district development and housing committee, southern district council progress report ... · 2017....

26
DDHC Paper No. 16/2016 (for discussion on 26.9.2016) District Development and Housing Committee, Southern District Council Progress Report on Planning Works in Southern District Annex 1 Matters discussed at previous meetings that required follow-up actions (Progress as at 12.9.2016) Annex 2 Planning DepartmentProgress Report on Planning Works in Southern District (Progress as at 31.8.2016) Annex 3 Highways DepartmentProgress Report on Road Works in Southern District (Progress as at 31.8.2016) Annex 4 Civil Engineering and Development DepartmentProgress Report on Other Works in Southern District (Progress as at 31.8.2016) Annex 5 Housing DepartmentProgress Report on Public Housing Works in Southern District (Progress as at 31.8.2016) Annex 6 Food and Environmental Hygiene DepartmentProgress Report on FEHD District Minor Works in Southern District (Progress as at 31.8.2016) Annex 7 Lands DepartmentProgress Report on Lands Department Temporary Government Lands Allocation in Southern District (Progress as at 31.8.2016) Annex 8 Follow-up on the Land Use upon MTRC Handing Back the Lands Currently Used as Work Sites (Progress as at 31.8.2016)

Upload: others

Post on 09-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

DDHC Paper No. 16/2016

(for discussion on 26.9.2016)

District Development and Housing Committee, Southern District Council

Progress Report on Planning Works in Southern District

Annex 1

Matters discussed at previous meetings that required follow-up actions

(Progress as at 12.9.2016)

Annex 2

Planning Department-Progress Report on Planning Works in Southern District

(Progress as at 31.8.2016)

Annex 3

Highways Department-Progress Report on Road Works in Southern District

(Progress as at 31.8.2016)

Annex 4

Civil Engineering and Development Department-Progress Report on Other Works in Southern District

(Progress as at 31.8.2016)

Annex 5

Housing Department-Progress Report on Public Housing Works in Southern District

(Progress as at 31.8.2016)

Annex 6

Food and Environmental Hygiene Department-Progress Report on FEHD District Minor Works in Southern District

(Progress as at 31.8.2016)

Annex 7

Lands Department-Progress Report on Lands Department Temporary Government Lands Allocation in Southern District

(Progress as at 31.8.2016)

Annex 8

Follow-up on the Land Use upon MTRC Handing Back the Lands Currently Used as Work Sites

(Progress as at 31.8.2016)

Page 2: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

1

Abbreviations for government departments in this report: (in alphabetical order)

ArchSD Architectural Services Department

CEDD Civil Engineering and Development Department

DSD Drainage Services Department

EPD Environmental Protection Department

FEHD Food and Environmental Hygiene Department

HD Housing Department

HyD Highways Department

LandsD Lands Department

LCSD Leisure and Cultural Services Department

MTR Corporation Mass Transit Railway Corporation Limited

PlanD Planning Department

WSD Water Supplies Department

Page 3: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

2

Annex 1

Matters discussed at previous meetings that required follow-up actions

(Progress as at 12.9.2016)

Latest Progress on Matters Date of First Discussion

(Date of updates)

1. Ex- Shek O Quarry

PlanD/HyD/MTR Corporation

The ex-Shek O Quarry site falls within an area zoned “Undetermined” on the Tai Tam and Shek O Outline Zoning Plan.

The then Civil Engineering Department in 1994 undertook rehabilitation works with the concept of developing the

rehabilitated quarry site for recreation-related uses, such as water sports centre. The site is temporarily used as a

casting basin for Shatin to Central Link by MTR Corporation and will be handed-over to LandsD in 2019. PlanD will

review the zoning of the subject site and consult the District Council when appropriate or before 2019.

30.11.2009

(19.5.2016)

Page 4: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

3

2. Request to Improve the Drainage System of the Villages in Southern District

(I) On Pokfulam Village

DSD arranged the second joint site visit with District Lands Office, Hong Kong West and South (DLO/HKW&S) on

10 August 2016 to ascertain the works boundaries within Pokfulam Village. A meeting among Mr. CHU Ching-hong

JP, Pokfulam Village Sewerage Concern Group, EPD and DSD has been arranged on 21 September 2016 to discuss the

latest project progress. DSD is now refining the project design.

