DDHC Paper No. 16/2016
(for discussion on 26.9.2016)
District Development and Housing Committee, Southern District Council
Progress Report on Planning Works in Southern District
Annex 1
Matters discussed at previous meetings that required follow-up actions
(Progress as at 12.9.2016)
Annex 2
Planning Department-Progress Report on Planning Works in Southern District
(Progress as at 31.8.2016)
Annex 3
Highways Department-Progress Report on Road Works in Southern District
(Progress as at 31.8.2016)
Annex 4
Civil Engineering and Development Department-Progress Report on Other Works in Southern District
(Progress as at 31.8.2016)
Annex 5
Housing Department-Progress Report on Public Housing Works in Southern District
(Progress as at 31.8.2016)
Annex 6
Food and Environmental Hygiene Department-Progress Report on FEHD District Minor Works in Southern District
(Progress as at 31.8.2016)
Annex 7
Lands Department-Progress Report on Lands Department Temporary Government Lands Allocation in Southern District
(Progress as at 31.8.2016)
Annex 8
Follow-up on the Land Use upon MTRC Handing Back the Lands Currently Used as Work Sites
(Progress as at 31.8.2016)
1
Abbreviations for government departments in this report: (in alphabetical order)
ArchSD Architectural Services Department
CEDD Civil Engineering and Development Department
DSD Drainage Services Department
EPD Environmental Protection Department
FEHD Food and Environmental Hygiene Department
HD Housing Department
HyD Highways Department
LandsD Lands Department
LCSD Leisure and Cultural Services Department
MTR Corporation Mass Transit Railway Corporation Limited
PlanD Planning Department
WSD Water Supplies Department
2
Annex 1
Matters discussed at previous meetings that required follow-up actions
(Progress as at 12.9.2016)
Latest Progress on Matters Date of First Discussion
(Date of updates)
1. Ex- Shek O Quarry
PlanD/HyD/MTR Corporation
The ex-Shek O Quarry site falls within an area zoned “Undetermined” on the Tai Tam and Shek O Outline Zoning Plan.
The then Civil Engineering Department in 1994 undertook rehabilitation works with the concept of developing the
rehabilitated quarry site for recreation-related uses, such as water sports centre. The site is temporarily used as a
casting basin for Shatin to Central Link by MTR Corporation and will be handed-over to LandsD in 2019. PlanD will
review the zoning of the subject site and consult the District Council when appropriate or before 2019.
30.11.2009
(19.5.2016)
3
2. Request to Improve the Drainage System of the Villages in Southern District
(I) On Pokfulam Village
DSD arranged the second joint site visit with District Lands Office, Hong Kong West and South (DLO/HKW&S) on
10 August 2016 to ascertain the works boundaries within Pokfulam Village. A meeting among Mr. CHU Ching-hong
JP, Pokfulam Village Sewerage Concern Group, EPD and DSD has been arranged on 21 September 2016 to discuss the
latest project progress. DSD is now refining the project design.
16.5.2011
(14.9.2016)
(II) On Shek O Village, Wong Chuk Hang San Wai Village, Kau Wai Village and Tai Hau Wan Village
FEHD advised that Railway Development Section of LandsD had requested MTRCL to replant trees at the proposed
location of Wong Chuk Hang San Wai Village Public Toilet according to the approved Tree Removal Application in
2011. FEHD has accordingly requested LandsD to waive to replant trees at the subject location so as to prevent
affecting the construction works of the public toilet. Railway Development Section of LandsD recently replied that
MTRCL is not required to plant the compensatory trees on the proposed San Wai Village Public Toilet site. Now,
FEHD is pending the reply from LandsD regarding application of land allocation. Also, FEHD is still pending Minor
Building Works Committee of ArchSD to approve the funding application for construction of the Wong Chuk Hang San
Wai Village Public Toilet.
LandsD advised that,as to the application for allocation of the site, DLO/HKW&S was awaiting responses from some
departments and would process the application as soon as possible after the responses were received.
(19.9.2016)
4
3. Short-term and Long-term Uses of the Site of Former Aberdeen Fire Station (AFS)
PlanD advised that the site is zoned “Other Specified Uses” annotated “Business(2)” (“OU(B)2”) on the Aberdeen & Ap
Lei Chau Outline Zoning Plan No. S/H15/30. According to the Notes of the “OU(B)2” zone, ‘Office’ and ‘Place of
Recreation, Sports or Culture’ use, including arts centre, arts gallery, artist studio and rehearsal room for arts
performances, are always permitted within the site.
