potentially such as initially greenfield subdivision plans for DPs or Section 88B instruments for

associated documents) will help minimise impost and encourage uptake. To assist with this,

consideration should be given to the technical support, such as training, that may be required to

assist industry members to begin to transition. This will also prevent a large initial adoption

immediately after the mandate coming into effect and avoid the resource strain that this may

pose. Once new solutions have been pilot tested then case studies with partaking firms should

be developed to identify possible issues and capture and communicate benefits to industry.

Page 50: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P50

An indicative implementation schedule has been shown overleaf. The timing of each element is

subject to the solutions chosen. The process may also include phased and parallel elements,

such as key digital associated documents being implemented while the technical solution for

digital deposited plans is designed.

The amount of change should also be considered and balanced, where synergies exist (e.g. a

transition to digital signatures and smart associated documents) then changes may be

implemented concurrently. Conversely, where changes are likely to cause significant disruption

(e.g. requiring the learning of a new software solution) these should be done independently to

avoid putting adverse stress on the industry. Finally, incentives to support early adoption should

also be considered. It was suggested by surveyors that reduced examination time and lower

lodgement fees would motivate them to lodge digital plans. However, it was reported by other

jurisdictions that little behavioural change was achieved through reduced fees and reduced

examination time is likely to be more effective. The Steering Committee should refer to the

experiences of other jurisdictions, notably NZ and WA, when determining how it can best

support early adoption.

Page 51: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

.

NSW DCS | Digital Survey Plans Review P51

Indicative process for phased solution design and implementation

Figure 6 - Indicative process for phased solution design and implementation

Page 52: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P52

5 Attachments

Table of attachments

A Surveyor sentiment

B Surveyor sentiment

C Council and utilities sentiment

D LRS sentiment

E DCS Spatial Services sentiment

F ORG sentiment

G Developer sentiment

H Software vendor sentiment

I Benchmark finding details by jurisdiction

J Sample scenarios for solution design

K Sample application of assessment framework

Page 53: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P53

Attachment A – Consultee details

Surveyors - Sydney focus group

> North Western Surveys

> Veris Australia

> RPS Group

> YSCO Geomatics

> D J Hore

> Craig & Rhodes

> RPS Group

> CMS Surveys

> Paul Lawson

Surveyors - Newcastle focus group

> Palmer Bruyn

> Le Mottee Group

> Tattersal Lander

> Bannister and Hunter

> Daly Smith

> Monteath & Powys

> Parker Scalon

> ADW Johnson

Regional surveyors

> PHL Griffith

> SMK Consultants

> Bradley Surveying

> Rygate & West

> King & Campbell

> Resource Design & Management

> Casey Surveying & Design

> Baxter Geo Consulting

> Hanlons Consulting

Page 54: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P54

> Hopkins Consultants

> Conway Burrows and Handcock

Utilities and councils

> Sydney Water

> Hunter Water

> Essential Energy

> Endeavor Energy

> Transport for NSW

> Tamworth Regional Council

> Penrith City Council

> Sutherland Shire Council

Software vendors

> Position Partners (distributor of Magnet)

> Landmark

> 12d

> LISCAD

Service provider

> LRS

NSW Government entities

> Spatial services - including the Surveyor General

> ORG - including legal and those involved in eConveyancing

> Department of Planning, Industry & Environment (DPIE) - ePlanning team members

> Transport for NSW (TfNSW) – including Roads and Maritime Services and Maritime

Benchmark jurisdictions

> Land Information New Zealand

> Landgate (Western Australia)

> Department of Planning, Transport and Infrastructure (South Australia)

> Department of Natural Resources, Mines and Energy (Queensland)

> Department of Environment, Land, Water and Planning (Victoria)

Page 55: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P55

Attachment B – Surveyor sentiment

Outcomes sought

Surveyors indicated that, regarding the lodgement of plans, they are motivated primarily by two

key elements:

> a desire to please clients – to achieve this they need to deliver a high-quality survey, at a

competitive cost, which will be lodged and registered quickly without contestation now or in

the future.

> passion and pride in their profession – there is a strong sense of professional integrity with

respect to the establishment of accurate boundaries; this minimises boundary disputes (and

possible indemnity issues), but also, in a tight-knit industry, maintains the reputation of the

surveyor.

Surveyors see not only their client, but also the next surveyor as the end user of their plans.

Surveyors rely on (after verification) the historic efforts of other surveyors to establish

boundaries; indeed, almost all surveyors consulted estimated that a large majority of what is

contained on a plan is only useful to other surveyors.

Surveyors see the next surveyor as the end user of their plans

Surveyor (Regional)

Attitude to digitalisation

Surveyors consulted feel it is important for the industry to adopt digital solutions relating to

plans, associated documents and approvals, to remain current.

If surveyors keep producing paper plans, we are going to be left behind as a profession; we

need to get better at sharing data

Surveyor (Sydney focus group)

As a highly technical field, it was reported that, despite the average age of registered land

surveyors being 5216, most surveyors are comfortable with digital technology. Whilst recognising

that the workflow sees ‘smart’ data being converted into a ‘dumb’ image, surveyors believe that

the current TIFF based survey arrangements work well. Consequently, there is some confusion

about what specific problem LXML is supposed to be the solution for – especially since a TIFF

image is still required by LRS. Surveyors feel the beneficiaries of LXML are largely LRS (easier

examination) and DCS Spatial Services (easier ingestion into the NSW Spatial Cadastre); yet

the costs are borne by surveyor’s clients.

The main benefits are for Government, we are just data collectors for them…if someone in

Government wants to play with it then fine, but why put the cost back onto our clients?

Surveyor (Regional)

16 https://www.bossi.nsw.gov.au/__data/assets/pdf_file/0010/222949/BOSSI_Statistical_Review_2019.pdf (accessed 20/11/19)

Page 56: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P56

Equally most surveyors consulted feel that it is critical that a monument-based approach is

adhered to and catered for within any solution. With this paradigm, the digital solution needs to

accommodate the non-mathematical, decision making aspects of the surveying process. There

is a perception that LXML focuses too much on coordinate data rather than decisions and may

be moving away from the monument-based system.

Monuments must rule, and measurements need to allow for variation

Surveyor (Newcastle Focus Group)

It’s not easy to digitise – it’s not a mathematical thing, it’s more a legal thing

Surveyor (Regional)

Issues with LXML

Short of mandating, the uptake of LXML depends on surveyors being motivated, either internally

or by their clients, to use it. Whilst some surveyors consulted saw benefits in LXML, almost all

voiced a number of issues that prevented them from utilising it regularly.

In LRS’ 2018 survey of surveyors, ‘time’ was the single largest inhibitor of adoption with 70% of

respondents selecting this when asked ‘What do you see as the barriers to adopting

LandXML?’17.

The (extra) time varies depending on the plan, two hours to two days, the plan is basically

redrawn to be able to export the LandXML format

Surveyor (response to 2018 LRS survey)

Surveyors consulted estimated that the average additional time to create a LXML is 30% extra.

This extra effort is due to the fact that in most software packages the LXML file must be created

separately. Whilst one software platform was praised for its handling of LXML, the majority were

seen to be difficult to use for LXML. Though creating just the boundary information in an LXML

file is not a significant addition of time, the inclusion of occupations, SCIMS and attributes was

stated to take a long time. It was also reported that manually editing the data (through Notepad

or similar) is difficult due to poor navigability of the file. Small existing lots in older areas with

complicated boundary definitions were seen to be particularly challenging to create in LXML.

Most of the time it is difficult to do things (in LXML) which are otherwise simple and quick

Surveyor (Newcastle Focus Group)

It’s time consuming including all the things in LandXML required for verification by LRS

Surveyor (Sydney Focus Group)

17 ‘Time’ was followed by ‘software vendor support’ (39%) which causes the additional time and ‘cost’ (34%), a result of the extra time.

Page 57: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P57

That the TIFF file has to be created in addition to the LXML is due to the poor quality of the

images rendered from LXML plans, such that they are not considered suitable for lodgement.

This is particularly problematic for bigger plans - it was reported that plans with over 90 lots

often struggled to render – and easements also complicate it.

The rendering is hopeless – just pages and pages of tables

Surveyor (Sydney Focus Group)

LandXML plan rendering is next to useless, thus requires an additional plan to be prepared

manually. The manually drafted plan needs to precisely reflect the LandXML coding, which

requires an additional check listing procedure. Also, the coding itself is extremely buggy and

can sometimes amount to several hours of debugging. LandXML coding as it currently exists,

requires surveyors to essentially double up on all plan preparation procedures

Surveyor (response to 2018 LRS Survey)

There is also a perception (particularly in regional areas) that LXML requires ‘unreasonable’

accuracies and that it focuses too much on coordinates instead of the bearings and distances.

LandXML is encouraging people to show distances down to the nearest mm and bearings to

the second, which is ridiculous

Surveyor (Regional)

Haven’t seen a package which ingests LXML and uses the reduced observations, not the

coordinates, to make the TIFF - but when LRS check the closure of the lots they use the

reduced observations

Surveyor (Regional)

The training required to effectively create LXML files was reported to be a considerable cost to

surveying firms. This includes both the costs of the courses themselves and, more significantly,

the lost productivity with staff attending training then becoming familiar with the format (most

surveyors estimated this took approximately two to four weeks). Training was also difficult to

access for some regional surveyors.

The training to get it (LXML) set up was significant

Surveyor (Sydney Focus Group)

Surveyors are frustrated by the fact that lodging a TIFF and LXML can, in some instances,

increase the chances of requisitions due to differences (many perceived to be inconsequential -

a few seconds or millimetres) between the two files18. Some surveyors, who create the LXML

file for QA only, do not lodge the file for this reason. Error reporting is also considered not-user

friendly, with the output hard to analyse to identify the major issues.

18 Though this is not an issue when using a software package that generates the TIFF and LXML from the same base data.

Page 58: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P58

Benefits of LXML

It is recognised that being able to retain smart data throughout the workflow would be useful,

both to minimise manual handling errors and for the reuse of data in future plan creation. In this

regard many surveyors who use LXML noted that they would highly value being able to access

LXML registered plans for their pre-calculations and plan preparation (as it would allow easy

plotting of adjoining information to a sufficient level of accuracy for a rendered plan). One

surveying firm consulted reported obtaining these plans from LRS, however all others were

either unaware of their availability or reported that accessing them is challenging.

Would be very handy to download a crown plan as an LXML file (as it is mathematically closed

and will save me a lot of time, maybe half a day building up a map of the surrounds)

Surveyor (Regional)

There were mixed views on whether LXML would improve survey quality and, in turn reduce

requisitions19. Most surveyors consulted believe that the nature of LXML is useful for QA as it

identifies issues such as mis-closes and other mathematical errors.

I pick up problems, missed lines or wrong connections, and use it even for plans I don’t lodge

with LXML

Surveyor (Regional)

Equally, most surveyors recognised that LXML would support automatic validation whereby the

file could be checked against LRS’ business rules prior to lodgement, allowing amendment of

any errors (and reducing subsequent requisitions). This service is already available; however

the validation is not in line with the current regulations and, due to the format of the error

reporting, is seen to be only marginally useful. Surveyors also recognised that the same

capabilities, if implemented well, would assist LRS in examination, in turn speeding up

registration of plans.

The realisation of benefits is largely seen as contingent on more effective software solutions.

Some surveyors noted that if the rendering of LXML improved they would then prepare the file

end-to-end themselves, rather than using a draftsperson who may inadvertently introduce

errors.

Despite the general consensus being that LXML would improve survey quality, there were a

small number of stakeholders consulted who did not support this view.

Electronic plans have the opportunities to have a lot of mistakes, might even increase, but

don’t think will significantly improve the accuracy

Surveyor (Regional)

19 However, surveyors noted that many clients do not expect requisitions and are therefore not appreciative of this as a benefit.

Page 59: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P59

Incentivising use of LXML

In absence of any intrinsic net benefits to surveyors, the incentives that were desired to use

LXML typically focused on their clients. As shown below, the 2018 LRS survey of surveyors

revealed the importance of turn-around time as a driver for uptake20. Being able to register a

plan faster was particularly compelling for developers with significant holding costs.

