document of the world bankdocuments.worldbank.org/curated/en/... · aid effectiveness, swap is an...

106
Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00004251 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA‐ 44780, IDA‐564860, TF 17128) ON A LOAN IN THE AMOUNT OF SDR15.3 MILLION (US$25 MILLION EQUIVALENT) AND AN ADDITIONAL CREDIT IN THE AMOUNT OF SDR13MILLION (US$20 MILLION EQUIVALENT) AND ADDITIONAL GRANT FROM THE HEALTH RESULTS INNOVATION TRUST FUND (HRITF) IN THE AMOUNT OF US$20 MILLION . TO THE REPUBLIC OF CAMEROON FOR THE Cameroon Health Sector Support Investment (SWAP) (P104525) July 9, 2018 Health, Nutrition & Population Global Practice Africa Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 11-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

Document of 

The World Bank 

FOR OFFICIAL USE ONLY  

Report No: ICR00004251 

IMPLEMENTATION COMPLETION AND RESULTS REPORT 

(IDA‐  44780, IDA‐564860, TF 17128)  

ON A 

LOAN  

IN THE AMOUNT OF SDR15.3 MILLION 

(US$25 MILLION EQUIVALENT) 

AND  

AN ADDITIONAL CREDIT    

IN THE AMOUNT OF SDR13MILLION (US$20 MILLION EQUIVALENT) 

 AND  

ADDITIONAL GRANT FROM THE HEALTH RESULTS INNOVATION TRUST FUND (HRITF) 

IN THE AMOUNT OF US$20 MILLION . 

TO THE  

 REPUBLIC OF CAMEROON   

FOR THE  

Cameroon Health Sector Support Investment (SWAP) (P104525)  July 9, 2018 

 Health, Nutrition & Population Global Practice 

Africa Region 

  

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

 CURRENCY EQUIVALENTS  

 

(Exchange Rate Effective {May 25, 2018}) 

 

                                                                         Currency Unit =CFAF (XAF) 

 US$1=560.23978 (XAF) 

 US$1 =‐SDR 1.79 

  

                                                                              FISCAL YEAR January 1 ‐ December 31 

 

  

                

 

Regional Vice President: Makhtar Diop 

Country Director: Elisabeth Huybens 

Senior Global Practice Director: Timothy Grant Evans 

Practice Manager: Gaston Sorgho 

Task Team Leader(s): Ibrahim Magazi, Jean Claude Taptue Fotso 

ICR Main Contributor: Kofi Amponsah  

Page 3: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

ABBREVIATIONS AND ACRONYMS  

ACV  Contracting and Verification Agency (Agence de Contrôle et de Vérification) AF  Additional Financing AFD  French Agency for Development (Agence française de Développement) AIDS  Acquired Immune Deficiency Syndrome ANC                   Antenatal care  ARV  Anti‐Retroviral  ASLO                  Local Associations AWPB                Annual Work Plan and Budget BCG                   Bacillus Chalmette–Guerin CAA                   Autonomous Depreciation Fund (Caisse Autonome d’amortissment) CEO                   Chief Executive Officer CTN  National Technical Unit (Cellule Technique Nationale) CMU  Country Management Unit CHW  Community Health Worker CPF  Country Partnership Framework 

  CNPS                  National Social Insurance Fund (Caisse Nationale de Prévoyance Sociale) CSI                     Core Sector Indicator DA                     Designated Account DPs                    Development Partners 

  DPML                Directorate of Pharmacy, Drugs and Laboratories                              (Direction de la Pharmacie, des Médicaments et des Laboratoires)                                DHIS                  District Health Management Information System DHMT  District Health Management Team DPO  Development Policy Lending 

   DTC                   Diphtheria, Tetanus, and whooping Cough FA  Financing Agreement FOSA                 Formation Sanitaire (Health Facility) FM  Financial Management FSPS  Special Fund for Health Promotion (Fond Spécial pour la Promotion de la Sante) FRPS  Regional Fund for Health Promotion (Fonds Régional pour la Promotion de la Sante) GFF                    Global Financing Facility GoC  Government of Cameroon GIP  Public Interest Group (Groupe d’Intérêt Public) HIPC  Heavily Indebted Poor Countries HIV  Human Immunodeficiency Virus HMIS  Health Management Information System HRITF  Health Results Initiative Trust Fund HSPRP               Health Systems Performance Reinforcement Project ICER                   Incremental Cost Effectiveness Ratio ICR  Implementation Completion Repot IDA  International Development Association IFR  Interim Financial Report 

   IGSPL                General Inspectorate of Pharmaceutical Services and Laboratories                              (Inspection Générale des Services Pharmaceutiques et des Laboratoires) IPP  Indigenous People Plan ISN  Interim Strategy Note 

Page 4: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

ISR  Implementation Status and Results Report KfW  German Development Cooperation LRSFHP  Littoral Regional Fund for Health Promotion 

  MINEPAT           Ministry of Economy and Planning                               (Ministère de l'Economie, de la Planification de l’Aménagement du Territoire)  

  MINSANTE        Ministry of Public Health (Ministère  de la Santé Publique) MDGs.    Millennium Development Goals MWMP  Medical Waste Management Plan MoF                   Ministry of Finance             MoPH                Ministry of Public Health M&E  Monitoring and Evaluation MTR  Mid‐term Review NGO  Nongovernmental Organization NPTU  National PBF Technical Unit OHADA  Organization for Harmonization for Business Law in Africa                             (Organisation pour l’Harmonisation en Afrique du Droit des Affaires)  PAISS  Health Sector Support Investment Project                            (Project d’Appui aux Investissement du Secteur de la Santé) 

  PCA                Complementary Package of Activities (Paquets Complémentaires d’Activités)  PPA  Performance Purchasing Agency PBF  Performance‐Based Financing PDO  Project Development Objective PFM                   Public Financial Management  PHRD                 Policy and Human Resources Develepment PIU  Project Implémentation Unit PMA  Minimum Package of Activities (Paquet Minimum d’Activités) PNC                    Postnatal care PNDS                  National Health Development Plan                              (Plan National de Développement Sanitaire) POU  Project Operational Unit  PSC  Project Steering Committee RHD                   Regional Health Delegation SDGs  Sustainable Development Goals SDR  Special Drawing Right SWAp  Sector Wide Approach TB  Tuberculosis TOR                    Terms of Reference TTL  Task Team Leader UGP  Unité de Gestion de Project UHC                    Universal Health Coverage UNICEF              United Nations Children and Education Fund WB                     World Bank WHO                  World Health Organization 

 

  

 

Page 5: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

 

TABLE OF CONTENTS  

DATA SHEET ............................................................................................................................ 1 

I.  PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES ........................................................ 6 

A. CONTEXT AT APPRAISAL ........................................................................................................... 6 

B. SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE) ...................................... 10 

II.  OUTCOME ...................................................................................................................... 15 

A. RELEVANCE OF PDOs .............................................................................................................. 15 

B. ACHIEVEMENT OF PDOs (EFFICACY) ........................................................................................ 16 

C. EFFICIENCY ............................................................................................................................. 21 

D. JUSTIFICATION OF OVERALL OUTCOME RATING ..................................................................... 22 

E. OTHER OUTCOMES AND IMPACTS (IF ANY) ............................................................................. 22 

III.  KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME ................................ 25 

A. KEY FACTORS DURING PREPARATION..................................................................................... 25 

B. KEY FACTORS DURING IMPLEMENTATION .............................................................................. 27 

IV.  BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME .. 30 

A. QUALITY OF MONITORING AND EVALUATION (M&E) ............................................................. 30 

B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE ..................................................... 31 

C. BANK PERFORMANCE ............................................................................................................. 33 

D. RISK TO DEVELOPMENT OUTCOME ........................................................................................ 34 

V.  LESSONS AND RECOMMENDATIONS .............................................................................. 35 

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS ............................................................ 37 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION ......................... 46 

ANNEX 3. PROJECT COST BY COMPONENT............................................................................. 48 

ANNEX 4. EFFICIENCY ANALYSIS ............................................................................................ 49 

ANNEX 5. BORROWER, CO‐FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS ... 55 

ANNEX 6. MAJOR REFORMS AND INITIATIVES ....................................................................... 57 

ANNEX 7. SUMMARY OF IMPACT EVALUATION RESULTS ....................................................... 66 

ANNEX 8. SUMMARY OF BORROWER’S ICR ........................................................................... 87 

ANNEX 9. SUPPORTING DOCUMENTS .................................................................................... 98 

ANNEX 10. MAP OF CAMEROON ......................................................................................... 100 

   

Page 6: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development
Page 7: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 1 of 100

         

DATA SHEET 

  

BASIC INFORMATION  Product Information 

Project ID  Project Name 

P104525  Cameroon Health Sector Support Investment (SWAP) 

Country  Financing Instrument 

Cameroon  Investment Project Financing 

Original EA Category  Revised EA Category 

Partial Assessment (B)  Partial Assessment (B) 

Related Projects            

Relationship  Project  Approval  Product Line 

Additional Financing  P146795‐Additional Financing to Cameroon Health Sector Support Project 

24‐Jun‐2014  IBRD/IDA 

Organizations 

Borrower  Implementing Agency 

Ministry of Economy, Planning and Regional 

Development Ministry of Public Health, PBF Technical Unit 

Project Development Objective (PDO)  Original PDO 

To increase utilization and improve the quality of health services with a particular focus on child and maternal health and communicable diseases.   

Page 8: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 2 of 100

FINANCING 

 

  Original Amount (US$)   Revised Amount (US$)  Actual Disbursed (US$) 

World Bank Financing        IDA‐44780 

25,000,000  24,962,097  23,420,436 

 IDA‐54860 

20,000,000  20,000,000  18,393,471 

 TF‐17128 

20,000,000  20,000,000  18,876,143 

Total    65,000,000  64,962,097  60,690,050 

Non‐World Bank Financing       

Borrower     0     0     0 

Total     0     0     0 

Total Project Cost  65,000,000  64,962,097  60,690,050  

  KEY DATES 

   

Approval  Effectiveness  MTR Review  Original Closing  Actual Closing 

24‐Jun‐2008  03‐Mar‐2009  06‐May‐2013  31‐Mar‐2014  31‐Dec‐2017 

   RESTRUCTURING AND/OR ADDITIONAL FINANCING 

 

 

Date(s)  Amount Disbursed (US$M)  Key Revisions 

10‐Mar‐2014  19.49  Change in Results Framework Change in Loan Closing Date(s) Reallocation between Disbursement Categories 

03‐Jan‐2017  42.01  Change in Institutional Arrangements 

  

KEY RATINGS  

 

Outcome  Bank Performance  M&E Quality 

Satisfactory  Satisfactory  Substantial 

 

Page 9: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 3 of 100

RATINGS OF PROJECT PERFORMANCE IN ISRs  

 

No.  Date ISR Archived  DO Rating  IP Rating Actual 

Disbursements (US$M) 

01  06‐Aug‐2008  Satisfactory  Satisfactory  .20 

02  31‐Aug‐2008  Satisfactory  Satisfactory  .20 

03  30‐Jan‐2009  Satisfactory  Moderately Satisfactory  .24 

04  20‐Mar‐2009  Satisfactory  Moderately Satisfactory  .24 

05  07‐Oct‐2009  Satisfactory  Moderately Unsatisfactory  .59 

06  18‐Jun‐2010 Moderately 

Unsatisfactory Moderately Unsatisfactory  .64 

07  09‐Feb‐2011 Moderately 

Unsatisfactory Moderately Unsatisfactory  .86 

08  25‐Oct‐2011  Moderately Satisfactory  Moderately Satisfactory  2.26 

09  28‐Apr‐2012  Moderately Satisfactory  Moderately Satisfactory  4.16 

10  10‐Dec‐2012  Moderately Satisfactory  Satisfactory  6.08 

11  12‐Jun‐2013  Satisfactory  Satisfactory  10.35 

12  28‐Dec‐2013  Satisfactory  Satisfactory  19.15 

13  20‐May‐2014  Satisfactory  Satisfactory  20.07 

14  18‐Nov‐2014  Satisfactory  Satisfactory  22.90 

15  20‐Apr‐2015  Satisfactory  Satisfactory  35.54 

16  23‐Oct‐2015  Satisfactory  Satisfactory  35.54 

17  29‐Apr‐2016  Satisfactory  Satisfactory  40.88 

18  31‐Oct‐2016  Satisfactory  Satisfactory  41.37 

19  05‐Apr‐2017  Satisfactory  Satisfactory  41.06 

20  12‐Oct‐2017  Satisfactory  Satisfactory  41.22 

21  21‐Dec‐2017  Satisfactory  Satisfactory  41.22 

 

Page 10: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 4 of 100

SECTORS AND THEMES  

 Sectors 

Major Sector/Sector  (%) 

 

Public Administration    30 

Central Government (Central Agencies)  20 

Sub‐National Government  10 

  

Health    60 

Health  60 

  

Social Protection    10 

Social Protection  10 

  Themes   

Major Theme/ Theme (Level 2)/ Theme (Level 3)  (%)  Human Development and Gender  100  

Disease Control  38  

HIV/AIDS  13   

Tuberculosis  25    

Health Systems and Policies  62  

Health System Strengthening  25   

Reproductive and Maternal Health  13   

Child Health  24  

   

ADM STAFF  

Role  At Approval  At ICR 

Regional Vice President:  Gobind T. Nankani  Makhtar Diop 

Country Director:  Mary A. Barton‐Dock  Elisabeth Huybens 

Senior Global Practice Director:  Lynne D. Sherburne‐Benz  Timothy Grant Evans 

Page 11: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 5 of 100

Practice Manager:  Lynne D. Sherburne‐Benz  Gaston Sorgho 

Task Team Leader(s):  Miriam Schneidman Ibrahim Magazi, Jean Claude Taptue Fotso 

ICR Contributing Author:    Kofi Amponsah 

         

Page 12: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 6 of 100

 

I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES 

 

A. CONTEXT AT APPRAISAL  

Country Context 

1. At appraisal, over 40 percent of Cameroon’s population lived below the poverty line due mainly to  economic  crisis  that  hit  the  country  in  the  1980/90s.    The  government  undertook  economic  and financial  reforms  to  improve  the  economy,  but  growth  fell  below  3  percent.  The  Government  also embarked on  the Heavily  Indebted Poor Countries  (HIPC)  initiative, which unfortunately did not  yield concrete  results  in  terms  of  improved  living  standards  and  service  delivery.  At  the  same  time,  the government made  considerable  progress  in  Public  Financial Management  (PFM)  reforms  through  the implementation of measures such as budget tracking; procurement reform and external auditing to tackle corruption, which helped to improve Cameroon’s score of transparency international from 1.4 in 1998 to 2.5  in  2007.  These  PFM  reforms were  also  intended  to  improve  the  effectiveness  of  public  services, including health services. Key among the reforms were the following (i) development of a medium‐term expenditure  framework  that  linked  sector  strategies  to  government  priorities,  (ii)  decentralization  of budget  execution  responsibilities  to  line ministries,  and  (iii)  computerization of  the budget processes. Other  measures  implemented  by  the  government  were  implementation  of  transparency  and accountability  projects,  which  were  expected  to  improve  budget  credibility,  transparency  and stewardship.    

2. To  improve  aid  effectiveness,  the  Government  demonstrated  leadership  in  strengthening coordination of several development projects in accordance with the principles of Paris Declaration on aid  effectiveness.  The  Bank  played  a  lead  role  in  the  aid  effectiveness  agenda  by  promoting mutual accountability with emphasis on government ownership, and alignment of development assistance to the needs of the country. This initiative was promoted in the health sector through a Sector Wide Approach (SWAp) that brought together all the key stakeholders in the sector. Emanating from Paris Declaration for aid effectiveness, SWAp is an approach to development that brings together key government institutions, development partners  (DPs), and other stakeholders  in a sector.    It encourages an open and  inclusive dialogue, with allocations based on priorities, payments based on results, and harmonized aid flow. It is characterized by a set of principles1 that allows each DP to focus on the government’s priority areas of development.    The  Cameroon  SWAp  was  intended  to  support  implementation  of  the  health  sector strategy. Under the SWAp agreement, the Bank would finance recurrent costs while Agence française de Développement  (AfD) and German Technical Cooperation  (KfW) were  to  finance  investment activities such as rehabilitation and equipment of health facilities. Despite this well‐thought initiative, the SWAp did  not materialize,  and  the  project  essentially  became  a  performance‐based  financing  (PBF)  project financed by the Bank and government (see section B below).    

1 1 Paris declaration outlined five principles: (i) ownership; (ii)alignment; (iii) harmonization; (iv) managing for results; and (v) mutual accountability. 

 

Page 13: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 7 of 100

Sector Issues 

3. Despite  government’s  efforts,  health  outcomes  lagged  other  countries  in  the  region,  making Cameroon off track for reaching the health and nutrition Millennium Development Goals (MDGs). Child and nutrition indicators were not the best. Malaria accounted for over 40 percent of morbidity among the population, and HIV infection rate was high with a national average of 5.5 percent. This particularly made women  vulnerable  with  the  rate  of  6.8  percent  compared  to  4.1  percent  among  men.  Tuberculosis prevalence rate (134 per 100,000 inhabitants) varied among provinces, ranging from 60 per 100,000 in the  western  provinces  to  261  per  1000,000  in  the  Littoral  province.  TB/HIV  co‐infection  rates  were estimated at 30‐40 percent, compounded by the emergence of multi‐drug resistant TB, whose treatment was considered as lengthy and costly with serious side effects. There was inefficient public spending on health with  larger  proportion  of  health  expenditure  going  into  administration  rather  than  supporting frontline  workers  who  deliver  health  services.  The  sector’s  performance  was  inhibited  by  significant governance problems such as: (i)informal or under the table payments which placed a disproportionate burden on poor patients; (ii) irregular procurement practices, sale of illicit drugs, and over‐billing which translated  into higher prices  for patients; and  (iii)  excessive  focus on controls and  lack of  transparent management of human resources (combined with extremely low salary levels) which drove individuals to abuse public funds and facilities; (iv) weak monitoring and evaluation of health sector performance caused by    lack  of  analytic  capacity  of  the Ministry  of  Public  Health  (MoPH),  and manual  paper‐based  data collection with limited feedback from the provinces. 

 

Rationale for Bank Involvement 

4. To  assist  the  Government  of  Cameroon  (GoC)  in  addressing  the  above  issues,  the  Bank collaborated  with  other  key  sector  Development  Partners  (DPs)  to  work  towards  improving  health outcomes,  including  strengthening  health  systems  in  order  to  attain  the  health MDGs.      The  Bank’s contribution strengthened visibility and credibility of the government’s health program, and  leveraged resources from other partners.  The project was aligned with the pro‐poor service delivery pillar of the 2006 Interim Strategy Note (ISN) by supporting  its three key dimensions of  (i) managing for results by promoting contracting of health districts and NGOs to deliver a package of health services; (ii) addressing governance issues and (iii) strengthening harmonization and building partnerships in close collaboration with DPs in the sector. 

 

5. Main Beneficiaries. The project targeted an estimated 2.5 million inhabitants in the original four regions (East, Littoral, North West and South West). The main beneficiaries were women of reproductive age, pregnant women and children under five years of age. The target population was increased by 88 percent (from 2.5 million to 4.7 million) through Additional Financing (AF) which was approved on June 24, 2014 (Credit No.54860), in the amount of 13 SDR million (US$20 million equivalent), and US$20 million TF No. 17128. The AF, which  targeted  the  indigent,  the poor and vulnerable population  increased the geographical coverage to three additional regions (Adamaoua, North and Far‐North). Institutionally, the project benefitted key institutions in MoPH, district health institutions as well as the communities through targeted capacity building interventions. 

 

Theory of Change (Results Chain) 

Page 14: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 8 of 100

6. The Cameroon Health Sector Investment Project (P104525, Credit No. 44780) approved on June 24, 2008 in the amount of SDR 15.3 million (US$25 million equivalent) focused on the provision of health services  delivery  and  institutional  strengthening  to  increase  utilization  and  improve  quality  of  health services for the target population.  The same theory of change applies to the AF which funded increased demand and activities through additional financing. 

 

7. Activities outlined to address service delivery issues included supervision, community outreach, recruitment of contractors and payment of performance bonuses to health facilities, capacity building and technical  assistance,  supply  of  consumables,  performance‐based  contracting,  rehabilitation  and equipment of health facilities2.  To increase utilization of maternal and child health services, the project introduced demand‐side interventions (e.g. fee waivers) for poor families. This was implemented through reimbursement of  facilities for  lost revenues.   The expected outcomes of these  interventions were:  (i) increased health services utilization, and (ii) improved quality of health services.  Key assumptions under which  the  operation  was  designed  included  the  following:  donor  funding  would  be  available;  local implementation support would be provided by Fond Spécial de la Promotion de la Santé (FSPS3)/ Special Funds for Health Promotion (SFHP), and government would fully support performance‐based financing (PBF) interventions. Figure 1 shows the project’s results chain.   

  Figure 1.: PAISS Results Chain 

  

2 Under the PBF, rehabilitation and equipment of facilities were financed by health facilities’ administrators using a portion of their PBF subsidies.  3 Now known as Fonds Régionaux de Promotion de la Santé   

Impact PDO Outcomes Outputs Activities Inputs 

Reduction in Infant Mortality  Reduction in Maternal Mortality 

Increased Health services utilization   Improved Quality of health services  

 

Contraception prevalence rate increased Pregnant women receiving antenatal care increased Tracer drugs available in target facilities TB treatment success rate increased 

 

Rehabilitation/equipment of health facilities Procurement and distribution of drugs  Capacity building Household visits Family planning services Community outreach/mobilization Setting up fee waivers mechanisms Monitoring and supervision 

Project Funds (PBF Funds to health facilities 

Action/Work Plans 

 

Intermediate outcomes 

Children Immunized People with access to basic health services Births attended by a skill health professional TB cases detected  Women beneficiaries 

Page 15: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 9 of 100

 

Key Administrative and implementation milestones and processes 

8. Nine years of project implementation were marked by key milestones and processes (Table 1).   Table 1. Administrative/implementation milestones and process 

EVENT/PROCESSES  DATES 

Administrative Milestones 

Approval  June 24, 20008 

Effectiveness  March 3, 2009 

Original Closing date  March 31, 2014 

Actual Closing Date  December 31, 2017 

First Restructuring  July 2010 

Second Restructuring  February 5, 2014 

Additional Financing  June 24, 2014 

Third Restructuring  January 3, 2017 

Implementation Milestones 

Beginning of PBF  2012 

First Extension   March 31, 2014‐January 31, 2016 

Second Extension  January 31, 2016‐ December 31 2017 

Project completion  December 31,2017 

M&E Processes 

 Baseline Impact Evaluation  May 2013 

Midterm Review (MTR)  May 6, 2013 

Midline Qualitative Impact Evaluation  December 2014 

End‐line Quantitative Impact Evaluation End‐line Qualitative Impact Evaluation 

March 24, 2017 March 27, 3017 

 

Project Development Objectives (PDOs) 

9. The project development objective (PDO) as stated in the original financing agreement (FA) is to increase utilization and improve the quality of health services with a particular focus on child and maternal health and communicable diseases.  

Key Expected Outcomes and Outcome Indicators 

10. To achieve the PDO the following key expected outcome and outcome indicators were agreed: 

  Increased Health Services Utilization: 

 

Percentage of children immunized for DPT3 (< 12 months); 

Percentage of births attended by a skilled professional; 

Percentage of children under‐five sleeping under insecticide treated bed‐nets the night before the survey; 

Tuberculosis treatment success rate (i.e. percentage of those who are smear positive and who are successfully treated). 

Page 16: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 10 of 100

  Improved Quality of Health Services: 

 

Percentage of patients reporting satisfaction with health services.  

Components4 

11. Component 1: District Service Delivery (Appraisal Estimate US$15 million; Actual US$47.5). The objective of  this component was to address three critical constraints  to service delivery:  (i) scarcity of funds available at  the  field  level  to meet operating expenses;  (ii)  lack of  focus  for  the achievement of actual  results and  lack of accountability  for performance of  the district health system; and (iii)  limited managerial  capacity  at  district  level.  Through  FSPS,  the  project  would  channel  financial  resources  to districts to enable them to meet their day‐to‐day requirements of managing a district health system. The funds  were  to  be  used  for  operating  costs,  goods,  and  technical  assistance,  including  payment  of performance bonuses  to health  facilities,  recruitment of  contractual workers,  supervision,  community outreach, and consumables. To address  the  issue of  lack of  focus on  results and  limited management capacity, the project would support pilot‐testing, on a reasonable scale, of a few different approaches to performance‐based  contracting/financing,  including  financing  of  contracts  with  private/NGO‐administered facilities. 

 

12. Component  2:  Institutional  Strengthening  (Appraisal  Estimate  US$5  million;  Actual  US$8.9 million). The objective of this component was to strengthen two key functions of the central Ministry of Health/Ministry  of  Public  Health  (MoHP),  at  the  provincial  and  district  levels  through:  (i)  setting  up institutional framework and systems and build capacity to prepare, negotiate, and manage contracts; and (ii) putting in place an information system to generate up to date, reliable, financial and programmatic data.  

B. SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE)  

Revised PDOs and Outcome Targets  

13. The PDO was not revised.   

Revised PDO Indicators  

14. To track implementation progress and ensure reliability of data reporting, the project team revised the unit of measurement  (from  percentages  to  absolute  numbers)  and  end‐of‐project  targets  of  three  PDO  indicators  (children immunized, births attended by skilled personnel, and consultation for the poorest households) in the results framework. 

4 The higher actual costs over appraisal estimates for the two components was as a result of additional financing (US$20million IDA and US$20million HRITF) the project received for scaling up project interventions  

Page 17: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 11 of 100

The team took this action because of difficulties in   measuring the indicators in proportions. The team also reformulated and introduced new PDO indicators through restructuring.   

Revised Components 

15. The components were not revised. 

 

Other Changes 

 

 

16. Other significant changes include:   

17.   Change in project approach.  As noted earlier, the SWAp brought new sense of enthusiasm and optimism to the 

development of the sector.  It brought together two key DPs (AfD and KfW). Under the SWAp agreement, AfD and KfW 

were to carry out construction and rehabilitation of health infrastructure while the Bank would finance operational costs.   

Operationally, the FSPS was to implement the project at district level, but it did not have legal status to operate effectively. 

To obtain legal status required adoption of loi de Groupe d’Intérêt Public (GIP)5 . AfD and KfW had to wait for the adoption 

of the law before they would commit to the SWAp agreement and that meant that they would not finance institutions 

that had no legal status. Two years later in 2010 the law was adopted, after the two DPs had already pulled out of the 

SWAp in 2008. The Bank continued with the design and implementation of PBF together with the government. 

 

18. Key  changes  during  implementation  are  summarized  in  table  2,  and  detailed  reasons  given  in  the  following section.  Table 2. Key of changes Activity  Date  Remarks 

Restructuring 

First Restructuring  July 2010   Addressed institutional arrangement constraints to improve implementation 

Second Restructuring  February 5, 2014  Extension of closing dates from March 31, 2014 to January 31, 2016 for 22 months; Revisions to results framework; Reallocation of expenditure categories. 

Additional Financing 

Board Approval  June 24, 2014   US$20 million IDA Credit and US$20 million Health Results Initiative Trust Fund (HRITF) grant respectively. The financing and grant agreements signed on September 26, 2014.   

Amendment to the Financing Agreement 

Amendment of Section 1.A.2 of the FA 

June 24, 2014  Government request for amendment to FA: (i) Changed PIU name to PBF Technical Unit; (ii) extension of closing date from January 31, 2016 to December 3i, 2017; Revisions to 

5 A law that provides territorial autonomy to public institutions and persons.  

Page 18: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 12 of 100

selected indicators and their targets. 