On 13 November 2015, the Legislative Council Panel on Home Affairs supported the proposed project to provide arts
space and arts facilities for use by local artists and art groups, as well as a permanent office for the Hong Kong Arts
Development Council in the future development at the subject site. The proposed project was endorsed by the Public
Works Subcommittee of Finance Committee and the Finance Committee on 24 February and 22 April 2016 respectively.
LandsD advised that the site has been included in the 2016-17 land sale programme (i.e. Aberdeen Inland Lot No. 462).
The Government announced on 29 June 2016 about the details of the land sale programme for the second quarter of
2016-17 (i.e. July to September 2016), including that the site will be sold by tender in the second quarter. LandsD will
issue a press release later before putting up the site for tender, to announce the Tender Invitation Date, Tender Closing
Date, and the major information of the site, including its size, user, minimum and maximum gross floor area etc.
26.3.2012
(12.7.2016)
4. Planning Application for the “Comprehensive Development Area” Site in Wong Chuk Hang
Updates on the item will be reported when there is further progress.
26.11.2012
5. Provision of Facilities in the Convenience of Residents at the Government Land Adjacent to Jumbo Pier
Proposal 2: Construction of public lavatory
FEHD advised that there is no updating for the suggested construction of a public toilet near Jumbo Pier.
4.2.2013
(11.7.2016)
5
Annex 2
District Development and Housing Committee, Southern District Council
Progress Report on Planning Works in Southern District
(As at 31.8.2016)
I. Outline Zoning Plan
District
Plan No. Project Description Remarks
Aberdeen &
Ap Lei Chau S/H15/30 The Town Planning Board (TPB) on 24.12.2015 gazetted the draft Aberdeen & Ap
Lei Chau Outline Zoning Plan (OZP) No. S/H15/30 under section 5 of the Town
Planning Ordinance for public inspection for two months. The OZP amendments
mainly involve the rezoning of a site at Lee Nam Road, Ap Lei Chau, from “Other
Specified Uses” annotated “Cargo Handling Area” (“OU(Cargo Handling Area)”),
“Government, Institution or Community” and “Industrial” (“I”) to “Residential
(Group A)4” for residential development; rezoning of a strip of land fronting Ap Lei
Chau West Industrial Area from “OU(Cargo Handling Area)” to “Open Space”; and
rezoning the Ap Lei Chau West Industrial Area from “I” to “OU” annotated
“Business(3)” and “Business(4)” to enhance the transformation of the area to
business uses.
During the two-month exhibition period which ended on 24.2.2016, a total of 607
representations were received. On 15 April, the TPB published the representations
for public comments. During the publication period which ended on 6 May, 16
comments related to the representations were received. The TPB will then hold a
“hearing meeting” to hear and consider the representations and comments received.
The representers and commenters, including their authorized representatives, will be
invited to attend the hearing meeting. The hearing meeting is scheduled on
27.9.2016 (Tue). About seven days before the meeting, the relevant representers
and commenters will be notified of the arrangements of the hearing and provided
with a copy of the relevant TPB paper.
Details of the amendments
please refer to DDEC Paper
No. 2/2016.
6
II. Planning Application
Application submitted for Town Planning Board’s Consideration (1.7.2016 to 31.8.2016)
District
Application No. Applied Use Location Consideration / Result Remarks
Wong
Chuk Hang Submission for
Partial
Fulfillment of
Approval
Condition (a)
under
Application No.
A/H15/232-2
Proposed
Fisherman’s
Wharf Hotel
Ocean Park,
Hong Kong
On 26.8.2016, the Metro Planning Committee of the
Town Planning Board (TPB) agreed that the
submission had satisfactorily fulfilled part of approval
condition (a) (i.e. the building form, layout, design,
disposition and building height of the proposed hotel
developments to the satisfaction of TPB) for the
proposed Fisherman’s Wharf Hotel.
(Note : Ocean Park
consulted the Southern
District Council on The
Fullerton Hotel @
Ocean Park (formerly
known as Fisherman’s
Wharf Hotel) on
21.3.2016.)
7
III. Hotel Developments in Wong Chuk Hang Business Area Approved by Town Planning Board with Planning Permission Still Valid
Location Remarks
1. 39 Wong Chuk Hang Road
Planning permission valid until Sep 2017.