Figure 7 - Drivers to increase LXML usage

The survey findings were supported through consultations, where it was commonly reported that

when LXML plans were prioritised for examination that this was an effective selling point to

encourage clients to pay for the creation of the LXML – particularly for larger subdivisions with

significant holding costs. That there is only minimal time difference between electronic

examination of LXML compared to manual examination of TIFF plan images now21 has made it

harder to sell LXML, but there was variable appreciation this is largely due to the fact that TIFF

lodgement speed has increased22. Some surveyors suggested that if LRS were to reimplement

prioritisation of LXML then a written statement of this would assist in communicating the benefit

to their clients.

Akin to faster registration, making the plan creation process faster by only having to create one

plan was reported as highly likely to assist uptake. This again stems from the aforementioned

issues with the rendering quality.

The biggest issue for me is preparing two documents, so just doing one, be it LXML or TIFF,

would be best. There is a lot of time in drafting, the rendering service doesn’t currently work but

if you could just do LXML it could be faster than doing it as a TIFF; then just render the key info

for a title diagram

Surveyor (Regional)

20 Not only was ‘Faster turnaround time’ the most popular response, ‘Reduced number of plan requisitions’ will lead to reduced time and ‘At the request of a client’ is typically due to faster registration. Those who selected ‘Other’ almost unanimously specified the reasons as being easier and faster to make than presently (particularly if rendering worked so that a separate TIFF file was not required) or if it were mandated.

21 As of 19 November 2019, LXML plans were being examined one day earlier (7 November) than non-LXML DPs (6 November) according to the LRS website.

22 This is partly due to a reduction in plans submitted and, if submission rates increase the ePlan (normal TIFF lodgements) lodgement time may revert to being more significantly slower than EPlan (LXML lodgements).

0 10 20 30 40 50 60

Other

At the request of a client

Reduced number of plan requisitions

Faster turn-around time

Which of the following reasons would make you start using LandXML? (tick all that apply)

Page 60: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P60

The following other incentives for increasing use of LXML were suggested by surveyors:

> reduced costs of submission - this is seen to be justified if only LXML is used (rather than

TIFF and LXML), as it is perceived that this would reduce the effort for examination required

by LRS

> free training and software – particularly relevant for surveyors who do not have a strong

incentive to invest in LXML due to a low volume of plans being created for lodgement. It is

also felt that if free training and software were provided by LRS or Government it would

improve consistency across the state.

> reduced requirements – simplifying what is included on the LXML plan to just the essential

geometry (see ‘What’s on a plan’ below) would significantly decrease the effort to create a

LXML file (it was estimated that this may only require one hour of extra work for a ‘normal’

plan)

> acceptance across stakeholders – it was noted that all stakeholders (councils and utilities)

should be required to accept LXML plans to maximise benefits and avoid duplication.

They (councils and other authorities) must accept LandXML files, can’t just make the surveyors

go digital and no one else does

Surveyor (Newcastle Focus Group)

Attitude to mandating LXML

Almost all surveyors consulted reported that if 100% digital plan lodgement in LXML is

mandated then the industry would adapt within 12-24 months. It is likely that there would be

minor disruption with some firms being better placed to respond (i.e. those already using LXML).

Surveyors felt strongly that disruption would be minimised if the software improved and a

reasonable time for transition is established to manage the change. Surveyors also noted that

the legal source of truth would have to be clarified between the TIFF and LXML if mandated.

Smaller firms and those preparing plans for lodgement less frequently (such as small regional

surveyors) will be more disadvantaged and less likely to want to change and invest in the

software and training. Some consultees believe that across the state there would be a small

number of older sole practitioners who may rather retire. It was also reported that there may be

an increase in the use of third parties to produce the LXML files for those who cannot do it in-

house.

The training and software’s not worth it for the amount of work we do; clients don’t even know

about it. We would possibly do the field work only and farm out creation of the LandXML file

Surveyor (Sydney Focus Group)

The expectation to learn LXML is not feasible, only doing one lot a year and would take two

weeks to come up with something to satisfy LXML, I haven’t got time to learn

Surveyor (Regional)

Page 61: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P61

It was suggested by some surveyors that an equitable approach may be to establish a threshold

number of plans which can still be lodged in TIFF, above which they have to be in LXML23.

Overall, surveyors feel that if LXML is mandated then it is a ‘level playing field’ and surveyors as

an industry would not be disadvantaged. However, costs would be passed on to their clients

(noting that it’s a Government requirement), in which case it is likely that any additional costs

would be ultimately passed on to the purchaser who buys the land.

What’s on a plan

The contents of survey plans were discussed with surveyors, both to gather data for the related

‘Re-imagining Plans’ project and to understand what a minimal viable product (MVP) may look

like if digitisation of a simpler plan is pursued. Surveyors are keen to produce user friendly

plans, both for surveyors and other parties, but, as mentioned previously, believe that a large

majority of the information on survey plans is useful only to other surveyors. Most surveyors feel

almost all information currently on the plan should remain, but that only a small amount needs to

be digitised. There is some sentiment that information already held by LRS should not be

included on survey plans, such as parish and county data, addresses, as well as the permanent

mark table. In this regard some surveyors feel they are unnecessarily moving data from one part

of Government to another.

We’re just shuffling around Government data from one entity to another

Surveyor (Regional)

The concept of separating the ‘survey’ plan (for surveyors) and ‘title’ plan (for banks, clients and

solicitors) was regularly mentioned. This previously occurred in NSW (pre-1983) and occurs in

other jurisdictions, including South Africa where there are two different documents, a full survey

and the legal document, which is a subset of just basic information (boundaries and easements)

that is registered to create the title.

Basic parcel information is universally agreed as essential for inclusion on any digital plan, other

elements were variably supported (as essential) by different surveyors as per the table overleaf.

23 Or a similarly scaled incentive process with no-lodgement fees and high prioritisation for first 10 LXML files, 25% lodgement fees and medium prioritisation for next 10 LXML files and so on.

Page 62: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P62

Element Support

Boundaries (including dimensions and area)

Agreed by all Lot number

Easements

Bearings

Agreed by some

Reference marks

Relevant occupations and structures

SCIMS control marks

Adjoining information

Lastly, a constant source of frustration for surveyors is the inclusion of street addresses on

plans due to the challenges and delays obtaining these from council.

Real addresses are an administrative thing (between LRS and local council) that don’t need to

be there; putting them on is no problem, but getting the addresses from council can take six

weeks

Surveyor (Regional)

Alternative plan file types

It was reported that LXML as a file format is not commonly used by other stakeholders and that

CAD files (DWG/DXF) are the most common format in the design and construction industry. It

was noted that some councils and utilities also request these (sometimes with specific layer

structures), whilst others may request a PDF or TIFF (or even printed A2 plans).

Almost all surveyors utilise CAD files to exchange information from their calculation packages to

their drafting packages in which the TIFF is created, and many advocated the idea of utilising a

structured CAD file as a digital format.

The best way would be a simplified DWG/DXF that just contains the boundaries and

easements - it would only be an extra hour to create – so still lodge the TIFF image and

accompany with DWG/DXF (will be a one for one with the plan and readable) – a title search

would then be connected to that, would print an A4 diagram of that lot for attaching to title docs

– rather than having to look at a whole DP, with 30 to 40 lots. The typical landowner doesn’t

want to see that

Surveyor (Regional)

Page 63: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P63

Some surveyors proposed a solution where the raw data from the calculation packages (which

can export in a variety of formats) could be uploaded directly into a portal that generates the

information required by LRS and DCS Spatial Services.

Lastly, a small number of users suggested smart PDF (with layers) and CEXML (as used by the

NT) could also be explored for suitability.

Approvals and associated documents

Surveyors consistently noted that digitising approvals and associated documents hold the most

potential for improved efficiency. The current process of obtaining ‘wet’ signatures for

documents is seen to be both time consuming and frustrating (with risks of forms being lost or

held up in the post). It is felt that digital signatures and parallel endorsements would result in

significantly faster registration.

The biggest opportunity for efficiencies is approvals, it’s all being done in a straight line

bouncing back and down the chain, needs to be done in parallel

Surveyor (Regional)

Spend a lot of admin time posting plans or 88Bs around to get signatures

Surveyor (Regional)

Can take 4 to 6 weeks for the mortgagee to sign and another four to six weeks for council and

they can’t have it together at the same time

Surveyor (Regional)

Digitalisation additionally presents the opportunity to have the status of approvals tracked and

required endorsements can be automatically and appropriately applied then revisited as

needed. Equally, it can help speed the creation and accuracy of associated documents by pre-

populating key information.

If creating easements for example, then it should automatically populate the admin sheet for

creation of the 88B

Regional Surveyor

There was also a suggestion to lodge plans (including associated documents) while waiting for

approvals. Similar to the current pre-examination process, at additional cost, a preliminary

examination would be conducted without signoff, but a guarantee would be provided that, when

all signatures come in it can be registered almost instantly (assuming no changes are flagged).

Strata plans

There were mixed views on opportunities for digitisation of strata plans. Some surveyors believe

that as they are simple plans compared to normal DPs, they are a good candidate for

digitisation. However, surveyors were not convinced that LXML is a suitable file format for strata

plans, again preferencing a CAD file.

Page 64: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P64

Some surveyors however, expressed concerns with possible liability issues arising from the

inherent generalisations in the strata plans (i.e. if someone used them to make a digital model

and then realised it did not perfectly line up with the space). There were also broader questions

about the appropriateness of surveyors’ strata plans, compared to those of the architects, being

used for the data records.

A lot more opportunity to do this with strata plans but LandXML is probably not the right format.

Need lot number and area determined by the surveyor. Strata plans are the most rubbery of

the lot, the way the legislation is written, have to replicate a complex building with two

thicknesses of lines - it’s impossible. We need a good picture but not something you can get an

area off of. More bang for your buck to make strata simpler, leave DPs out of it for now

Surveyor (Regional)

Other opportunities

Surveyors identified a number of other opportunities for improvements that digitalisation could

help enable. These included the following:

> automated notifications when other PPNs in close proximity to the surveyor’s are registered

> a more customer friendly plan search functionality for registered plans from LRS (this would

also benefit LRS by enabling self-service)

> enhanced boundary determination evidence such as photos and/or videos of where survey

marks were found, and information tagged to lines and points in the smart data.

Though unrelated to digitalisation directly, it was requested on multiple occasions that the

registration of plans be separated from the issuing of titles. The inclusion of these non-current

plans on a separate layer is seen as an opportunity to enhance currency of the NSW Spatial

Cadastre and would help avoid a survey being completed but not lodged for a period of time in

which another survey has been conducted that impacts the boundary definition.

Other findings

Through consultations surveyors also commonly expressed two other concerns; variable

satisfaction with the performance LRS, particularly the quality of requisitions, and frustrations

with the state of the NSW Spatial Cadastre.

Some surveyors reported that the performance of LRS had been variable in recent years.

Issues consistently related to the quality of requisitions and there is a perception that examiners

do not focus on the right elements due to a lack of surveying knowledge. Some surveyors

however, noted that in the last six months this has improved and LRS has been more inclined to

avoid minor requisitions where possible.

LRS used to be very much oriented to checking the position of the boundaries and the trail of

the title, any encumbrances etc. but now we have a tick a box mentality where we are getting

requisitions on every plan

Surveyor (Regional)

Page 65: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P65

LRS is getting better now, there will be a phone call with a minor error saying fix this up and

send it back and we won’t requisition you

Surveyor (Regional)

Many surveyors stated that they now assume they will be requisitioned for every plan. The

resolution of requisitions is also a pain point for surveyors who reported that call backs to

discuss issues with the examiner are too slow, and that it is faster and easier to just accept the

requisitions and make the modifications, even if it reduces the quality of the survey.

Can either change plan to get it accepted quickly or can dig your heels in and stick to what is

right

Surveyor (Regional)

Another minor issue noted was the lack of value in pursuing pre-examination as it conferred no

assurances to surveyors that their plans would be more likely to be registered faster. It is felt

that LRS should offer semi-automatic registration if the lodged plan does not differ from an

approved pre-examined plan.

Additionally, there is some confusion over the lack of ownership of the digitalisation of plans by

LRS, with some surveyors expressing surprise that LRS had not driven digital plans harder.

I honestly expected when LRS was privatised they would come up with a different stream for

LXML which would be faster and cheaper – but they don’t seem that interested, and we are

doing their work for them

Surveyor (Regional)

Lastly, some surveyors expressed frustration with the state of spatial cadastres across the state.