Restructuring 

Third Restructuring  January 2, 2017  Revised the FA to ensure flexibility of using funds from IDA and Trust Fund and vice versa; Transferred staff of PIU to PBF technical Unit to implement Health System Performance Reinforcement Project (HSPRP). 

  

 

19. First restructuring. On July 2010, the project underwent a level 2 restructuring. The restructuring was meant to address  institutional arrangement challenges that  inhibited project  implementation progress after  its effectiveness on March 3, 2009. Under the initial institutional arrangements, the FSPS was given the responsibility of purchasing health services from health centers.  However, as of December 2009, their mandate had not been revised to reflect eligibility conditions stated in the FA. Also, the FSPS did not have enough autonomy from health service providers as Performance Purchasing Agencies  (PPA).    In  addition,  apart  from  the  Littoral  region by  the project,  the  FSPS  in  the other  regions, targeted by the project, did not have the technical capacity to develop and implement PBF as expected.  This situation stalled project implementation for about two years, and as at March 2009 the project had only disbursed 6 percent of its total funds.  

  

20. Second restructuring. On February 5, 2014, the project was again restructured.   The restructuring was intended to:  (i) extend the closing date of  the project  for 22 months  from March 31, 2014 to  January 31, 2016;  (ii)  revise and reformulate  six  indicators,  their  units  of  measurement  and  end  targets;  (iii)  reallocate  funds  proceeds  between expenditure categories.  Major changes under the second restructuring included: 

 

Changes in the results framework. As noted, the units of measurement and targets of the three PDO indicators were  revised.    The  changes were  deemed  necessary  as  it was  difficult  to  compute  reliable  estimates  of  the population  covered.  Similarly,  the  unit  of  measurement  of  the  health  facilities  in  targeted  areas  that  used standard health management information system (HMIS) format indicator was changed from absolute number to percentage because the total number of health facilities implementing PBF had been established at the time of the review.  The satisfaction indicator was dropped as the team decided to measure satisfaction through impact evaluation. Table 3 summarizes the revised indicators and their targets. 

Table 3. Revised Indicators 

No.  Indicator Original target 

Revised Target (number)  Remarks 

PDO Level Indicators 

1.  People with access to a basic package of health, nutrition, or reproductive health services   

‐  750,000  New indicator and target 

2.  

Percentage of children immunized for DPT3 (< 12 months);  

85%  ‐  Original indicator 

Number of children immunized in targeted areas 

‐  100,000  Reformulated indicator 

Page 19: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 13 of 100

3.  

Percentage of births attended by a skilled professional;  

66%  ‐  Original indicator 

Number of births attended by skilled professional in targeted areas 

‐  30,000  Reformulated indicator 

4. 

Tuberculosis case treatment success rate in targeted areas. 

80%  ‐  Original indicator moved to intermediate outcome indicator level. 

New cases of tuberculosis detected and treated in targeted areas 

‐  5,000  Reformulated indicator 

5.  Direct Project Beneficiaries (number)  ‐  885,000  New indicator (CSI) 

5.1  Of which female beneficiary(number)  ‐  443,000  New indicator (CSI) 

Intermediate Outcome indicators 

6.  Pregnant women receiving antenatal care during a visit to a health provider 

‐  100,000  Reformulated indicator 

7.  New acceptors of modern contraceptive methods in targeted areas 

‐  20,000  Reformulated indicator 

8.  Children by the first anniversary who have received one dose of Vit. A in the last six months in targeted areas 

‐  100,000  Reformulated indicator 

Reallocation of funds. The project team also reallocated funds proceeds between expenditure categories as part 

of the second restructuring. Funds were reallocated as follows: (i) goods and services for PBF (increased by 13 percent from SDR6.2 million to about SDR7.0 million); (ii) operating costs (increased by 8 percent from SDR1.2 million to SDR1.3 million); (iii) approved NGO fees (decreased by 21 percent from SDR3.million to SDR2.4 million); (iv)  goods,  services and drug  supplies  (increased by 41 percent  from SDR2.8 million  to approximately  SDR4.0 million);, and (v)  consultants’ services and training (decreased substantially by 67 percent from SDR2.1 million to SDR688,304).  The reallocation was to meet demand for purchasing of health services, which increased at a faster rate  than expected,  resulting  in quicker  than expected disbursement and as more health  facilities had signed contracts with the PPAs. The increase in operating costs category was to cover a two‐month transitional period costs of the Littoral PPA. The increase in goods and services category was meant to finance US$2 million costs of emergency procurement of ARVs to prevent a national shortage of Anti‐retroviral) ARVs drugs for the HIV/AIDS program.  The decrease in consultant services and training category was to remove duplication of activities as a large part of  the activities  initially  stated under  this category were  included  in category 2  in compliance with Organisation pour L’Harmonisation en Afrique du Droits des Affaires (OHADA) regulations and procedures. Table 4 provides a summary of reallocation of funds among expenditure categories.  

                           Table 4: Reallocation of funds between expenditure categories 

No.  Expenditure Category 

Original Amount 

(SDR million) 

Reallocated Amount (SDR 

million) 

Increase (+)/ Decrease (‐) 

(%) 

1.  Category1(a): Goods and Services (PBF) 

6,200,000  6,999,492  +13 

2.  Category 1(b): Operating costs 

1,200,000  1,293,105  +8 

3.  Category 1(c): Approved NGO fees 

3,000,000  2,373,886  ‐21 

Page 20: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 14 of 100

4.  Category 2: Goods and Drug supplies 

2,800,000  3,945,493  +41 

5.  Category 3: Consultant Services and training 

2,100,000  688,024  ‐67 

  Total  15,300,000  15,300,000   

 

21. Additional financing.  On June 24, 2014 the Board approved a US$40 million AF, made up of US$20 million IDA Credit and US$20 million Health Results  Initiative Trust Fund (HRITF) grant. The financing and grant agreements were signed on September 26, 2014.   At the same time, the government requested an amendment of Section 1.A.2 of  the Financing Agreement (FA) to change the name of the project implementation unit from Project Operational Unit (POU) to National PBF Technical Unit (NPTU). The IDA US$20 million AF was to extend the project to cover additional 2.2 million (from 2.5 million to 4.7 million) target population in the poorest region of the northern part of the country (Adamaoua, North and Far‐North). The AF was also meant to support institutional strengthening under component 2 of the project.  The  US$20 million  HRITF was  to:  (i)  support  a  scale‐up  of  project  activities  in  the  26  districts  implementing  PBF  by extending PBF to the impact evaluation group facilities and (ii) complete impact evaluation and use the results to fine tune the PBF national strategy. The AF extended the closing date from March 31, 2014 to December 31, 2017 to enable the  project  team  to  (i)  carry  out  full  implementation  of  component  1  activities;  (ii)  complete  the  conduct  of  impact evaluation to inform decision‐making; (iii) complete preparation for scaling up of PBF interventions; and (iv) allow the GoC to develop institutional, regulatory and fiduciary framework for extension of PBF coverage nationwide.  In addition, most of the indicators’ targets at restructuring were met at the time of the approval of AF and given the pace of the results the project team doubled the targets (Table 5).  

         Table 5. Revised targets 

No.  Indicator Original target 

Revised Target 

AF Target Remarks 

PDO Level Indicators 

1.  People with access to a basic package of health, nutrition, or reproductive health services   

‐  750,000  1,500,000  Target revised upward 

3.  Number of children immunized in targeted areas 

‐  100,000  200,000  Target revised upward 

5.  Number of births attended by skilled professional in targeted areas 

‐  30,000  60,000  Target revised upward 

7.  New cases of tuberculosis detected and treated in targeted areas 

‐  5,000  10,000  Target revised upward 

8.  Direct Project Beneficiaries (number) 

‐  885,000  1,770,000  Target revised upward 

8.1  Of which female beneficiary(number) 

‐  443,000  885,000  Target revised upward 

  Intermediate Outcome indicators 

1.  Pregnant women receiving antenatal care during a visit to a health provider 

‐  100,000  200,000  Target revised upward 

2.  New acceptors of modern contraceptive methods in 

‐  20,000  40,000  Target revised upward 

Page 21: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 15 of 100

targeted areas 

3.  Children by the first anniversary who have received one dose of Vit. A in the last six months in targeted areas 

‐  100,000  200,000  Target revised upward 

Third restructuring. On January 2, 2017 the project was restructured for the third time.  The  third restructuring  

was to (i) revise the financing agreement to enable flexibility in the use of funds from both the IDA credit and the trust fund for PBF activities, including PBF subsidy payments, in the North‐West, South‐West, East and Littoral regions as well as the North, Far North and Adamaoua regions, and (ii) move the PAISS PIU staff to the National PBF  Technical  Unit  established  to  implement  the  new  Health  Systems  Performance  Reinforcement  Project (HSPRP) currently under implementation. 

Rationale for Changes and Their Implication on the Original Theory of Change 

22. As  noted,  the  first  restructuring  was  necessary  to  address  institutional  arrangement  constraints  to implementation progress. The second restructuring was to extend the closing dates from March 31, 2014 to January 31, 2016 for 22 months as project implementation improved significantly and more time was needed to completed project activities. The third restructuring, which amended the FA was to ensure flexibility of use of funds between IDA credit and the trust fund. The changes to the indicators were deemed necessary as it was difficult to compute reliable estimates of the population covered. When revising the indicators, the team intentionally decided that quality would be measured through impact evaluation; and therefore, dropped the PDO level satisfaction indicator. The reallocation of funds between expenditure categories was needed to forestall a national shortage of ARVs. The additional financing was necessary to extend project coverage to the indigent and poor population, and scale up activities in the original regions. The above changes did not affect the original theory of change as the PDO and project components remained the same.  The scope of the project increased and while the theory of change is the same, there would simply be more impact than previously expected.   

II. OUTCOME 

 

A. RELEVANCE OF PDOs 

 

Assessment of Relevance of PDOs and Rating  

23. Relevance  of  the  PDO  is  rated  high.  The  PDO  is  consistent  with  the  Bank’s  current  Country Partnership  Framework  (CPF)‐FY17‐FY21,  which  emphasizes  three  strategic  objectives:  (i)  addressing multiple poverty traps in rural areas (with a focus on northern regions); (ii) fostering infrastructure and private  sector  development;  and  (iii)  improving  governance6.  The main  objectives  of  strategic  focus  1 include:  (a)  increased  productivity  and  access  to markets  in  the  agriculture  and  livestock  sectors;  (b) 

6 Country Partnership Framework, for the Republic of Cameroon for the Period FY17‐FY21 February 28, 2017, Africa Region 

(Page 25)  

Page 22: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 16 of 100

improved maternal and child health, and nutrition; (c) enhanced quality of, and more equitable access to, education; (d) expanded social safety nets; and (e) improved access to local infrastructure. PAISS is fully consistent with objective 2 (improved maternal and child health, and nutrition) of strategic focus 1, which is  linked  to SDG3:  ensure healthy  lives and promote well‐being  for all  at  all  ages.    The project  is  also consistent with the GoC’s health development objective as enshrined in the National Health Development strategy‐PNDS  (2016‐2020)7,  whose  overall  objective  is  to  make  affordable  priority  essential  and specialized health services available in at least 50 percent of District and Regional Hospitals by 2020. When the project was being prepared, Cameroon had poor  child and nutrition  indicators, and women were vulnerable  to  high morbidity  because  of  prevalence of malaria  and HIV AIDS.  By  aiming  at  increasing utilization  and  providing  access  to  quality  health  services,  PAISS  buttresses  the  CPF’s  objective  of improving maternal and child health, and nutrition. To maintain relevance, during implementation, the project was extended to additional target population in the poorest region of the northern parts of the country through AF instrument.  

 

B. ACHIEVEMENT OF PDOs (EFFICACY)  

Assessment of Achievement of Each Objective/Outcome 

24. PAISS has substantially achieved its development objective. The PDO was to increase utilization and  improve  the  quality  of  health  services  with  a  particular  focus  on  child  and maternal  health  and communicable diseases. The project contributed to short to medium‐term interventions that sought to improve health  services  delivery,  and  directly  benefited  an  estimated  7.8 million people  (of whom 3.6 million were women) with access to improved health services. The project’s pro‐poor interventions enabled the poor and the vulnerable population to utilize quality health services. This is evidenced by an increase of  original  direct  project  beneficiaries  from  2.5 million  to  4.7 million  (88  percent)  to  reach  the  poor communities in the northern parts of the country.  Through PBF interventions the project strengthened health facilities capacity to deliver quality health care to the beneficiary population.  The capacity building and coaching interventions provided by the project enhanced health facilities and frontline health workers and project managers’ technical capacity and ability to implement the PBF initiatives.   

 

25. The PDO8  consists of  two objectives:  (i)  increase utilization of health  services with a  focus on health and communicable diseases; and (ii) improve quality of health services with a focus on health and communicable diseases. An assessment of  the  achievement of  the  two objectives  and  their  ratings  is provided below. It is important to note that, a split rating was not done because most of the targets were increased and scope increased. 

 

Objective 1: Increase utilization of health services with a focus on health and communicable diseases    

26. This  objective was  achieved,  and  all  its  performance  indicators’  targets were  surpassed.    The achievement of the objective is measured by: PDO indicator 1: People with access to a basic package of health, nutrition, or reproductive health services was fully achieved and its target surpassed.  At the end 

7 Plan National de Développement Sanitaire (PNDS) 2016‐2020, MINISANTE, Aout, 2016. 8 The achievement of the PDO is measured by the revised indicators and end‐of‐project impact evaluation. 

Page 23: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 17 of 100

of the project, 7,166,077 (against a target of 1,500,000) had access to basic package of health, nutrition and  reproductive  health  services.    Intermediate  outcome  indicator  1:  Pregnant  women  receiving antenatal care during a visit to a health provider butressed this achievement.  At the end of the project, 1,094,661  (against  a  target  of  200,000)  pregnant women  received  antenatal  care  from  a  health  care provider, exceeding the target by 17.7 percentage points. The results are also supported by intermediate outcome indicator 2: New acceptors of modern contraceptive methods in targeted areas. At the end of the project,  the number of new acceptors of modern contraception was 165,062 compared to 40,000 people targeted by the project. Major activities that supported the achievement of the PDO indicator 1 included antenatal and prenatal care and family planning services carried out through the community PBF initiative.   

27.   PDO Indicator 2: Number of children immunized.  This indicator was fully achieved and its target surpassed. At the end of the project, 392,889 children (against a target of 200,000) were fully immunized. The achievement of this indicator was supported by intermediate outcome  indicator 3: Children by the first anniversary who have received one dose of Vit. A in the last six months in targeted areas.  At the end of the project, 424,028 (against a targeted of 200,000) received one dose of Vit. A in their last six months. Community‐based intensive immunization campaigns were the main contributor to the achievement of this indicator.   PDO indicator 3: Number of births attended by a skilled professional. This indicator was fully achieved and its target surpassed. At the end of the project 310,816 births (against a target of 60,000) were attended by a skilled professional. PDO indicator 4: New cases of TB detected and treated in targeted areas. This indicator was fully achieved and its target surpassed. At the end of project 14,916 new cases (against  a  target  of  10,000)  was  achieved.  Intermediate  outcome  indicator  4:  tuberculosis  treatment success rate in targeted areas supported the achievement of this indicator. At the end of the project, 80.36 percent  (against a target of 80 percent) of TB cases were successfully treated. The achievement of the PDO was also measured by PDO  indicator 5: Number of direct project beneficiaries9, disaggregated by gender, who utilized health services. At the end of project 7,779,897 (of whom 3,766,286 were females) compared to 1,770,000 (of whom 885,000 were females) utilized health services.   

 

28. Major interventions that contributed to the achievement of  objective 1 include: (a) PBF payment to  health  facilities  to  provide  facility‐based  services,  outreach  services  provided  at  community  level (coordinating  household  visits),  and  fee  waivers  for    poor  families  (demand‐side  interventions);  (b) Payment  to  CHWs,  basic  curative  care,  household  visits,  community  mobilization  of  health  facility outreach activities, immunization and family planning campaigns, and patients referrals to facilities for complicated cases. Table 6 provides a summary of achievement of the project’s PDO indicators.                 Table 6.  Achievement of key performance indicator for PDO 1 No.  Indicator  Baseline  Target  Actual  % Achieved 

1.  People  with  access  to  a  basic  package  of health,  nutrition,  or  reproductive  health services 

‐  1,500,000  7,166,077  474.4 

2.  Number of Children fully immunized  ‐  200,000   392,889  196.5 

9 This is a core sector indicator introduced at midterm. It is measured by using three PDO indicators: (i) People with access to a package of health services (new consultations); (ii) Number of children fully vaccinated; and (iii) Number of births attended by qualified personnel.  

Page 24: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 18 of 100

No.  Indicator  Baseline  Target  Actual  % Achieved 

3.  Number  of  births  attended  by  skilled professional 

‐  60,000  310,816  518.0 

4.  New  cases  of  TB  detected  and  treated  in targeted areas 

‐  10,000  14,961  149.6 

5  Direct project beneficiaries  ‐  1,770,000  7,779,897  439.5 

5.1  Of which Female beneficiaries  ‐  885,000  3,766,286  425.6 

  

29. Project level data showed sustained trends (over 2012‐2017 period) in the achievement of the PDO outcome indicators in the four regions (East, Littoral, North West and South West) for which data were  available  (see  annex  1  for  a  summary  of  achievement  of  PDO  indicators  per  year). This  trend  is explained by a sturdy increase in utilization of services in health facilities supported by the project. A total of 12,776,432 beneficiaries received a range of services such as hospitalization, outpatient consultation, normal  delivery,  complicated delivery, minor  surgery, major  surgery  and  cesarean  section  in  the  four original regions. Service delivery increased as well in the three additional northern regions (Adamaoua, North and Far North) with an estimated 1,344,847 people benefiting from the range of services in facilities that served their communities (see annex 3 for a summary table of service delivery utilization indicators).  

 

30. The achievement of objective 1 is also corroborated by findings from end‐of‐project quantitative and  qualitative  impact  evaluations,  which  consisted  of  health  facilities  and  household  surveys.  The quantitative survey, which used difference‐in‐differences regression model methodology10 with a study period of between 2012 and 2015, found an increase in childhood vaccinations and utilization of modern family planning. The study  found  that antenatal  care  in  facilities with  the PBF  intervention performed better than those facilities with only additional supervision. The survey showed positive outcome of full vaccination coverage among children between 12 ‐ 23 months of age in PBF facilities. Mothers or primary caregivers of all children under five years of age were asked about their child’s vaccination history. In the PBF group, there was a 17‐percentage point increase in full vaccination (0.170, p‐value = 0.076).   

31. The  survey  also  observed  increased  health  services  utilization  by  examining  health  facilities registers.  It  showed  that  health  services provision  as  recorded  in  health  facilities  registers depicted  a sturdy trend in utilization over the study period. It assessed the reliability of data by examining the health service  counter‐verification  data  collected  routinely  as  part  of  the  PBF  program  design  through community client satisfaction surveys. The health service verification occurred in all PBF health facilities, as well as in health facilities in control groups C1 (additional financing) and C2 (additional supervision). Figure 2 shows the percentage of patients who were reported by health facilities to the PBF verification teams and confirmed to have received health services at the health facility.  In most quarters of the three‐year study period in all three study regions, over 80 percent of reported patients were confirmed. The trend in confirmed patients increased slightly over time in North‐West and East, with confirmation rates above 85 percent in all three regions during the final year of the study.  Facilities in the full control group had less incentive to keep records of all services provided than facilities in PBF group.  

10 The difference‐in‐differences regression model methodology hinges on a randomized control trials with four groups (T1: PBF with health worker performance bonuses; C1: Same per capita financial resources as PBF but not linked to performance; same supervision and monitoring and managerial autonomy as T1; C2: No additional resources but same supervision and monitoring as PBF arms and T1 and C1; C3: Status quo).  Measure of statistically significance: * = p < 0.10, ** p < 0.05, *** p< 0.01 

Page 25: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 19 of 100

 Figure 2. Percent of reported patients confirmed during verification 

                

Source : Cameroon PBF Quantitative Impact Evaluation Report, March 24, 2017  

32. These findings were corroborated by end‐of‐project qualitative impact evaluation, which found out that providers and patients indicated that PBF interventions increased service utilization because of a change  in  service delivery practices  (i.e.  intensive outreach activities  such as  community  visits,  school visits, the establishment of outreach posts, etc.) of the beneficiary health facilities  in the communities they serve.  The survey further showed that family planning information were integrated in the delivery of  services  such  as  ANC  or  PNC  visits,  and  childhood  vaccination,  which  significantly  sensitized  and informed women of good family planning practices.     The community PBF interventions (e.g.  intensive community level outreach and sensitization program) introduced by the project were the major factors in increased utilization of health services in facilities in the communities in which the beneficiaries reside. (see Annex 7 for a summary methodology and findings of the impact evaluations).   Objective 2: Improve the quality of health services with a focus on health and communicable diseases11  

33. The PDO lacked  indicators to measure quality. As noted earlier,  there was original satisfaction indicator  which was  to measure  the  quality  objective  aspect  of  the  PDO.  But  it  was  dropped  during restructuring because the project team decided to measure satisfaction through impact evaluation. For that  reason,  the  ICR  team mainly  assessed  objective  2 with  findings  from  two  end‐of‐project  impact evaluations  (quantitative  and  qualitative).  The  quantitative  survey  found  significant  improvement  in quality of health services because of project interventions.  The survey also assessed quantity and quality of health supplies, medicines, and equipment in the health facilities, and observed a large and consistent impact on health workers’ satisfaction with the quantity and quality of equipment and other supplies at health facilities.    It also found that both the PBF and the additional financing  interventions resulted in large and highly significant improvements with about 20 percentage point increase in satisfaction with the  quantity  of  equipment  (p<0.05),  a  25‐percentage  point  increase  in  reported  satisfaction with  the 

11 Due to lack of PDO indicators to measure quality, the ICR team mainly used results of end‐of‐project impact evaluation (quantitative and qualitative) and project level data to assess the quality objective. 

83

89

81

9894

86

40

60

80

100

Sept.2012

Dec.2012

Feb.2013

May.2013

Sept.2013

Dec.2013

Mar.2014

Jun.2014

Sept.2014

Dec.2014

Mar.2015

Jun.2015

Per

cen

t (%

)

North-West Est South-West

Page 26: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 20 of 100

quality of equipment (p<0.05), and a 40 percentage point increase in satisfaction with the availability of other supplies at the health facilities within the PBF and additional financing components (p<0.01). The survey’s findings are again buttressed by a key quality intermediate indicator 6: Health facilities achieving an average score of 75% of the quality index of services as measured in RBF in the targeted areas supported the achievement of this objective.   At the end of the project 63.5 percent of health facilities (against a target of 60 percent) achieved an average score of 75 percent of the quality index of services.   

34. Regarding  ANC  services,  the  overall  satisfaction  score  for  ANC  reported  during  facility  exit interviews showed that the PBF group was associated with an 8.6 percentage point increase in satisfaction (p < 0.077). Women’s satisfaction with health facility characteristics significantly increased as well. PBF was associated with a large and statistically significant 24.1‐percentage point difference from the control group (p<0.05) in women’s satisfaction with the health facility cleanliness. Focusing on reported facility cleanliness, women  in  the PBF and  the additional  financing group  (p<0.05) both  reported significantly higher levels of satisfaction than in the pure control group.  Compared to the control group, PBF resulted in a large and statistically significant 15.4‐percentage point increase in satisfaction with the facility’s hours. There  was  also  significant  impact  on  child  health  services  as  PBF  had  a  positive  impact  on  overall satisfaction with child health services. Compared with the pure control group, PBF was associated with a statistically significant 9.9‐percentage point increase in satisfaction (p<0.05).   

35.  The qualitative impact survey supported the findings of the quantitative impact survey.  Majority of respondents noted that structural changes such as availability of equipment, drugs and supplies, human resources and other important inputs, which have direct impact on quality of care in a health facility were the main  factors  that  contributed  to  the  achievement  of  this  outcome.  The  survey  further  sought  to establish  adequacy of  these  important  health  care  inputs  in  the health  facilities  surveyed.  In  the PBF intervention  areas  there  were  significant  increases  in  the  availability  of  the  necessary  equipment, particularly delivery and neonatal care materials.  This enabled health workers to carry out a set of quality checks (vital signs: blood pressure, weight, conjunctiva, hemoglobin, rhesus, urine glucose, uterine size, feel heartbeat and  fetal presentation) of health services provided  in  the  facilities. The evaluation also emphasized better health infrastructure, including rehabilitation, expansion and upgrade of facilities and equipment financed by the health facilities’ management with their PBF subsidies. Most health facilities were fully equipped with generators, autoclave, fridge, laboratory equipment, delivery beds, weighting scales,  bedsheets,  nets,  incinerators,  placenta  pit,  toilets  facilities.  The  facilities  also  benefited  from provision of motorcycles and office equipment such as computers and TV screens for DHMTs.  

 

Justification of Overall Efficacy Rating  

36. The project’s efficacy is rated Substantial as all its outcome objectives were achieved with only minor  shortcomings.  All  the  utilization  indicators’  targets  for  objective  1  were  fully  achieved  and surpassed.  There is also noteworthy evidence from the end‐of‐project impact evaluations (quantitative and qualitative), including project level data that supported the achievement of both objective 1 (increase utilization of health services) and objective 2 (improve quality of health services).  

    

Page 27: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 21 of 100

C. EFFICIENCY  

Assessment of Efficiency and Rating 

37. Cost  effectiveness  analysis.  To  assess  efficiency  of  project  interventions  a  cost  effectiveness analysis  was  conducted  as  part  of  project  closure.  The  results  of  the  analysis  showed  a  US$401.99 incremental  cost effectiveness  ratio  (ICER), estimated  from available service delivery costs and output data at health facility  level. Using the World Health Organization (WHO) standard for interpreting cost effectiveness analysis results (ICER = $/DALY averted < GDP per capita is very cost effective) the project was cost efficient as  the estimated  ICER ($401.99)  is  less  than Cameroon’s per GDP of $1,374.5  (WDI, 2016). It must be noted that cost effectiveness analysis was not conducted at appraisal; and so, the ICR team could not compare the results (ICER) with any appraisal estimates.  

 

38. Operational  /implementation  efficiency.  The  project  encountered  considerable  delays  (almost three  years  after  project  effectiveness)  due  to  the weaknesses  in  the  institutional  arrangements  for implementing the service delivery (PBF) component of the project. But this was corrected through project restructuring and extensions, including additional financing. The HRITF additional resources supported a scale‐up of project activities in the 26 districts implementing PBF.  Operational efficiency was also assessed by comparing actual project component costs with appraisal estimates. The analysis showed a variance of US$31.4million (Component 1: US$27.5 and Component 2:US$3.9million) at the end of the project. Total project  cost  at  appraisal  amounted  to  US$25  million,  made  up  of  Component  1  (US$20million)  and Component 2(US$5million) respectively. At ICR US$47.5million (237.7 percent of appraisal estimate) and US$8.9million (178.1 percent of appraisal estimate) were spent on components I and 2 respectively.   The high variance was due to additional financing (IDA‐ US$20million and HRITF‐US$20million) provided to support  increased  coverage  and  scale  up  of  project  activities.    As  noted  earlier,  the  IDA  AF  enabled extension of the project to additional 2.2 million target population in the poorest region of the northern part of the country (Adamaoua, North and Far‐North).  The AF improved efficiency as it was pro‐poor and results‐focused.  Available project results data shows that service utilization in the three poorest regions covered by the AF increased significantly with an estimated 1.3million indigents and the poor benefiting from a range of health services, including inpatient and outpatient consultations, minor surgery, normal and complicated delivery, cesarean sections etc.    