[The previous lease modification application for non-industrial use (including hotel) was
withdrawn by the applicant in 11/2012. The existing lease is for industrial use and hotel is
not permitted.]
The lot owner is currently applying lease modification for proposed covered footbridge link.
2. 41-43 Wong Chuk Hang Road
Planning permission valid until Nov 2019.
[The previous lease modification application for non-industrial use (including hotel) was
withdrawn by the applicant in 11/2012. The existing lease is for industrial use and hotel is
not permitted.]
8
Annex 3
District Development and Housing Committee, Southern District Council
Progress Report on Road Works in Southern District
(As at 31.8.2016)
I. Preliminary Project Plan of Construction Works
PWP No. / Cat. Type Project
Description Agency Progress / Remarks
Est. (Actual) Start
Date
Est. (Actual)
Completion Date
N.A. – Junction
Improvement at
Chung Hom Kok
Road / Stanley
Gap Road
Transport
Department
Chung Hom Kok Road and Stanley Gap
Road junction is confined by the adjacent
slopes, with limited road space. Junction
improvement works will require substantial
slope works, transplanting a large number of
trees, and temporary closure of traffic lanes.
Transport Department advised that they have
recently carried out traffic survey in the area
and the traffic condition is considered
acceptable. If other works are to be carried
out at the above area in future, such as slope
upgrading works, or new private
development, Transport Department will
request the project proponent to carry out
the junction improvement works.
– –
9
Annex 4
District Development and Housing Committee, Southern District Council
Progress Report on Other Works in Southern District
(As at 31.8.2016)
I. Works Commenced
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)] Est. (Actual)
Start Date
Est. (Actual)
Completion Date
186WC/A Replacement and
Rehabilitation of Water
Mains Stage 3
WSD
Water mains replacement and rehabilitation works in
Southern District under Contract No. 18/WSD/08
commenced on 18 March 2009. Works currently being
carried out in Southern District include:
(a) Pok Fu Lam Road Footpath and Carriageway
[97%](Pressure test for water mains to be completed
after swimming season (Jul to Sep) in October
2016.);
(b) Repulse Bay Road Footpath and Carriageway (Water
mains replacement works completed, remaining
abandonment of the existing covers of valve
chambers to be completed after swimming season
(Jul to Sep)) [99%];
(c) Red Hill Service Reservoir [100%];
(d) Stanley Gap Road Carriageway [100%];
(e) Stanley Village Road Footpath and Carriageway
(Water mains replacement works completed,
remaining abandonment of the existing covers of
valve chambers to be completed after swimming
season (Jul to Sep)) [99%];
(f) Area in the vicinity of Pok Fu Lam Service
Reservoir [100%]; and
(g) Pok Fu Lam Village [100%].
(3.2009)
(8.2010)
(7.2011)
(10.2010)
(3.2010)
(9.2010)
(11.2011)
(11.2011)
10.2016
10.2016
10.2016
(3.2016)
(4.2016)
10.2016
(4.2016)
(3.2016)
10
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)
Start Date
Est. (Actual)
Completion Date
191WC/A Replacement and
Rehabilitation of Water
Mains Stage 4 Phase 1
WSD Contract No.12/WSD/10, which consists of construction
works in Southern District, commenced on 18 July 2011.
Works are being carried out. Works in Southern District
are as below:
(a) Consort Rise Footpath and Carriageway (in progress)
[96%][Reason: Additional mainlaying works are
required to facilitate the site condition.];
(b) Bisney Road Footpath and Carriageway (in progress)
[95%] [Reason: Additional mainlaying works are
required to facilitate the site condition. ];
(c) Area in the vicinity of Aberdeen Water Treatment
Works (in progress) [99%] [Reason: Water suspension
required for water connection works involved a large
affected area which included sensitive consumers (i.e.
