By Anil K Mishra
MC i85 A/ B Specifications
Model Mci 85 a/b, External Crane( Inside lift shaft)
Base Mast – 7.5m
Jib – 50 Mtrs
Height Under Hook – 49.5 Mtrs
Maximum Capacity – 5 Tons
Load at 50 Mtrs – 1.3 Tons
Method statements:- Dismantling
•Preparation &Removal of Telescopic cage•Position of Derrick for counter weights•Removal of cabin•Position of derrick for main jib•Position of derrick for removing cat head, mast and anchorage frames•Position of Gantry for lowering the material.•Provision of storage on ground for shipping•General provisions
Potain Asia Range
Preparation for dismantling
•Ensure Crane is positioned approx 6 meters above the top slab to facilitate removal of telescopic cage (if fitted)
•Remove telescopic Cage using standard method
Potain Asia Range
Removal of Counter Weights using Special Frame or Derricks
Special FrameInstalled on counter jib
3 counter weights removedone by one
One counter weight will remainInstalled until main jib is removed
Position of Derrick for main jib removal
MAIN JIB
LENGTH CG ( HOOK POSITION) WEIGTH (+_5%)
50M 17.5M 6488 KGS
45M 16.2M 6237 KGS
40M 14M 5584 KGS
35M 12.87M 5351 KGS
Tentative location of Derrick for main jib dismantling
D- position of Derrick for Main jibD for CJ- Derrick position for Counter jib
D for CJ
Potain Asia Range
Removal of Main jib using special Derrick
Special derrick is positioned as per actual site condition to balance the load / CG as per jib length in use
Special Derrick
Lowering of Main jib on Top Slab
Main jib is rested on the top slab ensuring safety, Joining Pins are removed with load supported on slab
Removing of Control Panel and Hoist motor
Hoist Motor and Electrical control panel is removed using Chain Pulleys/ derrick as required
Main Jib dismantled into small parts and lowered to groundusing same winch or routing through derrick/ pulleys
Positioning of Derrick for Removing Vertical Structure
Derrick
Position
Vertical Structure with Cat head
Removing Cat head
Removing vertical Structure- Using Derrick
Cat is removed and all masts pulled up one by one using derrick and Hoist winch
Bringing down to Zero level
All Materials are brought down to Zero level with Derrick or gantry Crane which is positioned near edge of building on top
General Provisions
• All Precautions are taken to ensure crane is balanced and safe before start of work.
• At any given point, all derrick, pulleys and wire rope are inspected fully for any possible damage.
• Necessary safety is ensured at every stage of work
• Loads on hook, pulley, wire rope and number of falls calculated for each stage of work.
• Safety precautions for site specific is also followed by work and team
• Actual position of Derrick/ gantry may vary as per site condition and load CG.
• Site Support is essential for smooth and safe operation for dismantling