39. Efficiency was also enhanced as the project  interventions  led to better management of health 

facilities’  revenues,  reduction  of  parallel  sales  of  drugs,  display  of  costs  of  care  services  on  notices, 

laboratory  examinations,  and  medicines.  The  project  brought  much  more  competition  into  drugs 

purchasing and distribution of drugs and pharmaceuticals. Hitherto, drugs purchasing and distribution 

was highly centralized as it was the sole responsibility of the FSPS.  

 

40. Time overrun/underrun. In terms of timing, PAISS overall performed well, recording 19.5 months from concept to first disbursement compared with Cameroon average (36 months), Africa average (22.6) and Bank average (24 months). Project administrative cost was efficient as it was within the acceptable Bank‐wide practice.  Given the length of the project due to project extensions, the total administrative 

Page 28: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 22 of 100

cost12 of the project is deemed efficient as it is within the Bank’s overall administrative cost of between 5 to 10 percent of total project cost (see Annex 4 for a detailed efficiency analysis). 

 

41. Although  a  comparison  with  the WHO  cost  effectiveness  metric  shows  the  project  was  cost effective, efficiency would have been much stronger if additional comparison could be made with results of similar analysis at appraisal. Given that such an ex‐ante cost effectiveness analysis/cost benefit analysis (traditional efficiency measures) that could have allowed a comparison of end‐of‐project estimate with that of appraisal estimate was not conducted, efficiency is rated modest.

 

D. JUSTIFICATION OF OVERALL OUTCOME RATING 

42. Based  on  the  project’s  high  relevance,  substantial  efficacy  (achievement  of  development objective), and modest efficiency, the overall outcome is rated Moderately Satisfactory.    

 

E. OTHER OUTCOMES AND IMPACTS (IF ANY)  

Gender 

43. The  project  had  significant  impact  on  women.  As  indicated  above,  available  utilization  data showed that of the 7,779,897 total project beneficiaries, 3,766,286 were women, representing 48.4 percent of total project beneficiaries.  This was mainly due to  increased utilization of some key maternal health services such 

as antenatal care (ANC) and postnatal care (PCN).  Available health services utilization data   shows that 1,094,661 pregnant women  utilized  ANC  services  in  facilities which  benefited  from PBF  funding  throughout  the project life.  

Institutional Strengthening 

44. Major  institutional  development  impacts  occurred  at  national  and  subnational  levels.  At  the national level, the project substantially strengthened MoPH’s capacity to develop norms and guidelines for  use  by  operational  level  facilities.  PBF  changed  the  way  business  is  conducted  in  the  Ministry.   Directorates were required to produce their expected outputs before bonuses are paid to them. They signed performance contracts with the MoPH where each directorate is evaluated by two or three other directorates.   Through PBF government has strengthened the budgetary allocation system, whereby  it uses  PBF mechanism  to  pay money  directly  to  health  facilities  through  the  Treasury.    Also,  PBF  has significantly strengthened the MoPH’s management information system.   An information management system‐ District Health Information System (DHIS2)‐  which tracks key performance indicators has been developed and rolled out to districts.   

45.  The project  also  strengthened  the PIU’s  capacity  to manage and provide oversight of project activities. It strengthened its information management system by establishing a cloud‐based information 

12 Although not specified in the OPCS guidelines, the ICR team included the costs of Bank staff who worked on the project from preparation to supervision/ICR to ascertain full cost of project management from both the PIU and Bank side.  

Page 29: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 23 of 100

system  known  as  FBP  Cameroon.  The  system  produces  real  time  information  on  quantitative  and qualitative  indicators  as well  as  financial  data,  published  on  quarterly  basis.    The  software  also  gives instant graphical information on health facility level service delivery indicators, enabling the project team to  interpret  trends  in  the  achievement  of  project  results  for  effective  decision‐making.    To  further strengthen the PIU and make it more operational, it was transformed into a National PBF Technical Unit (CTN), which is responsible for the implementation of the new Health Systems HSPRP.  

 

46. At  the  subnational  level,  the  project  strengthened  the  capacity  of  heads  of  district  health administrations  to  coordinate,  evaluate  and  validate  the  performance  of  health  facilities  under  their supervision.  It strengthened the referral and counter referral systems by improving working collaboration between the health centers [providers of Paquet Minimum d’ Activités (PMA)] and the hospitals [providers of Paquets Complémentaires d’  Activités  (PCA)].  Health  facilities  capacity  to  report  on  their  activities improved  significantly.    The  intermediate  outcome  indicator  7:  Health  facilities  reporting  monthly activities using standard report form in targeted areas provided evidence of institutional impact of the project at facility level. At the end of the project 100 percent of 75 target health facilities reported their activities  using  standard  reporting  form.  The  project  also  improved  transfer  of  funds  and  the  entire financial  management  systems  at  health  facility  level.  The  existing  government’s  card  system  of transferring funds is characterized by delays, making it difficult for the facilities to have funds to undertake small maintenance and replacement of equipment.   With the introduction of PBF, funds could now be transferred directly into the accounts of the beneficiary health facilities. This allowed the facilities to have funds available always, and carry out their routine maintenance and equipment of the facilities. However, facilities suffered  from persistent delays  in payment of subsidies, a situation that need to be urgently addressed if PBF is to fully have development impacts.    

47. The project strengthened the pharmaceutical system by substantially reducing the parallel sales 

of drugs. Overall there is an improvement in financial governance as evidenced in better organization of 

health  facilities  revenues,  reduction  of  parallel  sales  of  drugs,  the  display  of  costs  of  care  services, 

laboratory examinations, and medicines. Despite  these  improvements,  the project could have directly 

upgraded infrastructure in the most disadvantaged facilities and district health administrations. During a 

field  visit  to  Littoral  region,  the  ICR  team  observed  very  limited  space  for  some  District  Health 

Management Team (DHMTs). A case in point is the Bangue, DMHT, which has 42 health facilities under its 

purview, but have very limited office space to carry out its day‐to‐day business. 

 

Mobilizing Private Sector Financing N/A 

 

Poverty Reduction and Shared Prosperity 

48. Poverty impact of the project was substantial. As noted above, through the AF interventions an 

estimated  1,344,847  of  indigents  and  the  vulnerable  population  in  Adamaoua,  North  and  Far  North 

(Yagoua  and Maroua)  benefited  from  a  range  of  services,  including  hospitalization  (one  day),  minor 

surgery,  normal  delivery,  complicated  delivery,  outpatient  consultation, major  surgery,  and  Cesarean 

Page 30: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 24 of 100

section  in  201713.  The  intensive  community  PBF  interventions  (sensitization  and  outreach  campaigns) 

carried out by the project were the main factors that impacted on the utilization practices of this cohort 

of the population. Table 7 provides a summary of key service utilization indicators in the three northern 

regions of the country.  

 

      Table 7. Service utilization by indigent and vulnerable population‐ three Northern Regions (Adamoua, North, 

& Far North) 

 Indicator Adamaoua  North 

Far North (Yagoua) 

Far North (Maroua) 

Total 

2017  2017   2017  2017    2017 

Hospitalization (one day)  111,375  63,258  55,662  144,596 374,891 

Minor Surgery  15101  17516  8437  12673  53,727 

Normal Delivery  14905  11667  6675  12670  45,917 

Complicated delivery  378  238  112  355 1,083 

Outpatient Consultation   251,755  173343  151,634  287,307 864,039 

Major Surgery  1219  471  965  846  3,501 

Cesarean section  730  315  359  285  1,689 

 Total  395,463  266,808  223,844  458,732  1,344,847 

Source: PIU Database 

 

Other Unintended Outcomes and Impacts 

49. Hospital sector reform. Although the tertiary sector interventions were not integrated into project 

design, the project supported implementation of PBF in a major hospital, Hôpital gynéco‐obstétrique et 

Pédiatrique de Yaoundé (HGOPY), Yaoundé through technical assistance.  Having observed PBF’s impact 

on  service  delivery  at  health  facilities  in  project  intervention  areas,  the  hospital management  sought 

support from the Bank to adopt and implement PBF initiatives with their own internally‐generated funds. 

The Bank provided them with PBF experts who trained over 20 managers, including the Chief Executive 

Officer  (CEO).    The  hospital  also  obtained  service  quality  assessment  support  from  the  Bank  through 

Littoral  region’s  ACV.  In  April  2015  PBF  implementation  started  in  three  units  of  the  hospital  and 

progressively extended to all clinical and administrative units.  This led to improved hospital efficiency and  

better management  of  resources:  (i)  an  increase  in  bed  occupancy  rate,  (ii)  improved  diagnostic  and 

treatment  capacity;  (iii)  an  increase  in  internally  generated  revenues;  (iv)    a  reduction  in  unjustified 

expenses; (v) a reduction in informal and under the table payments to staff; (vi) an improved quality of 

13 It must be noted that activities in the three northern regions were mainly implemented in 2017 due to insecurity issues and 

long procurement process of recruiting NGOs to establish performance purchasing agency for the project. 

  

Page 31: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 25 of 100

care;  (vii)  an  improved staff performance: punctuality,  team spirit  and  technical  competence; and  (ix) 

better remuneration for staff (Annex 6 for a summary of achievements). 

III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME  

A. KEY FACTORS DURING PREPARATION  

Design  

50. The project was designed as a SWAp intended to support implementation of the government’s health sector strategy. Project preparation  fully  involved key stakeholders  from both government and development partners. The MoPH and Ministry of Finance (MoF), and Ministry of Economy and Planning (MoEP),  were  the  key  government  institutions  involved  in  project  preparation.  Major  development partners involved in the preparation were AFD, KfW, World Bank (WB) and Health Organization (WHO).  

 

51. Key designed features include:  

 

Sound  background  analysis.  As  a  prerequisite  to  project  design,  the  Bank  team supported  studies  on  governance,  fiscal  space  analysis,  and  M&E  capacity assessment. These studies provided adequate background information as input into the project  design.  For  example,  a  Bank  financed  study  conducted  revealed  three major governance issues that inhibited sector performance. They include: (a) informal or under the table payments which place a disproportionate burden on poor patients; (b)  irregular  procurement  practices,  sale  of  illicit  drugs,  and  over‐billing  which translated into higher prices for patients; and (c) excessive focus on controls and lack of  transparent  management  of  human  resources,  coupled  with  low  salary  levels, which  led  to  lack  of  commitment  to  work,  particularly  at  facility  level.  The  study recommended  performance‐based  contracting/financing  approach  to  paying providers for results. This formed the basis for the design of the PBF interventions. The fiscal space analysis study outlined poor  linkage between health spending and disease burden. The M&E capacity assessment identified limited data management and analytic capacity of MoPH, including issues related to data collection processes, which were largely paper‐based.  

 

A novel  design  that  focused on performance.  The design was  simple with  clearly stated two components focusing on service delivery and institutional strengthening.  The design incorporated performance‐based financing initiatives, which established contractual  agreements  between  the  various  actors,  at  all  levels,  proven  to  be effective in other countries, in Africa, particularly Rwanda.  In particular, the design integrated  an  important  tool  (internal  performance  contracts)  for  central departments/directorates within MoPH to improve governance and stewardship in the central MoPH departments/directorates, whereby a directorate is evaluated by two or three other directorates.  

 

Page 32: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 26 of 100

Akin to the above is the Community PBF initiative introduced by the project. Under this  initiative,  local  communities  were  involved  in  preparation  of  health  facilities’ business plans and participating in community campaigns and sensitization programs. This  initiative also empowered Local Associations (ALSOs)14 to serve as interface of the health  system between  local  beneficiary population and healthcare providers. Their main functions were to (i) inform the population of a range of health services available  in  the health  facilities,  and encourage  them to  seek healthcare  in health facilities their communities; and (ii) identify community needs for health and inform health care providers appropriately.  

 

Results  Framework.  The  results  framework  was  logically  formulated  with  both intermediate and outcome indicators linked to the PDO. The PDO was realistic with clearly defined two outcome objectives (increased utilization of health services and improved  quality  of  health  services).  However,  PDO  level  indicators disproportionately  favored  the  utilization  outcome  objective.  Only  one  indicator (percentage of patients reporting satisfaction with health services) was a measure of quality  outcome  objective  of  the  PDO.  As  noted  above,  the  project  team  later dropped  this  indicator  because  they  decided  to measure  satisfaction  through  the conduct of impact evaluation.  

 

Project risks. Project risks at appraisal was overall rated moderate. The project team appropriately  identified key  risks  that  could potentially affect  implementation and outcome and outlined mitigation measures to address them. Prominent among the risks and their mitigation measures were:  (i)  the risks that fiscal  imbalances   could increase the country’s indebtedness and arrears (this risk was mitigated by increasing non‐oil  revenues,  reforming  inefficient  public  enterprises,  and  increasing effectiveness of public finance; (ii) poor planning of procurement operations leads to an increase in costs and delays in procuring goods and services (this risk was mitigated by    Bank‐supported  reforms  aimed  at  securing  sustainable  funding  for  improving national  procurement  systems  and  expenditure  management);  and  (iii)  informal payments to providers, lack of transparent management of personnel, and controls that slow down implementation (this risk was mitigated by introducing performance‐based contracting/financing initiative to enhance accountability and results). 

 

Lessons  learned  from  previous  project.  The  preparation  team  included  lessons learned from the previous health project into the design. They were: (i) adoption of a simplified  design;  (ii)  involvement  of  local  stakeholders;  (iii)  setting  of  realistic objectives  and  targets;  (iv)  establishment  of  systems  for  measuring  results;  (v) ensuring that  implementation and  institutional arrangements are  in place; and (vi) providing close supervision and involving Bank management. 

 

14 ASLOs signed a performance contract with PAAs and must produce a quarterly activity report and submit it to the PAA. 

 

Page 33: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 27 of 100

Strong  Government  Commitment.  Government  commitment  to  supporting  the implementation of the project was high. It demonstrated commitment by sending a team of four to study the PBF initiative in Rwanda.   The government team worked closely with the Bank team and the other DPs to complete a successful project design.  

 

B. KEY FACTORS DURING IMPLEMENTATION  

52. The project was approved by the Board on June 24, 2008 and became effective on March 3, 2009.  The delay  in  effectiveness was mainly  due  to  delay  in  fulfilment  of  three  effectiveness  conditions:  (i) adoption of an operations manual; (ii) establishment of operational unit;  (ii) recruitment of a program manager  (focal  point),  a  procurement  specialist,  an  accountant  and  an  internal  auditor,  and;  (iii) preparation of terms of reference for the recruitment of an external audit firm. After the initial delays (see para 46 below) project implementation commenced in earnest, and was aided by the following factors:  

(a) Factors subject to government and/or implementing entities control  

53. Government commitment. The GoC fulfilled its commitment to finance part of the costs of PBF subsidies,  including  the  operational  costs  of  the  Performance  Purchasing Agency  (PPA)  in  the  Littoral region and successfully paid US$1.6 million as part of its counterpart contribution. To further strengthen its commitment, MoPH budgeted about US$2 million for the PBF operations in the Littoral region in 2014. Specifically, the Ministry covered all output costs (i.e. purchasing of services from contracted facilities). This commitment was a good example of the momentum and buy‐in that PBF is gaining in Cameroon. The project also benefited from dedicated support from both the Minister of Public Health and the Head of the Project Steering Committee (PSC) who was respected among health professionals at operational and regional levels.  The Littoral regional government also played very effective role at the outset of project implementation by writing to continue with the Bank after the Germans and the French pulled out from the SWAp.  

 

54. Project management commitment.  Despite the limited staff, the PIU staff were committed and worked around the clock to ensure smooth implementation of activities. The project coordinator was an asset to the project as he was among the first beneficiaries of the PBF training in Rwanda. He effectively coordinated activities with different stakeholders at national, regional and district level.  

 

55. Results‐oriented  initiative  introduced by PBF enticed all  actors and  stakeholders  to  commit  to results. Through contracting agreements between the various actors involved in implementation, every actor’s performance was evaluated by a superior actor and that drove everyone to focus on performance. For  example,  CTN’s  performance  was  evaluated  by  MoPH.  At  the  regional  level,  CTN  evaluates  the performance  of  Agence  de  Control  et  de  Verification  (ACV),  the  Délégation  Régionale de  la  santé/ /Regional Health Delegation(RHD), and Fond Régionale  de la Promotion de la Santé (FRPS)/Regional Fund for Health Promotion(RFHP).   The RHD evaluates  the performance of  the District Health Management team (DHMTs), who in turn evaluates the performance of the health facilities. In addition, CTN conducts random verification of selected health facilities. This result‐driven approach was key to the success of the project. 

 

Page 34: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 28 of 100

56. Despite these positive factors, the project encountered considerable challenges due mainly to the following factors: 

57. Institutional  set  up.  The  project  suffered  from  institutional  constraints,  which  inhibited implementation for almost three years after project effectiveness. This was mainly due to the weaknesses in the institutional arrangement for implementing the service delivery (PBF) component of the project. The  plan  for  implementing  PBF  was  (i)  contracting  of  services  between  the  central  MoPH  and  the intermediate agencies, FSPS in costal, southwestern and northwest regions; and (ii) contracting of services between FSPS and the district health service delivery  facilities. The project documents did not  include detailed technical requirements as well as mechanisms for implementing PBF. In addition, the FSPS, did not have adequate autonomy to operate on their own independently from the health facilities. Except for Littoral region, the two original FSPS of South west and North West had limited capacity to design and implement PBF interventions.   Project implementation, therefore, stalled as these technical requirements were not adequately considered in the original project documents.  To address these issues, the Bank and the government agreed to restructure the project by (i) granting exceptional status to Littoral Regional Special Fund for Health Promotion (LRSFHP), creating a Performance Purchasing Agency (PPA) housed in LRSFHP,  and  (ii)  contracting  experienced  institutions  to  help  design  and  implement  PBF,  and  transfer capacity to implement PBF to the three regional FSPS. As noted, the project was restructured in July 2010, and a PPA was established in the Littoral Region, and the hiring process for experienced institutions to develop PBF in the other three regions was launched. However, the process stagnated due to a lengthy procurement process. It took almost two years before the process was completed.  

 

58. Delays in payment of PBF subsidies to health facilities. There was reportedly a delay in payment of PBF  subsidies  to health  facilities.  This problem persisted  throughout  the project’s  life. The delay  in payment of subsidies to health facilities was mainly caused by accumulation of arrears because of a pile up of invoices at the national level.  Two main factors accounted for this situation. First, funds from the initial  IDA credit was exhausted  in 2014. And to avoid  interruption of  implementation of activities the government requested for additional financing. The AF process, which started in March 2014 took nine months to complete.  Second, in 2016 funds from IDA credit were used to finance trust fund activities in the project areas.  But the provisions in the financing agreement did not require such practices. A project restructuring (see section B above) to remove the clause was initiated. Unfortunately, the restructuring took seven months to complete.  These situations led to a pile up of invoices coming from the field, and given the limited staff (only three people) at the PIU arrears built up.   The ICR team found out that in Bangue Health District in Douala, they are awaiting payment of arrears of the past five quarters.  

59. Limited facility autonomy.  Facility autonomy was regarded as the cornerstone of PBF’s theory 

of  change.    But  national  policies  limited  the  facilities’  ability  to:  (i)  make  independent  decisions;  (ii) operationalize  their  business  plans,  and  (iii) manage  their  entire  resources  and  staff.   Health  services providers and managers  repeatedly mentioned  lack of  autonomy  in making decisions due  to  conflicts between  the  PBF  practices  and  the  existing  laws  and  regulations,  particularly  issues  regarding management of funds and hiring of staff. These issues created tension and frustration for providers who decided to take no autonomous decisions at all, or take only some decisions, but with caution.   However, with the adoption of  loi de GIP15 in 2010, this problem was resolved.   

15 A law that provides territorial autonomy to public institutions and persons 

Page 35: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 29 of 100

 

60. Turnover  of  health  workers  at  facility  level.  There  is  reportedly  high  turnover  of  health professionals at  facility  level.   ACV and,  indeed, heads of district health management  teams  lamented about this situation.  After providing training to health workers, ACV finds new people all together when conducting next rounds of verification missions. This leads to retraining and continuous training. While this could be attributed to overall human resources for health issue, the delays in payment of subsidies to health facilities, in a large part, contributed to this situation.   

(b) Factors subject to World Bank control 

61. Adequacy of project supervision. The Bank supervision team consistently supervised the project. On average, supervision missions were undertaken every two months. During such missions,  the Bank team proactively work with project team to address implementation challenges. For example, although it took nearly two years to resolve, the Bank team eventually resolved the institutional arrangement issue that inhibited implementation through restructuring. 

 

62. Adequacy  of  reporting.  All  supervision  missions  were  adequately  reported  with  over  21  aid‐memoires and ISRs produced and documented. There was relatively low turnover of TTLs (three TTLs), which facilitated project reporting.  The mid‐term review (MTR) conducted by the Bank further enhanced stakeholders understanding of PBF initiatives. Organized in a participatory manner, the MTR provided the opportunity  for  implementing partners at all  levels  to present updates of project  implementation and discuss  overall  project  progress  and  its  associated  issues with  the Bank  team.  Implementing partners presented updates of their activities, which revealed interesting findings: (i) motivated health workers (ii) improved community voices, (iii) clean and better managed hospitals and health facilities; (iv) enhanced beneficiaries  understanding  of  the  PBF;  (v)  strong  relationship  between  health  facilities  and  the beneficiaries most of whom did not know that they could be cared for free of charge under the PBF.    

63. Additional  financing.  The  AF  provided  by  the  Bank  significantly  boosted  implementation.  To improve  project  implementation  and  increase  health  services  utilization  at  community  level,  the  AF introduced a Community PBF activities in the northern regions of the country. The aim was to improve health‐seeking behavior and geographical access to preventative and curative health services. Through the AF,  the project  introduced mechanisms  to  improve  the poor and vulnerable households’  financial access  to  essential  health  services  at  community  and  health  facility  level.  Prominent  among  the mechanisms were the establishment of exemptions systems for the poor to cover health services provided at  the  community  and  health  facility  levels  as  well  as  fee‐waivers  for  certain  essential  services  for vulnerable households. To mitigate against revenue shortfalls for health facilities, health facilities were reimbursed for services provided free of charge to vulnerable households.   

(c) Factors outside the control of government and/or implementing agency 

 

64. Security situation in Northern Cameroon.  Boko Haram operations in the project intervention areas in  the  northern  regions  hampered  the  project  team’s  ability  to  conduct  regular  field  supervision  and preparation  activities. The  scale‐up of  project  activities  to  the  north was  adversely  affected by  cross‐border  violence  from  Boko  Haram  in  several  health  districts  covered  by  the  project.  This  situation prevented the project team to conduct regular missions to the region.   

Page 36: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 30 of 100

 

65. Reluctance of health facility staff.  Most of health facility staff members were initially reluctant to implement PBF program, and, did not believe they could receive monetary bonuses.  Moreover, health facility workers were  hesitant  to  accept  the  drastic work‐style  changes  required  by  the  PBF  program before  receiving  payments  for  their  performance.  But,  with  the  initial  payment  of  bonuses,  as  well enhanced education, most of them became motivated and committed to implementing PBF interventions.   

IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME  

A. QUALITY OF MONITORING AND EVALUATION (M&E)  

M&E Design 

66. The M&E design included expected outcomes that measured progress towards the achievement of the PDO. The PDO was succinct in that it focused primarily on two main outcomes (increased utilization of health services and improve quality of health services). Although, the PDO indicators covered the two outcomes, they were largely utilization indicators. As noted, only one PDO indicator was a measure of quality.  The design included a provision for reviewing and revising project indicators and target values as and when required.  It also envisaged institutionalization of a system to improve availability, reliability, and timeliness of routine health services information system, including alignment to national processes; harmonization  of  approaches  to  performance  assessment;  capacity  building  and  health  information system strengthening; and systematic quality improvement. The design incorporated performance‐based contracting/financing whose impact was to be measured by impact evaluations (baseline, mid‐term, and end line). 

 

M&E Implementation  

67. M&E  implementation  was  largely  carried  out  through  three  rounds  of  impact  evaluations (baseline, mid‐term, and end‐line).  Although planned to be conducted earlier, the baseline survey was not conducted until 2011 due mainly to delay in project implementation. To ascertain evidence of project impact on beneficiaries, a mid‐line  (qualitative) and end‐line  (qualitative and quantitative) evaluations were  also  conducted.  The  quantitative  impact  evaluation  used  rigorous  and  randomized  sampling techniques to measure project  impacts at both household and health facility  levels. The approach was mainly a regression model that uses difference‐in‐differences to assess the project’s impact.  The end‐line qualitative  impact  evaluation, which  sought  to  further  deepen  the  results  of  the  quantitative  impact evaluation provided evidence of perspectives of health authorities at central, regional and district levels, health workers, and patients and beneficiary communities.  

 

68. At the project level, data management was not the best. Although the project established a portal in which project results are entered, data was not adequately and systematically documented. Routine data collection and systematic monitoring of indicators facilitated by ACV were largely and systematically carried  out  at  regional  and  local  levels.  However,  at  the  national  level,  data were  not  systematically aggregated and consolidated.   At  the  time of  ICR, M&E consolidated report  from the regions was not 

Page 37: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 31 of 100

readily available.   The ICR team also observed data gaps at the national level. There is a need to improve M&E data management capacity at project level.  

 

69. As part of M&E implementation the Bank and the project team conducted an MTR in May 2013.  The MTR aimed at reviewing implementation progress after the project was restructured in July 2010. The MTR  identified  the  following  issues:  (i)  lack of a national  technical unit  to guide PBF policy;  (ii) health facility  autonomy;  (iii)  delays  in  payment  of  PBF  subsidies;  (iv)  absence  of  a  centralized  routine  data collection and management system etc. The team worked with the project team to outline key actions that needed to be taken to address the issues.   

 

70. The indicators in the results framework were consistently reported in the ISRs. Overall, 21 ISRs were produced throughout the project life. As noted, the M&E design envisaged a revision to indicators and targets. This initial requirement was consistently followed through by the Bank and the project team that  revised  the  indicators  and  their  unit  of  measurements.    While  this  action  ensured  the  project remained focused towards the achievement of the PDO, it resulted in a complete overhaul of the PDO indicators which  ultimately  tended  to measure  only  the objective  1  (i.e.  increase  utilization  of  health services) of the PDO.  As noted, the team decided to drop the satisfaction indicator as they would use impact evaluation to measure the quality.    Therefore, the ICR team relied largely on the end‐of‐project impact evaluation to assess the quality objective. Despite this shortcoming, the M&E data collected were overall deemed reliable. The PBF requirement ensured data was consistently collected and verified by independent experts. At  the project  level about 26  indicators were monitored and collected at health facility  level on monthly basis.   These indicators were used as  inputs  into the determination of results framework indicators’ values.  

 

M&E Utilization 

71. M&E data, mainly in the form of regular supervision reports, were used to inform decision‐making at all levels of the project. The MTR, which was organized in a big workshop outside Yaoundé, provided the opportunity for program managers at national and regional levels to present and share their results and experiences with stakeholders.  Various presentations of specific thematic areas were made. This was followed by discussion of  issues  and how  to  address  them.  In  addition,  findings  from  the PBF  impact evaluations were  officially  disseminated  through  a workshop  attended  by  the Minister  of Health  and stakeholders, including   development partners in the sector.  

 

Justification of Overall Rating of Quality of M&E  

72. The M&E design was appropriate as it included impact evaluation to measure projects outcome. During  implementation,  the  Bank  and  the  project  team  used MTR  as  an  intervention  to  identify  and address implementation challenges. M&E information, including impact evaluation findings were used to inform decision‐making. However, there was inconsistency in routine data collection, and revisions to the results framework tended to favor only one aspect of the PDO.    The overall M&E is rated modest. 