Hospitals). Therefore, extra coordination work is
required with the affected premises. The pressure
logging for connection had been completed. Additional
time is required for discussion on the arrangement of
water suspension with WSD/HK&I.];
(7.2011)
(1.2012)
(1.2012)
(4.2012)
7.2017
12.2016
12.2016
11.2016
(d) Deep Water Bay Road Footpath and Carriageway (in
progress) [99%] [Reason: Water suspension required
for water connection works involved a large affected
area which included Shouson Hill Fresh Water Service
Reservoir. Therefore, extra coordination work is
required with the affected premises. The excavation
permit has been expired and the new excavation permit
is targeted to be granted in August 2016];
(e) Wah King Street Footpath and Carriageway (in
progress) [89%]
(f) Victoria Road Footpath and Carriageway (in progress)
[93%];
(11.2012)
(1.2014)
(1.2014)
11.2016
9.2016
3.2017
11
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)
Start Date
Est. (Actual)
Completion Date
(g) Repulse Bay Road Carriageway near Belleview Drive
(in progress) [25%];
(h) Aberdeen Praya Road Carriageway (in progress)
[47%];;
(i) Wong Chuk Hang Road footpath (in progress)
[98%][Reason: The water main alignment was
amended due to congested underground utilities]; and
(j) Kai Lung Wan Fresh Water Service Reservoir [23%]
(in progress)
(1.2016)
(10.2015)
(10.2015)
(1.2014)
12.2016
3.2017
10.2016
7.2017
12
Contract No.3/WSD/12, which consists of construction
works in Southern District, commenced on 15 March
2013. Works are being carried out. Works in Southern
District are as below:
(a) Pok Fu Lam Road near Pok Fu Lam Garden Footpath
and Carriageway (in progress) [95%] [Reason: The
mainlaying works are almost completed and the
pressure testing for connection works is in progress.];
and
(b) Aberdeen Praya Road near Fish Marketing
Organization at Footpath and Carriageway
(in progress) [95%] [Reason: Water suspension
required for wter connection works involved a large
affected area which included Aberdeen Fish Market.
Therefore, extra coordination work is required with the
affected premises. The mainlaying works and pressure
test have been completed. The water main connection
work will be completed in September 2016.].
(c) Tin Wan Street Footpath and Carriageway (in progress)
[50%];
(d) Tin Wan Praya Road Footpath and Carriageway
(in progress) [95%] [Reason: The progress was slightly
affected by the presence of congested underground
utilities];
(e) Victoria Road/Sha Wan Drive Footpath and
Carriageway (in progress) [35%]; and
(f) Wong Chuk Hang Road Footpath and Carriageway
(in progress) [10%].
(3.2013)
(8.2013)
(11.2015)
(1.2016)
(1.2016)
(5.2016)
(7.2016)
4.2017
10.2016
9.2016
12.2016
9.2016
12.2016
4.2017
13
341DS/A Harbour Area
Treatment Scheme,
stage 2A -
Upgrading of
Stonecutters Island
sewage treatment
works and
preliminary
treatment works
Drainage
Services
Department
The item comprises upgrading of the Stonecutters Island
Sewage Treatment Works and eight numbers of
preliminary treatment works at Hong Kong Island. The
project has been fully commissioned in December 2015.
Contract DC/2009/24 (Harbour Area Treatment Scheme
Stage 2A Upgrading of Preliminary Treatment Works
(PTWs) at Sandy Bay, Cyberport, Wah Fu, Aberdeen and
Ap Lei Chau), being part of the works of the above item,
has commenced on 31/8/2011. Since the full
commission of the project in December 2015, the treated
effluent from Sandy Bay, Cyberport, Wah Fu, Aberdeen
and Ap Lei Chau sewage treatment works has been
intercepted and conveyed to the newly expanded
Stonecutters Island Sewage Treatment Works for further
treatment. The water quality of the nearby waters is
improved, as there is no more direct discharge of treated
effluent into the areas. The works of DC/2009/24
mainly include the upgrading of the sewage treatment
and de-odourisation facilities in these PTWs. About
89% of works under the contract has been completed.
(8.2011) 12.2016
14
Progress Report on Landslip Prevention and Mitigation Works
PWP No. /
Cat.
Project Description Agency Progress / Remarks [Completion rate (%)] Est.
(Actual)
Start Date
Est. (Actual)
Completion
Date
Head 705
Subhead
5001BX/D
Landslip Prevention
and Mitigation
Programme
(LPMitP)
CEDD Landslip prevention and mitigation works for 114 man-made slopes and
5 natural hillside study areas in the Southern District are completed.
The natural hillside study areas are 11SW-C/SA3, 15NW-B/SA1,
11SW-C/SA4, 11SW-D/SA12 and 15NW-B/SA5. Landslip prevention
and mitigation works for 7 man-made slopes and 7 natural hillside study
areas are currently in progress.
