document no. qtr-72-1039 revision release date … · 2013-08-31 · document no. qtr-72-1039...
TRANSCRIPT
Document No. QTR-72-1039RevisionRelease Date r '
NASA CR-
QUALIFICATION TEST REPORT
BUMP PROTECTION HAT
(SUBASSEMBLY OF
TO20/M509 HEAD PROTECTIVE ASSEMBLY)
CONTRACT NAS 9-11905
TYPE II DOCUMENT
DRL T-706, LINE ITEM 61
(NASA-CE-140347) QUALIFICATION TEST N75-12618EEPORT BUMP PROTECTION HAT (SUBASSEMBLYOF T020/M509 BEAD PROTECTIVE ASSEMBLY)(General Electric Co.) 39 p HC $3.75 Unclas
CSCL 06- G3/54 04254
PREPARED BY: I, C>D. B. Willis - " .Product Engineer
APPROVED BY: _ _/_ _
G. E. WoodProject Manager
. ..- / ': C ,
GENERAL ELECTRICAPOLLO AND GROUND SYSTEMS
HOUSTON PROGRAMSHouston, Texas
https://ntrs.nasa.gov/search.jsp?R=19750004546 2020-03-17T03:07:12+00:00Z
ABSTRACT
The BPH (Bump Protection Hat), P/N 793-102, S/N 1001, was subjected to impacttesting in accordance with QTP-72-1037, Qualification Test Procedure, andGE-TPS-C-010. The BPH underwent three impacts at 35 foot-pounds of energy.The impacts generated stress cracks, but no penetration. All impacts resultedin deflections of less than one-half inch.
The BPH successfully passed the testing and is considered to be qualified forSkylab and the Rescue Vehicle.
Document No. QTR-72-1039Revision
Release Date 0 5 7
TABLE OF CONTENTS
Paragraph Title Page
1.0 INTRODUCTION . .............. .... . . . . . .
2.0 TEST APPARATUS . ................. . . . . .
3.0 PROCEDURE ............. .... .... 1
4.0 RESULTS . . . . ... . . . . . . . . . . . . . . . . . . . 1
5.0 CONCLUSIONS ............... ... ....... 2
APPENDIX A
APPENDIX B
APPENDIX C
Document No. QTR-72-1039RevisionRelease Date rPage 1 of 2
1.0 INTRODUCTION
In accordance with QTP-72-1026, Qualification Test Plan for SkylabT020/M509 Head Protective -Assembly, the only test required to qualifythe assembly is to perform impact testing on the BPH (Bump ProtectionHat). This report documents the performance of the required impacttest.
Testing was performed in accordance with QTP-72-1037, Impact TestQualification Test Procedure for the BPH (see Appendix A). Testingwas performed on GE-TPS-C-010 (Appendix B). One deviation was madeto the-test procedure. Figure 3 of the test procedure called for impactsto be performed on one side, the front, and the back of the helmet.The actual impacts were performed on one side, the front, and the topof the helmet. The top was impacted instead of the back for tworeasons: (1) It was felt that a top impact would be more realisticthan a back impact. (2) The test facility would have to be modifiedto perform a back impact.
Testing was performed on the side and top of the helmet on October 30,1972. The pendulum then had to be modified in order to perform thefront impact. Front impact was performed November 16, 1972.
2.0 TEST APPARATUS
The test equipment is shown in Figures 1 and 2 of the test procedure(Appendix A). Photographs number 1, 4, and 8 of Appendix C show thetest setup for the three impacts performed. The stop watch used duringtesting was not calibrated, as indicated on the Test Summary Sheet(Attachment A of QTP-72-1037).
3.0 PROCEDURE
Test procedures were according to QTP-72-1037 (Appendix A) and GE-TPS-C-010(Appendix B).
4.0 RESULTS
All three impacts caused stress cracks on the outside of the BPH. Theside impact also caused stress cracks on the inside of the BPH. Therewere no stress cracks on the inside of the BPH for the top and frontimpacts. Analysis of the side impact cracks showed that the outsidestress cracks were not the sane as the inside cracks, hence, there wasno penetration of the helmet. All cracks were acceptable according tothe pass-fail criteria of QTP-72-1026.
Document No. QTR-72-1039RevisionRelease Date tpr 1 1q77Page 2 of 2
4.0 RESULTS (Continued)
Analysis of the high-speed film for shell deflection showed thefollowing results for the three impacts:
a. Side Impact - Less than 3/8" deflection, though the exact amountcould not be determined.
b. Top Impact - Approximately 3/8" deflection.
c. Front Impact - Less than " deflection, though the exact amountcould not be determined because the impact was a glancing blow.