 

B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE  

Page 38: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 32 of 100

73. Safeguards.  The  project  fully  complied with  the  Bank’s  safeguards  policies  and  procedures  at appraisal. It was classified as category B and triggered two safeguard policies: Environmental (OP 4.01) and Indigenous People (OP 4.10).  An environmental assessment conducted at appraisal, found significant concerns about management of medical waste in most health facilities across the country.  To address the issues  and  mitigate  any  potential  risk  associated  with  disposal  of  medical  wastes,  the  government prepared and disclosed a Medical Waste Management Plan (MWMP) and Indigenous People Plan (IPP), but its implementation was never documented.  The plans were updated in 2016, but again issues around its implementation were not documented.    Fiduciary Compliance   

74. Financial  management.    Overall,  the  project  operated  a  sound  financial  management  (FM) system, buttressed by strong PBF mechanisms.  PAISS complied with the Bank’s FM operational policies and  procedures  (OP/BP  10.02).    The  project’s  FM  team  consistently  submitted  Interim  Financial Management Repots (IFR), but overall not always on time.  At the time of ICR, the 2016 audit report had been  submitted  with  qualified  opinion,  but  its  recommendations  had  not  been  implemented.    The recruitment of the external auditor for fiscal year 2017 was ongoing at the time of ICR, and is expected to be  completed by May 31,  2018.   Despite  a  good  disbursement  rate  at  project  closure,  the  fund  flow mechanism  did  not  completely  work  well  throughout  the  implementation  period  as  the  project  did experience, sat some point in time, inactive Designated Accounts (DA) situation for more than 6 months.  

75. Despite  complying  with  FM  policies,  there  were  significant  issues  associated  with  FM implementation. At project closure, the project had accumulated a total debt of US$7.0 million. This was mainly due to lack of routine contract management at project level. At the last FM supervision mission, the project team requested for the debt to be paid with funds from the new HSPRP.  The Bank FM team asked the project team to submit a detailed report on the debt situation to see what could be paid through PAISS and the new project.  However, the report was only submitted recently, but did not cover the whole project commitment. As a result, no action had been taken at the time of ICR mission. Other FM related issues include a fraudulent payment made by the National Payment Agency (CAA) and ineligible expenses (see annex 3) identified following an in‐depth FM review conducted by the FM team. The FM performance, following the review, was rated moderately unsatisfactory. 

 

76. Procurement. The project also complied with  the Bank’s procurement policies and procedures (OP/BP 11.00). At  its  inception, the project team prepared an 18‐month procurement plan, which was consistently updated to consider new activities that emerged during project implementation.  However, procurement was rated moderately satisfactory for most parts of project implementation due to issues such as weak procurement capacity, weak coordination among the PIU staff, delays in preparing terms of reference (TORs) and inadequate technical specification at the beneficiaries’ level.  The situation improved progressively as  the Bank closely monitored procurement activities and organized procurement clinics and trainings to improve the capacity of the procurement staff. The staff were also trained in the new Bank STEP system, and have started using the system. 

 

77. Disbursement.  Disbursement  was  overall  satisfactory.  At  ICR,  the  project  had  disbursed  96.4 percent of project funds. 

 

Page 39: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 33 of 100

C. BANK PERFORMANCE  

Quality at Entry 

78. As noted in section III, the Bank team effectively led the preparation process by bringing together major development partners to participate in the project preparation.  With funding from Japan’s Policy and  Human  Resources  Development  (PHRD)  grants,  the  Bank  facilitated  key  sector  studies  and assessments, which provided substantial background information for the project design. The Bank team also worked with the project team to incorporate lessons learned from previous project into the design. Together with the project team, the Bank appropriately identified project risks and developed measures to mitigate them. Regarding capacity building, the Bank sponsored two key project staff to a PBF workshop in Rwanda.  This enhanced the project team’s understanding of PBF mechanisms. The project components were  reasonably  developed  and  linked  to  the  achievement  of  the  PDO.   However,  the  PDO outcome indicators as stated in the results framework were disproportionately skewed toward measurement of the utilization of health services objective.    

Quality of Supervision 

79. The project did not suffer extended period for replacement of TTLs. Although there were three TTLs during the life of the project, the second and third TTLs who took over project management were all part of the project team.  Project supervision received impetus as the second TTL resided in the country.  The presence of the TTL at the country level, ensured smooth supervision and prompt resolution of project issues with both the PIU and the government. The ICR team’s investigation revealed that the government was  satisfied  with  the  proactiveness  of  TTLs  in  resolving  implementation  issues  with  them.      Bank performance was also manifested by the extent to which the Bank team carried out and maintained policy dialogue at the highest level of government. The team worked with International Monetary Fund (IMF) and the Country Management Unit (CMU) to trigger PBF mechanisms in the country’s Development Policy Operation (DPO).  This greatly helped push the PBF initiative at the higher level of government and that enticed Ministry of Finance to commit to supporting its implementation. 

 

80. The  Bank was  proactive  in  undertaking  supervision missions, which  enabled  it  to  resolve  key implementation  issues with  the government. As noted,  the Bank  team carried out an average of  two supervision missions per year. The team adequately documented supervision reports, such as ISRs, back‐to‐office‐reports, aide‐memoires, etc.  In all, over 21 ISRs were prepared and documented. Together with the project team, the Bank appropriately addressed implementation issues, particularly those that related to fiduciary. The Bank, however, did not see through implementation of safeguard activities even though two plans were prepared and updated.  At the end of project, no documented assessment of safeguard issues could be found at project level. The Bank provided regular procurement and FM support to staff on daily basis, the procurement and FM team were always willing and ready to help.   However, the Bank should have integrated flexible clauses in the legal agreement to allow easy transfer of funds from IDA designated account to trust fund account and vice versa. 

 

81.  As noted, the team identified difficulty in measuring project indicators and revised the indicators accordingly,  but  decided  to  drop  the  satisfaction  indicator  that  would measure  the  PDO  objective  2 (improve quality of health services) and used impact evaluation to measure quality.   At the end of the 

Page 40: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 34 of 100

project,  all  the  revised  PDO  indicators  could  only  be  used  to measure  the  PDO  objective  1  (increase utilization of health services).  While this was a shortcoming it was compensated by end‐of‐project impact evaluation whose findings allowed the ICR team to assess the achievement of PDO outcome 2.    

Justification of Overall Rating of Bank Performance  

82. Based  on  the  above  discussion,  the  overall  Bank  performance  is  rated  satisfactory.  The  Bank effectively guided project preparation and supervisions. At the design stage, the Bank ensured quality at entry by financing key background studies, which served as the basis for the project design. Whenever there  were  implementation  challenges,  the  Bank  worked  with  the  project  team  and  government  to address the challenges through projects restructuring and MTR.  The Bank ensured that there was no gap in TTL replacement, effectively guaranteed flow of project supervision, and avoided long learning curve for new TTLs.   

 

D. RISK TO DEVELOPMENT OUTCOME  

83. Major  risk  to  development  outcomes  is  financial  risk.  Through  PBF  interventions,  the  project financed  subsidies  to  health  facilities.  The  subsidies  enabled  the  facilities  to  undertake maintenance, renovation and equipment as well as paying bonuses to staff as motivation. However, transfer of subsidies to health facilities were characterized by delays over the life of the project. The delays led to accumulation of arrears in payment to health facilities.  This situation poses significant risk to development outcomes as it will stifle the health facilities from having the financial wherewithal to deliver quality health services to the population they serve. It will also affect the health facilities ability to improve their infrastructure and equipment, and address the issue of rampant turnover of health workers.  To address the issue of payment delays, in the HSPRP, all payments will be made electronically through PBF portal at the national level.    

84. Despite the above risk, the project  is deemed sustainable as a number of policy  initiatives are being implemented: (i) through DPO the government has fully taken ownership of moving PBF forward by allocating 15 percent of operating budget to support PBF implementation in regional and district health facilities, decentralizing the investment budget, and empowering the RFHPs to procure pharmaceutical products from accredited wholesalers (public or private) through simplified procedures. The DPO include key triggers that must be met by the government; (ii) a joint circular for modalities for managing regional and  districts  public  health  facilities’  financial  resources,  using  PBF  mechanism  has  been  signed  by Ministers of Health and Finance. The circular has been distributed to   facilities at all levels of the health system; and (iii) GFF  investment case has been  launched allowing  IDA funds to be match by GFF trust funds (See annex 6 for a summary of key reforms and initiatives). There is also ongoing follow‐on operation (HSPRP) which has scaled up PBF to the entire country.   

  

 

Page 41: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 35 of 100

V. LESSONS AND RECOMMENDATIONS  

Lessons Learned 

85. The following are key lessons learned: 

 

Obtaining the government’s buy‐in and support, including health officials and health facility managers  is essential  in motivating health workers, particularly at the outset of  the PBF program and prior to receipt of PBF subsidies. The level of commitment demonstrated by health officials at all levels of government was key to the success of PBF implementation.  

Empowering  districts,  communities  and  health  facility  level  management  improves transparency  and  accountability.    PBF  strengthened  the  managerial  capacities  of  health facility  administrators  by  enhancing  the  culture  of  work  through  transparency  and accountability.  

 

Ensuring that there is uninterrupted payment of PBF subsidies to health facilities is essential in motivating health personnel and improving health felicities’ operating environment.  PBF revolutionized the way business is done in the Cameroon’s health sector. But it was bedeviled by arrears in payment of subsidies, which led to lengthy delays in payments.   

 

Harmonizing provisions of financing agreements of IDA credit and trust funds is essential for ensuring uninterrupted implementation of activities.  The additional financing from IDA credit  and  HRITF  brought  significant  resources  to  support  project  implementation.  But differences  in  legal  and  financial  covenants  caused  considerable  delay  in  project implementation, including transfer of subsidies to health facilities. 

 

Empowering  key  stakeholders  (government,  health  facility,  and  community)  through  a results‐focused contractual agreement improves collaboration and working relation among them.    Through  PBF  interventions,  the  project  strengthened  the  existing  ties  between regional and district supervisory teams with health facilities, and between health facilities and the  communities  they  serve.  The  reporting  requirements  of  the  PBF  program  compelled stakeholders to collaborate more cohesively, as opposed to working as separate independent entities within a larger system.  

 

Supporting  and  providing  the  health  facilities  with  the  requisite  resources  improves transparency  and  accountability.  PBF  has  improved  governance  at  health  facility  levels through better management of revenues, improvement in the pharmaceutical subsector by reducing parallel  sales of drugs, displaying costs of care services,  laboratory examinations, and medicines. 

 

Establishing a strong M&E systems and mechanisms with competent and adequate staff is essential  for  effective  M&E  implementation.  Although  the  project  achieved  remarkable results, systematic and consistent M&E data collection, consolidation, and reporting was still a challenge at the national level. 

Page 42: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 36 of 100

 

Involving higher level of government, particularly the Ministry of Finance, at the outset of discussion of PBF  implementation could  lead to a significant policy development  impact. Through development policy operation, PBF has now been institutionalized  in the national budget with a budget line item.  

 

 Integrating  hospital  sector  interventions  in  the  design  of  future  PBF  project  could  help transform the operations of hospitals and improve efficiency  in service delivery. PBF has proven to be an effective tool for hospital sector reforms.   Although not  included in PAISS design, Hôpital  gynéco‐obstétrique  et  Pédiatrique de  Yaoundé has demonstrated  that  PBF could be used to improve efficiency and management of hospitals.  

  Recommendations 

  86. Based on the above lessons the following recommendations are proposed:  

The  government  should  continue  its  commitment  to  sustain  PBF  in  Cameroon.  This  will require  allocating  uninterrupted  sufficient  financial  resources  for  implementation  of  PBF interventions at health facility level.  

 

The health authorities should integrate sustainable managerial training programs for district and  health  facility  administers.  This  will  require,  among  others,  providing  them with  the requisite financial and material resources to carry out the training programs. 

 

To ensure timely transfer of  funds to health facilities,  future projects need to  improve the overall financial management systems and practices and ensure that FM units are adequately staff to carry out their day‐to‐day activities. The move to electronic system of payment under the new HSPRP is in the right direction.  

 

To  avoid  undue  delays  resulting  from  rigidities  of  provisions  in  IDA  and  trust  fund  legal agreements,  future projects should harmonize and  integrate provisions  that would ensure flexibility of transfer of funds between the IDA and Trust Fund accounts.  

 

The government needs  to make  the PBF program pro‐poor by appropriately  targeting  the poor and providing demand‐side interventions as well. 

 

Government  should  strengthen  health  facility  level  governance  by  continuously  providing them with the resources and materials for effective operations of their day‐to‐day activities.   

 

To  improve M&E  implementation,  future  projects  should  establish  a  strong M&E  system staffed with requisite and competent personnel. 

 

The Bank should consider and incorporate hospital sector interventions in future PBF design with significant funding support in both investment and technical assistance.  . 

Page 43: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 37 of 100

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS 

 

        

RESULTS INDICATORS  A.1 PDO Indicators       

  

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

People with access to a basic package of health, nutrition, or reproductive health services (number) 

Number  0.00  1500000.00  1500000.00  7116077.00 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017 

 

Comments (achievements against targets): 474.4% of the target people had access to basic package of essential services. 

     

  

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Children immunized  Text  0  0  200,000  392,889 

Page 44: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 38 of 100

 

(number)    31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): 196.5% of the target children fully immunized 

     

  

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of births attended by skilled professional in targeted areas 

Text  0  0  60,000  310,816 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): 518 % of the target number of births were attended to by skilled professional 

     

  

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

New cases of  TB detected and treated in targeted areas 

Number  0.00  0.00  10000.00  14916.00 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): 149.6% of the target new cases of TB in the target areas were  detected and treated 

     

  

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Page 45: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 39 of 100

 

Direct project beneficiaries  Number  0.00  0.00  1770000.00  7779897.00 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017  

Female beneficiaries  Percentage  0.00  0.00  885000.00  3766268.00 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017  

 

Comments (achievements against targets): Over 7.8 million (439.5% of target) people benefited from project intervention. 

  

 A.2 Intermediate Results Indicators      

 Component: District  Service Delivery 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Pregnant women receiving antenatal care during a visit to a health provider (number) 

Number  0.00  0.00  200000.00  1105937.00 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017 

 

Comments (achievements against targets): Comment: 117% ‐ End of project target is surpassed ‐Source: reports from health centers. Verified by PPA verification process. 

     

 Unlinked Indicators 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Page 46: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 40 of 100

 

New acceptors of modern contraceptive methods in targeted areas 

Number  0.00  0.00  40000.00  556458.00 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): 56% of end of project target is achieved ‐ Source: reports from health centers. Verified by PPA verification teams 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Children by the first anniversary who have received one dose of Vit. A in the last six months in targeted areas 

Number  0.00  0.00  200000.00  525746.00 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017 

 

Comments (achievements against targets): 212.0% of target children received one dose of Vit. A in the last six 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Tuberculosis treatment success rate in targeted areas 

Text  0  0  80%  80.36 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): 80.36 % success rate in targeted areas achieved 

   

Indicator Name  Unit of Measure  Baseline  Original Target  Formally Revised   Actual Achieved at 

Page 47: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 41 of 100

 Target  Completion 

Tracer drugs available in targeted health facilities on the day of the visit 

Percentage  0.00  0.00  75.00  20.97 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017  

Comments (achievements against targets): Comment: 45% of  health facilities have 100% of tracer drugs available the day of the last visit, over 382 total number of PBF health facilities. Source: reports from PPAs 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Health facilities achieving an average score of  75% of the  quality index of services as measured in RBF in the targeted areas 

Percentage  0.00  0.00  60.00  61.47 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017 

 

Comments (achievements against targets): Comment: 75 % for a target of 72.8% ‐ There are 286 health facilities using the standard report form from a total of 393 involved in the reporting facilities. Source: reports from PPAs 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Health facilities reporting monthly activities using standard report form in targeted areas 

Number  0.00  0.00  75.00  75.00 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017 

 

Comments (achievements against targets): Comment: All the 75 target health facilities reported their monthly activities using standard report form 

Page 48: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 42 of 100

    

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Consultations provided to people from the poorest quintile as measured by asset index in targeted areas 

Percentage  0.00  0.00  75000.00  866402.00 

  31‐Mar‐2009  31‐Mar‐2009  31‐Dec‐2017  31‐Dec‐2017 

 

Comments (achievements against targets): Comment: 1,155.2% of end of project target achieved ‐ Source: reports from health centers. Verified by the PPA verification teams. 

   

  

Table A.1. Summary of achievement of PDO indicators per annum (2012‐2017) 

Indicator  2012  2013  2014  2015  2016  2017 

People with access to a basic package of health, nutrition, or reproductive health services 415,803  984,908  1,389,928  1,362,430  1,455,664  1,557,344 

Number of Children fully immunized 42,213  65,477  58,611  68,567  75,103  82,918 

Number of births attended by skilled professional 25,389  46,399  51,932  56,061  59,439  71,596 

New cases of TB detected and treated in targeted areas 1,564  2,396  2,764  2,907  2,623  2,707 

Direct project beneficiaries 482,453  1,093,697  1,414,397  1,487,313  1,590,112  1,711,925 

Of which Female beneficiaries  231,577  524,975  678,911  713,910  763,254  821,724 

        

Page 49: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 43 of 100

A. KEY OUTPUTS BY COMPONENT  

  

Objective/Outcome 1: Increase utilization of health services with a focus on health and communicable diseases  

 Outcome Indicators 

 1.  People with access to a basic package of health, nutrition, or reproductive health services (number) 2. Children immunized (number) 3. Births attended by skilled professional(number) 4. New cases of TB detected and treated in targeted areas (number) 5. Number of direct project beneficiaries (number) 6. Of which female beneficiaries (number)  

Intermediate Results Indicators 

1. Pregnant women receiving antenatal care during a visit to a health provider (number) 3. Children by the first anniversary who have received one dose of Vit. A in the last six months in targeted areas (Number). 7. Health facilities reporting monthly activities using standard report form in targeted areas (Number). 8. Number of consultations provided to people from the poorest quintile as measured by asset index in targeted areas.    

Key Outputs by Component: District Service Delivery (linked to the achievement of the Objective/Outcome 1) 

1. Hospital admissions (one day)‐ 4,859,585 2. Minor surgery:                   694,422 3. Normal Delivery:                   333,438 4. Complicated delivery:       20,063 5. Cesarean Section:               25,036 6. Major surgery‐                     54,401 7. Outpatient consultations:  8,134,334 

Page 50: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 44 of 100

   

Objective/Outcome 2: Improve the quality of health services with a focus on health and communicable diseases 

 Outcome Indicators  N/A 

Intermediate Results Indicators 

1. Tracer drugs available in targeted health facilities on the day of the visit, 2.Health facilities achieving an average score of 75% of the quality index of services as measured in RBF in the targeted areas supported the achievement of this objective    

Key Outputs by Component:  (linked to the achievement of the Objective/Outcome 2) 

    

   

Table B.1: Summary of Service delivery indicators by region 

 Indicator Est  Littoral  North West  South West  Total  Adamaoua  North  Far North (Yagoua)  Far North (Maroua)     Grand Total 

2012‐2017  2012‐2017  2012‐2017  2012‐2017  2012‐2017  2017  2017  2017  2017  Total    

Hospitalization (one day) 

1,472,303  1,261,970  769,640  980,781  4,484,694 111,375  63,258  55,662  144,596 

374,891  4,859,585 

Minor Surgery  136,537  199,714  171,618  132,826  640,695  15101  17516  8437  12673  53,727  694,422 

Normal Delivery  90,436  87,814  53,978  55,293  287,521  14905  11667  6675  12670  45,917  333,438 

Complicated delivery 

5,360  139  9,532  3,949  18,980 378  238  112  355 

1,083  20,063 

Outpatient Consultation  

2,606,287  1,780,693  1,268,786  1,614,529  7,270,295 251,755  173343  151,634  287,307 

864,039  8,134,334 

Page 51: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 45 of 100

 Indicator Est  Littoral  North West  South West  Total  Adamaoua  North  Far North (Yagoua)  Far North (Maroua)     Grand Total 

2012‐2017  2012‐2017  2012‐2017  2012‐2017  2012‐2017  2017  2017  2017  2017  Total    

Major Surgery  15,446  11,062  6,427  17,965  50,900  1219  471  965  846  3,501  54,401 

Cesarean section 5,520  6,078  4,150 

7,599 23,347 

730  315  359  285 1,689  25,036 

Total  4,331,889  3,347,470  2,284,131  2,812,942  12,776,432  395,463  266,808  223,844  458,732  1,344,847  14,121,279 

Page 52: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 46 of 100

 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION 

     

A. TASK TEAM MEMBERS 

 

Name  Role 

Preparation 

Supervision/ICR 

Ibrahim Magazi, Jean Claude Taptue Fotso  Task Team Leader(s) 

Ibrah Rahamane Sanoussi, Monique Ndome Didiba Epse Azonfack 

Procurement Specialist(s) 

Celestin Adjalou Niamien  Financial Management Specialist 

Helene Simonne Ndjebet Yaka  Team Member 

Aissatou Chipkaou  Team Member 

Emanuela Di Gropello  Team Member 

Aissatou Diallo  Team Member 

Kristyna Bishop  Social Safeguards Specialist 

Damien B. C. M. de Walque  Team Member 

Kouami Hounsinou Messan  Team Member 

Sariette Jene M. C. Jippe  Team Member 

Robert Anthony Soeters  Team Member 

Paul Jacob Robyn  Team Member 

Maud Juquois  Team Member 

Nneoma Veronica Nwogu  Counsel 

Idrissou Mounpe Chare  Team Member 

Hamadou Saidou  Team Member 

Maria Ward Steenland  Team Member 

James Dunaway Long  Team Member 

Chrystelle Isabelle Mfout Tapouh  Team Member 

Page 53: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 47 of 100

Cyrille Valence Ngouana Kengne  Environmental Safeguards Specialist 

Kofi Amponsah                                                                                    Senior Economist (Health)          

STAFF TIME AND COST 

Stage of Project Cycle Staff Time and Cost 

No. of staff weeks  US$ (including travel and consultant costs) 

Preparation 

FY07  17.978  100,977.71 

FY08  35.781  257,802.60 

FY09  0     0.00 

Total  53.76  358,780.31  Supervision/ICR 

FY09  15.754  102,172.15 

FY10  22.198  158,995.28 

FY11  29.070  222,608.26 

FY12  10.433  166,625.47 

FY13  11.325  209,822.83 

FY14  6.990  70,851.03 

FY15  5.900  60,301.24 

FY16  20.732  157,702.63 

FY17  25.734  162,643.35 

FY18  33.365  228,510.40 

Total  181.50  1,540,232.64     

  

 

Page 54: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 48 of 100

ANNEX 3. PROJECT COST BY COMPONENT 

  

  

Components Amount at Approval  

(US$M) Actual at Project Closing (US$M) 

Percentage of Approval (US$M) 

District Service Delivery  20  47.6  237.6 

Institutional Strengthening  5  8.9  178.1 

Total     25.00   56.500  225.600 

Note: The over 200% of actual to total approval amount was due to two additional financing (IDA 20 million and HRITF US$20 million) granted during implementation. At the time of ICR, expenditure was still being made; therefore, actual expenditure could be higher that what is reported.  

Ineligible Expenditures 

 

A total payment of FCFA 59,469,411 from IDA funds for workshops and other missions 

were made without receipts and justifications. 

Payment of FCFA 5,400,000 were made to CTN‐PBF officials for bonuses over the period 

September to December 2017, but their contracts expired on September 30, 2017. 

Payments  totaling  FCFA  6,000,000  for  the  remuneration  of  the  National  Technical 

Coordinator of the PBF for the period     September 1, 2017 to December 31, 2017. His 

payments were made with no justification. The person’s contract expired on August 31, 

2017. 

Irregular  payments  amounting  to  CFAF  39,706,977  were made  to  EMECAM  from  the 

PAISS designated account D, based on fraudulent documents from the CAA. 

 

 

Table 3.1. Ineligible expenditure 

    

    

No.  Description Expenditure 

(FCFA) 

1.   Non‐justifiable expenditure since 2016  59,469,411 

2.  Bonuses of civil servants without contract  5,400,000 

3.  Payments to National Technical Coordinator without a valid contract 

6,000,000 

4.  Irregular payments to EMECAM  39,706,977 

5.  Expenses on ineligible transaction   21,856,311 

TOTAL   132,432,699 

Page 55: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 49 of 100

ANNEX 4. EFFICIENCY ANALYSIS  

1. This analysis includes: (A) analysis of cost effectiveness of project interventions; (B) operational efficiency analysis, which includes a comparison of actual project costs with appraisal estimates; and (C) analysis of administrative and operational costs incurred on project implementation management unit. 

A. COST EFFECTIVENESS ANALYSIS  

2. To  ascertain  whether  project  resources  were  efficiently  used  we  measured  efficiency  by 

conducting a cost effectiveness analysis (CEA) using available data at project level. That is, we assessed 

the cost of project  interventions per agreed health outcomes. The key outcome metric  for measuring 

efficiency is incremental cost effectiveness ratio (ICER). This was the focus of our analysis. 

            Methodology 

3. Project  Costs:  Project  costs  included  all  costs  associated  with  procurement  and  financial 

management, including additional financing.  Since transfers of subsidies went directly into the delivery 

of services at health facility  level, the total cost of transfers of subsidies to all the project  intervention 

areas’  health  facilities were  the main  cost  elements  included  in  the  analysis.  Total  costs  of  subsidies 

transferred per facility were aggregated by region amounted to US$29.9 million16. To make a meaningful 

comparison and arrive at acceptable ICER, health services utilization data from selected PBF and non‐PBF 

facilities were obtained from the regional level project database.  

 4. Health gains. The analysis used Disability Adjusted Life Years (DALYs) as a key measure of health 

gains  resulting  from  utilization  of  health  services.  A  DALY  is  a  common  metric  that  allows  direct 

comparison across diseases as well  as diverse  types of  interventions.  It  is  a  standardized quantitative 

method of a burden of disease. Using the available data on selected PBF facilities and non‐PBF facilities, 

we estimated the number of maternal deaths averted (i.e. reduction in maternal mortality, MMR) and the 

number of death averted among children under the age of 5 (U5MR) resulting from increased utilization 

of  health  services  across  the  project  regions.  Through  PBF  interventions,  particularly  the  community 

outreach  programs  the  project  significantly  increased  utilization  of  health  services  in  the  beneficiary 

facilities. These health services, among others, include outpatient consultations, inpatient consultations, 

antennal  care  (ANC)  for  pregnant women,  post‐natal  care  (PNC), minor  surgery,  normal  delivery  and 

complicated delivery etc.  Because DALYs have two components (mortality and morbidity) we estimated 

DALYs incurred due to mortality and morbidity respectively. Mortality is life expectancy minus the age at 

death, which translates into life years lost due to diseases (LY). The mortality component of the DALYs 

was calculated using the life expectancy (55 years) in Cameroon. The general effect of morbidity is given 

as disability weight, which usually ranges from 0 (fully health) to 1 (fully disabled).   Because effects of 

morbidity can be long term, we factored in the risk of morbidity for its duration. Thus, we multiply the 

disability weight by the duration of disability and arrived at Disability Adjustment (DA). We then combined 

the mortality and morbidity factors to arrive at a full DALY scores for the interventions. The estimated 

values for both PBF and non‐PBF interventions were then discounted at the discount rate of 12 percent 

(see below).  Table 4.1 provides a summary of our estimates of health gains (DALYs averted). 

