document of the world bank · transantiago-se into autonomous entity ongoing date achieved...
TRANSCRIPT
![Page 1: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/1.jpg)
Document of
The World Bank
Report No: ICR2086
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IBRD-73160)
ON A
LOAN
IN THE AMOUNT OF US$ 4.8 MILLION
TO THE
REPUBLIC OF CHILE
FOR A
SANTIAGO URBAN TRANSPORT TECHNICAL ASSISTANCE PROJECT
June 25, 2012
Sustainable Development Department
Bolivia, Chile, Ecuador, Peru and Venezuela Country Management Unit
Latin America and the Caribbean Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
![Page 2: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/2.jpg)
CURRENCY EQUIVALENTS
(Exchange Rate Effective May 31, 2012)
Currency Unit = CHILEAN PESO (CLP)
1.00 CLP = US$ 0,0019
US$ 1.00 = 518 CLP
FISCAL YEAR
[January 1 – December 31]
ABBREVIATIONS AND ACRONYMS
CAS Country Assistance Strategy
CPS Country Partnership Strategy
DPL Development Policy Loan
ERR Economic Rate of Return
ESTRAUS Transport Simulation/Planning Model (Modelo de Simulación de
Transporte)
FM Financial management
GEF Global Environment Facility
GEF project GEF Air Quality and Sustainable Transport Project for Santiago
P073985
GoCH Government of Chile
ICR Implementation Completion and Results Report
MINVU Ministry of Housing and Urban Development (Ministerio de
Vivienda y Urbanismo)
MODEM Methodology for vehicle emission calculation (Metodología para
el Cálculo de Emisiones Vehiculares)
MOP Ministry of Public Works (Ministerio de Obras Públicas)
MTT Ministry of Transport and Telecommunications
MUSSA Land Use Model for Santiago (Modelo de Uso de Suelo de
Santiago)
NOx Nitrous Oxide
O-D survey Origin and destination survey
OECD Organization for Economic Co-operation and Development
PAD Project Appraisal Document
PCU Project Coordination Unit
PDO Project Development Objective
PM Particulate Matter
PTUS Santiago Urban Transport Plan 2000 - 2010 (Plan de Transporte
Urbano para Santiago)
RPP Restructuring Project Paper
Santiago DPL Santiago Urban Transport Programmatic Development Policy
Loan P082412
SECTRA Transport Planning Secretariat (Secretaría de Planificación de
![Page 3: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/3.jpg)
Transporte)
SEISTU Urban Transport System Impact Evaluation System (Sistema de
Evaluación de Impacto sobre el Sistema de Transporte Urbano)
SEREMITT-RM Regional Service of the Transport Ministry in the Metropolitan
Region (Servicio Regional del Ministerio de Transporte y
Telecomunicaciones para la Región Metropolitana)
SERVIU Regional Service for Road and Urban Development (Servicio
Regional de Vialidad y Urbanismo)
SIVU One-stop process (Ventanilla Única) information system (Sistema
de Información Ventanilla Única)
TAL Technical Assistance Loan, here also used as synonym for the
Santiago Urban Transport Technical Assistance Project P086689
TOR Terms of reference
Transantiago Commonly used to refer to the public transport system in Santiago;
sometimes also used as a acronym for the PTUS as a whole or for
its public transport reform program
Transantiago-SE Executive Secretary of the Committee of Ministers for Urban
Transport in Metropolitan Santiago and PCU for this project
Vice President: Hasan A. Tuluy
Country Director: Susan Goldmark
Sector Manager: Aurelio Menendez
Project Team Leader: Elisabeth Goller
ICR Team Leader: Elisabeth Goller
![Page 4: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/4.jpg)
![Page 5: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/5.jpg)
CHILE
Santiago Urban Transport Technical Assistance Project
CONTENTS
Data Sheet
A. Basic Information
B. Key Dates
C. Ratings Summary
D. Sector and Theme Codes
E. Bank Staff
F. Results Framework Analysis
G. Ratings of Project Performance in ISRs
H. Restructuring
I. Disbursement Graph
1. Project Context, Development Objectives and Design ............................................... 1 2. Key Factors Affecting Implementation and Outcomes .............................................. 6 3. Assessment of Outcomes .......................................................................................... 10 4. Assessment of Risk to Development Outcome ......................................................... 16 5. Assessment of Bank and Borrower Performance ..................................................... 17 6. Lessons Learned ....................................................................................................... 19 7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners .......... 20 Annex 1. Project Costs and Financing .......................................................................... 22 Annex 2. Outputs/Outcomes by Component ................................................................ 23 Annex 3. Economic and Financial Analysis ................................................................. 39 Annex 4. Bank Lending and Implementation Support/Supervision Processes ............ 40 Annex 5. Beneficiary Survey Results ........................................................................... 42 Annex 6. Stakeholder Workshop Report and Results ................................................... 43 Annex 7. Summary of Borrower’s ICR and/or Comments on Draft ICR .................... 44 Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ....................... 51 Annex 9. List of Supporting Documents ...................................................................... 52 Annex 10. Status of Transantiago at the Time of ICR Preparation .............................. 53 Annex 11. Original Indicators and Degree of Achievement ........................................ 75
