discovery elementary/endeavour elementary addition –change...

3
Advance Notice April 9, 2020 Discovery Elementary/Endeavour Elementary Addition – Change Order #6 – Kuper/Mullins Action to be taken: I move the board approve the Discovery Elementary School Addition Change Order #6 from Kassel & Associates, in the amount of $15,320.00 plus $1,532.00 WSST for a total of $16,852.00. I move the board approve the Endeavour Elementary School Addition Change Order #6 from Kassel & Associates in the amount of $55,811.00 plus $4,799.75 WSST for a total of $60,610.75. Each proposal request listed on the attached change orders have been reviewed by the District Construction Coordinator for the project. Cost proposals were reviewed and reduced where possible and as proposed represent an equitable charge for the scope of work involved. DISCOVERY ELEMENTARY ADDITION CCD039 Additional handrail at the loading dock CCD054 Extend CMU cap wall CCD070 Revise entry 142-1, entrance to new classroom wing CCD073 Delete freestanding CMU wall Credit Credit for removal/no need for the Banker Tank from the project CR No. 38 Cost of overtime premium CR No. 41 Modifications to chiller slab CR No. 75 Remove unforeseen buried concrete ENDEAVOUR ELEMENTARY ADDITION CCD013 Revisions to footing of underground concrete vault CCD020 Revise concrete at cafeteria loading dock CCD044 Increase to thickness of wainscot backing CCD049 Additional asphalt demo for CMU wall CCD056 Extend CMU cap wall Credit Credit for removal/no need for the Banker Tank from the project CR No. 52 Cost of overtime premium CR No. 56 Additional rock at sewer trenches CR No. 58 Demolition of existing mow strips CR No. 59 Route discharge pipe to catch basin CR No. 60 Additional floor prep mitigation CR No. 61 Addition of wall finishes at entry between MPR and Gym CR No. 62 Provide makeup water meter and valve on condenser loop Original Contract Sum (without WSST) $17,084,000.00 Original Contract Total including WSST (calculated at 10%) $18,792,400.00 Previous Contract Total including change orders and WSST $19,367,074.42 Total Change Order #6 Discovery ES Total $15,320.00 WSST 10% on DIS Total $1,5320.00 Endeavour ES Total $55,811.00 WSST 8.6% on END Total $4,799.75 Total Change Order #5 including Tax $77,462.75 Revised Contract Total $19,444,537.17 The revised contract total is within the project budget. Jake Kuper or Tom Mullins will be available to answer any questions the board may have regarding this recommendation. Please scroll down to view Discovery Elementary/Endeavour Elementary Addition Change Order #6 (2 pages).

Upload: others

Post on 05-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Discovery Elementary/Endeavour Elementary Addition –Change ...apps.issaquah.wednet.edu/documents/events/1155/4-9... · 4/9/2020  · Discovery Elementary/Endeavour Elementary Addition

Advance Notice April 9, 2020 Discovery Elementary/Endeavour Elementary Addition – Change Order #6 – Kuper/Mullins Action to be taken: I move the board approve the Discovery Elementary School Addition Change Order

#6 from Kassel & Associates, in the amount of $15,320.00 plus $1,532.00 WSST for a total of $16,852.00.

I move the board approve the Endeavour Elementary School Addition Change Order

#6 from Kassel & Associates in the amount of $55,811.00 plus $4,799.75 WSST for a total of $60,610.75.

Each proposal request listed on the attached change orders have been reviewed by the District Construction Coordinator for the project. Cost proposals were reviewed and reduced where possible and as proposed represent an equitable charge for the scope of work involved.

DISCOVERY ELEMENTARY ADDITION CCD039 Additional handrail at the loading dock CCD054 Extend CMU cap wall CCD070 Revise entry 142-1, entrance to new classroom wing CCD073 Delete freestanding CMU wall Credit Credit for removal/no need for the Banker Tank from the project CR No. 38 Cost of overtime premium CR No. 41 Modifications to chiller slab CR No. 75 Remove unforeseen buried concrete

ENDEAVOUR ELEMENTARY ADDITION CCD013 Revisions to footing of underground concrete vault CCD020 Revise concrete at cafeteria loading dock CCD044 Increase to thickness of wainscot backing CCD049 Additional asphalt demo for CMU wall CCD056 Extend CMU cap wall Credit Credit for removal/no need for the Banker Tank from the project CR No. 52 Cost of overtime premium CR No. 56 Additional rock at sewer trenches CR No. 58 Demolition of existing mow strips CR No. 59 Route discharge pipe to catch basin CR No. 60 Additional floor prep mitigation CR No. 61 Addition of wall finishes at entry between MPR and Gym CR No. 62 Provide makeup water meter and valve on condenser loop

Original Contract Sum (without WSST) $17,084,000.00 Original Contract Total including WSST (calculated at 10%) $18,792,400.00 Previous Contract Total including change orders and WSST $19,367,074.42 Total Change Order #6

Discovery ES Total $15,320.00 WSST 10% on DIS Total $1,5320.00 Endeavour ES Total $55,811.00 WSST 8.6% on END Total $4,799.75

Total Change Order #5 including Tax $77,462.75 Revised Contract Total $19,444,537.17

The revised contract total is within the project budget. Jake Kuper or Tom Mullins will be available to answer any questions the board may have regarding this recommendation.

Please scroll down to view Discovery Elementary/Endeavour Elementary Addition Change Order #6 (2 pages).

Page 2: Discovery Elementary/Endeavour Elementary Addition –Change ...apps.issaquah.wednet.edu/documents/events/1155/4-9... · 4/9/2020  · Discovery Elementary/Endeavour Elementary Addition
Page 3: Discovery Elementary/Endeavour Elementary Addition –Change ...apps.issaquah.wednet.edu/documents/events/1155/4-9... · 4/9/2020  · Discovery Elementary/Endeavour Elementary Addition