16.5.2011

(14.9.2016)

(II) On Shek O Village, Wong Chuk Hang San Wai Village, Kau Wai Village and Tai Hau Wan Village

FEHD advised that Railway Development Section of LandsD had requested MTRCL to replant trees at the proposed

location of Wong Chuk Hang San Wai Village Public Toilet according to the approved Tree Removal Application in

2011. FEHD has accordingly requested LandsD to waive to replant trees at the subject location so as to prevent

affecting the construction works of the public toilet. Railway Development Section of LandsD recently replied that

MTRCL is not required to plant the compensatory trees on the proposed San Wai Village Public Toilet site. Now,

FEHD is pending the reply from LandsD regarding application of land allocation. Also, FEHD is still pending Minor

Building Works Committee of ArchSD to approve the funding application for construction of the Wong Chuk Hang San

Wai Village Public Toilet.

LandsD advised that,as to the application for allocation of the site, DLO/HKW&S was awaiting responses from some

departments and would process the application as soon as possible after the responses were received.

(19.9.2016)

Page 5: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

4

3. Short-term and Long-term Uses of the Site of Former Aberdeen Fire Station (AFS)

PlanD advised that the site is zoned “Other Specified Uses” annotated “Business(2)” (“OU(B)2”) on the Aberdeen & Ap

Lei Chau Outline Zoning Plan No. S/H15/30. According to the Notes of the “OU(B)2” zone, ‘Office’ and ‘Place of

Recreation, Sports or Culture’ use, including arts centre, arts gallery, artist studio and rehearsal room for arts

performances, are always permitted within the site.

On 13 November 2015, the Legislative Council Panel on Home Affairs supported the proposed project to provide arts

space and arts facilities for use by local artists and art groups, as well as a permanent office for the Hong Kong Arts

Development Council in the future development at the subject site. The proposed project was endorsed by the Public

Works Subcommittee of Finance Committee and the Finance Committee on 24 February and 22 April 2016 respectively.

LandsD advised that the site has been included in the 2016-17 land sale programme (i.e. Aberdeen Inland Lot No. 462).

The Government announced on 29 June 2016 about the details of the land sale programme for the second quarter of

2016-17 (i.e. July to September 2016), including that the site will be sold by tender in the second quarter. LandsD will

issue a press release later before putting up the site for tender, to announce the Tender Invitation Date, Tender Closing

Date, and the major information of the site, including its size, user, minimum and maximum gross floor area etc.

26.3.2012

(12.7.2016)

4. Planning Application for the “Comprehensive Development Area” Site in Wong Chuk Hang

Updates on the item will be reported when there is further progress.

26.11.2012

5. Provision of Facilities in the Convenience of Residents at the Government Land Adjacent to Jumbo Pier

Proposal 2: Construction of public lavatory

FEHD advised that there is no updating for the suggested construction of a public toilet near Jumbo Pier.

4.2.2013

(11.7.2016)

Page 6: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

5

Annex 2

District Development and Housing Committee, Southern District Council

Progress Report on Planning Works in Southern District

(As at 31.8.2016)

I. Outline Zoning Plan

District

Plan No. Project Description Remarks

Aberdeen &

Ap Lei Chau S/H15/30 The Town Planning Board (TPB) on 24.12.2015 gazetted the draft Aberdeen & Ap

Lei Chau Outline Zoning Plan (OZP) No. S/H15/30 under section 5 of the Town

Planning Ordinance for public inspection for two months. The OZP amendments

mainly involve the rezoning of a site at Lee Nam Road, Ap Lei Chau, from “Other

Specified Uses” annotated “Cargo Handling Area” (“OU(Cargo Handling Area)”),

“Government, Institution or Community” and “Industrial” (“I”) to “Residential

(Group A)4” for residential development; rezoning of a strip of land fronting Ap Lei

Chau West Industrial Area from “OU(Cargo Handling Area)” to “Open Space”; and

rezoning the Ap Lei Chau West Industrial Area from “I” to “OU” annotated

“Business(3)” and “Business(4)” to enhance the transformation of the area to

business uses.