16 This amount is the total of subsidies costs data per region obtained from PIU’s FM unit.  

Page 56: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 50 of 100

 

 

Table 4.1: Maternal and children deaths averted 

Region 

Health Gains (Deaths Averted) 

 PBF 2012 

 non‐PBF 2012 

 PBF 2013 

 non‐PBF 2013 

 PBF 2014 

 non‐PBF 2014 

 PBF 2015 

 PBF 2015 

 PBF 2016 

 non‐PBF 2016 

 PBF 2017 

 PBF 2017 

Total  PBF 

Total  Non‐PBF 

Total Cost  PBF  (in US$ m) 

Total Cost  non‐PBF (US$m) 

Littoral   

Maternal deaths averted 

89  78  362  233  302  243  367  233  489  348  493  358  2,102  1,493                 7.1    

           0.26    

Children under 5 deaths averted 

463  210  1,923  854  3,749  1,762  4,637  2,571  4,340  3,042  4,255  2,309  19,367 

10,748 

Est   

Maternal deaths averted 

102  99  439  201  387  277  488  308  368  207  462  190  2,246  1,282                 9.7    

           0.35    

Children under 5 deaths averted 

265  201  2,001  844  2,233  1,011  6,462  2,604  4,353  1,760  4,666  2,701  19,980 

9,121 

Sud Ouest   

Maternal deaths averted 

146  121  683  542  843  643  863  527  865  532  965  544  4,365  2,909                 6.1    

           0.22    

Children under 5 deaths averted 

621  400  1,422  730  1,195  855  4,501  1,987  4,632  2,568  3,700  1,740  16,071 

8,280 

Nord Ouest   

Maternal deaths averted 

232  117  1,441  645  1,369  940  1,398  938  1,269  876  1,367  1,367  7,076  4,883                 6.6    

           0.24    

Children under 5 deaths averted 

866  534  2,643  932  3,217  2,076  8,013  5,047  6,478  3,549  7,012  4,680  28,229 

16,818 

Adamaoua   

Maternal deaths averted 

689  500  1,241  754  1,166  933  1,698  867  1,486  750  1,854  809  8,134  4,613                0.23    

           0.01    

Children under 5 deaths averted 

855  471  2,654  876  3,227  2,477  5,213  3,890  7,410  3,741  6,222  2,403  25,581 

13,858 

Nord    

Maternal deaths averted 

347  256  1,350  956  1,465  861  1,491  901  1,279  956  1,441  860  7,373  4,790                0.23    

           0.01    

Children under 5 deaths averted 

998  634  2,634  1,254  3,257  2,002  6,112  4,000  6,236  3,680  6,798  4,570  26,035 

16,140 

Total   

Maternal deaths averted 

1,605 

1,171 

5,516  3,331  5,532  3,897  6,305  3,774  5,756  3,669  6,582  4,128  31,296 

19,970 

                29.9  

             1.08  

Children under 5 deaths averted 

4,068 

2,450 

13,277 

5,490  16,878 

10,183 

34,938 

20,099 

33,449 

18,340 

32,653 

18,403 

135,263 

74,965 

   Total deaths averted 

5,673 

3,621 

18,793 

8,821  22,410 

14,080 

41,243 

23,873 

39,205 

22,009 

39,235 

22,531 

166,559 

94,935 

     

 

         Key underlying Assumptions 

Net costs are defined as program costs adjusted for resulting changes in medical cost. 

Prevention  interventions  (e.g.  immunization  for  children) would  lead  to  a  fall  in medical  cost 

which would allow the beneficiaries to avert diseases. 

Cameroon per capita GDP= $1,374.5(2016, WDI) 

Life expectancy in Cameroon= 55 years. 

Page 57: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 51 of 100

A 12 percent discount rate was used as a proxy for average opportunity cost of capital, based on 

the average bank lending rate in Cameroon. 

From the project costs data, the GoC’s portion of the PBF funds transferred to health facilities 

amounted to U$1,075,216 (3.6 percent) of total PBF funds. Given that government spends on 

other interventions in the sector, we assume that the 3.6% of PBF costs for each region   is the 

costs of non‐PBF interventions in the regions.  

Exchange rate= 1US$= FCFA 548 

ICER = $/DALY averted < GDP per capita is very cost effective (WHO standard for interpreting 

ICER results). 

 

             Estimation of Incremental cost effectiveness ration (ICER) 

5. Upon the basis of the above methodology and assumptions, we estimated the ICER by comparing 

net costs with a health outcome metric (DALYs averted).  From the available costs data, we calculated the 

ICER numerator by subtracting the discounted costs of non‐PBF (B) from the discounted costs of PBF (A) 

interventions to arrive at net costs. For the ICER denominator we subtracted discounted non‐PBF DALYs 

averted from discounted PBF DALYs averted and arrived at net health gains.  This allowed us to estimate 

cost effectiveness ratio (the costs for standardized unit of health gained), which is the increment of health 

gained per increment of spending.  We then estimated ICER using the formula as shown in box 4.1 below. 

  Box 4.1:  ICER calculation formula 

∆ Costs/∆Health Outcomes 

 ICER= [Costs of A‐Costs of B]/ [Life Years A‐Life Years B]. 

Added Costs/ DALYs averted= [Net cost of A‐Net Costs of B /DAILYs of A‐DALYs of B] 

Where:  ∆ Costs is the change in the cost of A and B respectively 

              ∆Health Outcomes is DALYs averted (A) and DALYs averted (B)   

 

 

Results  6. Substituting the total values of costs and death averted in PBF and Non‐PBF facilities in Table 4.1 

we estimated the ICER as follows: 

 

Total costs: PBF=$29,867122; Non‐PBF=$1,075,216 

Total Deaths Averted: PBF=166,559; Non‐PBF = 94,935 

             [$29,867122‐$1,075,216]        $28,791,106 ICER=‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐= ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐= $401.99           [166,559‐94,935]                        71,624 

Page 58: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 52 of 100

 

Limitations 

7. Given that a cost effectiveness analysis was not conducted at appraisal, we cannot compare the 

results of the CEA at ICR with expected results at appraisal for this project.  We cannot also validate any 

assumptions in terms of expected health gains that would have been stated at appraisal. The analysis was 

also limited with data gaps due to the shortcomings of M&E implementation at project level.  

 

OPERATIONAL EFFICIENCY 

 

B. OPERATIONAL/IMPLEMENTATION EFFICIENCY 

 

8. This  section  assesses  operational  efficiency  of  PAISS  implementation.  It  includes  (i) 

implementation efficiency, including a comparison of actual component costs at the end of the project 

with estimated component costs at appraisal(ii) time overrun/underrun; (iii) analysis of operational and 

administrative of project management unit. 

 

9. The project encountered considerable delays (almost three years after project effectiveness) due 

to  the  weaknesses  in  the  institutional  arrangements  for  implementing  the  service  delivery  (PBF) 

component of the project. But this was mitigated through project restructuring and extensions, including 

additional financing. The HRITF additional resources also supported a scale‐up of project activities in the 

26 districts implementing PBF. 

Comparison of Actual and Estimated Component Costs

10. The  estimated  total  project  cost  at  appraisal  was  US$25  million  made  up  of  Component  1 

(US$20million) and Component 2(US$5million) respectively. Available expenditure data at ICR shows that 

US$47.5million  (237.7  percent  of  appraisal  estimate)  and  US$8.9million  (178.1)  percent  of  appraisal 

estimate) was  spent on Components  I  and 2  respectively.    There  is  a  total  amount of US$31.4million 

variance  (Component  1:  US$27.5  and  Component  2:US$3.9million).  The  high  variance  was  due  to 

additional  financing  provided  to  support  increased  coverage  of  project  activities  in  three  additional 

regions (Adamaoua, North and Far‐North).  Table 4.2 compares actual and estimated component costs. 

 

Table 4.2:  Actual Component Cost vs. Estimated Component Cost as at 12/31/2017 

COMPONENTS   

Appraisal Estimate    (US $m)   

Actual   (US$ m)   

Variance (US$) 

% 0f Appraisal (Actual/ Estimate) 

Component 1:  District Services Delivery  20,000,000  47,531,100  27,531,100  237.7 

Page 59: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 53 of 100

Component 2: Institutional Strengthening  5,000,000  8,903,630  3,903,630  178.1 

Total Project Costs  25,000,000  56,434,730  31,434,730   225.7 

Source: PIU expenditure database  

11. As noted, IDA additional financing of US$20 million enabled extension of the project to additional 

2.2 million target population in the poorest region of the northern part of the country (Adamaoua, North 

and  Far‐North),  and  to  support  institutional  strengthening  under  Component  2.    At  the  same  time, 

additional US$20 million HRITF was granted to support a scale‐up of project activities in the 26 districts 

implementing PBF, and complete  impact evaluation. The additional  financing  increased efficiency as  it 

was pro‐poor and results focused.  Available project results data shows that service utilization in the three 

poorest northern regions (Adamaoua, North, and Far North) covered by the AF was impressive within one 

year of implementation.  As shown in Table 4.3 below, as many as 1,344,847 [ Adamaoua (395,463), North 

(266,808),  Far  North‐Yagoua  (223,844),  and  Far  North‐Maroua  (458,732)]  indigents  and  vulnerable 

population utilized a range of services, including hospitalization (one day), minor surgery, normal delivery, 

complicated delivery, outpatient consultation, major surgery, and cesarean section in 2017 (table 4.3).  

 Table 4.3. Service utilization by the indigent and vulnerable population in the three Northern Regions 

 Indicator Adamaoua  North 

Far North (Yagoua) 

Far North (Maroua) 

Total 

2017  2017   2017  2017    2017 

Hospitalization (one day)  111,375  63,258  55,662  144,596 374,891 

Minor Surgery  15101  17516  8437  12673  53,727 

Normal Delivery  14905  11667  6675  12670  45,917 

Complicated delivery  378  238  112  355 1,083 

Outpatient Consultation   251,755  173343  151,634  287,307 864,039 

Major Surgery  1219  471  965  846  3,501 

Cesarean section  730  315  359  285  1,689 

 Total  395,463  266,808  223,844  458,732  1,344,847 

Source: PIU Database 

 12. Efficiency was also enhanced as the project  interventions  led to better management of health 

facilities’  revenues,  reduction  of  parallel  sales  of  drugs,  display  of  costs  of  care  services  on  notices, 

laboratory  examinations,  and  medicines.  The  project  brought  much  more  competition  into  drugs 

purchasing and distribution of drugs and pharmaceuticals.   Hitherto, drugs purchasing and distribution 

was highly centralized as it was the sole responsibility of the FSPS.  

  

Page 60: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 54 of 100

Time overruns/Underrun 

13. PAISS was  prepared  in  approximately  7 months  (from  concept  to  approval).  This  is  less  than 

Cameroon  (14.7  months),  African  (14  months)  and  Bank  (14  months).  Despite  relatively  faster 

preparation,  on  average,  from  approval  to  effectiveness  took  9.0 months  to  complete,  compared  to 

Cameroon  (8.6  months),  Africa  (6.4  months)  and  Bank  (5  months).  Time  from  effectiveness  to  first 

disbursement is higher than Cameroon (1.6 months), Africa (2.8 months) and (Bank 4 months) averages. 

The project had slow disbursement rate (6 percent) after effectiveness. A slow start of activities because 

of  institutional  challenges  the  project  encountered  contributed  to  the  slow  disbursement.    Table  4.4 

provides key project delivery times.   

 

Table 4.4. Project processing and implementation times. 

  Concept to Approval 

Approval to Effectiveness 

Effectiveness to First Disbursement 

Concept to First Disbursement 

PAISS  7.1  9.0  4.5  19.9 

Cameroon  14.7  8.6  1.6  36 

Africa  14  6.4  2.8  22.6 

Bank  14  5  4  24 

Source: Client Connection; Note: Number in months 

 

14. Staff turnover was relatively stable at the PIU level, and the project coordinator was still at post 

at the time of ICR. On the Bank side, the project did not suffer extended period of TTL replacement as 

both  the  first  and  second  TTLs  were  replaced  pretty  much  faster.  As  noted,  the  TTLs  already  had 

experience  on  the  project  as  team members.  This  obviously  reduced  the  learning  curve  for  new  and 

inexperienced staff.  

 

OPERATING AND ADMINISTRATIVE COSTS 

 

15. Total  operating/administrative  costs  of  the  project management  amounted  to  US$3.9million, 

representing about 6.9 percent of total project cost (US$56.9millon). Three expenditure items: regional 

level monitoring (US$561,153.12 or 14.5 percent of total), seminars and workshops (US$ 604,011.79 or 

15.6 percent of total expenses), training of UGP/PIU staff and others (US$443,247.17 or 11.4 percent of 

total) constituted the bulk of the PIU’s operating expenses. On the Bank’s side total expenditure on staff 

time  spent  on  project  preparation  and  supervision  amounted  to  US$1,823,359.05  (Preparation‐

US$358,780.31 and Supervision ‐US$1,464,578.74), a 3.1 percent of total project cost.   Combined with 

the administrative  cost of  the PIU,  the project  spent a  total of US$5,703,836.92 on management and 

operational  activities.  Given  the  length  of  the  project  because  of  project  extensions,  the  total 

administrative cost of the project is cost efficient as it is within the Bank’s overall administrative cost of 

between 5 to 10 percent of total project cost.  Table 4.5 shows the operational costs of the project as of 

December 31, 2017. 

Page 61: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 55 of 100

 

Table 4.5. Project’s operating and administrative costs 

Item of Expenditure Amount   Amount  

% of Total (in FCFA)  (in US$) 

Fuel and Maintenance  61,711,956  114,281  2.95 

Personnel‐Salaries  698,769,502  1,294,018  33.35 

Bank charges  14,809,751  27,426  0.71 

Communication  159,205,474  294,825  7.6 

Regional level monitoring  303,022,683  561,153  14.46 

Supervision   18,972,084  35,134  0.91 

Seminars and workshops  326,166,369  604,012  15.57 

Training of UGP staff and others  239,353,471  443,247  11.42 

Insurance  29,817,992  55,219  1.42 

Rental   134,775,000  249,583  6.43 

Study tours (domestic and International) 

1,045,000  1,935  0.05 

Refreshment   7,203,865  13,341  0.34 

Personnel Salaries (PIU)  100,604,902  186,305  4.8 

Total  2,095,458,049  3,880,478  100 

Bank staff          

Preparation     358,780    

Supervision     1,464,579    

Subtotal     1,823,359    

       

Total     5,703,837    

% of Total Project Cost (Actual)        10.0% 

 

  

 

 

 

 

    

ANNEX 5. BORROWER, CO‐FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS   

Page 62: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 56 of 100

 16. No comments were received from borrower and/or stakeholders.  

        

Page 63: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 57 of 100

ANNEX 6. MAJOR REFORMS AND INITIATIVES  

1. DEVELOPMENT POLICY IMPACT  

 

Pillar 3: Improve Social Services and Expand Social protection  17. To  increase  the  level  of  funding  and  improve  management  capacity  of  health  facilities,  the 

government  has  signed  a  decree  that  allows  health  facilities  at  all  levels  of  the  system  to  retain  all 

resources  in  the  health  facility  (eliminate  transfers  from  facilities  to  government)  and  allow  health 

facilities to directly procure pharmaceuticals and other medical inputs from accredited providers (public 

or private). 

 18. In  terms of budgetary allocations,  the 2018 Health Budget uses  a  resource allocation  formula 

based on regional / geographic health needs.  It allocates at least 15% of the operating budget to primary 

and secondary care institutions and regulatory agencies to enable them to practice performance‐based 

payments in PBF regions and districts (providers / region / district). The investment budget has also been 

decentralized  for  health  facilities  in  PBF  areas  through  "investment  units  or  service  delivery  quality 

improvement  bonuses".    And  the  Regional  Funds  for  Health  Promotion  is  empowered  to  procure 

pharmaceutical products from accredited wholesalers (public or private) through simplified procedures. 

  

19.  The  2019  Public  Health  Budget  follows  the  same  line  as  2018,  but  increases  the  minimum 

allocation to primary and secondary care facilities and regulators to 20%. And new health professionals 

introduced into the public service are recruited and managed at the regional level through a competitive 

recruitment  process,  distribution  of  new  positions  is  based  on  the  health  needs  of  the  population. 

Percentage of  the public  budget  allocated  to  primary  and  secondary  schools  and  regulators.  Baseline 

(2017): 8% Target: 20%.  

 20. The government has expanded the administrative coverage of the PBF program by introducing at 

least 4 performance contracts at the central level of the Ministry of Public Health and extended coverage 

of the PBF program at the operational level to at least 40% of the country's population. 

 21.  The government has expanded the administrative coverage of the PBF program by introducing at 

least 8 performance contracts at the central level of the Ministry of Public Health (and funding of at least 

50% of its budget through these contracts) and extensive coverage of the PBF Program at the operational 

level to at least 75% of the country's population with contracting and verification agencies established in 

the 10 regions. 

 22.  The government has expanded the administrative coverage of the PBF program by introducing at 

least 12 performance contracts at the central level of the Ministry of Public Health, including CENAME 

Page 64: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 58 of 100

(and funding of at least 50% of its budget through these contracts), and Extended coverage of the PBF 

program at the operational level to at least 90% of the country's population. 

 23. The importance of the above DPO triggers were   reinforced by the following Joint Circular singed 

by the Minster of Health and Minister of Finance.  

 Joint Circular of Ministry of Health and Ministry of Finance for modalities for management regional and districts public health facilities’   financial resources under performance‐based financing (PBF)   24. In view of the tremendousness results of the Cameroon’s health sector PBF approach, since 2011, 

the PBF is henceforth adopted as a national strategy to assist the government to achieve universal health 

coverage(UHC) for its population.    

 25. In accordance with the PBF principle all facilities involved in the implementation of PBF (primary, 

secondary, and regional and tertiary health facilities) and all the regulatory institutions (district, region, 

and central level) with PBF contracts are authorized to benefit from special condition of the PBF program.  

These conditions are defined  in Cameroon’s PBF  implementation manual validated on August 9, 2017 

under the chairmanship of the Minister of Public Health.  

 26. All  the special  rules  for accounts management are defined  in  the PFM manual which must be 

followed by all the health facilities involved in PBF program in Cameroon.  

 27. We expect strict application of these provisions from the date of this signature.   

 2. PHARMACEUTICAL SUBSECTOR REFORM 

 A Ministerial Circular Specifying Terms and Conditions for supply of pharmaceutical products by Regional Funds for the Health Promotion (FRPS)  28. In  accordance  with  Article  10  of  the  initial  convention  of  each  Regional  Fund  for  Health 

Promotion (FRPS), one of its main functions is to support the Ministry of Public Health in the supply of 

quality essential drugs, preferably generic, to health facilities at the operational level.  

 29. For  this  purpose,  I  authorize  each  FRPS  to  purchase  from  the  licensed  private  wholesale 

distribution companies in the event of a stock shortage at the Central Medical Store in accordance with 

the principles of good governance.  For any order from FRPS to CENAME, the latter has a maximum period 

of 72 working hours to send a proforma  invoice,  indicating  the quantities available  for delivery of  the 

products ordered.  If the central medical store (CENAME) fails to respond within this timeframe or there 

Page 65: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 59 of 100

is unavailability of certain pharmaceutical products, the FRPS shall consult a minimum of three   licensed 

private wholesale distribution companies with preference to generic essential drugs. 

 30. For any proforma invoice received, the FRPS has a maximum of 72 working hours to confirm 

the  order  with  CENAME.  For  any  order  confirmed,  CENAME  is  required  to  deliver  on  time  within  a 

maximum period of one month. After this deadline, the FRPS shall initiate the procedure for approved 

wholesale as described. Each FRPS must make its annual projected needs known to CENAME not later 

than 15 January of each year, and update them if necessary before July 5. To do this, they must collect 

the needs of each FOSA for consolidation. 

 31.  The  frequency  of  orders  from  FRPS  to  CENAME  should  be  as  much  as  possible  quarterly. 

However, for any other order, transport and removal ordered products are the responsibility of the FRPS. 

The FRPS should work as much as possible during acquisitions, to obtain wholesale suppliers, competitive 

prices for the departmental catalog of ceilings to patients. The FRPS is obliged to deliver to the health 

facilities and provide them with assistance in the good practices in storage, inventory management, and 

secure destruction of medicines unfit for consumption (expired, damaged, counterfeit, etc.). FRPS shall 

inform CENAME in storage and distribution to health facilities and Public Health Programs for drugs such 

as ARV or during epidemics. Each FRPS update the Minister of Public on their orders from CENAME on 

quarterly basis. The General  Inspectorate of Pharmaceutical Services and Laboratories (IGSPL) and the 

Directorate of Pharmacy, Drugs and Laboratories (DPML) are each responsible for the control, monitoring 

and strict application of these instructions in all the Health Districts of the country which, will be evaluated 

in the first half of December. 

 32. I expect all institution to adhere to and implement the provisions of this Circular. 

 3. SUMMARY OF GFF INVESTMENT CASE 

 33. While the final list of interventions and strategies to be supported by the GFF trust fund will be 

validated at the national level in mid‐2016, the GFF Investment Case prioritization workshop that was held 

in February 2016 identified several key areas for which support will be provided. These include: 

 

Support  to  a  multi‐sectoral  approach  to  address  adolescent  health,  education  and demographic challenges in the northern regions of Cameroon. 

  Provide support to reinforce nutrition services to ensure that services supported through PBF payments are of high quality and high impact; 

Support to the development and implementation of a communication and behavioral change strategy  including  formative  research,  identification  of  priority  behaviors,  key  message development,  development  of  communication  tools  and  training  manuals  for  health  and nutrition; 

Page 66: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 60 of 100

Support to the piloting of Kangaroo Mother Care (KMC) to reduce risks related to low birth weight; and 

 Provide  critical  support  for maternal  health,  neonatal  health  and  family  planning  services, family  planning  and  adolescent  health  services,  responding  to  gaps  in  financing  of  the Strategic Plan for the National Multisectoral Program for Combating Maternal, Newborn & Child Mortality in Cameroon (2014‐2020). 

 34. Aligned with the Sustainable Development Goals, and taking  into account the need to move 

towards universal health coverage, the overall objective of the investment case is to help reduce, by the 

end  of  2020,  maternal  mortality  /  morbidity,  neonatal  and  infant‐juvenile,  and  to  promote  the 

reproductive health of adolescents / young people primarily in the regions of Adamaoua, the East, the Far 

North and the North. To achieve this objective, one of the main strategies is to cover the intervention area 

with  a  set  of  specific  and  multi‐sectoral  interventions  that  ensure  complementarity  and  synergy  to 

facilitate the achievement of expected results while ensuring better outcomes. allocation and utilization 

of  available  resources  for  health.  To  this  end,  the  government  aware  that  Cameroon  can  no  longer 

continue to do the business as usual and is committed to health financing reforms. The following are key 

priority areas of intervention: 

 

Prioritization of the most vulnerable and at‐risk populations. 

Scaling up of best practices for better coverage of interventions. 

Capitalization of the comparative advantages of actors in the field. 

Intensification of collaboration / partnership as part of the multi‐sectoral approach 

Decentralization of the decision‐making space and the empowerment of the actors, to favor the use of the most adapted solutions to the different contexts to meet the needs of the beneficiaries.  

35. These will  be  achieved  through  innovative  strategies  for  effective  implementation.  Box  6.1. 

provides key Initiatives of the Investment Case. 

 

Box 6.1. Key investment case initiatives  The reconfiguration of the mode of financing of health by favoring, as much as possible, the allocation 

of resources according to the obtained results. 

Selective contractualization of public and private services with a view to optimally exploiting the comparative advantages of the actors of the health system. 

 The extension of the performance‐based financing (PBF) strategy to system regulators, for better performance of the health system. 

 The "discriminatory" subsidy (the poorest pay less than the poorest) health care for vulnerable groups and economically weak. 

 Strengthening Community‐Directed Interventions Across Versatile ASCs and Qualified CBOs. 

 Strengthening the integrated offer of promotional, preventive and curative care and services at every contact of clients with the health system. 

 Strengthening the multi‐sectoral approach to RH in view of the multifactorial nature of the causes of maternal and infant‐juvenile mortality. 

 Social mobilization targeting opinion leaders including traditional authorities, men, mothers, and mothers‐in‐law as key partners. 

Page 67: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 61 of 100

 Optimal exploitation of ICT. 

Strengthening social control and the "voice" of the community. 

Taking into account socio‐economic equity and geographical prioritization as needed. 

 The use of innovative approaches such as "Development Impact Bond" to finance the implementation of Kangaroo Mother Care. 

 The use of ROLES MODELS to mobilize different target groups. 

 The holistic framework of adolescents / young people in terms of life skills including education, physical, sexual / reproductive, socio‐economic. 

The introduction of PBF in the education sector with emphasis on the retention of girls in school. 

 

 

36. Among the expected results, the main ones are the following especially at the level of the "out‐

come" (Box 6.2). 

 

Box 6.2. Summary of key results  Modern contraceptive prevalence among women of reproductive age in union is increasing by at least 30% 

by the end of 2020 in the regions of Adamaoua, East, Far North and North where they are currently respectively 7.7%, 14.6%, 3.5% and 6.1% (MICS 2014). 

 The proportion of women aged 15‐49 who had a live birth during the last 2 years preceding the survey, who benefited from the NPC4 offered by qualified personnel, increases to at least 70% by the end of 2020 in Adamawa, East, Far North and North where it is currently 50%, 45.2%, 37.8% and 46.8% respectively (MICS 2014). 

 The proportion of pregnant women tested for HIV + on ARV treatment according to national guidelines is at least 95% by the end of 2020 in Adamawa, East, Far North, North, Center, Littoral, North West, West, South and South West where the current proportions are 87.4%, 68.4%, 62.2% 78.7%, 92%, 87%, 93%, 84%, 74.6% and 88%. (PROGRESS REPORT PMTCT N ° 10 of 2015). 

The proportion of deliveries assisted by qualified personnel has increased by 20% by the end of 2020 in Adamaoua, the East, the Far North and the North, whose current rates are 53%, 57%, 29% and 29% respectively. % and 36% (MICS 2014). 

The proportion of recorded prematurity / low birth weight cases that are supported by standards, including the incubator and / or Kangaroo method, is at least 80% in Adamaoua, East, Extreme North and North. 

 Percentage of women aged 15‐49 who had a live birth in the last 2 years preceding the survey and whose last birth had a post‐natal consultation for the baby within 48 hours after delivery, increases to at least 30% by the end of 2020 in Adamaoua, East, Far‐North and North where it is respectively 9.6%, 6.7%, 4.9%, and 9.6% (MICS 2014). 

 The proportion of malaria cases managed according to national standards (ACT the same day or the day after) among children under 5 is at least 40% by the end of 2020 in Adamaoua, East, Far North and North where current rates are 7.0%, 3.9%, 0.3% and 5.6% respectively. 

 The proportion of children aged 0 to 11 months who received VARR increased to at least 95% by the end of 2020 in the Adamawa, East, Far North and North regions where current rates are 80%, 99% (refugee coverage), 84%, and 82% (2015 EPI Routine Data). 

 The proportion of cases of acute malnutrition expected in children who are identified and supported according to the standards is greater than or equal to 75% in the regions of Adamaoua, North, Far‐North and East. 

 The proportion of teenagers / youths admitted for STIs / HIV who are supported according to the norms in the FOSA of Adamawa, East, Far North and North is at least 80% d 'here at the end of 2020. 

Page 68: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 62 of 100

 The number of adolescents / youths (aged 10 to 19) who have received life skills training increases by at least 30% in the regions of Adamaoua, East, Extreme North and North 

 

 

37. It is recommended that the following results be achieved within 4 years of implementation of 

the interventions planned in this investment case (Box 6.3). 

 

Box 6.3. Contribution to key health outcomes  Contribute to a 5% annual reduction by the end of 2020 in the national maternal mortality ratio of 596 

deaths per 100,000 live births (WHO estimate). 

Contribute to reducing by at least 4.5% per annum, by the end of 2020, the neonatal mortality rates in the Adamawa, East, Far North and North regions, which are 40, 39, 40 and 42 deaths per 1000 live births, respectively (MICS 2014). 

Contribute to reducing by 30%, by the end of 2020, the intra‐hospital mortality rate among newborns of low birth weight and / or premature babies receiving kangaroo care (Baseline to be determined). 

 Contribute to reducing from 19.6 to 16.1 deaths (4.5% per year) per 1000 births, by the end of 2020, the national stillbirth rate (DHS 2011). 