Maximum allowable deflection was 2'. All three deflections were withinthe allowable amount.
One DR was generated at post-test on the stress cracks (Appendix B).No FIAR's were generated. The DR is closed.
5.0 CONCLUSIONS
All three impacts successfully passed the test from the standpoint ofboth cracks and deflection.
It was agreed by the Test Conductor, Technical Monitor, and NASA QualityControl that the stop watch not being calibrated was no problem.Stop watches are normally not calibrated for such .tests. . Human reflexerror is a much more significant factor in timing the period ofoscillation.
The top of the helmet being impacted instead of the back is consideredvalid. for the following reasons:
1. A top impact is mudh more likely than a back impact.
2. It was originally not required to impact the top. It was agreedby the test parties that a top impact is desirable.
3. The back area of the helmet is similar to the front area, which wasimpacted.
4. Side impact is the most severe since there is no liner in theimpacted area to absorb part of the energy.
The BPH successfully completed qualification testing .for Skylab andRescue Vehicle.
APPENDIX A
TEST PROCEDURETEST SUMMARY SHEET
TEST DATA SHEETS
Document NJ. QTP-72-1037RevisionRelease Date ' [T 19 "M
IMPACT TEST
QUALIFICATION TEST PROCEDURE
LF'OR SKYIAB
BUMP PROTECTION HAT
P/N 793-102
CONTRACT NAS 9-11905 -
Type I. Document
DRL T-706, Line Item 63
PREPARED BY: A. 4" d APPROVED: /D. B. Willis Tec icaYonitorProduct Engineer
APPROVED: /e ,&APPROVED: / 1 4-. rBnch Chi e f
E. WoodProject Manager
APPROVED: ///
Chief ew "ystems Division
APPROVED: "tJ ; --/Qua ty Enginee ing
GENERAL ELECTRICAPOLLO & GROUND SYSTEMS
HOUSTON PROGRAMSHouston, Texas
Page i of ii
DOCUMENT CHANGE/REVISION 'LOG Dote
Chg Change Pages CEI S/NNo Authority Affected Change Description
- ii
Document No. QTP-72-1037Revision
Date nrT 1 177Page ii of ia
'TABLE OF' CONrENTS
Paragraph Title Page
1.0 INTRODUCTION . . . . . . . ............... . 2
2.0 PURPOSE . ....... .. . . . . ....... . . . 2
3.0 APPLICATION .............. ......... 2
4.0 REQUIREMENTS AND TEST PREPARATIONS ....... . ..... . 2
4.1 TEST EQUIPMENT AND FACILITY REQIJIRHE=NTS ... . ...... 2
4.2 TEST EQUIPMENT VALIDATION . ... ............ . 3
4.3 SAFETY PRECAUTIONS AND SPECIAL HANDLING .. ........ 3
4.4 TEST SETU ..P ....... ...... ..... . . . . . . . . . 3
4.5 TEST SETUP VALIDATION . ................. . 3
5.0 TEST PROCEDURE ... ......... . . . . .... 3
'REPRODbc .
ORIGLIN Ai iS 004 Document No. QTP-72-1037Revision
Date __
Page 2 of
1.0 INTRODUCTION PRECEDING PAGE BLANK NOT FILMED
This document details the procedure for subjecting the BPH (BumpProtection Hat) to impact testing according to QTP-72-1026, Qualifi-cation Test Plan for Skylab T020/M509 Head Protective Assembly.
2.0 PURPOSE
The purpose of the test is to determine the shock absorbing character-istics of the BPH when impacted with a fixed hemispherically shapedanvil. The impact shall be at 12 ft./sec. with a mass of 0.48 slugs,according to QTP-72-1026, or an equivalent energy of 35 foot pounds.High speed photography shall be used to determine the shell deflectionduring impact.
3.0 APPLICATION
Any discrepancies, difficulties, replacement of components,.deviationsfrom procedures, etc., experienced during the test shall be documentedon the Test Summary Sheet (Attachment A). The Test Conductor and theMSC Inspector shall sign the Test Summary Sheet. Any DR's or FIAR'sgenerated shall be written in accordance with paragraph 5.6.2 ofQTP-72-1026. Deviations from procedure shall be indicated on the TestData Sheet (Attachment B).