During the two-month exhibition period which ended on 24.2.2016, a total of 607

representations were received. On 15 April, the TPB published the representations

for public comments. During the publication period which ended on 6 May, 16

comments related to the representations were received. The TPB will then hold a

“hearing meeting” to hear and consider the representations and comments received.

The representers and commenters, including their authorized representatives, will be

invited to attend the hearing meeting. The hearing meeting is scheduled on

27.9.2016 (Tue). About seven days before the meeting, the relevant representers

and commenters will be notified of the arrangements of the hearing and provided

with a copy of the relevant TPB paper.

Details of the amendments

please refer to DDEC Paper

No. 2/2016.

Page 7: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

6

II. Planning Application

Application submitted for Town Planning Board’s Consideration (1.7.2016 to 31.8.2016)

District

Application No. Applied Use Location Consideration / Result Remarks

Wong

Chuk Hang Submission for

Partial

Fulfillment of

Approval

Condition (a)

under

Application No.

A/H15/232-2

Proposed

Fisherman’s

Wharf Hotel

Ocean Park,

Hong Kong

On 26.8.2016, the Metro Planning Committee of the

Town Planning Board (TPB) agreed that the

submission had satisfactorily fulfilled part of approval

condition (a) (i.e. the building form, layout, design,

disposition and building height of the proposed hotel

developments to the satisfaction of TPB) for the

proposed Fisherman’s Wharf Hotel.

(Note : Ocean Park

consulted the Southern

District Council on The

Fullerton Hotel @

Ocean Park (formerly

known as Fisherman’s

Wharf Hotel) on

21.3.2016.)

Page 8: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

7

III. Hotel Developments in Wong Chuk Hang Business Area Approved by Town Planning Board with Planning Permission Still Valid

Location Remarks

1. 39 Wong Chuk Hang Road

Planning permission valid until Sep 2017.

[The previous lease modification application for non-industrial use (including hotel) was

withdrawn by the applicant in 11/2012. The existing lease is for industrial use and hotel is

not permitted.]

The lot owner is currently applying lease modification for proposed covered footbridge link.

2. 41-43 Wong Chuk Hang Road

Planning permission valid until Nov 2019.

[The previous lease modification application for non-industrial use (including hotel) was

withdrawn by the applicant in 11/2012. The existing lease is for industrial use and hotel is

not permitted.]

Page 9: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

8

Annex 3

District Development and Housing Committee, Southern District Council

Progress Report on Road Works in Southern District

(As at 31.8.2016)

I. Preliminary Project Plan of Construction Works

PWP No. / Cat. Type Project

Description Agency Progress / Remarks

Est. (Actual) Start

Date

Est. (Actual)

Completion Date

N.A. – Junction

Improvement at

Chung Hom Kok

Road / Stanley

Gap Road

Transport

Department

Chung Hom Kok Road and Stanley Gap

Road junction is confined by the adjacent

slopes, with limited road space. Junction

improvement works will require substantial

slope works, transplanting a large number of

trees, and temporary closure of traffic lanes.

Transport Department advised that they have

recently carried out traffic survey in the area

and the traffic condition is considered

acceptable. If other works are to be carried

out at the above area in future, such as slope

upgrading works, or new private

development, Transport Department will

request the project proponent to carry out

the junction improvement works.