(1) Slope No. 15NE-A/C96 at South Bay Road
[100%] (Works Completed)
(3.2014) (7.2016)
(2) Slope No. 15NE-A/F68 at Repulse Bay Road
[100%] (Works Completed)
(3.2014) (7.2016)
(3) Slope No. 15NW-B/C136 at Main Street, Ap Lei Chau
[100%] (Works Completed)
(11.2015) (7.2016)
(4) Slope No. 11SW-D/C2259 at Deep Water Bay Drive [30%] (4.2016) 12.2016
(5) Slope No. 15NE-C/FR154 at Behind Correctional Services
Department Staff Quarters (Front Block), Stanley [20%]
(4.2016) 4.2017
(6) Slope No. 11SW-D/C1440 at Yue Kwong Road [15%] (6.2016) 12.2016
(7) Slope No. 11SW-C/R407 at Aberdeen Praya Road [5%] (7.2016) 1.2017
(8) Slope No. 11SW-D/R1222 at Near Lamppost No. 35053, Aberdeen
Reservoir Road [5%]
(7.2016) 1.2017
(9) Slope No. 11SW-D/R1223 at Near Lamppost No. 35053, Aberdeen
Reservoir Road [5%]
(7.2016) 1.2017
(10) Slope No. 15NE-A/R244 at Repulse Bay Main Sewage Pumping
Station [5%]
(7.2016) 1.2017
(11) 2 Natural hillside study areas behind Queen Mary Hospital
(Study Area Numbers 11SW-C/SA1 and 11SW-C/SA2) [97%]
(1.2012) 9.2016
(12) 1 Natural hillside study area above Ruby Court at South Bay Road
(Study Area Number 15NE-A/SA3) [65%]
(3.2014) 12.2016*
15
PWP No. /
Cat.
Project Description Agency Progress / Remarks [Completion rate (%)] Est.
(Actual)
Start Date
Est. (Actual)
Completion
Date
(13) 1 Natural hillside study area above Pok Fu Lam Road
(Study Area Number 11SW-C/SA5) [40%]
(11.2014) 3.2017
(14) 1 Natural hillside study area at Shek Pai Wan Road, Aberdeen
(Study Area Number 11SW-C/SA5) [25%]
(9.2015) 3.2017
(15) 1 Natural hillside study area above Ap Lei Chau fronting the
Aberdeen Channel (Study Area Number 15NW-B/SA2) [25%]
(12.2015) 2.2017
(16) 1 Natural hillside study area at Ap Lei Chau
(Study Area Number 15NW-B/SA6) [15%]
(4.2016) 10.2017
* Anticipated completion date is revised as the works have been affected by inclement weather
16
Head 705
Subhead
5001BX/D
Landslip Prevention
and Mitigation
Programme (LPMitP)
CEDD In the coming year, CEDD is planning to progressively commence the
landslip prevention and mitigation works for other 8 man-made slopes
and 1 natural hillside study area.
(1) Slope No. 11SW-D/C1058 at Hong Kong Police College Lower
Range, Police School Road, Aberdeen
@ @
(2) Slope No. 11SW-C/CR874 at Victoria Road 9.2016# 2.2017
#
(3) Slope No. 15NW-B/C385 at Island Road 10.2016 7.2017
(4) Slope No. 15NE-C/C320 at Canteen Outside The Prison
Compound, Stanley Prison
3.2017 10.2017
(5) Slope No. 15NE-A/C193 at Tai Tam Road 5.2017 4.2019
(6) Slope No. 11SW-C/CR981 at Pok Fu Lam Village 9.2016 4.2017
(7) Slope No. 15NE-A/C192 at Tai Tam Road 4.2017 6.2017
(8) Slope No. 11SE-C/C237 at Repulse Bay Road 7.2017 2.2018
(9) 1 Natural hillside study area Behind Police College at Wong Chuk
Hang (Study Area Number 15NW-B/SA3)
10.2016 3.2018
# #
# Anticipated start date and completion date are revised due to reschedule of works programme
@ @ Anticipated start date and completion date will be re-scheduled due to re-programming of works
17
PWP No. /
Cat.
Project Description Agency Progress / Remarks
Head 705
Subhead
5001BX/D
Landslip Prevention
and Mitigation
Programme (LPMitP)
CEDD CEDD is carrying out stability investigation for other 19 man-made
slopes in the Southern District, which are in the early stage of the LPMit
Programme. The stability investigations of these slopes are not yet
completed. Therefore, upgrading works to these slopes may not be
required if it is later confirmed that the slopes meet the required safety
standards.
