LAMPIRAN 2 PENAWARAN
ANALISA HARGA SATUAN MATA PEMBAYARAN
Project : ACEH RECONSTRUCTION PROJECT, ROAD SUB - PROJECT (JICA LOAN IP - 545)
Contract Package : No. 3 (Three)Contract Package : No. 3 (Three)
Package Name : KABAYAKAN - SP. KRAFT (STA. 3 + 850 - STA. 56 + 032)
Location : KABUPATEN ACEH TENGAHLocation : KABUPATEN ACEH TENGAH
Pay Item Number :7.15.2
Type Of Work :Demolition of ConcreteType Of Work :Demolition of Concrete
Payment unit :M3
PERKIRAAN HARGA JUMLAHPERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
HARGA
(Rp.) (Rp.)
A. TENAGA
1. Pekerja (L01) Jam 0.8032 7,150.00 5,742.881. Pekerja (L01) Jam 0.8032 7,150.00 5,742.88
2. Mandor (L03) Jam 0.2008 11,500.00 2,309.20
8,052.08JUMLAH HARGA TENAGA 8,052.08
B. BAHAN
JUMLAH HARGA TENAGA
B. BAHAN
0.00JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA BAHAN
1 Compressor Jam 0.2008 151,777.15 30,476.85
2 Jack Hammer Jam 0.2008 78,034.98 15,669.42
3 Wheel Loader Jam 0.0432 367,291.96 15,867.013 Wheel Loader Jam 0.0432 367,291.96 15,867.01
4 Dump Truck Jam 0.2370 241,830.76 57,313.89
5 Alat Bantu Ls 1.0000 1,000.00 1,000.005 Alat Bantu Ls 1.0000 1,000.00 1,000.00
120,327.18JUMLAH HARGA PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN( A + B + C ) 128,379.26
E. OVERHEAD & PROVIT = 5.0 % x D 6,418.96
F. HARGA SATUAN PEKERJAAN = ( D + E ) 134,798.22F. HARGA SATUAN PEKERJAAN = ( D + E ) 134,798.22
Note : 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuranNote : 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang
dibayar dari kontrak) dan biaya-biaya lainnya.dibayar dari kontrak) dan biaya-biaya lainnya.
Banda Aceh, 20 Juni 2012
PT. Perapen Prima Mandiri
Ir. MawardiIr. Mawardi
Direktur Utama
-
Type Of Work :Demolition of Concrete Analisa EI-3151
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work :Demolition of Concrete Analisa EI-3151
Payment unit :M3
Pay Item Number :7.15.2 URAIAN ANALISA HARGA SATUANPay Item Number :7.15.2 URAIAN ANALISA HARGA SATUAN
No. U R A I A N KODE KOEF. SATUAN KETERANGAN
I. ASUMSII. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.24 -5 Faktor pengembangan bahan Fk 1.24 -
6 Berat volume beton lepas D1 2.40 Ton/M3
II. URUTAN KERJA
1 Bidang yang akan dibongkar ditandai dengan cat/kapur1 Bidang yang akan dibongkar ditandai dengan cat/kapur
2 Penggalian dilakukan dengan Jack Hammer dan Compressor,
Hasil Bongkaran dimuat ke dalam Truk dengan Menggunakan Wheel Loader.Hasil Bongkaran dimuat ke dalam Truk dengan Menggunakan Wheel Loader.
3 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh : L 5.00 Kmlokasi jalan sejauh : L 5.00 Km
III. PEMAKAIAN BAHAN, ALAT DAN TENAGAIII. PEMAKAIAN BAHAN, ALAT DAN TENAGA
1. BAHAN
Tidak ada bahan yang diperlukanTidak ada bahan yang diperlukan
2. ALAT 2. ALAT
2.a. COMPRESSOR, JACK HAMMER ( E26)
Kapasitas bongkar bk 10.00 Menit/M3 (padat)Kapasitas bongkar bk 10.00 Menit/M3 (padat)
Faktor efesiensi Fa 0.83
Kapasitas prod/jam = Fa x 60 Q1 4.980 M3Kapasitas prod/jam = Fa x 60 Q1 4.980 M3
bk
Koefesien alat/M3 = 1 : Q1 0.2008 jamKoefesien alat/M3 = 1 : Q1 0.2008 jam
2.b. WHEEL LOADER (E15)
Kapasitas bucket V1 1.50 M3
Faktor bucket Fb 0.85
Faktor efesiensi alat Fa1 0.75Faktor efesiensi alat Fa1 0.75
Waktu muat.siklus Ts1 2.00 Menit
Kapasitas prod/jam = V1 x Fb x Fa1 x 60 Q2 23.14 M3 (padat)Kapasitas prod/jam = V1 x Fb x Fa1 x 60 Q2 23.14 M3 (padat)
Fk x Ts1
Koefesien alat/M3 = 1 : Q3 0.0432 jamKoefesien alat/M3 = 1 : Q3 0.0432 jam
2.c. DUMP TRUCK (E08) 2.c. DUMP TRUCK (E08)
Kapasitas bak V 5.33 M3