4.0 REQUIREMENTS AND TEST PREPARATIONS
4.1 TEST EQUIPMENT AND FACILITY REQUIREMENTS
The test will be conducted by the special projects laboratory of theCrew Systems Division's Material Development Section. The testapparatus shall be a pendulum and wooden .mannequin head assembly asshown in photograph 1.
The test article shall be one Bump Protection Hat, P/N 793-102,S/N 1001.
Support equipment shall include the following:
Item Part No. Specification
Communications Carrier 16536G-03 or -01 Class III
Camera -- 400 frames/sec.
Stop Watch -- Calibrated
Grid -- , squares or less
Document No. QTP-72-1037RevisionDate UI 9 1 .,Page 3 of.
4.2 TEST.EQUIPMENT VALIDATION
Prior to start of the test, a receiving inspection shall be performedon the BPH to assure no damage. The camera and stop watch shall beverified to be calibrated and functioning properly.
4.3 SAFETY PRECAUTIONS AND SPECIAL HARD)LINGC
There are no special safety precautions involved in this test. Cautionshould be exercised while handling the BPH, camera, and stop watch toprevent damage to the hardware.
4.4 TEST SETUP
The test equipment shall be set up as shown in Figures I and 2. TheCommunications Carrier shall be placed on the mannequin head and theBPH strapped over the Communications Carrier.
NOTE: Adjust the BPH suspension system to the mannequin head size.
4.5 TEST SETUP VALIDATION
The MSC Inspector shall verify proper test setup and stamp the TestData Sheet accordingly, prior to commencing test.
5.0 TEST PROCEDURE
5.1 Prepare pendulum and wooden head assembly per Figures 1 and 2.
5.2 Suspend the impact head with the BPH and Communications Carrier mountedas a pendulum, and determine the period of oscillation. Determineperiod by swinging the pendulum through an arc of < 60 and timing theperiod through 10 oscillations, using the stop watch to time.
5.3 Calculate the center of pe cussion of the impact assembly by thefollowing formula: L = gt /(2,r) 2 where L is the length from thepivot point to center of' percussion, g is acceleration due to gravity,and t is the period of oscillation of the pendulum. (See Figure 1.)
Document No. QTP-72-1037RevisionDate FT 1 197Page of 8
5.4 Weigh and record weight of the impact assembly with the BPH andCommunications Carrier mounted on the head.
Weight
5.5 Calculate 'the releas e angle required for a 35 foot-pound impact bythe following formulas:
a. E mgh where m is the mass of the impact assembly, g is theacceleration due to gravity, and h-is the vertical height when thecenter of percussion is raised.
b. -- = cos - (L-h) where ,L and h are defined in 5.3 and 5.5 respectively.
5.6 Orient the impact assembly such that region I of Figure 3 will be impacted.
5.7 Pull impact assembly back to the desired release angle as calculatedin step 5.5.
5.8 Begin countdown of 5-4-3-2-1 - Release. Turn camera on at count of; 2.
5.9 Impact helmet. Do not let helmet strike the anvil more than once.Stop camera.
5.10 Orient the impact assembly such that region 2 of Figure 3 will beimpacted.
5.11 Repeat steps 5.7 through 5.9.
5.12 Orient the imrnpact asserRmbly :;mch that reg:ion 3 of Figure 3 will beimpacted.
5.13 Repeat. steps 5.7 through 5.9.
5.14 Remove the BPH and inspect for damage. Pass-fail criteria for the BPHis defined in paragraph 6.3.2.2.3 of QTP-72-1026.
Document No. QTP-7P-J-O37RevisionDate CT 1 1J07Page 5 f
Oo-M
&&
4 -4
PHOTO # 1 - PENDLI~M ASSY
PIVOT POINT
LPENDULUM HEAD
WOODEN HEAD
IMPACT ANVIL2" Dia. Surface -t
HO CD0
FIG. /
FIG. 1 / 1 //// / ~/
BPHAdd weights if necessary to bringimpact assembly to a total of 15 25 -lbs., including BPH and Comm. Carrier
weight.
GRID
CAMERA
IIMPACT ANVIL
0 ,C
FIG. 2
-2tiC) ~s
CI
Document No. QTP-72-1037RevisionDate 1Page 8 of 8
Region 1 may beon either side.
SIDE VIEW
Region 3 is the sameas region 2, exceptthat it shall be onthe back side.