![Page 6: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/6.jpg)
![Page 7: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/7.jpg)
A. Basic Information
Country: Chile Project Name:
CL Santiago Urban
Transport Technical
Assistance Project
Project ID: P086689 L/C/TF Number(s): IBRD-73160
ICR Date: 06/25/2012 ICR Type: Core ICR
Lending Instrument: TAL Borrower: GOVERNMENT OF
CHILE
Original Total
Commitment: USD 4.80M Disbursed Amount: USD 2.37M
Revised Amount: USD 2.37M
Environmental Category: B
Implementing Agencies:
Transantiago-SE
Cofinanciers and Other External Partners:
B. Key Dates
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 10/02/2003 Effectiveness: 12/02/2005 12/02/2005
Appraisal: 03/18/2004 Restructuring(s): 10/02/2009
11/11/2011
Approval: 07/05/2005 Mid-term Review: 10/01/2007 05/23/2008
Closing: 12/31/2009 12/31/2011
C. Ratings Summary
C.1 Performance Rating by ICR
Outcomes: Moderately Satisfactory
Risk to Development Outcome: Low or Negligible
Bank Performance: Moderately Satisfactory
Borrower Performance: Moderately Satisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Bank Ratings Borrower Ratings
Quality at Entry: Moderately Satisfactory Government: Moderately Satisfactory
Quality of Supervision: Satisfactory Implementing
Agency/Agencies: Satisfactory
Overall Bank
Performance: Moderately Satisfactory
Overall Borrower
Performance: Moderately Satisfactory
![Page 8: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/8.jpg)
C.3 Quality at Entry and Implementation Performance Indicators
Implementation
Performance Indicators
QAG Assessments
(if any) Rating
Potential Problem Project
at any time (Yes/No): No
Quality at Entry
(QEA): None
Problem Project at any
time (Yes/No): Yes
Quality of
Supervision (QSA): None
DO rating before
Closing/Inactive status:
Moderately
Satisfactory
D. Sector and Theme Codes
Original Actual
Sector Code (as % of total Bank financing)
Central government administration 72 35
General transportation sector 25 62
Sub-national government administration 3 3
Theme Code (as % of total Bank financing)
Improving labor markets 13
Other social development 13 10
Other urban development 25 15
Pollution management and environmental health 25 15
Urban services and housing for the poor 24 60
E. Bank Staff
Positions At ICR At Approval
Vice President: Hasan A. Tuluy Pamela Cox
Country Director: Susan G. Goldmark Axel van Trotsenburg
Sector Manager: Aurelio Menendez Jose Luis Irigoyen
Project Team Leader: Elisabeth Goller Jorge M. Rebelo
ICR Team Leader: Elisabeth Goller
ICR Primary Author: Elisabeth Goller
F. Results Framework Analysis
Project Development Objectives (from Project Appraisal Document)
To support the implementation, monitoring, evaluation and continuous planning of the
urban transport reform program
![Page 9: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/9.jpg)
To strenghten the capacity and improve the procedures to mitigate potential adverse
impacts of transport infrastructure works
Revised Project Development Objectives (as approved by original approving authority) To support the Borrower in achieving an efficient and sustainable urban transport system
for Metropolitan Santiago
(a) PDO Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Improvement measure identified in the evaluations of Transantiago implemented
Value quantitative or Qualitative)
Improvement measure not
yet implemented
At least one
improvement
measure
implemented
Several
improvement
measures
implemented and
more improvement
measures still likely
to be implemented
Date achieved 09/03/2009 12/31/2011 12/31/2011
Comments (incl. % achievement)
Target exceeded
Indicator 2 : Information on the impact of the implementation of Transantiago on air quality
available
Value quantitative or Qualitative)
Information on the impact
of the implementation of
Transantiago on air
quality available
Information on
the impact of
the
implementatio
n of
Transantiago
on air quality
available
Information on the
impact of the
implementation of
Transantiago on air
quality available
Date achieved 09/03/2009 12/31/2009 12/31/2009
Comments (incl. % achievement)
Target met
(b) Intermediate Outcome Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Preparation of an institutional framework for Transantiago
Value (quantitative or Qualitative)
Institutional framework
not yet existing
Preparation of an
institutional
framework for