– –

Page 10: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

9

Annex 4

District Development and Housing Committee, Southern District Council

Progress Report on Other Works in Southern District

(As at 31.8.2016)

I. Works Commenced

PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)] Est. (Actual)

Start Date

Est. (Actual)

Completion Date

186WC/A Replacement and

Rehabilitation of Water

Mains Stage 3

WSD

Water mains replacement and rehabilitation works in

Southern District under Contract No. 18/WSD/08

commenced on 18 March 2009. Works currently being

carried out in Southern District include:

(a) Pok Fu Lam Road Footpath and Carriageway

[97%](Pressure test for water mains to be completed

after swimming season (Jul to Sep) in October

2016.);

(b) Repulse Bay Road Footpath and Carriageway (Water

mains replacement works completed, remaining

abandonment of the existing covers of valve

chambers to be completed after swimming season

(Jul to Sep)) [99%];

(c) Red Hill Service Reservoir [100%];

(d) Stanley Gap Road Carriageway [100%];

(e) Stanley Village Road Footpath and Carriageway

(Water mains replacement works completed,

remaining abandonment of the existing covers of

valve chambers to be completed after swimming

season (Jul to Sep)) [99%];

(f) Area in the vicinity of Pok Fu Lam Service

Reservoir [100%]; and

(g) Pok Fu Lam Village [100%].

(3.2009)

(8.2010)

(7.2011)

(10.2010)

(3.2010)

(9.2010)

(11.2011)

(11.2011)

10.2016

10.2016

10.2016

(3.2016)

(4.2016)

10.2016

(4.2016)

(3.2016)

Page 11: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

10

PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)

Start Date

Est. (Actual)

Completion Date

191WC/A Replacement and

Rehabilitation of Water

Mains Stage 4 Phase 1

WSD Contract No.12/WSD/10, which consists of construction

works in Southern District, commenced on 18 July 2011.

Works are being carried out. Works in Southern District

are as below:

(a) Consort Rise Footpath and Carriageway (in progress)

[96%][Reason: Additional mainlaying works are

required to facilitate the site condition.];

(b) Bisney Road Footpath and Carriageway (in progress)

[95%] [Reason: Additional mainlaying works are

required to facilitate the site condition. ];

(c) Area in the vicinity of Aberdeen Water Treatment

Works (in progress) [99%] [Reason: Water suspension

required for water connection works involved a large

affected area which included sensitive consumers (i.e.

Hospitals). Therefore, extra coordination work is

required with the affected premises. The pressure

logging for connection had been completed. Additional

time is required for discussion on the arrangement of

water suspension with WSD/HK&I.];

(7.2011)

(1.2012)

(1.2012)

(4.2012)

7.2017

12.2016

12.2016

11.2016

(d) Deep Water Bay Road Footpath and Carriageway (in

progress) [99%] [Reason: Water suspension required

for water connection works involved a large affected

area which included Shouson Hill Fresh Water Service

Reservoir. Therefore, extra coordination work is

required with the affected premises. The excavation

permit has been expired and the new excavation permit

is targeted to be granted in August 2016];

(e) Wah King Street Footpath and Carriageway (in

progress) [89%]

(f) Victoria Road Footpath and Carriageway (in progress)

[93%];

(11.2012)

(1.2014)

(1.2014)

11.2016

9.2016

3.2017

Page 12: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

11

PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)

Start Date

Est. (Actual)

Completion Date

(g) Repulse Bay Road Carriageway near Belleview Drive

(in progress) [25%];

(h) Aberdeen Praya Road Carriageway (in progress)

[47%];;

(i) Wong Chuk Hang Road footpath (in progress)

[98%][Reason: The water main alignment was

amended due to congested underground utilities]; and

(j) Kai Lung Wan Fresh Water Service Reservoir [23%]

(in progress)

(1.2016)

(10.2015)

(10.2015)

(1.2014)

12.2016

3.2017

10.2016

7.2017

Page 13: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

12

Contract No.3/WSD/12, which consists of construction

works in Southern District, commenced on 15 March

2013. Works are being carried out. Works in Southern

District are as below:

(a) Pok Fu Lam Road near Pok Fu Lam Garden Footpath

and Carriageway (in progress) [95%] [Reason: The

mainlaying works are almost completed and the

pressure testing for connection works is in progress.];

and

(b) Aberdeen Praya Road near Fish Marketing

Organization at Footpath and Carriageway

(in progress) [95%] [Reason: Water suspension

required for wter connection works involved a large

affected area which included Aberdeen Fish Market.