FRONT VIEW
Figure 3
Document No. QTP-72-1037
Attachment A
TEST SUMMARY SHEET
FOR
IMPACT TEST OF BUMP PROTECTION HAT
I. Test Hardware P/N 79 3- / Z
Test Hardware S/N / /
Date Test Performed /0/: :/7 L
2. Indicate Test Procedure deviations below:
qt i
3. Indicate DR's generated during test below:
4. Indicate FIAR's generated during test below:
5. Additional test data information:
o n q-oo
6. With the exceptions noted above, the test was successfully performedaccording to the procedures of QTP-72-1037, Impact Test QualificationTest Procedure for Skylab Bump Protection Hat.
st Conductor MSC Quali Inspector
Cdiin a tifac od. Ha
5.6 PH oriented for re 793on 1.
5.9 BPTs impacted for region 1.
5.10 BPH oriented for region
PARA5.11 BPH impacted for region 2l
42RcinInpc TECH INS p NASA
5.12 BPH oriented for region er3.formed n
Co5.13 PH dit ion satisfactoryn 3.
5.1 BPH inspected for P/N dam
5 generated at Post-Tesg hre. eo any DR's
Record any F lARis generated at Post-Pest hes
501M ASD4ij rn
EST DATA SHEET Attachment BTL SMD 7813 UOUNCLAI aI 1
Qual Test Procedure Bump Protection Hat 416PARV no no
793-102OCUMIW tlu ui l Irn ALWQQTTP-72-1037 1001 Pa1 of 1 Pages
PROCEDURE TECH IJNSP NASA
4.2 Receiving Inspection performed on BPH.Condition satisfactory.
BPH P/N 7?-- /BPH S/N fr,
4.2 Support equipment calibrated and functioningproperly.
4.5 Test setup verified proper.
5.2 Period of oscillation determined. Period isl2 "seconds.
5.3 Center of percussion determined. L isS _, 95 _ ft.
5.4 Weight of impact assembly is /5y,~2 lbs.,including BPH, Communication Carrier.
5.5 Release Angle = - degrees.
5.6 BPH oriented for region 1.
5.9 BPH impacted for region l.
5.10 BPH oriented for region 2.
5.11 BPH impacted for region 2.
5.12 BPH oriented for region 3.(R ~e4 2 of
5.13 BPH impacted region 3. 3 '
5.14 BPH inspected for damage. Record any DR'sgenerated at Post-Test here.
Record any FIAR's generated at Post-Test here.
eFsm ASOID 21
APPENDIX B
TPS' SDR'S
1,. A ConfigurationT Change 2. TPS No. -
B Non-Configuration T PREPARATION SHEET 3. S/C ca. o
4. Mod. Sheet Nu er-- NAS - MANNED SPACECRAFT CENTER
5. Page..L__ of6 S/C No /Model No. .7 Date 8. Time 9. Need Date
10. Drawings, Documents, Ocp's, & Part Numbers) 11. Confract Number
__ T --7 - _L 37 2' 3- - -__12. Serial Number
__ '4 6-- O Se TPS13. System 14. Ref. E. O. Number
15. TPS Short Title 16. Wt. Req.
17. Reason for Work: T f -J4 " " i ,- -- " -h, t -
18. DESCRIPTION (Print or Type) 21. Insp.Tech. 22. T
2c/IASA--6C-1 s/bA /o, v _o __
Ar i-'i- -..---- '..
i1~-1 L i3 , e, _ / ,-
c \4, j aj+ " •- a - K±C4LLSf ,. , ,_19. Prepared By 20. Final Acceptnc
~ REFER TO PROCEDURES FOR REQUIRED SIGNATURES REFER TO PROCEDURES FOR REQUIRED SIGNATURESContracDart e________ Date
MSC FORM 725 (JUL 65)NASA OC-m I.,: Hlv COPT I
TEST PREPARATION SHEET TPS No. 6 Tr-S/C Cat. No.
CONTINUATION SHEETNASA - MANNED SPACECRAFT CENTER
Page of
Insp.DESCRIPTION (Print or Type) Tech.Cont. NASA
_ _i w i a e i f
S_ VI P-
o__ C•ya ! •. I
- / d/ V '1 C7 - _,
s _ . ,Zz esiu'; .