Seminar on
metropolitan
transport authorities
![Page 10: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/10.jpg)
Transantiago organized; draft law
to create a such
authority pending;
Transantiago-SE
strengthened from
an organizational
point of view;
initiative to
transform
Transantiago-SE
into autonomous
entity ongoing
Date achieved 05/11/2005 12/31/2009 04/06/2012
Comments (incl. % achievement)
Target met
Indicator 2 : Design of an Action Plan to mitigate the negative effects of Transantiago on
street vendors
Value (quantitative or Qualitative)
Action Plan to mitigate
the negative effects of
Transantiago on street
vendors not yet available
Action Plan to
mitigate the
negative
effects of
Transantiago
on street
vendors
available
Action Plan to
mitigate the
negative effects of
Transantiago on
street vendors
available and
transport related
measures
implemented
Date achieved 09/03/2009 12/31/2011 12/31/2011
Comments (incl. % achievement)
Target met
Indicator 3 : Evaluation of pilot projects shows potential for public transport quality or
efficiency improvements
Value (quantitative or Qualitative)
No pilot implemented
Evaluation of
at least one
pilot project
shows
potential for
public
transport
quality or
efficiency
improvements
Both pilot projects
showed potential
for public transport
quality or efficiency
improvements
Date achieved 09/03/2009 12/31/2011 04/06/2012
Comments (incl. % achievement)
Target met
Indicator 4 : Real time information on the accrued payment obligation to operators and
respective penalties available
![Page 11: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/11.jpg)
Value (quantitative or Qualitative)
Real time information not
yet available
Real time
information on
the accrued
payment
obligation to
operators and
respective
penalties
available
Financial and fare
management
system improved,
but real time
information on the
accrued payment
obligation to
operators and
respective penalties
not available
Date achieved 09/03/2009 12/31/2011 04/06/2012
Comments (incl. % achievement)
Target not met, but some improvements to the financial and fare management
system
Indicator 5 : Information on total revenues, expenses, deficits/surpluses and the equilibrium
fare of the system available on a daily basis
Value (quantitative or Qualitative)
Information on total
revenues, expenses, etc.
not yet available on a
daily basis
Information on
total revenues,
expenses, etc.
available on a
daily basis
Financial and fare
management
system improved,
but information on
total revenues,
expenses, etc. not
available on a daily
basis
Date achieved 09/03/2009 12/31/2011 04/06/2012
Comments (incl. % achievement)
Target not met, but some improvements to the financial and fare management
system
G. Ratings of Project Performance in ISRs
No. Date ISR Archived
DO IP Actual
Disbursements (USD millions)
1 10/20/2005 Satisfactory Satisfactory 0.00
2 01/20/2006 Satisfactory Moderately Satisfactory 0.01
3 05/31/2006 Satisfactory Moderately Satisfactory 0.01
4 12/07/2006 Satisfactory Moderately Satisfactory 0.01
5 06/07/2007 Satisfactory Moderately Satisfactory 0.51
6 12/12/2007 Moderately Satisfactory Moderately Satisfactory 0.51
7 03/11/2008 Moderately Satisfactory Moderately
Unsatisfactory 0.51
8 10/22/2008 Moderately
Unsatisfactory Unsatisfactory 0.51
9 04/07/2009 Moderately
Unsatisfactory Unsatisfactory 0.51
10 07/23/2009 Moderately Satisfactory Moderately
Unsatisfactory 0.51
![Page 12: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/12.jpg)
11 12/06/2009 Moderately Satisfactory Moderately Satisfactory 0.51
12 05/21/2010 Moderately Satisfactory Moderately Satisfactory 0.99
13 12/21/2010 Moderately Satisfactory Moderately Satisfactory 1.49
14 06/28/2011 Moderately Satisfactory Satisfactory 1.98
15 11/26/2011 Moderately Satisfactory Satisfactory 2.28
16 12/28/2011 Moderately Satisfactory Moderately Satisfactory 2.39
H. Restructuring (if any)
Restructuring
Date(s)
Board
Approved
PDO Change
ISR Ratings at
Restructuring Amount
Disbursed at
Restructuring
in USD
millions
Reason for Restructuring &
Key Changes Made DO IP
10/02/2009 Y MS MU 0.51
To better align Bank assistance
with the operational and
financial challenges of the
public transport system in
Santiago. Main changes: (a)
modification of project scope;
(b) change in implementation
arrangements; (c) replacement
and fine-tuning of indicators;
(d) extension of closing date;
and (e) alignment of PDO in
PAD and Loan Agreement
11/11/2011 MS S 1.98
To cancel part of the loan funds
because they were not anymore
needed and to grant a four-
month grace period
If PDO and/or Key Outcome Targets were formally revised (approved by the original approving
body) enter ratings below:
Outcome Ratings
Against Original PDO/Targets Moderately Unsatisfactory Against Formally Revised PDO/Targets Moderately Satisfactory Overall (weighted) rating Moderately Satisfactory
![Page 13: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/13.jpg)
I. Disbursement Profile
![Page 14: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/14.jpg)