Therefore, extra coordination work is required with the

affected premises. The mainlaying works and pressure

test have been completed. The water main connection

work will be completed in September 2016.].

(c) Tin Wan Street Footpath and Carriageway (in progress)

[50%];

(d) Tin Wan Praya Road Footpath and Carriageway

(in progress) [95%] [Reason: The progress was slightly

affected by the presence of congested underground

utilities];

(e) Victoria Road/Sha Wan Drive Footpath and

Carriageway (in progress) [35%]; and

(f) Wong Chuk Hang Road Footpath and Carriageway

(in progress) [10%].

(3.2013)

(8.2013)

(11.2015)

(1.2016)

(1.2016)

(5.2016)

(7.2016)

4.2017

10.2016

9.2016

12.2016

9.2016

12.2016

4.2017

Page 14: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

13

341DS/A Harbour Area

Treatment Scheme,

stage 2A -

Upgrading of

Stonecutters Island

sewage treatment

works and

preliminary

treatment works

Drainage

Services

Department

The item comprises upgrading of the Stonecutters Island

Sewage Treatment Works and eight numbers of

preliminary treatment works at Hong Kong Island. The

project has been fully commissioned in December 2015.

Contract DC/2009/24 (Harbour Area Treatment Scheme

Stage 2A Upgrading of Preliminary Treatment Works

(PTWs) at Sandy Bay, Cyberport, Wah Fu, Aberdeen and

Ap Lei Chau), being part of the works of the above item,

has commenced on 31/8/2011. Since the full

commission of the project in December 2015, the treated

effluent from Sandy Bay, Cyberport, Wah Fu, Aberdeen

and Ap Lei Chau sewage treatment works has been

intercepted and conveyed to the newly expanded

Stonecutters Island Sewage Treatment Works for further

treatment. The water quality of the nearby waters is

improved, as there is no more direct discharge of treated

effluent into the areas. The works of DC/2009/24

mainly include the upgrading of the sewage treatment

and de-odourisation facilities in these PTWs. About

89% of works under the contract has been completed.

(8.2011) 12.2016

Page 15: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

14

Progress Report on Landslip Prevention and Mitigation Works

PWP No. /

Cat.

Project Description Agency Progress / Remarks [Completion rate (%)] Est.

(Actual)

Start Date

Est. (Actual)

Completion

Date

Head 705

Subhead

5001BX/D

Landslip Prevention

and Mitigation

Programme

(LPMitP)

CEDD Landslip prevention and mitigation works for 114 man-made slopes and

5 natural hillside study areas in the Southern District are completed.

The natural hillside study areas are 11SW-C/SA3, 15NW-B/SA1,

11SW-C/SA4, 11SW-D/SA12 and 15NW-B/SA5. Landslip prevention

and mitigation works for 7 man-made slopes and 7 natural hillside study

areas are currently in progress.

(1) Slope No. 15NE-A/C96 at South Bay Road

[100%] (Works Completed)

(3.2014) (7.2016)

(2) Slope No. 15NE-A/F68 at Repulse Bay Road

[100%] (Works Completed)

(3.2014) (7.2016)

(3) Slope No. 15NW-B/C136 at Main Street, Ap Lei Chau

[100%] (Works Completed)

(11.2015) (7.2016)

(4) Slope No. 11SW-D/C2259 at Deep Water Bay Drive [30%] (4.2016) 12.2016

(5) Slope No. 15NE-C/FR154 at Behind Correctional Services

Department Staff Quarters (Front Block), Stanley [20%]

(4.2016) 4.2017

(6) Slope No. 11SW-D/C1440 at Yue Kwong Road [15%] (6.2016) 12.2016

(7) Slope No. 11SW-C/R407 at Aberdeen Praya Road [5%] (7.2016) 1.2017

(8) Slope No. 11SW-D/R1222 at Near Lamppost No. 35053, Aberdeen

Reservoir Road [5%]

(7.2016) 1.2017

(9) Slope No. 11SW-D/R1223 at Near Lamppost No. 35053, Aberdeen

Reservoir Road [5%]

(7.2016) 1.2017

(10) Slope No. 15NE-A/R244 at Repulse Bay Main Sewage Pumping

Station [5%]

(7.2016) 1.2017

(11) 2 Natural hillside study areas behind Queen Mary Hospital

(Study Area Numbers 11SW-C/SA1 and 11SW-C/SA2) [97%]

(1.2012) 9.2016

(12) 1 Natural hillside study area above Ruby Court at South Bay Road

(Study Area Number 15NE-A/SA3) [65%]

(3.2014) 12.2016*

Page 16: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

15

PWP No. /

Cat.

