dmn trcp expense report as of march 31, 2014 dated april 28, 2014
TRANSCRIPT
Page 1
Trinity River Corridor Project 28-Apr-14Expenditure Report Based Primarily on March 31, 2014 Fund/Unit Summary
Project Components
Expended / Encumbered (as of
March 31, 2014)
Remaining / Planned
Expenditures Comments
1998 Bond ProgramTrinity Parkway $41,729,522 $35,508,433 Includes funding reserved for potential future Council
Actions including $100K for Geotech Re-evaluation, $18.3M for Parkway "borrow area" construction, $2.0M for ramp to Trinity Park from Houston/Jefferson Bridge, $2.0M for ramp to Trinity Park from Sylvan Avenue Bridge, $3.9M for Parkway Wetlands Mitigation, and $9.2M for NTTA ILA or to facilitate additional Parkway "borrow area" construction.
Margaret Hunt Hill Bridge (Woodall Rodgers) 36,007,330 $25,754 Includes $25,754 in remaining funds for Margaret Hunt Hill (Woodall Rodgers) Signature Bridge to be used for park benches and picnic area beneath the bridge.
Lakes 19,558,124 $11,782,626 Includes funding reserved for potential future Council Actions including $9.8M for Parkway "borrow area" construction and $2.0M for Trinity Standing Wave.
Great Trinity Forest/Park $40,200,238 $1,260,162 Includes funding reserved for potential future Council Actions including $1.2M for completion of Loop 12 and MLK Gateways.
Dallas Floodway Extension 24,658,084 $8,166 Includes funding reserved for potential future Council Actions including contingency funding for Upper Chain of Wetlands Remediation.
Elm Fork 17,767,472 $12,232,528 Includes funding reserved for potential future Council Actions including $12.2M for Elm Fork Drainage project.
Beckley Avenue Improvements 4,691,270 $1,276,255 Includes funding reserved for potential future Council Actions including $1.3M contingency funding for completion of Beckley Avenue Improvements.
TRCP Comprehensive Land Use Plan 1,090,188 $0 Funded with Trinity Proposition bond interest earnings.
East Levee Transmission Line Relocation 2,400,000 $777,818 Funded with Trinity Proposition bond interest earnings. Planned expenditures for additional costs related to relocation of East Levee Norwood Transmission Line.
West Levee Norwood Transmission Line 1,084,421 $0 Funded with Trinity Proposition bond interest earnings.
Implementation Costs FY 1999-2014 18,665,203 $535,971 Funded with Trinity Proposition bond interest earnings. Includes reimbursement to General Fund for Trinity River Corridor Project implementation costs.
Total 1998 Bond Program $207,851,852 $63,407,713
Page 2
Trinity River Corridor Project 28-Apr-14Expenditure Report Based Primarily on March 31, 2014 Fund/Unit Summary
Project Components
Expended / Encumbered (as
of March 31, 2014)
Remaining / Planned
Expenditures Comments
2006 Bond ProgramContinental - Industrial/Riverfront to IH 35E $5,240,312 $875,111 Project under construction. Estimated completion April
2016.
Industrial/Riverfront Improvements $2,329,038 $1,529,413 Project under construction. Estimated completion December 2016.
Sylvan Bridge from Irving to Gallagher - Amenities
$9,004,419 $537,382 Project under construction. Estimated completion August 2014.
Pressure Sewers $642,240 $0
Hampton-Oak Lawn Improvements (Baker Pump Station)
$57,513,993 $2,091,591 Project under construction. Estimated completion March 2015.
Pavaho Sump Improvements $38,098,944 $312,777
Sump A Improvements $9,457,677 $701,248 A portion of the 2006 Bond Funds were reprogrammed to fund necessary levee improvements.
Levee Improvements $40,331,431 $4,736 2006 Bond Funds were reprogrammed to fund necessary levee improvements.
Dallas Floodway Levee Land Acquisition $337,286 $211,914 Property acquisition for Dallas Floodway.
Audubon Center Land (Loop 12 Land Acquisition)
$3,200,000 $0 Project completed July 2008
Texas Horse Park $13,528,370 $144,186 Construction contract awarded May 22, 2013. Estimated completion September 30, 2014.
Joppa Gateway $252,276 $1,157,220 Land acquisition in process; Design awarded Dec 2011; Estimated completion March 31, 2015
Standing Wave $3,595,042 $132,108 PKR is working with consultant and Corps of Engineers to resolve bypass channel concerns
Belleview Trail Connector $186,719 $0 Funding reprogrammed to Trinity Standing Wave.
Reunion Gateway Land $12,391 $0 Funding reprogrammed to Trinity Standing Wave.
Continental Pedestrian Modifications $1,906,000 $0 Estimated completion May 31, 2014
West Dallas Gateway Park $1,709,914 $86 Estimated completion May 31, 2014
Trinity Strand (Old Trinity Trail Phase II) $602,198 $0 Estimated completion August 31, 2014
Elm Fork Trail $191,586 $0 2006 Bond Funds were reprogrammed to the Elm Fork Soccer Complex
Elm Fork Soccer Complex $14,335,716 $167 Project complete; submitted final retainage release on 4/22/14.
Total 2006 Bond Program $202,475,552 $7,697,939 Project list includes projects with some connection to the Trinity River Corridor Project.