There is confusion by some surveyors as to why new plans are being made to fit with old plans

rather than the other way around in the NSW Spatial Cadastre. Additionally, some surveyors

reported being concerned that some of their survey work does not result in accuracy improvements

to the NSW Spatial Cadastre (e.g. where redefining boundaries for rail infrastructure) and that so

many entities have their own spatial cadastres that do not interface with each other.

Sharing the spatial cadastre with more individual councils would be good, the more people that

are contributing to it and have access to it the better

Surveyor (Regional)

Page 66: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P66

Attachment C – Councils and utilities sentiment

Property - uses

Representatives from Property teams within councils and utilities reported that their primary use

of plans is to:

> update property records to deliver services

> produce planning certificates (e.g. spatial relationship to planning restrictions, roads or

environmental corridors)

> determine applicable rates

> record the location of assets (for maintenance and repair).

Property - spatial cadastres

Property teams typically maintain their own spatial cadastre, with some regularly drawing base

data from the NSW Spatial Cadastre. While most of the representatives engaged with indicated

a willingness to move towards only utilising the NSW Spatial Cadastre they reported that their

concerns with its accuracy prevent them from doing so. It also does not contain all types of

registered plans in all instances (e.g. registered leases, acquisition plans, easements). These

currently require manual effort by the property teams to digitise against their internal cadastres

wherever not captured in the NSW Spatial Cadastre. It was also noted by some representatives

that their own spatial cadastres are updated more rapidly than the NSW Spatial Cadastre (three

days compared to ten days).

Councils and utilities add data to their spatial cadastres at various stages, but all are eager to

incorporate data as soon as it is available to assist with other planning activities. Data is

typically received as a CAD file or PDF/TIFF file. Whilst some organisations, such as Sydney

Water24, have a specific layer structure for CAD files (for those prepared by a water servicing

coordinator at the proposed stage only)25, there is no standard structure used across the

industry. As such, entering data from CAD or image files into spatial cadastres was reported to

be currently labour intensive. The GIS systems were believed to support LXML for easy

ingestion, however the files are still required to be fit to the fabric of the organisation’s spatial

cadastre which requires manual effort. One council reported obtaining LXML from DCS Spatial

Services through the ‘capture on demand’ service and 40 councils have either production or

pre-production accounts26, however the format is not currently widely utilised. Representatives

from multiple other organisations noted that while they are not using LXML from DCS Spatial

Services, they are exploring LXML’s use for the future.

24 Sydney Water also developed an AutoCAD plugin which then assigns standard line weights and colours to specific layers.

25 Smaller subdivisions (2 lots) submitted to Sydney Water through its inhouse ‘Developer Direct’ service are submitted as PDF files.

26 A further lift in adoption is expected once the service is expanded to support strata plans.

Page 67: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P67

Property – plan contents

Representatives from Property teams had differing views regarding the information they

required from plans; however, the following elements were reasonably consistent:

> parcel information (boundaries, dimensions and area)

> easement lines and restriction references (indicative of asset locations)

> unit entitlements for strata plans

> roads and references.

Property representatives noted that it is desirable to confirm addresses at the DA stage, as it

enables them to tell developers the addresses for sales documentation and drive surveyors to

correctly sequence the lot numbers (street direction) It would also be beneficial to utilities (to

ensure meters are consistently assigned) and emergency services (to locate sites) during the

construction stage. However, managing this is problematic and complex, resulting in different

management processes utilised by councils across the state One of the councils consulted has

a process to provide address numbers for free within a day of receiving a request via email,

while others charge for the service and have longer service delivery timeframes.

The address is important when using it as sales document; it also helps force surveyors to

sequence the lot numbers in alignment with the direction of numbering of the street. At this

point in time it’s creating work, but important to have on there

Council GIS manager

It was also reported by Property team representatives that some private certifiers are approving

strata plans even when the directions of council (e.g. addresses allocated) have not been

adhered to. Unaware that this has occurred, surveyors are only discovering the strata plan is

wrong when registering it. Local surveyors who regularly work in the area were seen to be more

conversant with councils’ rules and requirements, more likely to correctly apply these and

therefore have plans processed more rapidly.

Planning

The other main user group within councils and utilities are the Planning teams who utilise plans

to confirm alignment with the conditions of consent stipulated at the Development Application

(DA) stage. For this purpose, an image was seen to be adequate for reviewing.

Some of the organisations consulted reported using the ePlanning portal for managing DAs.

These organisations asserted the ePlanning portal is a good tool for the end user, as it has

streamlined the front-end, ultimately increasing the speed of the process. Nonetheless, front-

end efficiencies have not been matched at the back-end, which still requires a significant

amount of effort and resources to manually create applications and endorse DA plans. These

DA plans must be physically printed and signed, then scanned back into the system. Systems

integration with enterprise software systems, such as Technology One, is being pursued and

should help automate workflows.

Page 68: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P68

ePlanning is great as the Government is now accountable for meeting the times for the

referrals (which can be tracked) rather than relying on council chasing, also great for

customers as it saves time driving between councils

Council Planning Administrator

Opportunities for digitalisation

Representatives from both Property and Planning teams across all the councils and utilities

consulted consistently articulated a number of opportunities for digitalisation. If implemented,

these would improve the efficiency, speed and quality of service relating to plans for registration.

A compelling benefit to both internal staff, as well as surveyors and their customers, is faster,

more accurate processing of plans enabled through digitising plans, particularly approvals and

associated documents. Digital signatures are seen to be an obvious improvement that would

support faster approvals. The current requirement to have wet signatures delays councils

signing off the subdivision or strata plan. Use of digital signatures would reduce internal

administrative effort and minimise holding costs for developers.

Some of the developers’ holding costs are $50,000 a day

Utility Approvals Manager

A digitised signature would give team members two to three hours a week back; broader

digitisation would save a few hours per application – huge benefits

Council Planning Administrator

Consultees expressed a degree of agnosticism for the specific format but believe, critical to

reducing internal effort, is the ability to automatically obtain smart data from plans (DP numbers,

lot numbers) to avoid manual entry. It was estimated by representatives from one organisation

that doing so would save significant time (half an hour per plan) from that process alone. This

metadata would also be useful for workflow automation, where it would be automatically

ingested into council and utilities work management systems.

Once the applicant has submitted the document it should be straight into LRS; a subdivision

certificate with a two to three week turn around could be reduced to one week

Council Planning Administrator

At the moment we are coding from one format to another, digitising off PDFs, none of that

would exist if we had smart digital plans as the standard for proposed land and registered, it

would be so much faster - LXML isn’t necessarily the requirement, the key thing is getting the

data electronically including the metadata

Utility Spatial Manager

It was also suggested that a digital workflow system should connect automatically to a portal for

automatic notification of approvals by other parties. This portal system would enable visibility of

the status of an application for all parties, including when documents are changed by a surveyor

(at the request of other authorities) and may require subsequent re-review of approvals already

given. Presently these changes may occur without the approvers (particularly utilities)

knowledge.

Page 69: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P69

A bit more communication between the council and utilities rather than having the applicant as

the middleman would be much better

Council Planning Administrator

It should be coming back for signing after changes have been made – there is a need to sign it

every time its requisitioned with currently manual signing back and forth between LRS and

Council which could be digital

Council Planning Administrator

Almost all of the representatives consulted from councils and utilities desire to utilise smart

documents (pre-populated forms with inbuilt data validation) wherever possible to enhance

accuracy and save time. Having standardised templates that can be easily populated, (e.g.

Section 88Bs with standard clauses), and with mandatory fields, (e.g. plan purpose, underlying

DP, lot numbers), that can be automatically validated is seen to be a major opportunity for

digitalisation. This would also assist to drive consistency across the state. It was reported that

LRS have made changes to land title dealing forms - the idea of interactive forms has been well

received, but it was noted that they have missed administrative information, which requires

handwritten amendments.

88Bs can be problematic (e.g. used the wrong memorandum). Ideally digital data comes

through and is colour coded depending on the type of interest being created (still want to check

the title plan); it would save a fair bit of time, look at tonnes of these every year – probably

half-a-day’s work per plan and look at over 60 a year. There are less than twelve different

memorandums which could be templated and would cover 90% of cases.

Utility Asset Manager

The concept of a dataset was suggested whereby a single source of truth for the application has

the key information entered once. This information would then be automatically included in the

relevant plan documents. This would also enhance consistency of naming files and labelling

elements, which is currently an issue.

Another opportunity raised by councils and utilities representatives, primarily those from the

Property teams, is the potential for operational staff to access digital information in the field if

there is an increase in digitalisation. This is in line with the broader ambition to go paperless

within almost every organisation consulted; many reported that digital signatures and fillable

PDFs are becoming common practice. Likewise, there is a current push for renewed focus on

customer service across organisations27.

We are trying to keep stuff digital, once it is created digitally it stays digital

Council DCS Spatial Services Manager

27 Relevant initiatives in this space include one council reporting that the Planning team is now customer oriented as a ‘one stop shop’ for development approvals (planners, engineers etc. all in one division now to assess) as well as online mapping capabilities being shared with public and a self-help portal showing developers their current database to aid their planning efforts.

Page 70: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P70

We are required to have hard copy documents with wet signatures, it’s the biggest thing that

needs to change and the only process left that is still hard copy

Council Development Assessment Coordinator

Lastly, it was noted that digitalisation presents opportunities for enhanced strata data being

captured and carried over for building information management (BIM) applications. Similarly,

having additional clarity through easy identification of lots and maximum extent information is

increasingly useful when assessing planning permits for strata / stratum developments.

Barriers to change

Whilst a definite willingness for digital change was observed, some councils suggested that the

smaller scale of regional councils, that typically have small teams and a low volume of DAs,

would be limited their ability to invest in digitalisation. There is also a diversity in terms of

internal software (Technology One, Civica Authority, SAP and others) that somewhat

complicates solution interoperability.

Page 71: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P71

Attachment D – LRS sentiment

Outcomes sought

LRS acts as the middle party between Government and the industry, it therefore sees its

customers as both the general public and surveyors. The function of LRS is to facilitate the

necessary transactions to create and maintain land title records on behalf of the NSW

Government. In this regard a primary outcome sought from its operations is maintaining the

satisfaction of the ORG – this is contingent upon the integrity of the Titles Register being

preserved and enhanced. LRS also reported a desire to ‘improve plan lodgement, examination

and registration outcomes for customers and citizens of NSW’.

Additionally, as a commercial entity, LRS must adhere to the conditions of its contract and

operate in a commercial manner. It is therefore driven to provide services efficiently as possible

without compromising service quality.

Opportunities for digitalisation

LRS perceives robust opportunities for digitalisation to help achieve the outcomes sought. This

includes faster assessment of plans and increased quality, leading to reduced plan requisitions

and amendments.

Currently LRS examiners have to check both the TIFF and the LXML if submitted. This is a

manual and burdensome process that requires more effort to examine than if only a TIFF is

lodged. Smart digital surveys have the potential to allow for increased accuracy and automation

of examination. Human assessment of decisions will still be necessary in all cases, but digital

plans were seen to offer the ability to include enhanced information about where the survey was

started from and what methodology was applied in boundary decisions. LRS stakeholders did

not indicate a preference for any particular file format for lodgement, noting that they were

somewhat agnostic as long as it could be easily converted into another suitable format (if

required to be).

Minimising requisitions is seen to be a significant benefit for LRS and surveyors and a strong

opportunity for digitalisation. LRS stakeholders cited a number of minor typographical errors

they encounter that could easily be mitigated through smart associated document forms with

data controls (e.g. compulsory fields and data validation). They have started with some

automated templates, which have reportedly been well received.

The current manual entry (hard copy) channel, which accounts for approximately 20% of plans

lodged, requires additional effort to manage and process paper documents. LRS would support

mandating digital lodgement.

More broadly, LRS is keen to simplify and automate the lodgement process and plans as much

as possible, making it easier to create and examine plans.

Page 72: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P72

Barriers to change

LRS accepts its responsibility for supporting and driving digital change. However, it is mindful of

the history of the introduction of LXML and is keen to not replicate the previous approach,

where there was insufficient engagement with surveyors and benefits were not balanced. As

such there is a strong preference for industry co-design and involvement in the process.

Page 73: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P73

Attachment E – DCS Spatial Services sentiment

Outcomes sought

As the provider of spatial and land information services, DCS Spatial Services’ stated primary

objective is to ‘fully leverage spatial products and services in support of the NSW Government

Digital Strategy which, in turn, has improving service to the community, Government, industry

and the environment as its purpose’28. A key success factor, critical to achieving its objective, is

ensuring the NSW Spatial Cadastre is current, complete and accurate. The NSW Spatial

Cadastre graphically shows legal and other approved boundaries applying to land and supports

a range of community, business and Government activity – from tourism and land management,

to electoral boundaries.