Project Description Agency Progress / Remarks [Completion rate (%)] Est.

(Actual)

Start Date

Est. (Actual)

Completion

Date

(13) 1 Natural hillside study area above Pok Fu Lam Road

(Study Area Number 11SW-C/SA5) [40%]

(11.2014) 3.2017

(14) 1 Natural hillside study area at Shek Pai Wan Road, Aberdeen

(Study Area Number 11SW-C/SA5) [25%]

(9.2015) 3.2017

(15) 1 Natural hillside study area above Ap Lei Chau fronting the

Aberdeen Channel (Study Area Number 15NW-B/SA2) [25%]

(12.2015) 2.2017

(16) 1 Natural hillside study area at Ap Lei Chau

(Study Area Number 15NW-B/SA6) [15%]

(4.2016) 10.2017

* Anticipated completion date is revised as the works have been affected by inclement weather

Page 17: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

16

Head 705

Subhead

5001BX/D

Landslip Prevention

and Mitigation

Programme (LPMitP)

CEDD In the coming year, CEDD is planning to progressively commence the

landslip prevention and mitigation works for other 8 man-made slopes

and 1 natural hillside study area.

(1) Slope No. 11SW-D/C1058 at Hong Kong Police College Lower

Range, Police School Road, Aberdeen

@ @

(2) Slope No. 11SW-C/CR874 at Victoria Road 9.2016# 2.2017

#

(3) Slope No. 15NW-B/C385 at Island Road 10.2016 7.2017

(4) Slope No. 15NE-C/C320 at Canteen Outside The Prison

Compound, Stanley Prison

3.2017 10.2017

(5) Slope No. 15NE-A/C193 at Tai Tam Road 5.2017 4.2019

(6) Slope No. 11SW-C/CR981 at Pok Fu Lam Village 9.2016 4.2017

(7) Slope No. 15NE-A/C192 at Tai Tam Road 4.2017 6.2017

(8) Slope No. 11SE-C/C237 at Repulse Bay Road 7.2017 2.2018

(9) 1 Natural hillside study area Behind Police College at Wong Chuk

Hang (Study Area Number 15NW-B/SA3)

10.2016 3.2018

# #

# Anticipated start date and completion date are revised due to reschedule of works programme

@ @ Anticipated start date and completion date will be re-scheduled due to re-programming of works

Page 18: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

17

PWP No. /

Cat.

Project Description Agency Progress / Remarks

Head 705

Subhead

5001BX/D

Landslip Prevention

and Mitigation

Programme (LPMitP)

CEDD CEDD is carrying out stability investigation for other 19 man-made

slopes in the Southern District, which are in the early stage of the LPMit

Programme. The stability investigations of these slopes are not yet

completed. Therefore, upgrading works to these slopes may not be

required if it is later confirmed that the slopes meet the required safety

standards.