Faktor efisiensi alat Fa 0.83 -Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts2 menitWaktu siklus Ts2 menit
- Muat = V : D1 : (V1 x Fb x Fa1) x Ts1 T1 4.65 menit
- Waktu tempuh isi = (L : v1) x 60 T2 7.50 menit- Waktu tempuh isi = (L : v1) x 60 T2 7.50 menit
- Waktu tempuh kosong = (L : v2) x 60 T3 5.00 menit
- Lain-lain T4 4.00 menit- Lain-lain T4 4.00 menit
Ts2 21.15 menit
Kapasitas Produksi / Jam = V x Fa x 60 Q3 4.22 M3 padatKapasitas Produksi / Jam = V x Fa x 60 Q3 4.22 M3 padat
D1 x Fk x Ts2
Koefisien Alat / m3 = 1 : Q3 (E08) 0.2370 Jam
Berlanjut ke halaman berikutBerlanjut ke halaman berikut
-
Type Of Work :Demolition of Concrete Analisa EI-3151
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work :Demolition of Concrete Analisa EI-3151
Payment unit :M3
Pay Item Number :7.15.2 URAIAN ANALISA HARGA SATUANPay Item Number :7.15.2
Lanjutan
URAIAN ANALISA HARGA SATUAN
No. U R A I A N KODE KOEF. SATUAN KETERANGAN
2.d. ALAT BANTU2.d. ALAT BANTU
Diperlukan alat-alat bantu kecil Lump Sump
- Pahat / Tatah = 2 buah- Pahat / Tatah = 2 buah
- Palu Besar = 2 buah
3. TENAGA 3. TENAGA
Produksi menentukan : JACK HAMMER Q1 4.98 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 34.86 M3Produksi Galian / hari = Tk x Q1 Qt 34.86 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.8032 Jam- Pekerja = (Tk x P) : Qt (L01) 0.8032 Jam
- Mandor = (Tk x M) : Qt (L03) 0.2008 Jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
5. ANALISA HARGA SATUAN PEKERJAAN
Lihat perhitungan dalam FORMULIR STANDAR UNTUKLihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.SATUAN.
Didapat Harga Satuan Pekerjaan :
Rp. 134,798.22 / M3
6. WAKTU PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan : 2.00 HariMasa Pelaksanaan : 2.00 Hari
7. VOLUME PEKERJAAN YANG DIPERLUKAN7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume pekerjaan : 36.00 M3
-
LAMPIRAN 2 PENAWARAN
ANALISA HARGA SATUAN MATA PEMBAYARAN
Project : ACEH RECONSTRUCTION PROJECT, ROAD SUB - PROJECT (JICA LOAN IP - 545)
Contract Package : No. 3 (Three)Contract Package : No. 3 (Three)
Package Name : KABAYAKAN - SP. KRAFT (STA. 3 + 850 - STA. 56 + 032)
Location : KABUPATEN ACEH TENGAHLocation : KABUPATEN ACEH TENGAH
Pay Item Number :7.15.1
Type Of Work :Demolition of Stone MasonryType Of Work :Demolition of Stone Masonry
Payment unit :M3
PERKIRAAN HARGA JUMLAHPERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
HARGA
(Rp.) (Rp.)
A. TENAGA
1. Pekerja (L01) Jam 0.6024 7,150.00 4,307.161. Pekerja (L01) Jam 0.6024 7,150.00 4,307.16
2. Mandor (L03) Jam 0.2008 9,500.00 1,907.60
6,214.76JUMLAH HARGA TENAGA 6,214.76
B. BAHAN
JUMLAH HARGA TENAGA
B. BAHAN
0.00JUMLAH HARGA BAHAN 0.00
C. PERALATAN
JUMLAH HARGA BAHAN
1 Compressor Jam 0.2008 151,777.15 30,476.85
2 Jack Hammer Jam 0.2008 78,034.98 15,669.42
3 Wheel Loader Jam 0.0432 367,291.96 15,867.013 Wheel Loader Jam 0.0432 367,291.96 15,867.01
4 Dump Truck Jam 0.2067 241,830.76 49,986.42
5 Alat Bantu Ls 1.0000 500.00 500.005 Alat Bantu Ls 1.0000 500.00 500.00
112,499.71JUMLAH HARGA PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN( A + B + C ) 118,714.47
E. OVERHEAD & PROVIT = 5.0 % x D 5,935.72
F. HARGA SATUAN PEKERJAAN = ( D + E ) 124,650.19F. HARGA SATUAN PEKERJAAN = ( D + E ) 124,650.19
Note : 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuranNote : 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang
dibayar dari kontrak) dan biaya-biaya lainnya.dibayar dari kontrak) dan biaya-biaya lainnya.