 Contribute to reducing by 5% per annum, by the end of 2020, infant and child mortality rates in the regions of Adamaoua, East, Far North and North which are respectively 127, 127, 154 and 173 deaths per 1000 live births (MICS 2014). 

 Contribute to reducing to less than 5%, by the end of 2020, the prevalence of global acute malnutrition among children aged 0‐5 years in the regions of Adamaoua, East, Far North and the North where it is respectively 6.8% (15233), 1.0% (1022), 13.9% (82515) and 6.5% (530689) (2015 SMART Nutritional Survey). 

 Contribute to a reduction of at least 7.5 points by the end of 2020 in the prevalence of chronic malnutrition among children under 5 in the Adamawa, East, Extreme North and North where it is respectively 37.8%, 35.8%, 41% and 33.8% (MICS 2014). 

 Contribute to reducing the prevalence of teenage pregnancies by at least 30% by the end of 2020 for girls aged 15 to 19 in the Adamawa, East, Far North and Montenegro regions. North where it is respectively 31.7%, 53.1%, 29.0%, and 28.7% in 2014 (MICS 2014). 

 Contribute to increase the adjusted net enrollment rate of secondary education (TNF) of girls by at least 50% by the end of 2020 (Baseline to be determined). 

 Contribute to reducing the incidence of catastrophic health‐related expenditure (ECAM 5) from 

 

  

1. HOSPITAL SECTOR REFORMS  38. Although the tertiary hospital sector interventions were not integrated in PAISS design, there 

was a spillover effect on a major hospital, HGOPY.  Having observed PBF’s impact on service delivery at 

health facilities in project intervention areas, the hospital management sought support from the Bank to 

adopt and implement PBF initiatives with their own resources. The Bank provided them with PBF experts 

who trained over 20 managers, including the CEO.  They obtained service quality assessment support from 

the Bank through Littoral ACV. In April 2015 PBF the hospital started PBF implementation in three units 

and progressively extended to all clinical and administrative units.  This led to improved hospital efficiency 

and better management of resources: (i) an increase in bed occupancy rate, (ii) improved diagnostic and 

treatment capacity; (iii) an increase in internally generated revenues; (iv) decrease in unjustified expenses; 

Page 69: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 63 of 100

(v)  a  reduction  in  informal  and  under  the  table  payments  to  staff;  (vi)  improved  quality  of  care;  (vii) 

improved  staff  performance:  punctuality,  team  spirit  and  technical  competence;  and  (ix)  better 

remuneration for staff. 

 

RESULTS  Increased Services Delivery   

 

Table 6.1. Key service delivery indicators 

 Indicator 

2013  2014 2015  (PBF  Start‐up) 

2016 

Nombre de consultations 70 557  74 458  75 971  78 869 

Nombre de CPN 9,755  9,813  10,066  11,327 

Nombre d'hospitalisations 10 593  10,546  11,760  13,958 

Nombre d'accouchements 2,886  2,778  2,860  3,062 

Nombre de césariennes 661  721  744  898 

Nombre de femmes reçues pour planning familial 

679  1,194  1,807  3,146 

Nombre d'interventions chirurgicales 2,040  2,068  2,079  2,590 

Nombre d'enfants malnutris pris en charge 21  27  62  93 

Durée moyenne de séjour 4.20 jrs  3.63 jrs  3.49 jrs  3.41 jrs 

Taux d'occupation des lits d'hospitalisation 53.45%  45.25%  47.31%  56.25% 

Indigents 98  90  85  166 

 

INTERNALLY‐GENERATED REVENUES  Figure. 6.1: Trends Internally generated funds 

Page 70: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 64 of 100

 

 

  Average monthly revenues before and after PBF implementation 

   2013  2014  2015 PBF start‐up   2016   2017 

Recettes Moyennes  115,402, 442  118,756,691  135,531,319  161,431,591  167,503,120 

Trend       14.12%  35.93%  40.05% 

  QUALITY OF SERVICES  

0

100,000,000

200,000,000

300,000,000

400,000,000

500,000,000

600,000,000

Début du PBF

Page 71: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 65 of 100

   BASE T2 2015 (Mars 2015 Début PBF) 

T3 2015  T4 2015  T2 2016  T3 2016  T1 2017  T2 2017 

QUALITE DU SERVICE 

25%  31%  29%  50%  56%  61%  67% 

 

39. Following  the  successful  pilot  of  the  PBF,  the Cameroon health  team and  the WBG’s Africa 

Region  Vice  President  visited  the  hospital  to  observe  the  results  on  the  ground.  The  visit  served  as 

motivation and encouragement to the hospital management.  

 

4. FOLLOW‐ON PROJECT: HEALTH SYSTEMS PERFORMANCE REINFORCEMENT PROJECT     40. The  Cameroon  Health  Systems  Performance  Reinforcement  Project(HSPRP)  is  a  follow‐on 

project of PAISS.   The Project Development Objective  (PDO)  is  to  increase utilization and  improve the 

quality of health services with a particular focus on reproductive, maternal, child and adolescent health 

and nutrition services. The main direct beneficiaries are women, adolescents and children under 5, as well 

as displaced and refugee populations affected by the insecurity in the region. 

 41. The IDA allocation for this project is US$100 million. A grant of US$27 million from the Global 

Financing Facility (GFF) Trust Fund will support investments in RMNCAH and nutrition (US$25 million) and 

civil registration and vital statistics (CRVS) systems (US$2 million). 

 42. The project will support the ongoing implementation of PBF in the 26 health districts covered 

by the PAISS the 18 health districts recently added through the Additional Financing, and an incremental 

roll  out  of  PBF  to  national  coverage.  With  a  coverage  at  25  percent  of  the  population  in  2016,  the 

operation would support a gradual scaleup of approximately an additional 20 percent of the population 

per year between 2017 and 2020. During the first phase of the extension (2016‐2018), the HSRPP will 

focus on scaling up to the remaining 36 districts in the three northern regions of Cameroon (Far North, 

North,  and Adamawa)  to  address  the  urgent  and  growing  needs  in  those  regions.  In  total,  the  three 

northern regions include 54 health districts with a population of 7,614,882 (2016). 

 43.  Following a successful pilot of PBF at the national pediatric hospital in Yaoundé to test PBF at 

the  tertiary  level,  the  HSPRP  will  increase  the  geographical  coverage  of  PBF  by  providing  technical 

assistance in rolling‐out PBF to regional and tertiary‐level hospitals in the country.  Under the pilot, PBF 

subsidies were paid with internally‐generated revenues. To avoid incentivizing overproduction of services 

Page 72: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 66 of 100

to  increase  hospital  revenue,  the  main  function  of  the  PBF  program  in  the  tertiary  hospital  was  to 

redistribute revenue based on performance outcomes linked to quality improvements.  

 44. Under HSPRP, the implementation of PBF at tertiary hospitals, including payment of subsidies, 

will be supported by both the public budget and internally‐generated revenues. HSPRP project will not 

finance the actual payment of PBF subsidies to tertiary facilities, but will provide the necessary technical 

assistance to design and  implementation of PBF  interventions,  including providing support  to contract 

management and verification activities to be conducted by the CDVAs in each region. 

ANNEX 7. SUMMARY OF IMPACT EVALUATION RESULTS 

45. To  ascertain  the  evidence  of  project  results/outcome,  two  rounds  of  end  of  project  impact 

evaluations (quantitative and qualitative) were conducted at the end of the project. The ICR team used 

the  results  of  the  two  evaluations  to  support  the  assessment  of  the  achievement  of  the  project 

development objective. A summary methodology and sampling techniques are as follows: 

Quantitative Impact evaluation: 

46. Methodology and sampling techniques.  The methodology for the quantitative impact evaluation 

is as follows: 

Selection of study groups: 

47.   Four study groups were formed by randomizing medicalized health centers, or primary health 

centers with a medical doctor on staff, as well as integrated health centers (i.e. primary health care centers 

without a doctor). To ensure that all stakeholders were fully represented, the evaluation team publicly 

organized randomization ceremonies in the intervention regions. This brought together all health facility 

management staff in the districts covered by the evaluation. Box 7.1 shows the selected treatment groups. 

 

Box 7.1. Selected study groups  T1: PBF with health worker performance bonuses. 

C1: Same per capita  financial  resources as PBF but not  linked to performance; same supervision and monitoring and managerial autonomy as T1. 

C2: No additional resources but same supervision and monitoring as PBF arms and T1 and C1 

C3: Status quo.  

 Basis of the evaluation 

48. To distinguish between the influence of the different components of the PBF reform and ascertain 

the desired results, the evaluation team considered four key packages. They include: (i) the standard PBF 

package,  (ii)  the  same  level  of  financing  but  not  linked  to  performance,  and  with  the  same  levels  of 

Page 73: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 67 of 100

supervision, monitoring, and autonomy as PBF, (iii) no additional resources or autonomy, but the same 

levels of supervision and monitoring as PBF, and (iv) pure comparison. The randomization took place at 

the health facility level, and overall, the four study groups were well balanced at baseline. The analysis 

also established that the levels of financing between the first two groups (standard PBF and additional 

financing) was indeed equivalent at end‐line. The evaluation used a combination of household and health 

facility surveys conducted at baseline and end‐line to assess the impact of PBF interventions. 

 49. Health facilities in group T1 implemented all the above package.  Group C1 received a fixed per 

capita budgetary supplement that matches the per capita budgetary allocation for T1 facilities but the 

supplement was not linked to performance. C1 facilities received the same supervision, monitoring, and 

managerial autonomy over the budgetary supplement received. Both T1 and C1 facility managers had the 

autonomy to hire staff with their PBF budget supplements. They also had the autonomy to fire these staff 

if  need  be.  T1  and  C1  facility  managers  also  had  the  autonomy  over  how  to  use  PBF  revenues.  No 

additional  funds were  given  to  group C2  facilities,  but  they benefited  from  the  same  supervision and 

monitoring as T1 and C1 facilities. District‐level supervisors of T1, C1 and C2 facilities used the same tools 

and received the same supplementary payments for visits to facilities in these three groups.  Quality scores 

were linked to facility payments only in the case of T1 facilities. C3 facilities were the ‘business as usual’ 

facilities and did not receive any additional resources or inputs. C2 and C3 facility managers did not have 

the autonomy to hire/fire staff or financial autonomy. Public and private health facilities in the 14 study 

districts who registered with the Ministry of Public Health (MPH) were included in the study. Given the 

critical role that   the 14 districts hospitals play in supervising and acting as a source of referrals, they were 

included in the study.  

 

50. The main methodology used for the analysis was difference‐in‐differences regression model with 

a study period of between 2012 and 2015 

Data sources  51. Two main sources of data were used for the evaluation: (i) household survey: A household survey 

implemented at baseline (i.e., before implementation of PBF began), and at end‐line (i.e., after PBF was 

implemented) and; (ii) Facility‐based survey implemented both at baseline and end‐line. 

Sampling technique  52. A total of 259 health facilities (226 public and 33 private) were sampled.  In the Eastern Region, 

79 health facilities [public (81%) and private (19%)] were sampled.  In the North‐West region, 105 facilities 

[ public (57%) and private (43%)] were sampled. Finally, in the South West 75 facilities [public (66%) and 

private (43%)] were sampled. Table 7.1 shows a summary of the sampled facilities 

 

 

 

 

 

Page 74: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 68 of 100

Table7.1. Sampled health facilities 

District 

Number of health facilities 

CSI Public CMA Public 

District Hospital 

Confessional CSI/ CMA/ Hospital 

For‐profit/ Para‐public  Total 

Private (%) 

Bingaman  14  2  1  4  2  23  27 

Doume  9  1  1  2  1  14  23 

Lomie  7  2  1  2  0  12  18 

Messamena  9  1  1  2  0  13  17 

Nguelemendouka  5  0  1  1  0  7  17 

Kette  9  0  1  0  0  10  0 

Total in East  53  6  6  11  3  79  19 

Kumbo East  17  2  1  6  4  30  34 

Nkambe  11  2  1  4  2  20  32 

Ndop  12  2  1  8  4  27  46 

Fundong  9  3  1  12  3  28  56 

Total in North West  49  9  4  30  13  105  43 

Mamfe  11  1  1  1  0  14  8 

Kumba  10  1  1  5  1  18  35 

Buea  10  3  1  0  9  23  41 

Limbe  10  1  1  1  7  20  42 

Total in South West  41  6  4  7  17  75  34 

Pilot Zone total  143  21  14  48  33  259  33 

 RESULTS  53. Based on the above methodology, the following results were achieved.  

 A. HEALTH SERVICES UTILIZATION 

 HOUSEHOLD SURVEY UTILIZATION RESULTS 

 Coverage of Reproductive Health Services among Women who were Pregnant in the Previous 24 months  54. For antenatal care, facilities with the PBF intervention performed better than those facilities with 

only additional supervision. There was no difference between the control group and the PBF group, or the group that received additional financing in the change in skilled delivery over the study period. (Table 7.2).   Table 7.2. Delivery with a skilled birth attendant 

Indicator  Impact estimate 

Page 75: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 69 of 100

Skilled Delivery  -0.043 * = p < 0.10, ** p < 0.05,  *** p< 0.01 Results from difference‐in‐differences regression models examining the effect of PBF on reproductive health service use among female respondents  included  in  the household survey who had been pregnant  in  the previous 24 months. Regression model adjusted for individual (age, marital status, education level, religion, ethnicity, working status and type of work) and household control variables (number of individuals in the household, housing type, house ownership, water source, and type of sanitation). Standard errors were clustered at the health facility level. 

 Full Vaccination Coverage Among Children Between 12 ‐ 23 Months of Age  55. Mothers or primary care givers of all  children under  five years of age were asked about  their 

child’s  vaccination  history.  For  all  children  with  a  vaccine  card,  study  enumerators  recorded  all 

documented vaccinations and their respective receipt dates. Mothers/primary caretakers were also asked 

to report any vaccinations that were not recorded in the vaccine card. For these questions, enumerators 

asked a separate question for each vaccine type that referenced the vaccine name and gave an indication 

of its method of administration (i.e. for polio “that is drops in the mouth”) as a guide for respondents. 

Only children between 12 – 23 months of age were included in these analyses. Both outcomes include the 

following  vaccines:  oral  polio  vaccine,  yellow  fever,  diphtheria,  tetanus,  and  whooping  cough  (DTC), 

measles,  and  Bacillus  Chalmette–Guerin  (BCG).  Table  7.3  shows  in  the  PBF  group,  there  was  a  17‐

percentage point increase in full vaccination (0.170, p‐value = 0.076). 

 Table 7.3 Full Vaccination Coverage Among Children Between 12 ‐ 23 Months of Age 

Indicator  Impact estimate 

Fully vaccinated documented by vaccine card  0.170* 

* = p < 0.10, ** p < 0.05, *** p< 0.01 Results from difference‐in‐differences regression models examining the effect of PBF on child vaccination among children (12 – 23 months) included in the household survey. Regression model adjusted for individual (age, father in the household, religion, ethnicity) and household control variables (number of individuals in the household, housing type, house ownership, water source, and type of sanitation). Standard errors were clustered at the health facility level.  

FACILITY SURVEY UTILIZATION RESULTS 

The results of PBF on health services provision as recorded in facilities registers.  56.  The study examined the health service counter‐verification data that was collected routinely as 

part of the PBF program design through community client satisfaction surveys. Health service verification 

took place in all PBF health facilities, as well as in health facilities in control groups C1 (additional financing) 

and C2 (additional supervision). The study sampled 35 for 7 health service categories each quarter. Figure 

7.1 below shows the percentage of patients who were reported by health facilities to the PBF verification 

terms, who were  later  confirmed  to  have  received  health  services  at  the  health  facility.  During most 

quarters of the three‐year study period in all  three study regions, over 80% of reported patients were 

confirmed. The  trend  in  confirmed patients  increased  slightly over  time  in North‐West and East, with 

confirmation rates above 85 percent in all three regions during the final year of the study.  Facilities in the 

full control group had less incentive to keep records of all services provided than facilities in PBF group. 

Figure 7.1: Percent of Reported Patients Confirmed During Verification 

Page 76: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 70 of 100

  Source : Cameroon PBF Quantitative Impact Evaluation report March 24, 2017  QUALITY OF HEALTH SERVICES  PATIENT SATISFACTION   Overall Satisfaction Score for Antenatal Care Reported during Facility Exit Interviews  57. Women  were  asked  a  series  of  twelve  questions  related  to  their  satisfaction  with  individual 

elements of their visits including, for example, their satisfaction with costs, wait times, and health worker 

communication. For each, a statement was read, and women were asked if they agreed, were neutral, or 

they disagreed. Binary variables were created by coding responses as “1”  if a woman agreed, and “0” 

otherwise. Overall satisfaction scores were calculated by averaging over these twelve components. An 

overall score of “1” indicates that a woman agreed with all twelve questions, while a score of “0” indicates 

that she either disagreed or was neutral on all twelve questions. The impact of the interventions on overall 

satisfaction are shown in Table 7.4 below. There is no indication that satisfaction changed over time in 

the control group (β = 0.006, p = 0.847). Relative to the pure control, the PBF group was associated with 

an 8.6 percentage point increase in satisfaction (p = 0.077). The results suggest a stronger effect in the full 

PBF than in the additional supervision group (10.5‐percentage point increase).  

 

Table 7.4 Overall ANC satisfaction score (PBF vs. Control group) 

Indicator  Impact estimate 

Satisfaction score  0.086* * = p < 0.10, ** p < 0.05, *** p< 0.01 Results from difference‐in‐differences regression model examining the effect of PBF on the overall satisfaction score for antenatal care reported by patients during facility exit interviews. Regression model adjusted for individual (age, literacy, marital status, education level) and facility‐level control variables (type of health facility public/private/religious, urban/rural). Standard errors were clustered at the health facility level.  

  

83

89

81

9894

86

40

60

80

100

Sept.2012

Dec.2012

Feb.2013

May.2013

Sept.2013

Dec.2013

Mar.2014

Jun.2014

Sept.2014

Dec.2014

Mar.2015

Jun.2015

Per

cen

t (%

)

North-West Est South-West

Page 77: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 71 of 100

Satisfaction with health facility characteristics during antenatal care reported during facility exit interview  58. Women’s  satisfaction  with  health  facility  characteristics  increased  significantly.  PBF  was 

associated with  a  large  and  statistically  significant  24.1‐percentage  point  difference  from  the  control 

group (p<0.05) in women’s satisfaction with the health facility cleanliness and facility hours. Compared to 

the  control  group,  PBF  results  in  a  large  and  statistically  significant  15.4‐percentage  point  increase 

satisfaction with the facility’s hours, while the additional supervision is associated with a non‐significant 

reduction in satisfaction relative to the pure control (Table 7.5).  

 

Table 7.5: Satisfaction with health facility characteristics during ante natal care 

Indicator  Impact estimate 

Satisfaction score on cleanliness  0.241** Satisfaction score on operating hours  0.154**

* = p < 0.10, ** p < 0.05, *** p< 0.01 Results from difference‐in‐differences regression models examining the effect of PBF on satisfaction with health facility characteristics reported by patients during facility exit interviews. Regression model adjusted for individual (age, literacy, marital status, education level) and facility‐level control variables (type of health facility public/private/religious, urban/rural). Standard errors were clustered at the health facility level. 

 Satisfaction  with  health  worker  characteristics  during  antenatal  care  reported  during  facility  exit interview  59. Table  7.6  provides  an  overview  of  women’s  reported  satisfaction  with  health  worker 

characteristics.    Women  attending  facilities  receiving  the  full  PBF  intervention  reported  significantly 

higher levels of satisfaction with health worker communication than did women attending control clinics 

(β=0.106, p<0.05), but there was no evidence of an impact of PBF on the courteousness of health staff, 

time with health workers, or the ease of getting prescribed medicines. 

Table 7.6 Health worker satisfaction during ANC score 

Indicator  Impact estimate 

Satisfaction score on health worker communication   0.106** * = p < 0.10, ** p < 0.05, *** p< 0.01 Results from difference‐in‐differences regression models examining the effect of PBF on satisfaction with health worker characteristics during antenatal care reported by patients during facility exit interviews.  Regression model adjusted for individual (age, literacy, marital status, education level) and facility‐level control variables (type of health facility public/private/religious, urban/rural). Standard errors were clustered at the health facility level. 

 

 

 

 

 

Page 78: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 72 of 100

SATISFACTION WITH CHILD HEALTH CONSULTATIONS (< 5 YEARS OLD) 

 Overall satisfaction score for child health consultations reported during facility exit interviews  60. PBF had a positive impact on overall satisfaction with child health services. Relative to the pure 

control, the PBF was associated with a statistically significant 9.9‐percentage point increase in satisfaction 

(p<0.05). Table 7.7 shows satisfaction score of PBF against C2 and C3. 

 Table 7.7 Overall child consultation satisfaction score  

Indicator  Impact estimate 

Satisfaction score   0.099*** * = p < 0.10, ** p < 0.05, *** p< 0.01 Results from difference‐in‐differences regression model examining the effect of PBF on the overall satisfaction score for child health consultations reported by mothers during facility exit interviews. Regression model adjusted for individual (child age, child sex, maternal literacy, marital status, education level) and facility‐level control variables (type of health facility public/private/religious, urban/rural). Standard errors were clustered at the health facility level. 

 Satisfaction with selected health facility characteristics during child health consultations reported during facility exit interviews  61. As  shown  in  table  7.8  PBF  is  associated  with  a  large  and  statistically  significant  impact  on 

satisfaction with the health facility cleanliness (β=0.227, p=0.090). Neither the additional financing nor 

the additional supervision intervention groups (C1 and C2) performed better on cleanliness at end‐line 

than  they  did  at  baseline.  Focusing  on  waiting  times,  all  the  intervention  arms  appear  to  result  in 

improvements over the control group, although none of the differences were statistically significant. All 

the arms also resulted  in  increased satisfaction with the privacy at health facilities, and the very  large 

point estimate on the PBF (33.6 percentage points) is significant at p<0.01. Satisfaction with the opening 

hours did not change over time in any of the treatment groups, and there were no differences between 

groups for this outcome. 

 Table7.8 Satisfaction with selected health facilities 

Indicator  Impact estimate 

Satisfaction score on cleanliness  0.227* Satisfaction score on privacy   0.336***

* = p < 0.10, ** p < 0.05, *** p< 0.01 Results  from  difference‐in‐differences  regression  models  examining  the  effect  of  PBF  on  satisfaction  with  health  facility characteristics reported by mothers during facility exit interviews. Regression model adjusted for individual (child age, child sex, maternal  literacy,  marital  status,  education  level)  and  facility‐level  control  variables  (type  of  health  facility public/private/religious, urban/rural). Standard errors were clustered at the health facility level  

 

 

 

Page 79: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 73 of 100

HEALTH WORKER SATISFACTION AND MOTIVATION 

Physical condition of the health facility and ability to provide high quality care given health facility conditions    62. Table  7.9  below  provides  an  overview  of  reported  satisfaction with  the  physical  condition  of 

health facilities. Health workers in the PBF arm were 31 percentage points more likely to be satisfied with 

the physical condition of the health facility building, relative to the pure control (p<0.01). 

 Table 7.9 The physical condition of the health facility building 

Indicator  Impact estimate 

Satisfaction on physical condition of the health facility building 

0.306*** 

* = p < 0.10, ** p < 0.05, *** p< 0.01 Results from difference‐in‐differences regression model examining the effect of PBF on the overall satisfaction score for antenatal care reported by patients during facility exit interviews. Regression model adjusted for individual (age, literacy, marital status, education level) and facility‐level control variables (type of health facility public/private/religious, urban/rural). Standard errors were clustered at the health facility level.

 HEALTH WORKER AVAILABILITY IN THE HEALTH FACILITY  

 Number of nurses present at the health facility on the day of the survey  63. The facility survey asked the head of the health facility, or the most informed staff member, to 

list the names of the all the health workers employed at the health facility. The staff roster also collected 

information on the post occupied by each health worker and on whether they were present on the day of 

data collection. Table 7.10 below presents results from analysis of the number of nurses present at the 

health facility on the day of data collection. There was a small and non‐significant increase in the number 

of nurses present over the study period. The increase in the number of nurses in the PBF group was greater 

than in the full control group (p‐value 0.010). Adding the coefficient on the interaction term of PBF and 

post  to  the coefficient on  the post  indicator  (0.191+1.222=1.413)  indicates  that  there was an average 

increase of almost 1.5 nurses present in PBF facilities over the study period. The coefficients on the two 

other  treatment  groups  –  additional  financing  and  additional  supervision  –  were  not  statistically 

significant; however,  there was a  larger  increase  in  the  full PBF group compared to  the change  in  the 

additional supervision group.  

 Table 7.10 Number of nurses present at the health facility score 

Indicator  Impact estimate 

Number of nurses  1.222*** * = p < 0.10, ** p < 0.05, *** p< 0.01 Results from difference‐in‐differences regression models examining the effect of PBF on the number of nurses present at the health  facility  on  the day of  the  survey.  Regression model  adjusted  for  facility‐level  control  variables  (type of  health  facility public/private/religious, urban/rural). Standard errors were clustered at the health facility level. 

 

Page 80: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 74 of 100

DRUGS AND EQUIPMENT IN THE HEALTH FACILITY  

 Quantity and quality of health supplies, medicines, and equipment in the health facilities 

64. There was a  large and consistent  impact on health workers’ satisfaction with the quantity and 

quality of equipment and other supplies at health facilities, shown in Table 7.11 below. Both the PBF and 

the  additional  financing  arms  resulted  in  similarly  large  and  highly  significant  improvements  in  these 

measures: an approximately 20 percentage point increase in reported satisfaction with the quantity of 

equipment (p<0.05), approximately 25 percentage point increase in reported satisfaction with the quality 

of equipment (p<0.05), and a 40‐percentage point increase in satisfaction with the availability of other 

supplies at the health facilities within these two arms (p<0.01). 

 Table 7.11 Quantity and quality of health supplies 

Indicator  Impact estimate 

Quantity of equipment in the health facility  0.190** 

Quality and physical condition of equipment in the health facility  0.256** 

Availability of other supplies in the health facility  0.404*** * = p < 0.10, ** p < 0.05, *** p< 0.01 Results from difference‐in‐differences regression models examining the effect of PBF on the quantity and quality of health supplies, medicine, and equipment in the health facility reported by health workers. Regression model adjusted for individual (age, sex, marital status, education level) and facility‐level control variables (type of health facility public/private/religious, urban/rural). Standard errors were clustered at the health facility level. 

 65. A  composite  indicator  was  created  to  assess  any  impact  on  the  availability  of  basic  clinical 

equipment. The indicator included information on the presence of a clock, a child weighing scale, height 

measure,  tape measure,  adult weighing  scale,  blood pressure  instrument,  thermometer,  stethoscope, 

fetoscope, otoscope, flashlight, stretcher, and wheelchair. Scores indicate the proportion of these thirteen 

pieces of equipment that was available at a given facility and range from 0 to 1. Point estimates indicate 

the estimated impact on this score.  

Availability of Basic clinical equipment available at health facilities  66. As shown in table 7.12.  Both the PBF and the additional financing intervention arms resulted in 

large and statistically significant improvements in the availability of equipment. Facilities in the PBF arm 

had a 10.0 percentage point increase over that seen in the control (p<0.05), while those in the additional 

financing arm had an increase of 12.5 percentage points over the control (p < 0.01). This increase was not 

seen  in  the  improved  supervision  arm;  while  the  point  estimate  was  positive,  it  was  small  and  not 

statistically significant. There was no measurable difference in the impacts of the PBF and financing only 

arms,  but  there  was  statistically  significant  difference  between  the  PBF  intervention  and  improved 

supervision (p<0.05). 