(1) Slope No. 15NE-A/C176 at Tai Tam Road
(2) Slope No. 15NE-A/C608 at Tai Tam Road
(3) Slope No. 15NE-A/C90 at South Bay Road
(4) Slope No. 15NE-A/C195 at Tai Tam Road
(5) Slope No. 15NE-A/C197 at Tai Tam Road
(6) Slope No. 11SW-D/FR651 at Wong Chuk Hang San Wai
(7) Slope No. 15NE-A/CR454 at Tai Tam Road Catchwater
(8) Slope No. 15NE-A/F45 at Tai Tam Road
(9) Slope No. 11SE-D/C406 near the junction between Shek O Road &
Cape Collinson Road
(10) Slope No. 15NE-A/FR34 at Repulse Bay Road
(11) Slope No. 15NE-A/C241 at West of Eden View, Stanley Gap Road
(12) Slope No. 15NE-A/C118 at Northeast of the junction of Repulse
Bay Road and Headland Road
(13) Slope No. 15NE-A/C240 near the junction of Stanley Gap Road and
Headland Road
(14) Slope No. 15NE-D/R8 at Ngai Choi Hang Village, Cape D’aguilar
Road
(15) Slope No. 15NW-B/C97 at Island Road
(16) Slope No. 15NE-A/C13 at Repulse Bay Road
(17) Slope No. 15NE-B/C235 at Shek O Road
(18) Slope No. 11SE-D/C104 at Shek O Road
(19) Slope No. 11SE-D/C669 at Shek O Road
18
Annex 5
District Development and Housing Committee, Southern District Council
Progress Report on Public Housing Works in Southern District
(As at 31.8.2016)
I. Works Commenced (up to the end of two financial years later)
Project Description
PWP / Estate Responsible Team Est. (Actual) Start Date Est. (Actual)
Completion Date Remarks
Lift Modernisation
for Ap Lei Chau
Estate
BSE/ECM2 May 2014 (May 2014) November 2017 The lift modernisation project for Ap Lei
Chau Estate involves four sections of works.
The works for the fifteen lifts in Section I
and Section II were completed. The works
for the ten lifts in Section III (Lei Yee House
L1; Lei Ning House L6; Lei Chak House L9,
L12 and L13; Lei Tim House L18; Lei Fook
House L19 and L23; and Lei Moon House
L25 and L29), commencing in late February
2016 in phases, will be completed in the first
quarter of 2017. The works for the last
section, following the completion of Section
III, will commence in the same of quarter of
the year. The whole project is scheduled for
completion in the fourth quarter of 2017.
19
Annex 6
District Development and Housing Committee, Southern District Council
Progress Report on FEHD District Minor Works in Southern District
(As at 31.8.2016)
Item
No.
Proposed
Minor Works Location
Estimated
Start Date
[Actual
Start Date]
Estimated
Completion
Date
[Actual
Completion
Date]
Remarks FEHD Contact
Person
ASD Contact
Person
1.
Refurbishment
of Shek O
Village Public
Toilet
Shek O
Village near
Shek O
DSD Plant
[Aug 2016] May 2017 Works in progress
Senior Health
Inspector
(Cleansing/Pest
Control) Southern,
Ms. WONG Ka-wai
【2903 0402】
Property
Services
Manager/
PM14,
Mr. WONG
Wing-lim,
William
【2773 2426】
20
Annex 7
District Development and Housing Committee, Southern District Council
Progress Report on Lands Department Temporary Government Lands Allocation in Southern District
(As at 31.8.2016)
Item
No.
TGLA No./
File Ref.
Type of
TGLA
(New/
Renewal)
Location
Proposed
Area (m2)
Proposed
User
Proposed
Term
User Dept.
(Allocatee)
Date of
Allocation
Date of
Withdrawn
Remarks
(Current Situation)
1. GLA-THK 1753
504/SHGS/82
Renewal Government
land between
No.24 and 25
Shum Wan
Road, Wong
Chuk Hang
126 Car
parking
spaces
Extend up to
11.2.2020
C of P - - Regarding the objection
from DDHC, C of P
responded that the
proposed parking was
for its operational
needs.TD had no
comment and Security
Bureau had given
approval to the
proposed extension.