Banda Aceh, 20 Juni 2012
PT. Perapen Prima Mandiri
Ir. MawardiIr. Mawardi
Direktur Utama
-
Type Of Work :Demolition of Stone Masonry Analisa EI-3151
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work :Demolition of Stone Masonry Analisa EI-3151
Payment unit :M3
Pay Item Number :7.15.1 URAIAN ANALISA HARGA SATUANPay Item Number :7.15.1 URAIAN ANALISA HARGA SATUAN
No. U R A I A N KODE KOEF. SATUAN KETERANGAN
I. ASUMSII. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.24 -5 Faktor pengembangan bahan Fk 1.24 -
6 Berat volume beton lepas D1 2.40 Ton/M3
II. URUTAN KERJA
1 Bidang yang akan dibongkar ditandai dengan cat/kapur1 Bidang yang akan dibongkar ditandai dengan cat/kapur
2 Penggalian dilakukan dengan compressor dan Jack Hammer, Hasil
Bongkaran dimuat ke dalam Truk dengan Menggunakan Wheel Loader.Bongkaran dimuat ke dalam Truk dengan Menggunakan Wheel Loader.
3 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh : L 5.00 Kmlokasi jalan sejauh : L 5.00 Km
III. PEMAKAIAN BAHAN, ALAT DAN TENAGAIII. PEMAKAIAN BAHAN, ALAT DAN TENAGA
1. BAHAN
Tidak ada bahan yang diperlukanTidak ada bahan yang diperlukan
2. ALAT 2. ALAT
2.a. COMPRESSOR, JACK HAMMER ( E26)
Kapasitas bongkar bk 10.00 Menit/M3 (padat)Kapasitas bongkar bk 10.00 Menit/M3 (padat)
Faktor efesiensi Fa 0.83
Kapasitas prod/jam = Fa x 60 Q1 4.980 M3Kapasitas prod/jam = Fa x 60 Q1 4.980 M3
bk
Koefesien alat/M3 = 1 : Q1 0.2008 jamKoefesien alat/M3 = 1 : Q1 0.2008 jam
2.b. WHEEL LOADER (E15)
Kapasitas bucket V1 1.50 M3
Faktor bucket Fb 0.85
Faktor efesiensi alat Fa1 0.75Faktor efesiensi alat Fa1 0.75
Waktu muat.siklus Ts1 2.00 Menit
Kapasitas prod/jam = V1 x Fb x Fa1 x 60 Q2 23.14 M3 (padat)Kapasitas prod/jam = V1 x Fb x Fa1 x 60 Q2 23.14 M3 (padat)
Fk x Ts1
Koefesien alat/M3 = 1 : Q3 0.0432 jamKoefesien alat/M3 = 1 : Q3 0.0432 jam
2.c. DUMP TRUCK (E08) 2.c. DUMP TRUCK (E08)
Kapasitas bak V 6.67 M3
Faktor efisiensi alat Fa 0.83 -Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts2 menitWaktu siklus Ts2 menit
- Muat = V : D1 : (V1 x Fb x Fa1) x Ts1 T1 5.81 menit
- Waktu tempuh isi = (L : v1) x 60 T2 7.50 menit- Waktu tempuh isi = (L : v1) x 60 T2 7.50 menit
- Waktu tempuh kosong = (L : v2) x 60 T3 5.00 menit
- Lain-lain T4 4.75 menit- Lain-lain T4 4.75 menit
Ts2 23.06 menit
Kapasitas Produksi / Jam = V x Fa x 60 Q3 4.84 M3 padatKapasitas Produksi / Jam = V x Fa x 60 Q3 4.84 M3 padat
D1 x Fk x Ts2
Koefisien Alat / m3 = 1 : Q3 (E08) 0.2067 Jam
Berlanjut ke halaman berikutBerlanjut ke halaman berikut
-
Type Of Work :Demolition of Stone Masonry Analisa EI-3151
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work :Demolition of Stone Masonry Analisa EI-3151
Payment unit :M3
Pay Item Number :7.15.1 URAIAN ANALISA HARGA SATUANPay Item Number :7.15.1
Lanjutan
URAIAN ANALISA HARGA SATUAN
No. U R A I A N KODE KOEF. SATUAN KETERANGAN
2.d. ALAT BANTU2.d. ALAT BANTU
Diperlukan alat-alat bantu kecil 1.0000 Ls Lump Sump
- Pahat / Tatah = 2 buah- Pahat / Tatah = 2 buah
- Palu Besar = 2 buah
3. TENAGA 3. TENAGA
Produksi menentukan : COMPRESSOR DAN JACK HAMMER Q1 4.98 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 34.86 M3Produksi Galian / hari = Tk x Q1 Qt 34.86 M3
Kebutuhan tenaga :
- Pekerja P 3.00 orang- Pekerja P 3.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.6024 Jam- Pekerja = (Tk x P) : Qt (L01) 0.6024 Jam
- Mandor = (Tk x M) : Qt (L03) 0.2008 Jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
5. ANALISA HARGA SATUAN PEKERJAAN
Lihat perhitungan dalam FORMULIR STANDAR UNTUKLihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.SATUAN.
Didapat Harga Satuan Pekerjaan :
Rp. 124,650.19 / M3
6. WAKTU PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan : 3.00 HariMasa Pelaksanaan : 3.00 Hari
7. VOLUME PEKERJAAN YANG DIPERLUKAN7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume pekerjaan : 78.00 M3