DCS Spatial Services is also responsible for the surveying profession’s standards through the

Surveying and Spatial Information Act and Regulation and the Surveyor General’s (SG)

directions.

Opportunities for digitalisation

DCS Spatial Services has developed a tool to automatically validate then convert LXML files

into the ArcGIS format required for importing into the NSW Spatial Cadastre. This process has

already been seen to provide benefits to DCS Spatial Services by enabling faster, more efficient

upload of accurate information to the NSW Spatial Cadastre.

It was reported that the utilisation of the validation tool has identified geometry errors in

registered plans prior to upload into the NSW Spatial Cadastre. It is felt that these errors could

be picked up by LRS prior to plan registration if the same validation tool was utilised, enhancing

the accuracy of information received. Validation tools also provide the ability to identify

incomplete data sets. More generally, by improving the accuracy and usefulness of the NSW

Spatial Cadastre it is probable that more organisations will cease operating their own disparate

spatial cadastres and there will be convergence towards a single source of truth.

Automated checking and ingestion into the NSW Spatial Cadastre is also seen to offer

significant efficiency gains by minimising double handling through multiple manual entries.

Capture once, use many times

DCS Spatial Services representative

28 https://www.spatial.nsw.gov.au/about_us (accessed 20/11/19)

Page 74: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P74

More broadly, representatives from DCS Spatial Services also cited a number of other

opportunities for digitalisation, including:

> faster, more user-friendly plan discovery for surveyors

> inclusion of a more detailed and complete proposed layer29 in the NSW Spatial Cadastre

integrated into the broader property development life cycle and supporting other

Government initiatives like the ePlanning portal

> enhanced workflows and integration with other related datasets such as Survey Control

Information Management System (SCIMS), transport network and imagery

> propagation and support of the survey control network, by incorporating newly placed

permanent survey marks while also updating the status of permanent survey marks and

upgrading the accuracy of their recorded location

> the potential to enhance the evidence and defensibility of boundary decisions; in turn

supporting the SG to improve the quality of survey practice in NSW

> improved integrity of the cadastre through more comprehensive regulatory compliance

measures enacted in a more customer friendly way

> supporting progression towards the national Cadastre 2034 vision30 and NSW digital twin31.

Strata plans are seen to be another opportunity for digitalisation, especially to provide more

information on where the relevant space is within the parent lot (i.e. which building an apartment

is in within a multi-building estate). It is felt that this would have significant benefits for the

general public relating to mapping (e.g. emergency service access) but that, before this can

progress, there should be agreement on what digital data for strata plans is required (e.g.

dimensions and height information).

A lot of information on a full LXML plan is not required for the current scope of the NSW Spatial

Cadastre (and is not ingested). It is felt that a LXML ‘lite’ or similar format may be feasible and

that this would not need to include elements such as occupations or adjoining information. It

was reported that the file would, at a minimum, require complete geometry for every parcel

(including boundaries, bearings and distances) as well as survey control and that, whilst

currently RMs and easements aren’t ingested, in future these may be a useful addition to the

NSW Spatial Cadastre.

DCS Spatial Services has developed its current system to ingest LXML files into the ArcGIS

format required for the NSW Spatial Cadastre. It would require adjustment to accept other file

types, however this is possible. Whilst it is recognised that CAD files do not contain intelligent

digital data it was noted that the system could be modified to ingest these and that DXF may be

a viable option worth exploring.

29 Currently this information is only obtained from councils at subdivision certificate sign-off; digital plans may support automatic addition of this information at the DA stage.

30 This envisages a fully automated process with a federated (based on common standards) 3D cadastral system which is survey accurate. In the short to medium term this is likely to include a 2D map base with 3D information in an adjacent dataset.

31 A 3D or 4D cadastre is essential data underpinning the digital twin which has a broad range of use cases across land use planning, the built environment, infrastructure development, natural resource management, emergency services planning, and Government services.

Page 75: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P75

Barriers to change

Whilst LXML is utilised currently, it was noted by DCS Spatial Services’ representatives that it is

not an ideal format. LXML is seen to be ‘inefficient and cumbersome’ to use and the poor

rendering quality prevents easy visual interrogation of the data. There is also not a suitable

place to include all data contained within the administration sheet attached to a plan in a

machine-readable form. Ultimately however, the biggest barrier preventing DCS Spatial

Services from benefiting from digital plans has been the low take up of LXML by industry.

A number of entities across the state (particularly councils and utilities) maintain their own

spatial cadastres. This was initially prompted by previous business model to charge users to

access the NSW Spatial Cadastre. Though this is now a free service, over time, other entities

have improved their spatial cadastres to the point where they are more accurate or aligned with

the other entities’ datasets than the NSW Spatial Cadastre. This multiplicity of datasets

contributes to a disaggregation of benefits and lack of ownership for improvements. DCS Spatial

Services have been working with councils to demonstrate and improve the quality of the NSW

Spatial Cadastre; the benefits of digitalisation should augment these efforts.

Page 76: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P76

Attachment F – Developer sentiment

Outcomes sought

Developer representatives reported a simple objective from the process of plan registration;

being to have plans registered as quickly as possible with the least complexity, in a cost-

effective manner.

It was noted that when plans are being processed by LRS is often at the height of debt and

investment for the developer, where a delayed registration can have material financial

consequences. Developers are therefore highly motivated to ensure the plan registration

process is as quick as possible. They are also keen for it to be efficiently priced, recognising

that increases in cost in some cases may be overall worthwhile if there is a resultant decrease

in time to registration.

Opportunities for digitalisation

Developers engaged with are strongly supportive of digitalisation. They perceive significant

opportunities relating to the speed and transparency of the plan registration process.

It is believed that digital plans will enable quicker examination and registration by LRS. One

developer noted that when LXML was first introduced they had a very positive experience where

a plan was lodged and registered within 48 hours.

We thought as an industry it was a great idea – the gap between finishing the subdivision and

house construction commencing can be 6 to 9 months and there are costs with loans.

Developer

Developers also have high expectations for the ability of digital plans, particularly associated

documents and approvals, to speed up the end to end process by facilitating automated

workflows between the various reviewers and approvers.

Can’t see why there isn’t a situation where, once a utility issues their certification, it is

electronically transferred to council, then automatically released to LRS who automatically

assess and register it - then the loans are settled, and house construction starts

Developer

Developers noted that they have only a ‘casual engagement’ with the plan registration process

and rely on whatever information is provided by their surveyors. It is seen to be a very complex

process with a multitude of elements, where increased transparency would be highly valued to

enhance their customer experience and potentially also assist in the speed.

It would be great being able to see where referrals and maters arising are siting or why

additional information has been requested. We always have to do it through consultants who

blame each other and the approvers

Developer

Page 77: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P77

Delays can lead to clients saying that their builders now want to put up house prices and then

we find out that a missed $450 fee has held up a 2,000 lot subdivision being registered

Developer

Related to transparency is the ability to integrate data streams into other digital elements.

Developers suggested that linking digital plans with other aspects of the whole development

cycle, such as ePlanning and eConveyancing, should be explored.

We have digital information and spatial information and planning regulation and other

regulations; if we could integrate to be able to use and measure performance in real time that

would make a big difference

Developer

Integrating the digital plan data into the design and construction side of developments is also

seen to be an opportunity. Developers reported not being too concerned with the contents of a

plan (provided there is a clear boundary with dimensions and easements). However, being able

to obtain final plans in a CAD format that builders could use as a base plan to sight houses on

would add to the value chain.

Barriers to change

It was noted by developers that the low uptake of LXML from the surveying industry had

surprised them. Speculations were made as to the reasons for this, but developers reported

feeling as though many surveyors did not value LXML. This has had some reputational

consequences and shifting industry (both developers and surveyors) sentiment was seen as

critical to achieving digital change.

LXML was supposed to be the great saviour and that fell over, not sure what happened but as

developers we are a bit sceptical

Developer

Educating the market of any changes and benefits was seen to be very important to supporting

adoption. Training, providing content for seminars and establishing partnerships with industry

associations are all viable options to achieve this education. Through the process, consideration

must be given to the diverse scale of entities and recognition that the major companies are likely

well informed but that smaller ones will not be.

Page 78: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P78

Attachment G – ORG sentiment

Outcomes sought

The ORG sees its customers as landowners, surveyors, conveyancers and developers

(including big developers and ‘mum and dad’ developers), among others. It needs to ensure

integrity of titles and the cadastral system. In practice this means overlapping boundaries and

mistakes in documentation are minimised and easements and restrictions are always on the

title. Preventing errors after registration helps to reduce Torrens Assurance Fund (TAF) claims,

as well as professional indemnity claims. More broadly the ORG desires to increase efficiency,

accessibility and availability to ensure better outcomes for customers.

Opportunities for digitalisation

The ORG is very keen to progress digitalisation as it is a Government priority (‘Government

made easy’) and there is significant support for this within Government to increase efficiency,

accessibility and availability to ensure better outcomes for customers.

ORG believes that digitising plans will present opportunities for automated validation, which will

help eliminate plans being registered with errors (in turn minimising subsequent amendment

actions). It is also felt that digital plans, particularly digital approvals and associated documents,

will help increase the speed of registration and in turn, reduce holding costs for developers.

Whilst most of the opportunities for digitalisation do not directly apply to the ORG, there is

potential for digital information to assist the ORG in its regulatory role if it can quickly consume

data and extract relevant insights.

Lessons from eConveyancing

Through the introduction of eConveyancing a number of observations were made, and lessons

learned. Representatives from the ORG reported the most salient of these were realising the

importance of:

> commercial benefit – the most obvious benefit was the substantial decline in time required

by lawyers and conveyancers - from minimising data entry, time spent on the phone with

financial institutions (obtaining relevant information for the transaction) and remedying

mistakes and errors - freeing their time up for other work.

> governance – the ORG retained responsibility for the governance and policy, LRS was

responsible for the IT solution and business rules.

> industry engagement – the ORG lead engagement with stakeholders via constant digital

communications and multiple roadshows across NSW to promote benefits and obtain input

from regional and metropolitan stakeholders.

> mandating – this assisted with driving industry uptake and without this the uptake would

have taken much longer. It was also noted that adhering to the stipulated timelines conveys

the right message to industry that Government is committed to the initiative. The mandate

Page 79: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P79

notice period should be reasonable and decided upon after close consultation with

stakeholders, including strong partnership with peak industry bodies.

> staged roll-out – eConveyancing was introduced through a three-stage mandate which

focused on the easier, high volume documents first in the transition towards complete

adoption. In 2017 it was stipulated that all standalone mortgages and refinances go digital,

in 2018 standalone transfers, caveats and all refinance documents had to be lodged

digitally, and finally in July 2019 all mainstream property transactions had to be lodged

digitally. These timeframes were believed to be the shortest possible to achieve a practical

and sustainable outcome for eConveyancing.

> support for industry – it was reported that PEXA provided valuable one-on-one systems

training for an initial number of transactions. Additionally, peak bodies (such as Australian

Institute of Conveyancers and the Law Society of NSW) provided group training on the

reform in general (including new regulatory and legal requirements). This support to industry

assisted with promoting the platform and bringing users onboard incrementally, preventing a

rush of users signing up at the last moment and causing unnecessary strain on the system.

The ORG representatives noted that, as a result of the changes to eConveyancing, namely the

removal of middle parties, it is now closer to the customer and its customer base has expanded.

Page 80: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P80

Attachment H – Software vendor sentiment

Business drivers

Most of the software vendors engaged provide civil engineering software in addition to

surveying software. While the latter typically represents a smaller revenue stream than the

former, all maintained that providing surveying software packages is core to their business. The

importance of the NSW survey market also varied between software vendors; again though, it

was consistently noted that it was an important one32.

All software vendors reported valuing a close working relationship with their clients and, in

response to their anticipation of the industry moving towards mandated LXML, have added

LXML capabilities to their software. It was observed, however, that despite an initial surge (seen

to correlate with prioritised examination), surveyors’ interest in LXML has subsequently

decreased.

Benefits of digitalisation

Software vendors are naturally very supportive of digitalisation of survey plans. There is a

general consensus that, whilst LXML is not perfect, it should remain unless a better alternative

is developed, and that the NSW recipe is appropriate.