Table 7.12 Basic clinical equipment available at health facilities 

Indicator  Impact estimate 

Page 81: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 75 of 100

Basic clinical equipment  0.100** * = p < 0.10, ** p < 0.05, *** p< 0.01 Results from difference‐in‐differences regression models examining the effect of PBF on the basic clinical equipment available at the health facility. Regression model adjusted for facility‐level control variables (type of health facility public/private/religious, urban/rural). Standard errors were clustered at the health facility level  

Delivery equipment available at the health facility 

67. Table 7.13  shows the impact on delivery equipment, which includes the following: delivery bed, 

partograph, delivery light, aspirator, newborn resuscitation bag, newborn eye drops or ointment, scissors, 

umbilical cord clamp or sterile tape/tie, suturing material, examination gloves, sterile cotton gauze, hand 

soap or detergent, hand scrubbing brush, sterile tray, plastic container with plastic liner for the placenta, 

plastic container with a plastic  liner for medical waste, adult stethoscope, pinard or fetal stethoscope, 

blood pressure  instrument,  kidney basin, protective apron and plastic  draw sheet, baby  scale,  needle 

holder,  syringes  and  disposable  needles,  16‐  or  18‐guage  needles,  speculum,  clamps,  hand  or  foot 

operated  suction  pump,  vacuum  extractor,  and  a  uterine  curette.  Both  the  PBF  and  the  additional 

financing interventions had large and positive impacts on the availability of delivery equipment. Scores in 

the PBF arm improved by 21 percentage points more than did those in the control. 

 Table 7.13 Delivery equipment available at the health facility score 

Indicator  Impact estimate 

Delivery equipment  0.209*** * = p < 0.10, ** p < 0.05, *** p< 0.01 Results from difference‐in‐differences regression models examining the effect of PBF on the delivery equipment available at the health facility. Regression model adjusted for facility‐level control variables (type of health facility public/private/religious, urban/rural). Standard errors were clustered at the health facility level.  

Family planning methods available at the health facility  68. The same is true for family planning methods as shown in Table 7.14. The index is comprised of 

condoms, oral  contraceptive  tablets, Depot Medroxyprogesterone Acetate  (DMPA), and  implants. The 

estimated impact for PBF is large at 16.8 percentage points and statistically significant (p < 0.10). The point 

estimates indicating the effect of the other two different treatment arms are also positive, though they 

are not  large enough  to pass  the  test of  statistical  significance. Also,  the effect  in  the PBF group was 

statistically significantly different from the effects observed in the other treatment groups.  

Table 7.14: Family planning methods available at the health facility 

Indicator  Impact estimate 

Family planning   0.168* * = p < 0.10, ** p < 0.05, *** p< 0.01 Results from difference‐in‐differences regression models examining the effect of PBF on family planning methods available at the health facility. Regression model adjusted for facility‐level control variables (type of health facility public/private/religious, urban/rural). Standard errors were clustered at the health facility level 

 

Page 82: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 76 of 100

QUALITATIVE IMPACT EVALUATION 

Summary of qualitative impact evaluation  69. The qualitative  impact evaluation  focused exclusively on  intervention  (PBF)  facilities  and  their 

catchment  areas.    It  aimed  at  assessing  the  impact  of  the  PBF  intervention  on many  health  service 

provision and health outcome indicators, measured both at the facility and the household levels. 

 Methodology and sampling technique:  70. The  roles  of  qualitative  research  imbedded  in  a  PBF  impact  evaluation  are  numerous.  They 

include:  

 

To determine the set of issues that are relevant to the specific country context;  

To construct relevant quantitative measures. 

To explore relevant issues in greater levels of depth and detail. 

To understand the role of place, time, practices and processes.  

To enhance interpretation of quantitative results. 

Table 7.15. Sampling technique 

Level Type of Respondent

Respondent Details  

Estimated number of respondents  

Instrument Type  

Description of Data  

National and Regional  

Ministry of Health officials, Policy makers, Program implementers  

• Individuals in the Ministry and partners  • Regional delegates and/or PBF focal point  • Regional managers and/or assistant of Purchasing Agency

Ministry official: 5  Regional delegates: 3  Purchasing agency personnel: 3  Tot. = 11  

IDI  

Challenge of implementing PBF in Cameroon and solutions devised to address the challenges. The role of PBF in shifting operating processes within the health system at regional and national levels (i.e. the introduction of a Purchasing Agency has changed the dynamics at the regional and national levels). The ways in which PBF reinforces (or 

Page 83: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 77 of 100

Level Type of Respondent

Respondent Details  

Estimated number of respondents  

Instrument Type  

Description of Data   undermines) autonomy across levels. Awareness, knowledge and application (perceived or enacted) of PBF components targeting the very poor, and challenges with targeting the very poor.  

District  

District Medical Officer  

District Medical Officer  

District Medical officers: 3 in each region  Tot. = 9

IDI  

Changes in daily work schedule brought about by PBF. How context affected PBF’s ability to influence indicators (particularly as relevant to performance indicators in PBF, i.e. vaccination, family planning, childbirth). How challenges associated with PBF are mitigated. The role of PBF in improving (or undermining) retention of facility‐based providers. Awareness, knowledge and application (perceived or enacted) of PBF components targeting the very poor, and challenges with targeting the very poor.  

Page 84: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 78 of 100

Level Type of Respondent

Respondent Details  

Estimated number of respondents  

Instrument Type  

Description of Data  

Facility Level  

Hospital and Health Center  

Providers within 1 hospital and 3 health centers per region  

Hospital‐based providers: 3 per hospital  (tot. 9)  Health center‐based providers: 2 per health center  (tot. 18)  Tot. = 27

IDI  

PBF’s role in influencing indicators (particularly as relevant to performance indicators in PBF, i.e. vaccination, family planning, childbirth). Perceptions of autonomy in relation to PBF. Facilitators or barriers to enacting change within the context of PBF (specifically contextual factors such as the supply chain). PBF’s impact on the lives and daily routines of providers. Levels of satisfaction with operational aspects of PBF and opportunities for improvement in this regard (probing on distribution of funds and governance aspects). Awareness, knowledge and application (perceived or enacted) of PBF components targeting the ultra‐poor; process/challenges with identifying and ultimately reaching (or not reaching) the very poor  

Page 85: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 79 of 100

Level Type of Respondent

Respondent Details  

Estimated number of respondents  

Instrument Type  

Description of Data  

Community  

Female Patients/Clients  

• 3 FGDs per region (1 per district)  • 3 IDIs/region with women who delivered at home  • 5 IDIs per region with women who use/do not use FP methods

FGDs  Tot. = 9  IDIs: 5+3 per region  Tot. = 24

 IDI and FGD  

Care‐seeking pathways and preferences and PBF’s influence on the experience of seeking and receiving care. Community understandings related to care‐seeking for specific illnesses or conditions (particularly as relevant to performance indicators in PBF, i.e. vaccination, family planning, childbirth). Community sense of engagement in PBF and perceptions of PBFs impact on access to care among the very poor.  

Total IDIs = 71  FGDs = 9

 

71. Key evaluation questions are:  

 At the National and Regional level: 

What were the challenges the Ministry and regions faced to implement and support PBF? What are the solutions adopted?  

How did the national level stakeholders address the challenges   posed by PBF? (including the lack of counter‐verification). 

Page 86: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 80 of 100

How has the introduction of a Purchasing Agency affected health system dynamics at regional and national levels?  

How is the concept of autonomy (as it is advocated by PBF) perceived by the authorities?  

What is the awareness, knowledge and application (perceived or enacted) of PBF components targeting the ultra‐poor, and what are the challenge associated with targeting the ultra‐poor?   

At the District level:  

How has daily work changed in the context of PBF? (Including supervision, production and use of data)  

 What contextual factors have facilitated or inhibited change in terms of implementing the PBF program?  

How did district level staff address the challenges posed by PBF? 

 How (if at all) did PBF affect provider retention?  

 What is the awareness, knowledge and application (perceived or enacted) of PBF components targeting the ultra‐poor, and what are the challenges associated with targeting the ultra‐poor?   

At the (Facility‐based) Provider level:   

How has PBF   brought about changes in some aspects of service provision (vaccination, FP) and not others (skilled birth attended) – as suggested by the changes captured on the single PBF indicators by the quantitative impact evaluation?  

 How has autonomy and limits to autonomy influenced the ability to produce change?  

 How has the context (including the drug supply chain) influenced the ability to bring about change or otherwise?  

 How has daily work changed following the introduction of PBF? (Including reference system, workload, social control, home visits, production and use of data).  

Are providers satisfied with the system of distribution of money and governance applied by the PBF program?  

 How (if at all) has care for indigents been established in given facilities?  

 What is the awareness, knowledge and application (perceived or enacted) of the PBF components targeting the ultra‐poor? What process/challenges are inherent in identifying and ultimately reaching (or not reaching) the ultra‐poor?   

At the Community level   

Where does the community go for treatment and why? How has PBF affected decisions related to care‐seeking pathways? Has PBF redirected demand towards specific facilities?  

 Why has PBF produced changes in some aspects of service and not in others – as suggested by the changes captured on the single PBF indicators by the quantitative impact evaluation?  

How has PBF affected the community perception of quality of health care?  

 How has the community been engaged in PBF?  

How has PBF impacted access to care among the poorest of the poor (if at all)? 

 

Page 87: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 81 of 100

RESULTS 

72. The results of  the qualitative  impact evaluation show that PBF  improved staff satisfaction and 

motivation, and led to better quality of care and improved work environment. Facilities were equipped 

and stuffed with better drugs and better equipment. Supervision and coaching also improved significantly. 

Major improvements noted are as follows: 

 73. Improved  attitude  of  health  workers  toward  work.  Through  PBF  interventions,  the  project 

significantly  changed  workers’  mentality  and  attitude  towards  work.    PBF  changed  health  workers’ 

mentality and attitude towards work. Majority of health workers  indicated that PBF requirements and 

standards  they  had  to  meet  helped  them  to  become  more  serious  with  their  work  and  strived  for 

excellence. The change  in mentality and attitude was  triggered by  the  requirements  in PBF contracts, 

which defined the quantity of services provided (which leads to higher PBF revenues for facilities) and 

standards for service delivery.  Box 7.2 provides testimonies of some health workers.                  Box 7.2: Development impact of PBF interventions (1) 

“The changes I have seen with PBF are more positive than negative. Now we have means of measuring our own output, which in turn gives you some satisfaction. And above all most of our services have improved in the eyes of the users. (...) PBF has brought a change in mentality. It has made people to be more focused, it makes some of us in leadership positions feel that we are doing something” (a DMO).  “In the first few years, it was exciting. We saw a lot of improvement in quality and quantity which motivated the workers. They were all excited about it. There was even some contamination effect, the extent that even those who were not in the program started copying the good practice that are in the program” (Regional Delegate).  “Now they have improved. If you work well you are going to be motivated and it also gives us a sense of direction   which is very important (...). PBF has made us change our attitudes: it is good to give your clients goods services, which PBF can also buy” (Provider, District Hospital). 

 

 

74. Enhanced capacity of health workers. A considerable number of health workers  indicated that 

they learned a lot from PBF initiatives, which enabled them to effectively use clinical and administrative 

tools such as the partogram during deliveries and the facilities’ business plan (Box 7.3). 

             Box 7.3 Development impact of PBF interventions (2) 

“(We had) improvements in our district supervision. I think PBF has opened our eyes to things which we didn't do before” (DMO).  “They supervise us to ensure that everything is well done. I have seen that they are really making us change our attitude towards work and we learn new things every day. When they come (for supervision), they teach us” (Provider, Health Center, South‐West region). 

  

Page 88: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 82 of 100

75. Improved supervision and coaching at facility level: Facility level service providers were supported 

immensely under PBF because of increased supervision from the DHMT as well as training provided by 

staff of the purchasing agency (Box 7.4). 

 

Box 7.4 Development impact of PBF interventions (3) 

“Everything is codified in such a way that one had to work within a certain rhythm. I have the contract with the district and the region I must sign for that. They tell you specifically that, you have to do this number of supervisions and you have to have this or that., Because the rules are very clear, it allows for transparency, clarity, …initiatives, pro‐activity, good governance, good management, and so many things that are for the common good of all and not individuals” (DMO).  “Au début du programme, ils (staff de l’AAP) venaient avec des informations pendant les supervisions 

de  qualité.  Ils  venaient  nous  montrer  ce  qu’il  faut  faire.  Donc,  ils  venaient  nous  former  dans  les 

connaissances que nous on n’avait pas avant (…). Ils nous ont montré beaucoup de techniques que nous 

appliquons  déjà  maintenant.  Le  PBF  nous  a  amené  à  comprendre.  Par  exemple,  au  niveau  des 

prescriptions  quand  il  s’agit  des  IST  (infections  sexuellement  transmissibles),  avant  on  prescrivait 

vraiment n’importe quoi. Ils sont venus avec le protocole national des IST qu’on nous on n’avait pas ici” 

(Provider, Heath Center, Eastern region). 

 

76. Improved  reporting  at  the  central Ministry  of  Health.  Directors  and  health  authorities  at  the 

central  level  emphasized  that PBF  strengthened  the use of  reporting  tools  and enforced  standards  in 

service delivery  in both public and private facilities. Before PBF, private facilities     did not provide any 

information to the Ministry of Health (Box 7.5). 

 Box 7.5 Development impact of PBF interventions (4) 

“There is virtually no distinction between public health unit and private for profit and conventional, because all 

of  them      produce  the  same  results.  That  is  a  substantial  change. Now private  health  units  produce  reports 

statistics” (central‐level interview). 

 

77. Changes  in  the work  environment.:    PBF  significantly  changed  the  environment within which 

health  facilities  operate.  It  led  to:  (i)  clean  work  places;  (ii)  improved  infrastructure;  (iii)  effective 

procurement of drugs and pharmaceuticals; and (iv) increased number of health personnel.  

 

Clean workplace: Health workers and district managers reported that their workplaces are now 

cleaner, tidier and more hygienic than before.  Thanks to the additional financial resources that 

they received from the project. 

Improved health infrastructure and equipment: PBF also led to better infrastructure and buildings 

(e.g.  upgrade  facilities’  premises,  renovation  of  infrastructure,  etc.)  and  equipment,  including 

generators, autoclave, fridges, laboratory equipment, delivery beds, weighing scales, bedsheets, 

nets, incinerator, placenta pit, toilets for facilities; and motorcycles, computers and TV screens 

for DHMTs.  These improvements were realized because of availability of extra funds from PBF, 

and  the  fact  that  the  facilities had  to ensure  that basic  infrastructure and equipment existed, 

Page 89: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 83 of 100

which  were  a  requirement  under  PBF  and  were  linked  to  the  quality  score  and  payment 

calculation. However, PBF did not adequately address the major challenges such as lack of running 

water  and  electricity,  and  the  so‐called  plateau  technique  (i.e.  the  availability  of  technical 

equipment for service delivery) remained uneven across the facilities and districts (Box 7.6). 

Box 7.6 Development impact of PBF interventions (5) 

“The environment has greatly changed, there  is a  lot of order, the place  is clean, there  is no odor. They have renovated the buildings too, they have painted the walls and put tiles on the floor” (Provider, District Hospital).  “On await des préoccupations en matière d’approvisionnement en intrants , en médicaments, en matière d’infrastructures, d’équipements, en matière même des ressources humaines, mais avec le PBF, il y a quand même une amélioration dans les infrastructures, il y a beaucoup de structures sanitaires qui ont eu à assurer leur extension en termes d’équipement aussi en ressources humaines, il y a eu beaucoup de personnels qui ont été recruté sous fonds PBF, voilà, je pense que c’est tout au moins des améliorations qui sont assez palpantes, oui, oui” (Regional Delegate).  “Je prends l’exemple de l’hôpital de District de la Cité des Palmiers, qui est un exemple patent. Quand le projet 

commençait,  il  n’avait  qu’un  bâtiment. Mais  avec  les  possibilités  que  le  PBF  lui  a  apportées,  les  activités  de 

l’hôpital de district se sont tellement agrandies qu’il a dû étendre les bâtiments, il a même voulu construire un … 

Malheureusement avec le problème administratif, il n’a pas pu, mais il a étendu vraiment ses activités” (central‐

level interview). 

 

78. Improved human resource situation:  Improved human resource situation:  The implementation of 

PBF interventions allowed facilities to have budgets and managerial autonomy, which enabled them to 

address human resource challenges. With PBF funds, the facilities could recruit and pay salaries of new 

staff in most workplaces.  It’s been reported that there are positive effects on the quality of care in most 

health facilities. However, delays in PBF payments affected retention of staff recruited with PBF funds. 

Some of these workers did not receive their salaries for several months and so left their posts after some 

time.    Also,  rigidities  in  administrative  and  labor  regulations  affected  the  legal  status  of  the  locally‐

recruited workers  as  there was  no  clarity  of  their minimum  contributions  to  the Caisse Nationale  de 

Prévoyance Sociale(CNPS) (Box 7.7).   Box 7.7 Development impact of PBF interventions (6) 

Quand le PBF est arrivé à l’Est, on avait par exemple dans le district de santé de Moloundou qui est le district le plus éloigné, on avait 70% des FOSA publique qui étaient fermés parce qu’il n’y avait pas de personnel. Aujourd’hui, toutes les FOSA publique du district de Moloundou sont ouvertes parce qu’il y a des personnels recrutés sous fond PBF” (CVA manager).  “Avec les retards de virement, les 75% du personnel qui avait été recruté dans le District de santé de …1 ont tous démissionné par faute de salaire !” (DMO).  

  

79. Strengthened relationship between facilities:  PBF has indeed strengthened working relationship 

between health facilities’ staff as well as the communities they serve. Through a participatory process of 

Page 90: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 84 of 100

developing business plans, staff working relations has significantly strengthened.   There are now more 

collaborations and better transparency in decision‐making. There are also regular weekly and monthly 

staff meetings. By employing the index tool provided by the PPA, decisions for sharing bonus to staff are 

done without conflict.   District and health centers’ providers point of view are as follows (Box 7.8).   Box 7.8 Development impact of PBF interventions (7) "It (staff meeting) involves everybody, everybody comes, and sit and we take decision and prioritize the needs. And then, we take the need that are favorable and we tackle them. It is a bottom‐top approach” (Provider, District Hospital).  “Je peux dire qu’on nous paye selon l’indice, selon les performances de tout un chacun. Ça n’a jamais 

créé les problèmes ici, mais… bon, nous sommes quand même des êtres humains, donc [sourire] pour 

la répartition, comme on sait que c’est selon l’indice, c’est selon les performances,  les catégories et 

tout tout tout, la responsabilité et tout ça, bon. On calcule avec le chef par rapport à ça. [Chercheur : 

et tout le monde est d’accord ici ? Ça ne créé pas des tensions ?]. Ah ! Parfois. Mais plus généralement, 

ça ne créé pas des tensions, on gère selon l’indice. On a un chef et le chef quand lui il décide, on marche 

selon ce qu’il dit et selon les décisions aussi” (Provider, Health Center, Eastern region). 

 

80. While PBF has improved working relations among staff of health facilities, there are others who 

held opposing views.  Some of them indicated that there are less positive relations amongst staff. They 

contended that they were rarely involved in decision‐making and that there was lack of transparency in 

the use of funds (i.e. facilities’ investment funds, recurrent costs, and individual staff motivation funds).  

In some instances, certain managers; though, absent from work assign themselves with high scores to 

obtain high PBF bonuses. Aggravating the situation is delays in payment of bonuses, which made some 

staff  get  the  impression  that  their managers are  siphoning  their money  for personal  gain.  The  survey 

shows that hospitals and the larger facilities suffered worse interpersonal relations than the smaller ones. 

Moreover, health workers in the facilities that provided services other than those related to maternal and 

child health (which are covered by the PBF program) pointed out tension between staff working in the 

maternity and pediatric wards and staff working in the other wards. Testimonies of providers in health 

centers are as follows (Box 7.9). 

 Box 7.9 Development impact of PBF interventions (8) “La réalité que j’ai observée dans notre hôpital c’est que c’est la direction qui prend les décisions de tout, que ce soit le business plan, les ten keys, la répartition des finances, l’outil indice, c’est eux qui gèrent tout à leur niveau. Et bon donc… et nous, on ne participe pas beaucoup, par exemple dans mon unité, je ne sais pas…“ (Provider, Health Center, South‐West region).  “Il  (chef  du  centre)  n’est  jamais  là.  Mais  lors  des  partages  des  subsides,  lui  il  est  présent.  Il  a  ses  points complètement. Par contre, nous nous perdons nos points. Oh, tu as eu l’absence de trois ou quatre jours, on te fait perdre les points comme ça là (…). Je pensais que le PBF allait mettre une ligne que c’est : chacun bouffe à la sueur de son front, que normalement c’est ce qui devait se passer, mais je me rends compte que tu travailles et les autres mangent” (Provider, Health Center, Eastern region).  

Page 91: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 85 of 100

“Les payements des subsides ne sont pas régulier ‐ vous voyez. Le personnel lui il ne comprend pas ça forcement 

‐ vous voyez, il va attendre six mois. Par exemple là, il y a des subsides de mars qui ne sont pas payés. Donc vous 

voyez qu’ils vont attendre, ce qui fait que ce n’est pas toujours bon pour nous lorsqu’on commence à se laisser 

aller au découragement, on commence même à boycotter, parfois en se disant que le directeur, il a reçu malgré 

ce qu’il nous dit là, il a reçu. Il s’est assis sur l’argent ou bien…” (Provider, District Hospital). 

 

81. Improved relationship with patients and community.:  While in general the relationship between 

providers and patients were reported to have improved (at least, from the perspective of the providers) 

as health workers were  increasingly aware of  the  importance of a good reception of patients, specific 

accounts of their relations with the community were both positive and negative. In particular, under PBF, 

feedback from patients was collected during the community verification and then shared with providers. 

This feedback was appreciated by   majority of the respondents and valued as a means of enabling health 

workers  to  improve  their  practice.  In  some  cases,  however,  the  feedback  caused  tension  in  the 

communities when the health workers were found to disagree with the assessment made about their 

work. 

 

82. Community participation in decision‐making is also, in principle, requested by PBF which requires 

regular meetings with  the health management  committee  (COSA,  COGE,  CODESA,),  and needed  their 

participation in the drafting of the business plan. However, in practice, this was rarely mentioned in the 

interviews  with  the  health  workers,  and  district  managers  interviewed  indicated  that  community 

participation to the management of the facilities was still very limited and problematic. 

 83. Health care seeking behavior.   The survey shows  that women who sought antenatal  care  in a 

facility  close  to  their  area of  residence was  60.9  percent,  55  percent  for  deliveries,  and 60.6  percent 

postnatal care. At baseline, 52.3 percent for women who received antenatal 51.9 percent delivered, and 

only 56.1 percent   sought postnatal care in facilities close to their area of abode.  

 

 The “health care shopping” behavior whereby households bypass the closest health facility is also present 

for deliveries and postnatal care. At baseline, focusing on women for whom we have information about 

the service location and who sought care in a facility, only 51.9 percent delivered, and only 56.1 percent 

sought postnatal care in linking changes to a facility with their corresponding treatment group.  

Knowledge of PBF and project  84. Despite  its  remarkable  success,  PBF was only  known among  few women  in  the  communities. 

Majority of the women did not link the changes to the efforts of PBF. Only few women correctly linked 

PBF to the home visits carried out by the facility staff to check the hygiene standards in the homes in the 

community, and had a positive opinion of those visits.   Some women knew about  it because they had 

been involved in a CBO in charge of carrying out the community verification, or because they had been 

selected as patients to be checked during the community verification. 

 

Page 92: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 86 of 100

  Changes in health facilities:  85. During the FGDs, women were also directly asked about the changes that they observed in the 

facilities over time, with reference to the facility in their community, selected only from the treatment/full 

PBF group. In their responses, they mentioned that indeed some (mostly) positive changes had occurred 

in  terms  of  infrastructure  (new  buildings,  new  blocks,  laboratory  facilities,  separate  wards,  etc.), 

availability of drugs (though not in all facilities), increase in outreach activities, extended opening hours 

and availability of staff. However, in some facilities in the North‐West region, participants said that there 

were fewer nurses and   lack of equipment (7.10). 

 Box 7.10 Development impact of PBF interventions (9) Il y avait manque des infirmiers. Mais maintenant là,  le jour comme la nuit  il y a les infirmiers de garde et les numéros de téléphone sont là ; à n’importe quelle heure tu arrives, tu vas trouver l’infirmière là. (...) Et tu vas trouver les médicaments. Ce n'est plus comme avant ou il fallait aller chercher les autres médicaments ailleurs“ (FGD, Eastern region).  “Il (infirmier titulaire) accueille bien ses malades et il est trop gentil. Même si que tu accouches que tu n’as pas l’argent,  il  va dire  je  t’accouche,  je  te  fais accoucher,  tu vas chercher  l’argent après.  Il est  trop gentil!”  (FGD, Eastern region).  “There is a new structure, a lab, separate ward for women, new maternity. It is clean (...). The number of nurses 

increased. There are now 3 nurses and 1 midwife, formerly there was only one nurse here” (FGD, North‐West 

region). 

 

86. Demand Side interventions and assisted delivery. Secondly, extending the point above further, 

demand‐side  barriers  emerged  as  a  key  factor  to  influence  uptake  of  certain  services.  Such  barriers 

included, critical, geographical and financial ones which are related to the distance to the facility as well 

as direct and indirect (e.g. transport) costs of accessing services. Demand‐side barriers were not explicitly 

addressed by the PBF program, and for some services, such as assisted delivery, they would have been 

more difficult to overcome by providers alone. For example, during outreach in the communities, both 

vaccinations and family planning can be provided and women can be informed about family planning and 

be provided related devices when at the facility for other reasons., Assisted deliveries on the other hand 

require patients  to physically go to  the facility, and at specific point  in time. This may be complicated 

because of lack of transport or funds to cover it, or because of the costs associated to delivery in facilities. 

 87. Finally, it is important to stress that PBF was not introduced in a void.  A number of other programs 

and  projects  continued  to  be  implemented  in  the  same  facilities  and were  likely  to  influence  health 

outputs  and  outcomes.  These  programs  included,  the  introduction  of  delivery  kits mentioned  above, 

support to family planning provided by the GIZ, to vaccination from UNICEF, and to other services by other 

donors,  and  the  creation  of mutuelles  de  santé  or  externally‐supported  insurance  schemes  (e.g.  for 

women’s care by GIZ), etc. It could be interesting to explore whether these programs similarly affected 

facilities  across  the  regions,  districts,  and  the  different  arms  of  the  trial  or  whether  they  were 

Page 93: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 87 of 100

implemented only in some areas/facilities. This would allow investigating whether PBF has a multiplicative 

effect when coupled with other interventions, and those addressing demand‐side barriers. 

  88. The analysis contributes to further explore and shed light on one of the findings of the quantitative 

impact evaluation which found a significant increase in child vaccinations and utilization of modern family 

planning. Even though significant changes were not noted in assisted deliveries between PBF and control 

facilities, both providers and patients’ narratives indicated that, there had been change over time in the 

service delivery practices. Providers and women’s narratives converged to indicate that outreach activities 

(whether  in  the  form  of  community  visits,  school  visits  or  the  establishment  of  outreach  posts)  had 

become  more  common  in  recent  years.  Interestingly,  providers’  narratives  further  explained  that 

increased investments in outreach activities were made possible by the increase in the resources provided 

by PBF. The investment was made considering a clear understanding that it will further enhance one’s 

utility through the attainment of a specific set of performance indicators. 