(1) Slope No. 15NE-A/C176 at Tai Tam Road

(2) Slope No. 15NE-A/C608 at Tai Tam Road

(3) Slope No. 15NE-A/C90 at South Bay Road

(4) Slope No. 15NE-A/C195 at Tai Tam Road

(5) Slope No. 15NE-A/C197 at Tai Tam Road

(6) Slope No. 11SW-D/FR651 at Wong Chuk Hang San Wai

(7) Slope No. 15NE-A/CR454 at Tai Tam Road Catchwater

(8) Slope No. 15NE-A/F45 at Tai Tam Road

(9) Slope No. 11SE-D/C406 near the junction between Shek O Road &

Cape Collinson Road

(10) Slope No. 15NE-A/FR34 at Repulse Bay Road

(11) Slope No. 15NE-A/C241 at West of Eden View, Stanley Gap Road

(12) Slope No. 15NE-A/C118 at Northeast of the junction of Repulse

Bay Road and Headland Road

(13) Slope No. 15NE-A/C240 near the junction of Stanley Gap Road and

Headland Road

(14) Slope No. 15NE-D/R8 at Ngai Choi Hang Village, Cape D’aguilar

Road

(15) Slope No. 15NW-B/C97 at Island Road

(16) Slope No. 15NE-A/C13 at Repulse Bay Road

(17) Slope No. 15NE-B/C235 at Shek O Road

(18) Slope No. 11SE-D/C104 at Shek O Road

(19) Slope No. 11SE-D/C669 at Shek O Road

Page 19: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

18

Annex 5

District Development and Housing Committee, Southern District Council

Progress Report on Public Housing Works in Southern District

(As at 31.8.2016)

I. Works Commenced (up to the end of two financial years later)

Project Description

PWP / Estate Responsible Team Est. (Actual) Start Date Est. (Actual)

Completion Date Remarks

Lift Modernisation

for Ap Lei Chau

Estate

BSE/ECM2 May 2014 (May 2014) November 2017 The lift modernisation project for Ap Lei

Chau Estate involves four sections of works.

The works for the fifteen lifts in Section I

and Section II were completed. The works

for the ten lifts in Section III (Lei Yee House

L1; Lei Ning House L6; Lei Chak House L9,

L12 and L13; Lei Tim House L18; Lei Fook

House L19 and L23; and Lei Moon House

L25 and L29), commencing in late February

2016 in phases, will be completed in the first

quarter of 2017. The works for the last

section, following the completion of Section

III, will commence in the same of quarter of

the year. The whole project is scheduled for

completion in the fourth quarter of 2017.

Page 20: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

19

Annex 6

District Development and Housing Committee, Southern District Council

Progress Report on FEHD District Minor Works in Southern District

(As at 31.8.2016)

Item

No.

Proposed

Minor Works Location

Estimated

Start Date

[Actual

Start Date]

Estimated

Completion

Date

[Actual

Completion

Date]

Remarks FEHD Contact

Person

ASD Contact

Person

1.

Refurbishment

of Shek O

Village Public

Toilet

Shek O

Village near

Shek O

DSD Plant

[Aug 2016] May 2017 Works in progress

Senior Health

Inspector

(Cleansing/Pest

Control) Southern,

Ms. WONG Ka-wai

【2903 0402】

Property

Services

Manager/

PM14,

Mr. WONG

Wing-lim,

William

【2773 2426】

Page 21: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

20

Annex 7

District Development and Housing Committee, Southern District Council

Progress Report on Lands Department Temporary Government Lands Allocation in Southern District

(As at 31.8.2016)

Item

No.

TGLA No./

File Ref.

Type of

TGLA

(New/

Renewal)

Location

Proposed

Area (m2)

Proposed

User

Proposed

Term

User Dept.

(Allocatee)

Date of

Allocation

Date of

Withdrawn

Remarks

(Current Situation)

1. GLA-THK 1753

504/SHGS/82

Renewal Government

land between

No.24 and 25

Shum Wan

Road, Wong

Chuk Hang

126 Car

parking

spaces

Extend up to

11.2.2020

C of P - - Regarding the objection

from DDHC, C of P

responded that the

proposed parking was

for its operational

needs.TD had no

comment and Security

Bureau had given

approval to the

proposed extension.

Case in progress.

Page 22: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

21

2. GLA-THK1892

L/M

988/SHMS/82 A

Renewal Tin Wan Praya

Road, Aberdeen

820 Works Area Extend up to

31.12.2017

DSD - - Departmental circulation

completed. Pending

Approval. DSD had

been requested to provide

supplementary

information before

processing the

application for renewal.

3. GLA-THK1550

413/SHGS/82

Renewal Hok Tsui Village 667 Sitting out area

and meeting

venue

Extend up to

30.6.2017

HAD,

DO(S)

- - Departmental circulation

completed. Pending

approval.