Software vendors all reported that digital plans should lead to time savings in the production of

surveys, (particularly when working within digitally established boundaries), and cited that it

could reduce the need for a draftsperson if rendering is better capable of producing a plan

image. It was also noted that digital plans would enable automated pre-validation and

examination, reducing human error. This would be further supported by the ability to include

additional survey evidence as metadata, such as photos (though it was reported that the format

may have to change slightly).

Issues with LXML

Despite overall support of LXML, software vendors raised a number of concerns. These were

primarily related to the ability of the format to render plans, its suitability for 3D and

inconsistency across jurisdictions.

Whilst the approaches to implementing LXML within the software packages varied, there is

consistent acknowledgement that the format is data based and not well suited to rendering plan

images. Whilst all software vendors reported that their software packages could produce a

LXML, the amount of additional effort to do so (compared to producing a CAD file or TIFF)

varied between packages. The frustrations of surveyors around having to duplicate effort to

create a LXML is appreciated by vendors (who likely anticipated an effective rendering solution

32 And one for which they would respond to changes, particularly mandates.

Page 81: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P81

being provided). As noted above, it is felt that if the LXML could be lodged without a TIFF then

the total time of creation would be similar to just creating a TIFF.

LXML doesn’t have a presentation layer, it’s purely data – we are trying to get a format which is

not designed for a plan into a plan - things like font size and direction are just not in LXML

Software vendor

Whilst some software vendors reported that strata plans could be produced in LXML, the

general consensus is that it is not an ideal format. This stems from the belief that LXML strata

plans are too complicated and that a 3D native format should be adopted with the potential to

support a 3D cadastre and align with building information modelling (BIM).

Software vendors were frustrated that the LXML recipe is not consistent across the country,

making it harder to invest in a single solution. The challenges that prevent this were largely

understood but some software vendors believed these could be at least partially overcome with

national coordination. As a result, most of the software vendors focus their products on only one

or two jurisdictions, with the differences across states requiring subtle but significant effort to

customise the software.

They say it’s ePlan for Australia but it’s not, very different inclusions in LXML between each of

the states – until they have one cadastral system for the country it won’t happen

Software vendor

There was also sentiment expressed from some software vendors that, whilst the content is

good, the NSW LXML is not well defined and there are elements and attributes that can be

interpreted differently. As a result, the implementation of LXML across different software

packages is believed to differ slightly. It was noted that whilst they can still import/export LXML

files into any of the software packages, there is a need for clear definitions of all the attributes.

Alternative formats

Most software vendors have not explored other formats in detail and there is no strong

consensus on an ideal solution. Suggested formats included CityXML (used in Singapore), Land

and Infrastructure Conceptual Model Standard (LandInfra) or Industry Foundation Classes (IFC)

but these would require further investigation.

Two software vendors suggested that the best way forward would be for NSW to develop its

own XML based file format. If NSW led the creation of a new format it would ensure it has the

exact information required by all stakeholders within NSW (and could potentially then be

modified for other jurisdictions). This could be similar to the current LXML format but with some

improvements (effectively a superset of the current LXML elements) and clear definitions. XML

is seen to be ideal due to its Unicode implementation (able to handle many languages). It is also

believed to be a secure ‘archivable’ format which will be readable in the far foreseeable future.

It is believed that developing a tool to convert from LXML to a new XML format would not be

technically challenging, and that most software packages could be modified to work with the

new format within a short period of time (three to twelve months depending on the extent of

Page 82: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P82

change). This would require an acceptance that a visual plan (other than potentially a simple

rendered boundary plan) is no longer required. In turn it will enable digital interrogation of the

file to fit the users’ purposes (e.g. turning on relevant layers and being able to zoom in digitally).

The file format could also support additional metadata such as photos, videos or textual

comments to provide evidence of boundary decisions.

Whilst it is recognised by software vendors that CAD files fit within the current standard industry

workflow, it was also believed by some software vendors that allowing these diminishes the

benefits of genuine ‘smart’ formats such as those which are XML-based. It was also noted that

the proprietary nature of DWG should exclude it from consideration as a format (as this will go

against the Government’s view on open and accessible data).

DWG is not an industry friendly format; it’s so locked down. It should not be anything

proprietary as this is against Government’s view on accessible and open data. DXF doesn’t

have those issues, but it’s still a CAD format and is not designed for smart data - then you are

still locked into drafting, the same thing that has held industry back for years when we should

be focusing on data.

Software vendor

Page 83: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P83

Attachment I – Benchmark finding details by jurisdiction

New Zealand

Digital survey lodgement in New Zealand (NZ) has been 100% since 2007, when it became

mandatory. Surveys are lodged in LXML format, and pictures, text and PDF documents that

support the data set are uploaded as a Cadastral Survey Dataset package.

Land Information New Zealand (LINZ) developed an electronic system called Landonline for the

lodgement and processing of cadastral surveys and land title dealings, which became fully

operational in 2003. The initial uptake of digital lodgement from 2003 was low. In 2006 it was

announced that digital lodgement would become mandatory from 2007. At this time private

brokerage firms established services to help smaller surveying firms transition to digital

lodgement. These have since disappeared as the surveying industry has become accustomed

to the digital operating environment.

There was a significant backlog of plans being lodged as NZ approached mandatory digital

lodgement. Discounts of approximately 50% were offered for digital lodgement, but it has been

reported that this did not influence the market significantly.

For survey and titles, existing legislation was based around paper filing, as such, the existing

Castral Survey Act was updated, with supporting regulations, and Surveyor General rules. It

took two years to make legislative changes, and this was done prior to the launch of Landonline.

The new Cadastral Survey Act 2002 introduced the concept of a Cadastral Survey Dataset

rather than plans of subdivision. Titles refer back to plan numbers, which links back to the

dataset. Plans contain boundary definitions, easements, and adjoining allotments.

A private practice surveyor, representing the surveying industry was part of a team established

during the design and roll out of digital surveys in NZ, and extensive stakeholder management

with the surveying institute was undertaken, including testing the design with surveyors and

seeking feedback and input. Sharing the strategy with stakeholders was well received. LINZ

contracted an early adopter survey firm, to train other firms, and an education training group

visited surveying firms that were lodging with mistakes.

Landonline is an electronic workspace for surveyors. LXML was chosen as the format as no

better alternatives were identified at the time. Standardisation of file format was important for the

development of Landonline.

12D is the major survey software provider in NZ with 80-90% market share and facilitates

conversion of survey data to LXML format. Surveyors download data from Landonline, combine

it with data collected in the field in their survey software. They then load the package into a

Landonline workspace, where some (approximately 10%) massaging of the data is generally

required for compliance, completion of data capture, and plan generation. Once uploaded into

the workspace the file cannot be exported back out into survey software such as 12D.

Automated business rules for pre-validation are provided and automated warnings are flagged

to surveyors, although these can be ignored. There is an approximately 50% requisition rate.

Page 84: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P84

Landonline allows the supporting documentation to be completed with drop down menus, using

pre-populated templates.

The result is the NZ cadastre is effectively one giant LXML dataset, which surveyors can use to

easily select existing survey data to use for their pre-calculations. Surveyors pay an annual

licence fee of $1200 to access the dataset.

Lodgement fees are adjusted for how much it costs to approve, and there is a drive to automate

approval processes to reduce the cost of LINZ overheads, and reduce lodgement fees.

Surveyors have reportedly found digital plans more seamless to use and accept digital data as

more important than the plan. Title plans can be rendered directly from the Landonline system.

LINZ had to commission its own system to render plans.

The future of digital surveys in NZ is moving to the cloud, where digital data is what the surveyor

produces, and can be visualised with common tools. Putting business rules in the cloud will

make it easy for surveyors to lodge fully compliant and validated plans by empowering

validation within the software packages. A Surveyor Working Group with 10 surveyors from

across NZ has been established to provide guidance to this project. LINZ is also developing a

3D cadastre.

Western Australia

Digitisation of survey information in Western Australia (WA) began in 1995, driven by reforms to

reduce salary costs in the examination of plans. For all subdivision plans, surveyors must lodge

a Cadastral Survey Data (CSD) file, a proprietary digital data format, in addition to a plan

graphic and survey field notes. The agency responsible for land titles, Landgate, has allowed

electronic lodgement of the plan graphic and field notes in PDF format since 2003.

The CSD file captures digital data on polygons, addresses, boundary corners, roads, cadastral

boundaries, lot and plan number. This provides an efficient mechanism for bringing in spatial

data with points, and point to lines, and lines geometrically aligned. Dimensions are retained as

provided by the surveyor, but the system fits new polygons with existing records, by identifying

common points. It then contains calculated length and the surveyor’s length, and all data is

available to surveyors. It is the surveyor’s responsibility to ensure the parcel fits within the

existing cadastral fabric, and checks are made to ensure it fits within reasonable tolerances.

Surveyors can obtain a spatial cadastre export in several formats, with DXF the most common.

Landgate provides a Land Transactions Toolkit, including a CSD user guide.

Survey field notes are provided with the plan, and the regulations around this specifies

information that is not required on the plan. Surveyors can upload a scan of the notes, or a

drafted version. Some surveyors collect everything in their total station, download into drafting

package, join dots and make notations, then lodge as a PDF.

The plan graphics in WA is only of the subject parcel, and adjoining information is not required,

as surveyors are only required to sign-off on what they have surveyed, not the surrounds. Plans

Page 85: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P85

label the abuttals, but Landgate does not check these (as they are not material to the integrity of

the Land Titles Register).

The WA Planning and Development Act 2005 allows most easements to be created just by

spatial definition on a plan, especially in greenfield subdivisions. Easements that cannot be

automatically created require a deed to be lodged and the surveyor hands over to a settlement

agent to complete the title dealings (the plans status is known as ‘awaiting dealings’ before a

dealing has activated them).

Plan examination has been simplified in WA and includes checks that all land in the original title

is accounted for, dealings are for the right land, spatial miscloses are within tolerances, and

legal annotations are correct. This results in a significantly lower requisition rate compared with

other jurisdictions (approximately 2% for freehold deposited plans lodged). A requisition penalty

regime was introduced, with penalties relating to the severity of the breach. Severe breaches

lead to the Land Surveyors Licensing Board disciplining a surveyor, potentially, but rarely, with

loss of practising certificate/licence.

The central state Planning Commission (WAPC) endorses surveyor certified plans that have

been checked by Landgate, with electronic signatures on PDF.

The term ‘registered’ has a different meaning in WA, referring to documents that are part of the

Land Titles Register, but the register does not include plans. Survey plans are ‘lodged’ and

‘approved’, but their status can also be ‘with WAPC’ and then ‘in order for dealings’, but not

registered.

The change to simpler plan examination processes with fewer checks meant surveyors

ultimately became more responsible for their work. Regulations have become less prescriptive

in methodology, with a focus on principles and outcomes. Surveyors essentially became

‘approved examiners’. A licensed surveyor can only undertake cadastral surveying if they

maintain a practising certificate, which mandates continuing professional development, including

keeping up to date with all plan lodging requirements.

The future for digital lodgement in WA is the Portal Plan Project (NLR-Plan Surveyor Portal). It

is part of the New Land Registry suite (an Advara/Landgate product), and is a bespoke survey

portal, the preliminary development of which has been underway for three and a half years.

Portal Plans will provide the capability for surveyors to lodge a completely digital plan, with the

surveyor drafted PDF plan no longer needed, as it will instead be able to be rendered from

digital data.

The surveyor will create new interests (such as easements) within the portal, allowing the CSD

file and PDF plan image to be in alignment.

All through production of the plan, the portal will enforce compliance with relevant business

rules and drafting rules, and ensure full compliance with the existing cadastre, and existing

easements.

Page 86: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P86

Surveyors have several paths to the portal depending on their choice of software, allowing them

to go from the field to CSD efficiently. Surveyors can import either a CSD (which can be directly

exported from calculation packages such as Magnet), DWG or ASCII points file into the portal.

Many surveyors import survey observations into CSD Editor, coordinate geometry software that

has been developed by Landgate in conjunction with ESRI, from which a compliant CSD file can

be exported.

When the CSD/DWG/ASCII file is imported, the portal then renders a graphic that can be edited

by the surveyor. The portal creates a PDF to be electronically certified by a surveyor within the

portal, and then creates a matching CSD file at lodgement of the PDF file. The NLR-Plan

Workflow module receives the PDF file, CSD file and any other required forms from the portal

for manual and automatic plan examination.