M ,k -OM V5 (JLcILs-ieu S651 CPA . 4 .,C
___ 1 4-, 16U-_-r V_;I__O_- e o VV
QC FQRM1225A (JUL 6 5)
TEST PREPARATION SHEET s o.TP
S/C Cat. No.CONTINUATION SHEET
NASA - MANNED SPACECRAFT CENTER Page of 3
DESCRIPTION (Print or Type) Tech. In p.___ _Cont. NASA
__ ;- A+ v: c- - V ' -rv /_ ov __
13.. "/ .
MSC FOaM 25A (JUL 65) • COPY I
1. A ConfigurationChange 2. TPS No. o- d O
P B Non-Configuration TEST PREPARATION SHEET 3 s Cat. No.
4. Mod. Sheet Number NASA- MANNED SPACECRAFT CENTER
S _7_ - 15. Page of6. S/C No/Model No. 7. Date .8. Time 9. Need Date
10. Drawings. Documents. Ocp's, & Part Number(s) 11. Contract Number
.4A+7- he 412. Serial Number
13. System 14. Ref. E. 0. Number
15. TPS Short Title 16. Wt. Req.
17. Reason for Work:
18. DESCRIPTION (Print or Type) 21. Insp.Tech. . CONT 2 A
~f f _ P__ / /_1k-
____+ w-tA 4 "4:' 4__T'J; _ ___.__,
• , r. e . _ _
19, Prepared Y 20. Final Acceptance Date
REFER TO PROCEDURES FOR REQUIRED SIGNATURES REFER TO PROCEDURES FOR REQUIRED SIGNATURESContractor Date NA" I----Date
FOM 22 JUl 65 NASA-MS--. Com.. ". '• ,"'es Coov 1
1. CategoryDISCREPANCY REPORT/MATERIAL REVIEW RECORD
NASA - MANNED SPACECRAFT CENTER PAGE / OF_/2. Arti Na 3. Drawing Number 4. Serial/Lot Number 5. RECORDNUMBER
f, ; rZiA /T" 7- o_7 /o o/ ,DR6. ontractor's Name 7. Contractor's Drawing Number 8. Contractor's Serial Number -6e4L 1l:ci-R T c DR/MRR g 0o
9. Supplier's Name 10. Supplier's Drawing Number i1. Supplier's Serial No. 12. Next Higher Assy. / 0-b
13. REF. Document No. 4. ce aft 1516 . 17. Cuse rigin 18. S e 19. Disposition
DISCREPANCY
F eA/c6 /, o - Ps - (2 J/ _21&JLFJ7-cr04,F r . - Z 'c7-. 4~/ L, _ -. sT-ss -- g _-, s ,4" A466
20. In I Sign 21. Stamp Number 22. Organization and Location/ lnitator 23. Dt
DISPOSITION24. MR Action Requiredl 25. Replacement Part Number 26. Retest Required 27. Retest Accept Date 28. FIAR Number
Y<ES O No ] Yes No
29. MRB Decision INSTRUC STAMPINSTRUCTIONS QC S AMP
O USE.AS IS" CONT. NASA
O REPAIR
0 REWORK l %.'O SCRAP
l30. DATE-./
0 /.DAE7 ,- FINAL ACCEPTANCE
MRB APPROVAL SIGNATURES
31 (Cneer a or) DATE 32 fngi _ee I SA) DATE
33 ty Co tro oC ) DATE/ 34. y C P) DA
P m Offic p. (Office Code) ATE DATE
ISC FORM 2176 (Re Apr 68) NASA-MSC--Coml., Houston, Texas
APPENDIX C
PHOTOGRAPHS
Document No. QTR-72-1039RevisionRelease DateT rTt Tij
PHOTOGRAPH DESCRIPTIONS BY NUMBER
1. Test Setup for Side Impact
2. Side Impact Viewed from outside helmet
3. Side impact viewed from inside helmet
4. Test setup for top impact
5. Top of helmet viewed prior to impact
6. Top of helmet after impact (magnified 3 times)
7. Top inside of helmet after impact
8. Test setup for front impact
9. Front of helmet viewed prior to impact
10. Front of' helmet after impact
11. Front inside of helmet after impact
NOTE: All high-speed film taken to determine deflection is in file atGeneral Electric.
6 15
- ZL
-Svs
vN
FI
4..44 p4w
-p
-C-A
- -Ai s
NA
SAS
-72
-51
94
8
'k4A
05 6 15 -
SV
SVN
()At
041
AMIN
tip,Ak
Ai
~/
().
r12
*40
I\
i i , i6 '
41
lp
VSVN
C VSVN
C4