Case in progress.
21
2. GLA-THK1892
L/M
988/SHMS/82 A
Renewal Tin Wan Praya
Road, Aberdeen
820 Works Area Extend up to
31.12.2017
DSD - - Departmental circulation
completed. Pending
Approval. DSD had
been requested to provide
supplementary
information before
processing the
application for renewal.
3. GLA-THK1550
413/SHGS/82
Renewal Hok Tsui Village 667 Sitting out area
and meeting
venue
Extend up to
30.6.2017
HAD,
DO(S)
- - Departmental circulation
completed. Pending
approval.
4. GLA-THK950
177/HGS/82
Renewal At Stanley Gap
Road
127 Manoeuvring
and/or Parking of
Waterworks
Vehicles to/from
Stanley Mound
Fresh Water
Pumping Station
& Extension
Extend up to
31.5.2020
WSD - - Departmental circulation
completed. Pending
approval.
22
5. GLA-THK 1875
988/SHMS/82B
Renewal Sandy Bay,
Pok Fu Lam
1,480 Works Area Extended up
to
31.12.2017
DSD - - Under departmental
circulation.
DSD applied for further
extension upto
31.12.2017. .
6. GLA-THK 1538
L/M 7/SHGS/82
(68)
Renewal Pak Sha Wan, Ap
Lei Chau
799 Works Area for
installation and
maintenance of
Shark Prevention
Nets
Extended up
to 30.6.2018
LCSD - - Under departmental
circulation.
7. GLA-THK 1922
574/SHGS/82
Renewal Ap Lei Chau Praya
Road, Ap Lei Chau
666 Works Area for
management and
maintenance of
Roads
Extended up
to 30.6.2021
HyD - - Under departmental
circulation.
23
Annex 8
District Development and Housing Committee, Southern District Council
Follow-up on the Land Use upon MTRC Handing Back the Lands Currently Used as Work Sites
(As at 31.8.2016)
Location Anticipated
Handover
Date
Approximate
Area Size
(m2)
Managing
Agent
Planned Use/Follow-up Actions
(Provided by Managing Department/Agent) Date of First Discussion
(Date of updates)
Site next to
Ocean Park
Handed over
in the end of
June 2016
6,230
LandsD
Long-term planned use of the land is to be advised by
PlanD. LandsD would facilitate any application for
use of the land in accordance with applicable
procedures.
(PlanD’s comments: The subject site falls within an
area zoned “Government, Institution or Community”
(“G/IC”) on the approved Aberdeen & Ap Lei Chau
Outline Zoning Plan No. S/H15/29 and is reserved for
provision of GIC facilities.)
26.1.2015
(15.7.2016)
24
Location Anticipated
Handover
Date
Approxim
ate Area
Size
(m2)
Managing
Agent
Planned Use/Follow-up Actions
(Provided by Managing Department/Agent) Date of First Discussion
(Date of updates)
Chung Hom
Shan Magazine
Site
Handed over 2,500 LandsD Long-term planned use of the land is to be advised by
PlanD. LandsD would facilitate any application for
use of the land in accordance with applicable
procedures.
(PlanD’s comments: The subject site falls within an
area zoned “Other Specified Uses” annotated
“Composite Signals Organization Station Complex”
on the approved Stanley Outline Zoning Plan No.
S/H19/10 intended primarily to provide land for
composite signals organization station complex and
its ancillary facilities.)
26.1.2015
(26.1.2015)
25
Chung Hom
Shan Nursery
Site next to
Magazine Site
2nd Half 2017
(To tie in with the
latest progress of
the reprovisioning
works at Harcourt
Garden, some of
the trees
temporarily
transplanted from
Harcourt Garden
at the Chung Hom
Shan Nursery Site
need to be
maintained for a
longer period. The
reprovisioning is
expected to be
substantially
completed by the
end of 2017.)
6,400 LandsD Long-term planned use of the land is to be advised by
PlanD. LandsD would facilitate any application for
use of the land in accordance with applicable
procedures.
(PlanD’s comments: The subject site falls within an
area zoned “Other Specified Uses” annotated
“Composite Signals Organization Station Complex”
on the approved Stanley Outline Zoning Plan No.
S/H19/10 intended primarily to provide land for
composite signals organization station complex and
its ancillary facilities.)
26.1.2015
(10.9.2015)