Victoria

Victoria uses an online portal-based approval system called SPEAR (Surveying and Planning

through Electronic Applications and Referrals) for processing all plan based approvals under

various legislation including the Subdivision Act 1988, Transfer of Land Act 1958, Local

Government Act 1989, Planning and Environment Act 1987 and others.

SPEAR is voluntarily used by all key parties involved in the planning and subdivision processes,

but in differing capacities:

> Applicant contact: surveyors or planners submit, manage and track application progress.

Licenced Surveyors use digital certificates to digitally sign their plans and surveys, thus

replacing all ‘wet signatures’.

> Responsible authorities: all 79 Victorian councils receive, manage, refer and approve

applications. Delegated council officers use digital certificates to digitally sign key council

decisions, such as planning permits, certification and statement of compliance. This has

replaced all ‘wet signatures’.

> Referral authorities: all 54 Statutory Referral Authorities (service authorities/utilities) receive

and respond to referrals made under the provisions of various legislation. SPEAR allows

them to request further information, or request plan amendments if required.

> Lodging parties: solicitors and conveyancers prepare the application lodgement, including

all forms, consents and other supporting documentation, and lodge electronically to Land

Use Victoria (LUV). Lodging parties use digital certificates to digitally sign all their forms.

This has replaced all ‘wet signatures’.

> Land Use Victoria: receive applications from SPEAR and utilise information in SPEAR to

prepopulate other Government databases. SPEAR also allows LUV staff to request

amendments to application documents, including plan changes and/or survey amendments,

in some cases these changes require council to re-assess the application. All these

workflows are enabled in SPEAR.

SPEAR applications account for 98% of all plans lodged at LUV. From 01 January 2020,

SPEAR will be compulsory for the creation and processing of all supported application types.

Page 87: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P87

Whilst the majority of information supplied in SPEAR is either in PDF format or direct data input,

SPEAR does allow surveyors to submit 2D plans in ePlan format (LandXML). This is currently

available for all land subdivision plan types under the Subdivision Act.

Industry uptake of ePlan has been very low with less than 1% of total plans lodged in SPEAR

being supplied in ePlan format. LUV is exploring options to streamline the creation of ePlan,

which currently relies heavily on third-party software vendors to provide ePlan capability to

surveyors.

LUV’s initial focus on streamlining the ePlan creation process for 2D plans is to collaboratively

develop a structured CAD file format with industry. It is envisaged that the structured CAD file

will include all layers used in the creation of a cadastral plan and survey, including subject

parcel boundary, traverse, connections, survey marks, new lot boundaries, easement

information, annotations, owners corporations schedules and any other administrative data

required on the plan. Procurement for a facilitator of the co-design project is about to

commence.

The next step will be to develop and host a web service (API) converter that will allow the

structured CAD file to be converted to ePlan (LandXML) and vice-versa. This initiative is

proposed to be rolled out by end of 2020.

Increasing ePlan take up will directly benefit another significant Victorian Government project:

The Digital Cadastre Modernisation Program. Currently the project is in the process of back-

capturing existing plans into LandXML format (to date, over 360,000 of approximately 3.3 million

parcels have been captured from 50,000 cadastral plan and survey records). The aim is to

complete the back-capture program by the end of 2022. To ensure that back-capturing of plan

and survey information is not an ongoing maintenance requirement of the digital cadastre, it is

imperative that surveyors embrace ePlan as a means of providing current plan and survey

information to the cadastre.

The aim of these initiatives is to ultimately allow surveyors to easily convert their CAD files to

ePlan format, and therefore radically increase ePlan submissions in SPEAR to support

Victoria’s digital cadastre journey into the future.

South Australia

South Australia (SA) introduced a system for online portal Electronic Plan Lodgement (EPL) in

2009. Surveyors lodge a TIFF image of the plan and a textual sheet which is generated in the

system, and includes easements. Lodgement of plans in TIFF format has been mandated,

although strata amendments are excluded.

Plan numbers are issued on lodgement, but the conveyancing processes (via PEXA or manual

lodgement) activates the plan for issuing title, not lodgement. Plans are approved for data and

deposited once documents to enact the process have been lodged as a separate process. The

titling system is known as the SA Integrated Land Information System (SAILIS) and facilitates

pre-population of title data. The EPL links to the Electronic Development Application Lodgement

Page 88: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P88

and Assessment System (EDALA), which is done manually prior to planning approval via the

EDALA system.

The concession holder, Land Services SA (LSSA), capture all lodged survey plans using a

software program called PCplans and provide the Surveyor General’s Office with a CXML

output to maintain the spatial cadastre. PCplans checks parcel closures and connects the

parcels to coordinated survey marks to enable spatial accurate representation of the parcels.

PCplans is also available to surveyors to pre-check closures and coordinate joins before

lodging. A pre-lodgement checklist is provided by LSSA.

The TIFF remains the source of truth, and no legislative changes have been needed to date.

SA has not adopted ePlan or LXML. LXML is perceived to be a cumbersome format which

would limit the use of 3D in survey land information.

LSSA would like a ‘data-in-data-out’ format and see the benefit of digital surveys to move

towards automation and reduce examination effort. LSSA are driving digital data lodgement and

Government is supportive of these initiatives. A small industry group will be piloting new

software for digital data lodgement with LSSA over the next 6-12 months.

Queensland

In Queensland all lodgement is with the Titles Office, and is undertaken at lodgement centres for

paper plans, with a bundled approach to registration and creation of title. From September 2019

plans scanned to PDF are accepted in the document-based system via approved lodgers.

Easements are shown on plan, and easement documents are lodged either with the plan or later.

Queensland had been working towards EPlan and a model for LXML digital survey; however, a

major overhaul of the cadastral system in 2017 led to pausing this process. The need to replace

30-year-old IT systems and refresh business processes was a contributing factor.

A 10-year strategic roadmap was developed with high level outcomes including digital

lodgement, 3D cadastre, pre-registration layers in the spatial cadastre, and automation of plan

examination. A surveying reference group of a cross section of different types of firms was

established specifically to address digital lodgement and was engaged more generally on

issues relevant to the transformation of the cadastral system.

The high cost of implementing this roadmap has impeded progress, and the current strategy is

to take a step back and align the work with activities in other jurisdictions, including numeric

cadastre and digital twins. While the land registration differences between jurisdictions have

made it difficult for a single LXML system to be defined, Queensland favours collaborative

cadastral development by a National Committee, and is open to alternative or multiple formats,

as long as the data requirements are well understood.

Page 89: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P89

Attachment J – Sample scenarios for solution design

The following scenarios do not consider Information Brokers independently of LRS. Given the

critical role Information Brokers play in exclusively delivering some survey plan products and

information to third-party consumers, including surveyors, councils, utilities and developers, it is

imperative that they are considered in any further assessment of future models.

Page 90: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P90

Scenario DP 1: Roll back digital – surveyors lodge TIFF only

Under this scenario surveyors do not lodge survey plans in LXML or any other digital format,

and only lodge the TIFF of their plan drawings. Surveyors can continue to use LXML for their

own requirements, such as an internal quality assurance of their surveys to validate bearings

and distances on their plans prior to lodgement of the TIFF. The TIFF is the only file examined.

This may potentially result in a lower requisition rate, as inconsistencies between TIFF and

LXML will no longer be an issue and less elements are checked – however it will prevent

validations which may instead lead to increased requisitions. The registered plan is the TIFF.

The TIFF format plans can be subsequently digitised by LRS into LXML format for use by DCS

Spatial Services, surveyors, utilities, councils and other users. The solution from LRS to

produce digital plans would be the same or similar conversion process that occurs for back-

capture of existing plans. The timing between examination of the lodged TIFF and conversion to

LXML format would need to be agreed.

The feasibility of this scenario option would depend on the cost per plan to back-capture

negotiated with a provider by LRS, and should this be the digital solution proposed by LRS,

these costs should not be passed through to lodging parties as an addition to the fixed

lodgement fees agreed in the concession.

The approvals process and associated documents should still be digitised even if plans remain

in TIFF format.

Outcomes assessment

Customer Criteria Scenario outcome

Surveyors Speed of creation

Accuracy of plans

Completeness of information

No change to the current completeness, accuracy or speed of creation of plans lodged as TIFF only.

Councils & utilities

Efficiency of review

Ease of approval

Speed and accuracy of addition to records

No change to current for approvals, potential for faster incorporation into GIS from converted LXML after registration.

LRS Speed of examination

Accuracy of examination

No change to examination time and accuracy of TIFF plans only. Slower examination of large TIFF and LXML plans (where LXML speeds up examination).

ORG & Surveyor General

Accuracy of titles

Appropriateness of the plans for homeowners

Enhanced surveying practice

No change to current (TIFF files only).

Page 91: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P91

Outcomes assessment

Customer Criteria Scenario outcome

DCS Spatial Services

Currency of NSW Spatial Cadastre

Completeness of NSW Spatial Cadastre

Accuracy of NSW Spatial Cadastre

Survey plans back-captured in LXML format by LRS at registration will be uploaded to the NSW Spatial Cadastre (with same completeness and currency as Capture on Demand program). The service levels (speed and accuracy) would be determined during LRS’ procurement of a conversion provider and according to the specifications prescribed by the SG and RG.

Developers Reduced time to market

Cost effective plan registration

No change to current (TIFF files only).

Homeowners Readable and reliable plans

Faster and reduced costs of purchase

No change to current (TIFF files only).

Implementation assessment

Element Criteria Scenario outcome

Technical feasibility

Amount of change to surveying practices

Feasibility of technical solutions

No disruption to surveyor’s current methods of surveying.

Technical solution to back-capture LXML plans from lodged TIFF plans currently demonstrated.

Cost of change

To surveyors

To consenting authorities

To LRS

To DCS Spatial Services

No cost of training for surveyors – however, surveying companies that have previously invested in LXML capability would be unlikely to recover the associated costs, although can continue to use for internal QA.

Cost to LRS of ongoing back-capture.

No cost to councils and utilities, nor to DCS Spatial Services.

Legislative change

Amount and ease of legislative change required

No change required.

Page 92: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P92

Scenario DP 2: Structured CAD file – surveyors lodge DXF only

Similar to the developing strategy for digital survey plans in Victoria, this scenario requires

surveyors to submit a DXF file that is structured according to defined business rules and layers

that contain a specified information, e.g. a ‘boundary’ layer. The specific requirements for the

layers would need to be agreed and approved by DCS Spatial Services and ORG, but would

include a minimum set of information prepared by surveyors, such as subject boundaries, lot

numbers and areas, reference marks and easements.

The full DXF plan will include all the information surveyors currently include on survey plans.

The key layers will be extracted from the DXF file, and converted by surveyors to a LXML

through a portal which may require slight adjustments or manual addition of metadata. The

resulting LXML file will:

> contain boundary information – ideally a solution will allow for override of the line

measurements to the surveyors adjusted distance and bearings (and ideally capture these

decisions)

> be able to be rendered to produce a usable boundary diagram suitable for registration

> be able to be ingested into the NSW Spatial Cadastre

> be able to be examined automatically by LRS

> be searchable and available to surveyors to use for their pre-calculations.

The DXF and converted LXML file would then be provided by LRS to surveyors when obtaining

precedent plans for plan preparation. A TIFF image would no longer be required for submission.

This scenario would require:

> a DXF to LXML conversion tool to be developed and operated by LRS

> a simplified LXML rendering tool to be developed and operated by LRS

> business rules for terminology and other layer requirements of the structured DXF file to be

clearly articulated and communicated to the surveying industry.

This review has identified some market capability to both convert and render LXML plans from

DXF files, however a more advanced capability would be required to be developed by LRS.

Outcomes assessment

Customer Criteria Scenario outcome

Surveyors Speed of creation

Accuracy of plans

Completeness of information

Speed of creation may be similar to TIFF only, depending on amount of automation in conversion of DXF to LXML.

Plans will be created with all boundary definition evidence captured however potential for this evidence to be captured digitally and manual handling reduced, increasing accuracy.

Page 93: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P93

Outcomes assessment

Customer Criteria Scenario outcome

Councils & utilities

Efficiency of review

Ease of approval

Speed and accuracy of addition to records

Utilities and some councils typically have GIS functions which are used to consume DWG/DXF formats, and surveyors are used to engaging with these utility companies. This may aid in efficiency of review and speed of addition to records.