4. GLA-THK950

177/HGS/82

Renewal At Stanley Gap

Road

127 Manoeuvring

and/or Parking of

Waterworks

Vehicles to/from

Stanley Mound

Fresh Water

Pumping Station

& Extension

Extend up to

31.5.2020

WSD - - Departmental circulation

completed. Pending

approval.

Page 23: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

22

5. GLA-THK 1875

988/SHMS/82B

Renewal Sandy Bay,

Pok Fu Lam

1,480 Works Area Extended up

to

31.12.2017

DSD - - Under departmental

circulation.

DSD applied for further

extension upto

31.12.2017. .

6. GLA-THK 1538

L/M 7/SHGS/82

(68)

Renewal Pak Sha Wan, Ap

Lei Chau

799 Works Area for

installation and

maintenance of

Shark Prevention

Nets

Extended up

to 30.6.2018

LCSD - - Under departmental

circulation.

7. GLA-THK 1922

574/SHGS/82

Renewal Ap Lei Chau Praya

Road, Ap Lei Chau

666 Works Area for

management and

maintenance of

Roads

Extended up

to 30.6.2021

HyD - - Under departmental

circulation.

Page 24: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

23

Annex 8

District Development and Housing Committee, Southern District Council

Follow-up on the Land Use upon MTRC Handing Back the Lands Currently Used as Work Sites

(As at 31.8.2016)

Location Anticipated

Handover

Date

Approximate

Area Size

(m2)

Managing

Agent

Planned Use/Follow-up Actions

(Provided by Managing Department/Agent) Date of First Discussion

(Date of updates)

Site next to

Ocean Park

Handed over

in the end of

June 2016

6,230

LandsD

Long-term planned use of the land is to be advised by

PlanD. LandsD would facilitate any application for

use of the land in accordance with applicable

procedures.

(PlanD’s comments: The subject site falls within an

area zoned “Government, Institution or Community”

(“G/IC”) on the approved Aberdeen & Ap Lei Chau

Outline Zoning Plan No. S/H15/29 and is reserved for

provision of GIC facilities.)

26.1.2015

(15.7.2016)

Page 25: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

24

Location Anticipated

Handover

Date

Approxim

ate Area

Size

(m2)

Managing

Agent

Planned Use/Follow-up Actions

(Provided by Managing Department/Agent) Date of First Discussion

(Date of updates)

Chung Hom

Shan Magazine

Site

Handed over 2,500 LandsD Long-term planned use of the land is to be advised by

PlanD. LandsD would facilitate any application for

use of the land in accordance with applicable

procedures.

(PlanD’s comments: The subject site falls within an

area zoned “Other Specified Uses” annotated

“Composite Signals Organization Station Complex”

on the approved Stanley Outline Zoning Plan No.

S/H19/10 intended primarily to provide land for

composite signals organization station complex and

its ancillary facilities.)

26.1.2015

(26.1.2015)

Page 26: District Development and Housing Committee, Southern District Council Progress Report ... · 2017. 3. 17. · 10 August 2016 to ascertain the works boundaries within Pokfulam Village

25

Chung Hom

Shan Nursery

Site next to

Magazine Site

2nd Half 2017

(To tie in with the

latest progress of

the reprovisioning

works at Harcourt

Garden, some of

the trees

temporarily

transplanted from

Harcourt Garden

at the Chung Hom

Shan Nursery Site

need to be

maintained for a

longer period. The

reprovisioning is

expected to be

substantially

completed by the

end of 2017.)

6,400 LandsD Long-term planned use of the land is to be advised by

PlanD. LandsD would facilitate any application for

use of the land in accordance with applicable

procedures.

(PlanD’s comments: The subject site falls within an

area zoned “Other Specified Uses” annotated

“Composite Signals Organization Station Complex”

on the approved Stanley Outline Zoning Plan No.

S/H19/10 intended primarily to provide land for

composite signals organization station complex and

its ancillary facilities.)

26.1.2015

(10.9.2015)