 89. Moreover,  it  seemed  that  sensitization  of  family  planning  has  increasingly  been  provided  to 

women outside of situations that target specifically family planning and information about it.   This has 

somewhat been integrated in the delivery of other services (for example, women are  informed during 

ANC or PNC visits, or during child vaccination). Women also generally identified providers as their primary 

source of  family planning knowledge16. These  findings  seem to  imply  that providers have proactively 

changed the practices related to the delivery of some services, to increase utilization to maximize their 

income. This change was aimed at activities and services that were known as  ‘low hanging fruits’, e.g. 

where a substantial change  in coverage could be obtained at a  low cost.  In most cases,  the strategies 

enacted consisted of increased outreach and sensitization which are likely to have had an impact on family 

planning and vaccination outputs. 

 

ANNEX 8. SUMMARY OF BORROWER’S ICR 

90. The implementation of PAISS took place in Cameroon in a context marked by inefficiency of health 

expenditure and the policies which were implemented. In fact, between 2001 and 2010, Cameroon had 

more than doubled its health expenditure (public and private) per capita from $26 in 2001 to USD in 2010, 

but  most  of  its  health  indicators  stagnated  or  improved  very  slowly,  with  an  even more  worrisome 

situation in the impoverished areas. It should be noted, however, that at the same or lower expense, most 

low‐income countries can achieve better results. 

 

91. To cope with this situation and to sustainably improve the performance of the health system in 

Cameroon, particularly maternal, neonatal and infant mortality, the government, with the support of the 

World Bank, implemented the PAISS project and introduced a new reform, known as the performance‐

based financing in the health sector. 

 

Page 94: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 88 of 100

92. The objective of this project was to improve the quality and accessibility of healthcare services. 

The focus was on maternal and children’s health and the prevention of communicable diseases. The PAISS 

implementation approach is PBF, which is results‐oriented (quality, efficiency, equity) reform of the health 

system.  It  involves  transferring  financial  resources  to  health  facilities  in  proportion  to  their  monthly 

benefits. To benefit from more resources, each health facility (and staff) were supposed to put in place 

innovative strategies to improve the quantity and quality of healthcare services provided. 

 

93. The  Financing Agreement  for  the project was  signed between  the government and  the World 

Bank on October 30, 2008 and  its effective date was declared on January 29, 2009. Given the success 

of the project,  it was  agreed upon  that an additional  funding of  $  20 million  and another $ 20 million 

donation be given on September 19,2014 and September 26, 2014 respectively. 

 94. Project activities were organized around two components, namely: 

 

Component  1 "Provision  of  services  at  district  level”: This  component  provides  support  to financing  contracts  based  on  past  performance  of  regional  funds  for  health,  district  health committees, NGOs and / or health centers. 

Component  2 " institutional  strengthening" This  component  includes  financial  and  technical support  to  strengthen  two  key  normative  functions  of  the  Ministry  of Public Health at  the national,  regional  and  district  levels. Support  is  provided  in  two  main  areas:    contract management and design, and the establishment of a unified information system. 

 95. Under  the  terms  of  the credit  agreements IDA  credit  No.  4478‐CM  and No.  5486‐

CM and Don number MDTF‐HRI GRANT No. TF017128, a final evaluation of the project is provided by the 

government and the transmission ratio of the said assessment submitted by IDA no later than December 31, 

2017. 

 96. This completion report is a document prepared by the Government to assess the performance of 

the ISSA project while analyzing its relevance, effectiveness, efficiency, sustainability and impact, 

 97. Specifically, it was to: 

  

Evaluate the design and relevance of the actions carried out by the Health Investment Support Project in view of the policies in force and the expectations of the beneficiary populations; 

Measure the performance of the Health Sector Investment Support Project in terms of the level of execution of the activities and the results, including measures taken for their sustainability; 

Determine the effects and impact of the Project on the beneficiaries and   the health sector in general; 

Evaluate the institutional and organizational scheme of the Project; 

Evaluate the procurement and monitoring‐evaluation systems of the project; 

Evaluate the project planning mechanism; 

Evaluate the performance of the various actors involved in the implementation of the project; 

Page 95: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 89 of 100

Analyze the financial management of the project; 

Identify the difficulties encountered and the solutions applied or envisaged; 

Evaluate the  impact of exogenous factors on the performance of  the  implementation and the quality of the responses; 

Identify lessons learned; 

Evaluate the prospects for sustaining the achievements of the Project, the actions to be taken to ensure the sustainability of the infrastructures set up by the project. 

  98. To  achieve  these  objectives,  a  methodological  approach based  on  five key  milestones  was 

adopted.  They are;  

(i) the establishment of a working group in charge of the final evaluation following the decision of the 

Minister of Economy, Planning and Spatial Planning,  

(ii)  the  collection  and  exploration  of  findings  in  the  documents  made  available  by PAISS  project 

implementation according to age and other factors. 

(iii)  the  organization  of  a  workshop  for  the  adoption  of  the  project  intervention  approach  and  the 

guidelines for the report.  

(iv)  the organization of  the  focus groups on  the appreciation of  the  implementation of PAISS with  the 

participation of the beneficiary health facilities. 

(v)  the organization of  two workshops devoted  respectively  to  the  review and  validation  of  the draft 

version of the completion report. 

 99. At  the  end  of the  process,  the  overall  performance  of  PAISS was  deemed 

satisfactory. The disbursement rate at December 31,2017 is 96.36% and the project achieved (see below) 

its  objective  since  the  targets  of  all  the  related  indicators  were  largely  exceeded. Indeed, the 

implementation of  the project made possible the signing of 584 performance purchase contracts with 

health facilities:  

(i) 3,175,893  people  (instead  of  1,500,000)  have  had access  to  a  basic  health 

package. 

(ii) increased the number of births attended by skilled personnel i.e. from 57 139 per 

quarter to 147,269  (a 245% achievement rate). 

(iii) increased the number of fully immunized children (PENTA 3) 90 595 to 182,901 

(a completion rate of 91%). 

RELEVANCE 

 

100. To evaluate the relevance of the PAISS project, we analyzed the following:  

 

(i) The alignment of the development objective with national policies in the health 

sector. 

(ii) The relevance of the mechanism put in place for performance‐based financing. 

(iii) The consideration of expectations of beneficiaries. 

 

Page 96: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 90 of 100

101. At the end of the evaluation, the performance of the PAISS project in terms of its relevance was 

considered    satisfactory   because it received at least a satisfactory rating for each of the three criteria. 

The  development  objective  of  the  project that remained  aligned  with  the  policies  in  the 

health sector including  the  ECSD  regarding  its  axis  human  capital  development  and  the  health  sector 

strategy was concerned with the servicing aspects of all the health districts with a view to achieving the 

MDGs. 

 102. Regarding  the  PBF  approach,  it  should  be  noted  that  the  implementation  process  has  not 

undergone major changes  throughout  the  implementation of PAISS. The  improvement was concerned 

with only the simplification of the payment procedures using the grant of this function for the PMU. Thus, 

in  accordance  with  PAISS's  rating  methodology  for  this  criterion,  its  performance  was 

judged   satisfactory   because of the slight changes made in the implementation mechanism of the PBF. 

 103. In terms of considering the expectations and needs of the beneficiaries, the latter indicated that 

despite their weak involvement in the project preparation: (i) the performance indicators were in line with 

the priority needs of the health system, and (ii) the training received was fully consistent with their needs, 

although there are still additional training needs. Despite the low involvement of the beneficiaries, the 

performance of PAISS is taking into account the fact that their expectations were considered satisfactory 

due to the consistency between the indicators purchased and the priority needs of the health system, the 

MDGs and the sectoral strategy.  

  

EFFECTIVENESS   

 

104. The effectiveness of the project was rated satisfactory. The targets of the indicators selected to 

assess the level of achievement of the expected results of the project implementation have been reached 

at more than 90%, which is largely exceeded (achievement rate above 125% and reaching up to at 245% 

for some indicators). One of the key success factors of the project remains the strong political will of the 

government and the good appropriation of the approach by all the actors of the PBF chain. 

 105. Despite the positive results achieved, it should be noted that the satisfactory implementation of 

the business plan remains one of the major challenges that the operationalization of the PBF approach in 

the health sector still faces as one of the main constraints. The following were noted:   

 (i) The cumbersome payment procedures resulting in the irregularity of such payments.    

(ii) The decline in FOSA receipts due to the unilateral change in the cost of purchasing certain 

indicators. 

(iii) The cumbersome procurement procedures that prove to be mandatory for the realization 

of investments whose cost is greater than 5 million FCFA. 

EFFICIENCY  

Page 97: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 91 of 100

106. The performance of the PAISS project in terms of its efficiency is considered satisfactory. Looking 

at  the  functioning  of  the  institutional  mechanism  of  the  project  and  that  of  the  of  the  PBF,  all  the 

structures put in place have adequately fulfilled their functions although some challenges remain in PBF 

communication and awareness, on one hand, and the annual organization of the indicator review work 

on the other.  

 107. In terms of timing, it should be noted that the implementation deadlines were extended by two 

years for initial funding due to the lack of consideration of the time needed for the project formulation. 

This was necessary for the appropriation and implementation of all the tools of the PBF approach. This 

time frame was met for additional funding and donation, given that the above constraints had already 

been tackled. 

 108. With respect to procurement, it should be noted that the number of contracts to be awarded was 

quite  limited  compared  to  other  projects  in  the  portfolio. However,  the  main  constraint  was  the 

cumbersome procedure. Despite this constraint, the project's performance is considered satisfactory. 

 109. With respect to fiduciary management, it is important to note that the disbursement rate of all 

the resources made available to the project was 96.36%. Project performance was satisfactory given that 

resources were disbursed according to plan and compliance with reporting obligations and auditing. 

 110. Regarding monitoring and evaluation, it should be noted that all the products expected had been 

produced. Moreover, the effectiveness of the functions of the PBF portal must simplify the process of data 

transfer. 

SUSTAINABILITY  111. The appreciation of PAISS  in  terms of  sustainability  is satisfactory because it has, on one hand 

supported the  establishment of  new  sustainable  institutions  in  the  health  sector  and  on  the  other 

contributed to the capacity building of this sector. This was done during the introduction of the funding 

mechanism based on the performance as an innovative approach to improving access to quality health 

care. 

 112. The provisions relating to the establishment of these institutions, particularly the CTN and the 

regional health funds are a guarantee for their legal survival, given the key role played by these structures 

in the field of health and the framework of the institutionalization of the PBF approach in Cameroon. 

 113. In terms of financial sustainability, the government has not only mobilized additional resources 

for the scaling up of the PBF approach, but also plans to allocate at least 20% of MINSANTE's budget to 

the purchase of performance in health facilities. 

  114. In  addition,  in  view  of  the  results  obtained,  the  PBF  approach  was  chosen  as  a  transversal 

dimension  of  implementation  of  the  new  health  sector  strategy  covering  the  period  between  2016‐

Page 98: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 92 of 100

2027.Despite  this,  there  are  still  some  challenges  in  strengthening  PBF  ownership  and  involving  all 

stakeholders  in  the  process  of  updating  the  PBF  implementation  tools. In  this  regard,  we  make  the 

following recommendations: 

IMPACT  115. The implementation of the PBF approach through PAISS has considerably increased the level of 

attendance  of  health  facilities  under  PBF  contract which  increased from  2,448,270  people  in  2013  to 

3,774,895  in  2016  (i.e.  54.18%  increase  in  almost  three  years). This  situation  had  a  positive  impact 

on maternal and child health indicators in the targeted regions, particularly in the Eastern Region where 

almost all (14) the health districts were covered. The delivery rate witnessed an increase of 8% while it 

stagnated in almost all the other parts of the country, per the results of the MICS 2014. 

 

116. Worthy of note  is  the fact  that the  implementation of PBF has helped to  increase the number 

of assisted childbirth by medical staff (1.3% increase) in health facilities under PBF while it fell by 0.7% in 

other health facilities. The implementation of PAISS has also improved the quality of services and health 

care. The  level of availability of essential drugs has increased by more than 10% at the health facilities 

under PBF while it has stagnated (1% increase) in other health facilities. In addition, the quality of technical 

equipment of health facilities in PBF has improved. The proportion of essential equipment for delivery has 

increased  significantly  in  the health  facilities under PBF while it has virtually  stagnated  in other health 

facilities. As  a  result,  the  level  of beneficiary satisfaction with services  provided  for  children  under  5 

increased by 15% for PBF facilities while this indicator decreased by 7% in the other health facilities.  

117. Also, a prelude to the introduction of the PBF approach indicate that, Cameroon was one of the 

countries where health expenditure is found to be too high for mediocre results. In this regard, it should 

be noted that, in accordance with the conclusions of the impact study, health expenditure has decreased 

at  the  level  of  households  attending  health  facilities  under  PBF, whereas  they would  have  increased 

considerably  in  households  frequenting  other  health  facilities. The  same  is  true  of  parallel  payments, 

which would have increased considerably at the level of health facilities that are not under PBF while they 

have dropped by 882 FCFA at the level of health facilities under PBF.  

118. Worthy of note  is  the fact  that  the beneficiaries expressed their satisfaction with the changes 

made by PAISS in their health facility. In addition to improving the quality of the management of these 

establishments, PAISS made it possible for several investments to be made.  This is particularly the case 

of the district hospital of the city of palms which has built new buildings, has new services and raised its 

technical platform. Several other health facilities in other regions have inexperienced staff who would be 

more efficient under a PBF contract, which has not only improved the quality of care but also increased 

the package of services offered by the said health facilities. 

PERFORMANCE OF PARTNERS  

119. The  main  implementing  partners  for  PAISS  were  the  government  (MINEPAT,  MINSANTE  and 

MINFI  through CAA)  and  the World  Bank.  In  the  case  of  the World  Bank,  it  should  be  noted  that  its 

performance was rated “very satisfactory”. This is because this partner played its role appropriately both 

in terms of resource provision and facilitation, supervision and coaching for successful implementation of 

Page 99: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 93 of 100

PAISS. In addition, it has always issued its Non‐Objection Notice (NOA) and its comments on the AWPB, 

the PPM,  the Terms of Reference,  the Technical Specifications and the various stages  for  the markets 

subject to a prior approval within deadlines. This was quite impressive (i.e. one to two days maximum). 

 

In the case of the government, its performance is rated “satisfactory” because, despite the delays in the 

implementation and the respect of payment deadlines, it performed its functions appropriately. One of 

the main challenges facing this partner must resolve is the timely mobilization of counterpart funds and 

the budget allocated by the government for the payment of subsidies.   SUMMARY OF LESSONS LEARNED AND RECOMMENDATIONS: 

 Lessons learned from the relevance of the project: 

 

120.   In general, the PAISS project has been perfect in terms of the country's development policies, 

particularly  in  the  health  sector. From  the  relevance  analysis,  the main  lessons  learned  focus  on  the 

implementation of the PBF approach in Cameroon, the involvement of beneficiaries in the development 

of tools and the monitoring chain of project implementation. It should be noted that:  

The results obtained in the implementation of the PBF approach have enabled Cameroon to 

become  a  privileged  destination  for  sharing  experience  in  the  field,  and  encouraged  the 

government  to  transform  budgetary  resources  of  PBF  and  spread  to  other themes  such 

as education, early  childhood  development, marital  status and  public  finance  (public 

procurement.); 

The weak involvement of regional health delegations and health districts  in the revision of 

PBF operationalization tools (performance indicators, cost of purchasing indicators, method 

of validation of services provided to users, etc.) has not facilitated the appropriation of the 

said  tools  by  implementing  PBF  stakeholders  at  the  decentralized  level  (health  facilities, 

district s health, etc.); 

The weak involvement of health facilities in the process of validating their bill was not only a 

factor of demotivation, but also a major constraint in the implementation of their business 

plan (to the extent that they no longer received all resources planned and necessary for the 

smooth implementation of their business plan); 

The  lack  of  a  complaint  handling  and  redress  mechanism  would  not  have  allowed  the 

beneficiaries  to express their concerns. This situation would have  led to  the withdrawal of 

some health facilities that their grievances had been ignored by the PBF; 

Lack of knowledge of subcontracting management mechanisms, the lack of transparency of 

the main co‐contractor and the fact that the co‐contracting party receives 20% of subsidies 

from subcontracting health facilities is likely to discourage certain health facilities from joining 

the PBF; 

The relatively low cost of purchasing subsidies as well as the modification of the Community 

PBF indicators have not been favorable factors for the implementation of the Community PBF; 

Health facilities and other stakeholders of the PBF seem more oriented in their activities to 

areas where the cost of purchasing indicators seems quite high. This situation could create an 

eviction effect on the implementation of their business plan. 

Page 100: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 94 of 100

Several activities carried out by health districts, like routine controls, would not be included 

in performance indicators purchased under the PBF, which could negatively impact the quality 

of regulation at the district health level. 

  

    On the effectiveness of the project: 

 

121. Regarding the effectiveness of the project, the following were lessons learned: 

 

The implementation of the PBF approach has strengthened the managerial capacities of 

health facility managers through transparency in management and has also introduced 

the culture of accountability at the level of regulators and providers. 

Instituting  a  rule  that  requires  health  facilities  to  purchase  medicines  primarily  from 

regional health funds has led to the lack of tracer drugs in some health facilities 

The administrative workload imposed by the PBF and other MINSANTE programs have an 

impact on the amount of time that the health care staff devote to health care delivery 

This  is  because  of  the  detailed  documentation  of  information  about  each  program, 

project, and PAISS which they were required to send to the Ministry of Health at the end 

of every month. 

The modification of data collection parameters on performance indicators without prior 

information from the FOSA reduced their performance. 

The replacement of the indicator linked to the supervision of community pharmacies in 

the health districts by the supervisors of the community pharmacies led to the absence 

of tracer drugs in certain health facilities. 

Regular non‐payment or late payment of subsidies to regulators and providers poses a 

serious threat to the PBF. 

  

 On the efficiency of the project: 

The lack of a timetable for the elaboration of the AWPBs made it impossible to have it on time. 

Failure to comply with the deadline for submitting invoices created a delay in the processing of 

invoices for the payment of subsidies. 

The  understaffing  of  the  project's  fiduciary  team  also  led  to  the  delay  in  the  payment  of 

subsidies. Indeed,  after  the  restructuring  of  the  project,  the  workload  of  the  fiduciary  team 

increased. This situation improved slightly with the recruitment of financial assistance within the 

UGP. 

The  non‐operational  effectiveness  of  the  PBF  portal  led  to  the  continuity  of  manual  invoice 

processing, particularly in the South West and Littoral regions. 

  

On the performance of the partners: 

Ownership of the project in MINSANTE and the involvement of the Minister of Public Health in 

the project enabled  the mobilization of about 670 million  in  the budget of MINSANTE  for  the 

payment of subsidies in 2016. 

 

Page 101: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 95 of 100

 

  

On the sustainability of the project: 

 

The establishment of a Health Programs Monitoring Committee made it possible to federate all 

efforts to achieve the objectives of the SSS. 

Capitalization of PAISS staff in setting up the PBF National Technical Unit at MINSANTE 

  

II‐   RECOMMENDATIONS 

 

122. In view of the difficulties encountered and lessons learned in the implementation of PAISS, the 

following recommendations were made: 

Relevance of the project 

Organize consultations of actors at the deconcentrated level as a prelude to the revision of PBF operational tools. 

Reinforce the appropriation of the operational tools for implementing the PBF approach, such as 

the index tool by providers (health facilities). 

Put in place a mechanism to resolve complaints within the framework of the PBF. 

Define a clear mechanism and credible criteria for the selection of health districts and facilities 

eligible for PBF. 

Initiate a reflection to identify additional indicators that could be purchased at health districts to enable the team to accomplish their mission. 

Involve health districts in the regulatory activities of hospitals in their area of responsibility. 

Recruit an expert  in  communication and knowledge management  to better  communicate and 

document the best practices observed in operationalizing the PBF approach. 

Reflect on improving the management of subcontracts under the PBF. 

Initiate consultations to better determine the cost of purchasing  indicators for the community 

PBF. 

  Effectiveness of the project  

123. To  improve  the  performance  of  future  projects  implemented  under  the  PBF  approach,  the 

following recommendations were made: 

Speed up the PBF portal's scalable maintenance process so that it can acquire new features 

to enable the facilities to use electronic invoice processing. 

Simplify the chain of payment of subsidies so that the NTC can pay bills directly without going 

through the Minister of Public Health and by the CAA. 

Ask  the health  districts  to  draw up  the AWPB of  the  actors  in  their  geographical  area of 

competence. 

Page 102: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 96 of 100

Increase  the  number  of  CTN's  financial  services  staff  so  that  they  can  play  their  role  of 

payment agency. 

Initiate  a  reflection  with  a  view  to  setting  up  a mechanism  to  ensure  that  the  expenses 

incurred on the payment of subsidies are consistent with the activities planned in the FOSA 

business plans. 

 Create a special account at the level of the Public Treasury for the payment of subsidies to 

health facilities / PBF providers. 

Establish processing time folders to all levels of the chain. 

Simplify and harmonize data collection and processing sheets for all projects operating at the 

level of a FOSA. 

 Extend the period of updating the business plan to six months to reduce the administrative 

workload at the level of the FOSA. 

Initiate a reflection with a view to simplifying the procurement mechanisms in the framework 

of the realization of investments to be financed by PBF resources. 

 

    Efficiency of the project  

124. In view of efficiency in the implementation of future operations in the sector, we recommend the 

following; 

That CTN is enabled to fulfill its communication and outreach functions by strengthening its 

staff through the recruitment of a communications specialist. 

 That the PBF approach should be strengthened by (given the scalability of the PBF approach) 

the CTN workforce to facilitate the implementation of cross‐check activities trimestral/ semi 

benefits at the health facilities. 

That workshops be organized annually with the involvement of all actors for the revision of 

the indicators such as cost costs, and that criteria should be predefined. 

That the annual national PBF seminar be regularly organized. 

That  a  schedule  for  the  development  of  the AWPB for  the  project  be  developed  and 

disseminated. This schedule must include the constraints on the transmission of AWPB for 

non‐objection no later than November 30 of each year. 

That the period of ownership of PBF tools be considered in the formulation of future projects 

to  be  operationalized  following  this approach, if  a  pilot  phase  of  the  approach  is  to  be 

experienced in the project preparation phase. 

To document  the  truncated practices of  the  financial  execution monitoring mechanism  so 

that it can be capitalized as part of the ongoing operation.: 

To carry out another impact evaluation of the PBF. 

    Partner Performance 

Concerning the MINEPAT, it is necessary to indicate in the correspondence, the required 

legal documents and a deadline for the receipt of the documents taking into consideration 

the deadlines for fulfilling the conditions of entry into force. 

Regarding  the  MINSANTE,  it  was  recommended  that  steps  be  taken  to  expedite  the 

disbursement of counterpart funds in collaboration with MINEPAT. 

Page 103: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 97 of 100

 

 

Sustainability  

125. The following recommendations were made: 

 

Consideration should be given to setting up an. CTN financing operating mechanism to limit its financial dependence on HSPP capacity. Its staff should be strengthened to make the transition across the region a PBF approach. 

That the administration and maintenance of the PBF portal be progressively transferred and that the IT department of the Ministry of Health institutionalize this tool. 

That a manual of the PBF standard operating procedures portal be developed for the transfer of certain powers relating to the introduction of invoices and the updating of data from health units to health districts 

That regulatory indicators be introduced in the PBF portal. 

That the annual PBF indicator map validation workshops be held with the effective participation 

of district health representatives, graves and stroke. 

                           

Page 104: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 98 of 100

ANNEX 9. SUPPORTING DOCUMENTS   

1. Aide‐memoires 2008‐2017 

2. Audit  Social  en  faveur  des  Indigents  et  des  Populations  Autochtones,  volume  1 :  Evaluation 

Sociale, CHEUMANI NOUDJIEU Charlotte, Février 2016, Consultant Socio‐environnementaliste.Des 

indigents et des Populations Autochtones, Volume 2, Plan d  ’Action. Fevrier 2016. CHEUMANI 

NOUDJIEU Charlotte, Consultant Socio‐environnementaliste.  

3. Elaboration du Plan de Gestion des Déchets Biomédicaux du Project d’Appui au Investissements 

dal le Secteur de la Sante. DJOCGOUE Pierre François, Socio‐environnementaliste Rapport révise, 

Février 2016. 

4. Enquête de Base de l’Evaluation de l’Impact du Financement Base sur le Résultat dans le Secteur 

de  la  Sante  Réalisée  par  :    L’Institut  de  Formation  et  de  Recherche Démographiques  (IFORD) 

Rapport Final, Yaoundé, Mai 2013. 

5. Financing  Agreement  (Additional  Financing  for  Health  Sector  Support  Investment  Project) 

between REPUBLIC OF CAMEROON and INTERNATIONAL DEVELOPMENT ASSOCIATION, Dated 26 

SEPT 201f ,2014 

6. International Bank for Reconstruction and Development, International Development Association, 

International  Finance  Corporation,  and  Multilateral  Investment  Guarantee  Agency,  Country 

Partnership Framework for Republic of Cameroon for the Period 2017‐21, February 28, 2017. 

7. International Development Association,  Project  Paper  on  a  Proposed Additional  Credit,  in  the 

Amount of SDR 13 million, (US$20 million equivalent), with an Additional Grant from the Health 

Results  Innovation  Trust  Fund  (HRITF)  in  the  Amount  of  US$20  million  to  the  Republic  of 

Cameroon for the Health Sector Support Investment Project May 30, 2014. 

8. Manuel  de  Procédures  Administratives,  Financières  et  Comptables  du  Projet  d’appui  aux 

Investissements dans le Secteur de la Sante (PAISS). 

9. Midline Qualitative Study Findings Report, Cameroon PBF Impact Evaluation, December 2014. 

10. Plan National de Développement Sanitaire (PNDS) 2016‐2020, MINISANTE, Aout, 2016. 

11. Project  Appraisal  Document  on  a  Proposed  Credit  in  the  Amount  of  SDR  15.3 million  (US$25 million equivalent) to the Republic of Cameroon for a Health Sector Support Investment Project May 29,2008. 

12. Project paper on a Proposed Additional Credit  in  the Amount of SDR13 million  (US$20 million equivalent) with an Additional Grant from the Health Results Innovation Trust Fund (HRITF) in the Amount of us$20 million to the Republic of Cameroon for the Health Sector Support Investment Project, May 30, 2014. 

13. Qualitative  Research  to  Explain  and  Unpack  Quantitative  Findings  from  a  Performance‐Based 

Financing Pilot in Cameroon Final report March 27, 2017. 

14. Rapport  d’Achèvement  du  Project  d’Appui  aux  Investissements  du  Secteurs  de  la  Sante, 

Décembre 2017. 

15. Republic of Cameroon, Cameroon PBF impact evaluation, March 24, 2017. 

16. Restructuring  Paper  on  a  Proposed  Project  Restructuring  of  Cameroon Health  Sector  Support 

Investment Project Credit: 4478‐CM to the Republic of Cameroon May 11, 2011. 

17. Restructuring  Paper  on  a  Proposed  Project  Restructuring  of  Cameroon Health  Sector  Support 

Investment Project Credit: 4478‐CM to the Republic of Cameroon February 5, 2014. 

Page 105: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 99 of 100

18. Restructuring  Paper  on  a  Proposed  Project  Restructuring  of  Cameroon Health  Sector  Support 

Investment Project Credit: 4478‐CM to the Republic of Cameroon January 2, 2017. 

19. Rapport de  la Revue Approfondie de  la Gestion Financière, Projet d’Appui aux  Investissement 

dans le Secteur de la Santé « PAISS », Mars 2018. 

20. Dossier  d’investissement  pour  l’amélioration  de  la  santé  de  la  reproduction,  de  la  mère,  du 

nouveau‐né, de l’enfant et de l’adolescent/jeune au Cameroun 2017‐2020. 

  

  

                                

Page 106: Document of The World Bankdocuments.worldbank.org/curated/en/... · aid effectiveness, SWAp is an approach to development that brings together key government institutions, development

The World Bank Cameroon Health Sector Support Investment (SWAP) (P104525)

Page 100 of 100

ANNEX 10. MAP OF CAMEROON