LRS Speed of examination

Accuracy of examination

LRS examine the LXML plans which will help with speed and accuracy.

ORG & Surveyor- General

Accuracy of titles

Appropriateness of the plans for homeowners

Enhanced surveying practice

A more digital workflow (than TIFF only) should minimise human error.

If enhanced evidence can be captured digitally there is a potential for improvements to surveying practice.

DCS Spatial Services

Currency of NSW Spatial Cadastre

Completeness of NSW Spatial Cadastre

Accuracy of NSW Spatial Cadastre

Ingestion into NSW Spatial Cadastre enhanced as boundary data is provided by LRS as LXML.

Registered plan and boundary details in the NSW Spatial Cadastre are generated from the same source and therefore aligned.

Developers Reduced time to market

Cost effective plan registration

Depending on the efficiency of the DXF to LXML conversion process there may be an increase or decrease in the overall efficiency and in the time to market.

Homeowners Readable and reliable plans

Faster and reduced costs of purchase

Should be little change to readability (assuming render from LXML is adequate).

Cost of purchase may change slightly depending on efficiency of conversion from DXF to LXML.

Implementation assessment

Element Criteria Scenario outcome

Technical feasibility

Amount of change to surveying practices

Feasibility of technical solutions

Surveyors are typically familiar with CAD software and DXF file formats.

TIFF format no longer used, surveyors will have to utilise DXF for reviewing other survey details.

Conversion from DXF to LXML will likely require a portal solution – this is complex and

Page 94: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P94

Implementation assessment

Element Criteria Scenario outcome

will need to allow for surveyors to override measurements from the linework to align to adjusted bearings and distances.

Implementing business rules for DXF ‘boundary’ layer, and communicate updates as required is relatively simple.

Cost of change

To surveyors

To consenting authorities

To LRS

To DCS Spatial Services

Costs to train surveyors on new requirements likely low.

Likely significant cost to LRS to develop tool to convert structured ‘boundary’ DXF layer to LXML and then adequately render ‘boundary’ LXML into image for title.

Legislative change

Amount and ease of legislative change required

Change required as TIFF will be replaced by reduced boundary image.

Page 95: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P95

Scenario DP 3: Lite LXML – surveyors lodge TIFF and lite LXML

This scenario would ideally form a transition pathway to eventual 100% lodgement of LXML

plans. Under this scenario it would be mandated for surveyors to lodge a Lite LXML plan in

addition to the TIFF plan currently required.

The Lite LXML would require sufficient detail to examine the boundary. All other information (as

required by other surveyors) would continue to be captured on the TIFF plan, which would

remain the legal source of truth, and legislative changes would not be required at this stage.

While this would require surveyors to produce two plans, the lite LXML should require less effort

for surveyors to produce compared to the current full LXML, while still providing them with a pre-

lodgement quality check on their measurements. This would allow surveyors to become

accustomed to using LXML enabled software, and may provide incentive to the software

vendors to develop their products to be more accessible and useful to surveyors.

Both the TIFF and the Lite LXML would be examined by LRS, and the Lite LXML would be able

to be ingested into the NSW Spatial Cadastre without requiring conversion.

Outcomes assessment

Customer Criteria Scenario outcome

Surveyors Speed of creation

Accuracy of plans

Completeness of information

Additional work for some surveyors who have a workflow requiring them to produce two separate plans; Lite LXML would not require as much effort as a full plan in LXML.

Survey accurate digital data could be made available to surveyors for use in their pre-calculations. However, this would not include chain of evidence for how boundaries were previously determined, and surveyors would likely continue to use TIFF plans.

Councils / Utilities

Efficiency of review

Ease of approval

Speed and accuracy of addition to records

Limited metadata from plans could be made available to councils and utilities in a smart fashion.

LRS Speed of examination

Accuracy of examination

Examination of both TIFF and lite LXML may be slower than TIFF only (though faster than examining TIFF and full LXML) and would be slower than LXML only.

Potential for enhanced automated examination of lite LXML may provide speed and accuracy benefits.

ORG & Surveyor- General

Accuracy of titles A more digital workflow (than TIFF only) should minimise human error.

Page 96: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P96

Outcomes assessment

Customer Criteria Scenario outcome

Appropriateness of the plans for homeowners

Enhanced surveying practice

Likely no change to current; potential for increase in quality of plan information as surveyors would be using LXML to check their work.

DCS Spatial Services

Currency of NSW Spatial Cadastre

Completeness of NSW Spatial Cadastre

Accuracy of NSW Spatial Cadastre

DCS Spatial Services acquires a simple plan in LXML format that can be directly ingested into the NSW Spatial Cadastre.

Developers Reduced time to market

Cost effective plan registration

Potential minor increase in time to market if dual plan examination is slower and results in an increase in plan requisitions (however likely faster than TIFF and full LXML).

Homeowners Readable and reliable plans

Faster and reduced costs of purchase

No change to current (TIFF files only) readability unless suitable rendering of LXML lite is developed which may be easier to read.

Possibly increase in costs of purchase compared to TIFF and full LXML due to increased effort for surveyors and dual examination by LRS.

Implementation assessment

Element Criteria Scenario outcome

Technical feasibility

Amount of change to surveying practices

Feasibility of technical solutions

Change favours larger surveying firms; impact of change greater to small firms with limited resources.

Cost of change

To surveyors

To consenting authorities

To LRS

To DCS Spatial Services

Potential costs to surveyors to learn the new requirements and to purchase software to produce the LXML.

Cost of tool to adequately render ‘boundary’ LXML (optional if the TIFF is what appears on registered plans).

Legislative change

Amount and ease of legislative change required

No changes required.

Page 97: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P97

Scenario DP 4: Full LXML – surveyors lodge TIFF and full LXML

This scenario is a mandated version of the current state where surveyors lodge a TIFF and full

LXML.

Outcomes assessment

Customer Criteria Scenario outcome

Surveyors Speed of creation

Accuracy of plans

Completeness of information

Slower to create plans for many surveyors; minimal additional effort for others depending on choice of surveying software.

Overall increase in plan accuracy, with LXML forcing surveyors to check measurements. However, if each plan is created from a separate workflow there is an increased chance for requisitions due to misalignment between the two plans.

Councils / Utilities

Efficiency of review

Ease of approval

Speed and accuracy of addition to records

Metadata from plans could be made available to councils and utilities in a smart fashion.

LRS Speed of examination

Accuracy of examination

Surveyors are required to lodge both TIFF and LXML plan until LXML plans can be adequately rendered, while the plan graphic remains the source of truth.

LRS will examine both the TIFF and the LXML plan to ensure alignment, which requires more effort and resources, and is more likely to result in requisitions.

ORG & Surveyor- General

Accuracy of titles

Appropriateness of the plans for homeowners

Enhanced surveying practice

A more digital workflow (than TIFF only) should minimise human error and full LXML should allow robust automated validation leading to improved accuracy of titles.

No change to appropriateness of plans from TIFF only.

Surveying quality may improve however efficiency may decrease.

DCS Spatial Services

Currency of NSW Spatial Cadastre

Completeness of NSW Spatial Cadastre

Accuracy of NSW Spatial Cadastre

DCS Spatial Services acquires a full survey plan in LXML format containing all survey information that can be directly ingested into the NSW Spatial Cadastre.

Page 98: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P98

Outcomes assessment

Customer Criteria Scenario outcome

Developers Reduced time to market

Cost effective plan registration

Potentially increased time due to plans taking longer to create, and increased chance of requisitions.

Homeowners Readable and reliable plans

Faster and reduced costs of purchase

No change to current (TIFF files only) readability unless suitable rendering of LXML is developed which may be easier to read.

May increase costs of purchase (compared to TIFF only) as there will be increased effort for surveyors and potential delays from more requisitions.

Implementation assessment

Element Criteria Scenario outcome

Technical feasibility

Amount of change to surveying practices

Feasibility of technical solutions

Severely burdens survey firms that don’t lodge many plans.

Not all current software packages used by surveyors provide a LXML capability. This would advantage some surveyors already using software that easily enables LXML without additional effort.

Cost of change

To surveyors

To consenting authorities

To LRS

To DCS Spatial Services

Additional effort required of surveyors would mean increased costs passed onto customers.

Surveyors may need to change or upgrade software.

Surveyors would require training to learn LXML, which can be significant time away from revenue generating tasks.

LXML plans may not be able to be produced by lower cost drafters, instead more expensive resources may have to produce digital plan.

Additional effort for LRS to examine two plans.

LRS may need to invest in software and training to reliably examine LXML plans.

Legislative change

Amount and ease of legislative change required

No changes required.

Page 99: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P99

Scenario DP 5: Full LXML only – surveyors lodge full LXML only

Under this scenario a LXML plan is the primary file that surveyors produce, similar to the New

Zealand approach. The LXML file, either the data captured, massaged and recorded by

surveyors, or a suitably rendered image of the file plan becomes the legal source of truth, and a

TIFF is no longer lodged or used.

This will require three major changes:

> significant investment in a tool to adequately render plans from LXML files that contain all

information surveyors document to demonstrate how they defined a boundary. The current

standard/quality of rendering of LXML by LRS tools has been the most common complaint

from surveyors when asked for feedback on digital lodgement

> complete disruption/change to the way most surveyors produce plans

> legislative changes that allow data collected by surveyors to become the legal source of truth.

Adoption of this scenario would be a major change impacting the surveying industry and would

likely have significant costs that need to be determined. Some of the impacts of such a change

could be mitigated by first adopting the lite LXML scenario, in a staged approach to 100% digital

survey plans in NSW.

Outcomes assessment

Customer Criteria Scenario outcome

Surveyors Speed of creation

Accuracy of plans

Completeness of information

Surveyors only required to produce their plan in a single digital format.

Councils / Utilities

Efficiency of review

Ease of approval

Speed and accuracy of addition to records

Potentially significant impact on how authorities would assess plans for approval; if the LXML plan can be suitably visualised then changes would be minimal. However, if the data in the LXML file can only be interpreted using specialised viewing software, changes would be significant. Likewise, the ability to easily ingest the data (in this and all scenarios) is critical.

LRS Speed of examination

Accuracy of examination

Only examine a single LXML plan, which is much faster than examining the TIFF and LXML.

Potential for increased automation of plan examination.

Potential for pre lodgement validation of LXML plans by surveyors to enforce business rules.

ORG & Surveyor- General

Accuracy of titles A more digital workflow (than TIFF only) should minimise human error and full LXML should

Page 100: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P100

Outcomes assessment

Customer Criteria Scenario outcome

Appropriateness of the plans for homeowners

Enhanced surveying practice

allow robust automated validation leading to increased accuracy of titles.

If suitable rendering of plans can be developed than plans should be appropriate for homeowners.

Surveying quality may improve if software packages enable robust creation of LXML files with enhanced evidence.

DCS Spatial Services

Currency of NSW Spatial Cadastre

Completeness of NSW Spatial Cadastre

Accuracy of NSW Spatial Cadastre

DCS Spatial Services acquires a full survey plan in LXML format containing all survey information that can be directly ingested into the NSW Spatial Cadastre.

Developers Reduced time to market

Cost effective plan registration

Faster end to end process from plan production to plan examination and registration.

Homeowners Readable and reliable plans

Faster and reduced costs of purchase

Plans should be readable (if rendering can be developed) and reliable (as they will be based on the source data).

May decrease or increase costs of purchase (compared to TIFF only) as there will be increased effort for some surveyors to create the file but faster examination by LRS.

Implementation assessment

Element Criteria Scenario outcome

Technical feasibility

Amount of change to surveying practices

Feasibility of technical solutions

Not all current software packages used by surveyors provide a LXML capability. This would advantage some surveyors already using LXML.

Severely burdens survey firms that don’t lodge many plans.

Option to create a portal or cloud based LXML workspace for surveyors to generate their plans in, similar to NZ.

Current ability for system to adequately render LXML data into meaningful plan images is poor and unsatisfactory.

Depending on the extent of change to the legal source of truth: either a significant improvement in software to render the full plan, or software that can render a simpler ‘Lite boundary image’ for printing to paper purposes would be required.

Page 101: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P101

Cost of change

To surveyors

To consenting authorities

To LRS

To DCS Spatial Services

Many surveyors will have to adapt to a new way of working using new systems.

Surveyors will complete their own plans instead of drafters doing part of the work; this may be offset if plans can be produced faster once surveyors are competent with LXML.

Consenting authorities will need to be able to easily ingest and interpret LXML plans; data transformation processes should be minimised.

Likely significant cost to LRS to procure and implement a suitable system that supports surveyors to lodge digital plans, including automated validations, and that can adequately render plan graphics to the requirements of the RG and SG.

LRS overheads would be lower once a technical solution for digital plans is established, as the ability to examine plans in LXML is considerably faster and can utilise automation.

Legislative change

Amount and ease of legislative change required

Significant change to the definition of what a plan is; will depend on the effectiveness of a technology solution to rendering.

Data potentially becoming what surveyors produce.

No change to principle of monuments over measurements.

Page 102: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P102

Scenario: Digital strata plans

In this scenario strata plans are digitally lodged in a smart format.

Outcomes assessment

Customer Criteria Scenario outcome

Surveyors Speed of creation

Accuracy of plans

Completeness of information

Potentially faster to create strata plans if the required content is simplified.

Accuracy to be determined; strata plans currently not produced to be survey accurate.

Plans could be more user-friendly, particularly if 3D information can be captured digitally.

Councils / Utilities

Efficiency of review

Ease of approval

Speed and accuracy of addition to records

Faster to approve if the digital strata plan can be readily viewed by consenting authorities.

Metadata can be made available in a smart fashion.

LRS Speed of examination

Accuracy of examination

Opportunity to automate some checks undertaken by LRS during examination.

ORG & Surveyor- General

Accuracy of titles

Appropriateness of the plans for homeowners

Enhanced surveying practice

Potentially more customer friendly process, depending on requirements for digital boundary definition capture for strata.

DCS Spatial Services

Currency of NSW Spatial Cadastre

Completeness of NSW Spatial Cadastre

Accuracy of NSW Spatial Cadastre

NSW Spatial Cadastre completeness improved. Currently representation of strata subdivisions in NSW Spatial Cadastre is limited to the parent parcel only; more granular detail such as separate buildings within a strata scheme is not currently captured.

Developers Reduced time to market

Cost effective plan registration

Shorter end to end process depending on approvals.

Homeowners Readable and reliable plans

Faster and reduced costs of purchase

Likely limited to no change.

Page 103: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P103

Implementation assessment

Element Criteria Scenario outcome

Technical feasibility

Amount of change to surveying practices

Feasibility of technical solutions

New surveying practice for strata which is not currently digital.

Technical solutions already evident in 3D rendering of buildings by architects and designers.

Cost of change

To surveyors

To consenting authorities

To LRS

To DCS Spatial Services

Increased cost to surveyors if they have to spend more time capturing accurate boundary information; potentially offset if existing digital building plans are accessible.

Cost to authorities if they require specialised software to view strata plans for approval.

Additional cost to LRS if digital strata plans are to be in LXML format.

Increased cost to developer/purchasers if surveyors have to spend more time developing digital plans.

Legislative change

Amount and ease of legislative change required

Potentially significant change, in line with DPs, depending on the extent of digital data captured, and how the plan is required to be presented on a page, or accessible via a viewing system.

Page 104: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P104

Scenario: Digital approvals & smart associated documents

In this scenario digital signatures are introduced through a portal for managing approvals. The

portal allows approval processes to occur in parallel, progress to be tracked, and stakeholders

notified automatically.

Smart associated documents are also designed which can be automatically pre-populated and

have inbuilt data validations.

Outcomes assessment

Customer Criteria Scenario outcome

Surveyors Speed of creation

Accuracy of plans

Completeness of information

Enhanced accuracy of information between plan and associated documents.

Improved accuracy of easements on plan.

Faster process from field to lodgement.

Councils / Utilities

Efficiency of review

Ease of approval

Speed and accuracy of addition to records

Faster and simpler approvals process.

Reduction of manual tasks.

LRS Speed of examination

Accuracy of examination

Potential impacts on examination speed and accuracy of associated documents and approvals by enabling automated checking of data fields and workflow management.

ORG & Surveyor- General

Accuracy of Titles

Appropriateness of the plans for homeowners

Enhanced surveying practice

Improved certainty that all registered plans have been verified and approved by the relevant authorities.

Will support greater efficiency of the surveying industry.

DCS Spatial Services

Currency of NSW Spatial Cadastre

Completeness of NSW Spatial Cadastre

Accuracy of NSW Spatial Cadastre

Potentially easier to include additional information in the NSW Spatial Cadastre earlier in the development process.

Developers Reduced time to market

Cost effective plan registration

Potential to significantly reduce time to market (weeks).

Page 105: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

NSW DCS | Digital Survey Plans Review P105

Outcomes assessment

Customer Criteria Scenario outcome

Homeowners Readable and reliable plans

Faster and reduced costs of purchase

Should improve reliability by reducing typographical errors.

Should contribute to reduced purchase costs by decreased administrative effort and potential reduction in holding costs for larger developments.

Implementation assessment

Element Criteria Scenario outcome

Technical feasibility

Amount of change to surveying practices

Feasibility of technical solutions

Technical solutions for digital approvals are available in the market; are used.

Cost of change

To surveyors

To consenting authorities

To LRS

To DCS Spatial Services

A single entity would need to take the lead on establishing a system that enables digital approvals; how this is funded would need to be agreed across all impacted parties; ongoing costs could be passed through to users.

Legislative change

Amount and ease of legislative change required

Change would be required to move to digital signatures (this has already been enacted in Victoria).

Wider changes would be required to allow surveyors to create automatic easements on the plan.

Page 106: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

.

NSW DCS | Digital Survey Plans Review P106

Attachment K – Sample application of Assessment Framework

The following tables show a simplified overview of the application of the Assessment Framework against seven digitalisation scenarios (five for

deposited plans and one each for strata plans and approvals and associated documents).

The scenarios have been designed and assessed without extensive input from stakeholders and serve to illustrate the use of the Framework and to

prompt discussions on possible solutions.

Summary of Scenarios against the Outcomes Assessment Framework Criteria

Customer Criteria

Potential Scenarios

Digital Deposited Plans Digital strata plans

Digital approvals & associated

docs TIFF only DXF TIFF + Lite LXML TIFF + LXML LXML only

Surveyors

speed of creation

current workflow

minor change

additional workflow

double effort

new workflow

new workflow

✓✓✓

time savings

accuracy of plans

no change

slight improvement

✓✓

slight improvement

✓✓

slight improvement

✓✓

slight improvement

potentially more

accurate

✓✓✓

improved document

management

completeness of information

no change

no change

no change

no change TBD

potentially more

complete

N/A

Page 107: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

.

NSW DCS | Digital Survey Plans Review P107

Summary of Scenarios against the Outcomes Assessment Framework Criteria

Customer Criteria

Potential Scenarios

Digital Deposited Plans Digital strata plans

Digital approvals & associated

docs TIFF only DXF TIFF + Lite LXML TIFF + LXML LXML only

Councils & utilities

efficiency of review

no change

minor improvement

minor improvement

minor improvement

TBD TBD

✓✓✓

online access to review and smart

notifications

ease of approval

no change

no change

no change

no change TBD TBD

✓✓✓

digital approvals

speed and accuracy of addition to records

no change

streamlined ingestion into GIS and other

records

streamlined ingestion into GIS and other records

✓✓

streamlined ingestion into GIS and other records

TBD TBD

✓✓✓

digital records workflow

LRS

speed of examination

single plan manual

examination

single plan manual

examination

TBC

dual plan examination but

allows streamlining

TBC

dual plan examination but

allows streamlining

✓✓✓

single plan electronic

examination

TBD

reduced typographical

errors

accuracy of examination

no improvement

single plan manual

examination

some improvement and

consistency

improvement and consistency

✓✓

consistent high accuracy

TBD

smart documents enhance accuracy

Page 108: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

.

NSW DCS | Digital Survey Plans Review P108

Summary of Scenarios against the Outcomes Assessment Framework Criteria

Customer Criteria

Potential Scenarios

Digital Deposited Plans Digital strata plans

Digital approvals & associated

docs TIFF only DXF TIFF + Lite LXML TIFF + LXML LXML only

ORG & Surveyor- General

accuracy of Titles

no change

possibly reduced

human error

automated validation and error checking

automated validation and error checking

✓✓

automated validation and

error checking on source of truth

TBD

smart documents enhance accuracy

enhanced surveying practice

no change

potential for improvements

potential for improvements

potential for improvements

potential for improvements

TBD ✓

appropriateness of the plans for homeowners

no change

subject to rendering tool

subject to rendering tool

subject to rendering tool

subject to rendering tool

TBD ✓

DCS Spatial Services

currency of NSW Spatial Cadastre

no change

digital boundary

information acquired sooner

digital boundary information

acquired sooner

digital boundary information

acquired sooner

digital boundary information

acquired sooner

TBD

earlier inclusion in spatial cadastre

completeness of NSW Spatial Cadastre

no change

could include easements

could include easements

could include easements

TBD

strata details in

NSW Spatial

Cadastre

N/A

Page 109: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

.

NSW DCS | Digital Survey Plans Review P109

Summary of Scenarios against the Outcomes Assessment Framework Criteria

Customer Criteria

Potential Scenarios

Digital Deposited Plans Digital strata plans

Digital approvals & associated

docs TIFF only DXF TIFF + Lite LXML TIFF + LXML LXML only

accuracy of NSW Spatial Cadastre

no change

small improvement

small improvement

small improvement TBD N/A N/A

Developer

reduced time to market

no change

no change

additional surveyor time

additional surveyor time

TBD TBD ✓✓✓

faster approvals

cost effective plan registration

no change

no change

additional surveyor time

additional surveyor time

TBD TBD

✓✓✓

less manual effort

Homeowners

readable and reliable plans

no change

no change

subject to rendering tool

subject to rendering tool

subject to rendering tool

TBD

reduced typographical

errors

faster and reduced costs of purchase

no change TBD TBD TBD TBD TBD

✓✓

faster registration and reduced

manual administrative

effort

Page 110: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

.

NSW DCS | Digital Survey Plans Review P110

Summary of Scenarios against the Implementation Assessment Framework Criteria

Customer Criteria

Potential Scenarios

Digital Deposited Plans Digital

strata plans Digital approvals &

associated docs TIFF only DXF TIFF + Lite LXML TIFF + LXML LXML only

Technical feasibility

amount of change to surveying practices

✓✓✓

no change

✓✓

some change

significant change

major change

complete change

complete change

✓✓

beneficial workflow change

feasibility of technical solutions

✓✓✓

current requirement

✓✓✓?

CAD tools widely in

current use by industry

Conversion to LXML

capability unknown

no current solution for

guaranteeing TIFF and LXML

match

no current solution for

guaranteeing TIFF and LXML

match

no current rendering solution

no current rendering solution

✓✓

proven market capability

Cost

to surveyors ✓✓✓

no change

✓✓

some change

software change and training

software change and training

software change and

training

software change and

training

✓✓

none

to consenting authorities

no change

no change

no change

no change

change to systems and processes

TBD TBD

Page 111: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

.

NSW DCS | Digital Survey Plans Review P111

Summary of Scenarios against the Implementation Assessment Framework Criteria

Customer Criteria

Potential Scenarios

Digital Deposited Plans Digital

strata plans Digital approvals &

associated docs TIFF only DXF TIFF + Lite LXML TIFF + LXML LXML only

to LRS

cost of back-

capture

cost of conversion and rendering tool

no change

no change

cost of rendering tool

TBD TBD

to DCS Spatial Services

no change

no change

no change

no change

no change TBD TBD

Legislative change

amount and ease of legislative change required

no changes required

changes required

no changes required

no changes required

changes required

TBD TBD

Page 112: Digital Survey Plans Review - Registrar General · NSW DCS | Digital Survey Plans Review P3 Executive Summary Almost half of the total outlay for a new house and land package in a

Contact Us

Chris Robertson

t (02) 8274 9200 m 0413 214 817

e [email protected]

abn 47 105 237 590 acn 105 237 590

e [email protected]

w grosvenor.com.au

Level 15, 379 Collins Street Melbourne VIC 3000 t (03) 9616 2700

Level 7, 15 London Circuit Canberra ACT 2601 t (02) 6274 9200

Level 18, 1 Castlereagh Street Sydney NSW 2000 t (02) 8274 9200

Level 6, 200 Adelaide Street Brisbane QLD 4000 t (07) 3184 5724

Subscribe to our news

Follow us @GrosvenorPG

Connect with us