![Page 15: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/15.jpg)
1
1. Project Context, Development Objectives and Design
1.0 Introduction
1. The Santiago Urban Transport Technical Assistance Loan (TAL) accompanied
the Santiago Urban Transport Programmatic Development Policy Loan (Santiago DPL –
P082412) to underpin the policy and institutional reforms envisaged to transform the
public transport system in Santiago, also known as Transantiago. The reforms were
outlined in the 2000-2010 Santiago Urban Transport Plan (PTUS) and had an
unprecedented scope and complexity for a Latin American city, applying to the city as a
whole and affecting all public transport modes. Unlike Bogota with its well-regarded
TransMilenio Bus Rapid Transit (BRT) corridors performing just over 25% of public
transport trips while operating side-by-side with a chaotic mix of traditional informal
sector buses that carry the bulk of the passenger traffic, Transantiago called for a
complete transformation of the public transport system more typical of an advanced
country of the Organization for Economic Co-operation and Development (OECD).
2. In February 2007, after a first phase of preparatory activities, the Government of
Chile (GoCH) implemented the full Transantiago reform. This meant that overnight the
GoCH changed the bus routes and stops in the city, reduced the bus fleet, integrated bus
and underground services, altered the fare structure and payment method, modified the
way bus operators operated and were remunerated, and made other changes. It led to
chaos in Santiago mainly for the following reasons: (i) the number of buses operated in
the streets was insufficient, (ii) the new route network did not provide adequate coverage
and required more transfers, (iii) the new fleet control, ticket validation and other systems
did not yet function properly, and (iv) people were not familiar with the new system.
There was also a huge delay in the construction of the segregated bus corridors, which
meant higher travel times and a need for more buses than planned. Finally, enclosed pre-
payment areas for off-board payment, which would have speeded up boarding, were not
considered. The GoCH immediately reacted and addressed these launch problems by
increasing the number of buses and services, reducing transfers, reserving street space for
bus use only, changing the fare structure and payment mechanism for operators,
constructing provisional enclosed pre-payment areas and more. For more details on the
implementation of the reform, the launch problems, and the way they were addressed see
the Implementation Completion and Results Report (ICR) of the Santiago DPL.
3. According to an independent review commissioned to complete this ICR (annex
10) in the beginning of 2012, the public transport system in Santiago had reached a stable
phase. At that time the efforts of the GoCH focused on renegotiating contracts with the
bus operators, providing them with increased responsibilities in terms of operational
decisions and making their revenues more sensitive to the number of passengers
transported. It was expected that the changes would force the operators to be more aware
of the level of service provided, carry more passengers, and fight fare evasion, therefore
reducing the financial deficit of the system. When viewed from a broad perspective and
using other Latin American systems as comparison, Transantiago provided a good level
of service for an affordable fare. However, the bus-based trips were still unreliable
![Page 16: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/16.jpg)
2
mainly due to the increase in car use and traffic in Santiago, the service level varied in
different areas of the city, and a number of other challenges still laid ahead.
4. The troubled introduction of Transantiago directly impacted the TAL since the
GoCH shifted its focus to addressing them and nearly paralyzed project implementation
for about a year at a time when the first project activities had just started. They also
required project restructuring to realign the Bank assistance with the operational needs of
the public transport system after the launch crisis.
1.1 Context at Appraisal
Sector Background
5. Although Santiago’s transport system at appraisal was less chaotic than systems
in other large Latin American cities, it suffered from serious problems, which included
the following:
Exponential increase in car ownership and use in the period between 1977 and 2001,
putting pressure on the urban transport system through growing traffic and
congestion;
Steady and steep decrease in public transport modal share in the same period;
Deficiencies in the organization of the bus system: for instance, (i) bus operators
competed for passengers in the streets, which generated operating inefficiencies and
dangerous driving; (ii) fragmented bus ownership with few sizable companies, lack of
professional management and informality; (iii) poorly coordinated and chaotic
transport supply not adapted to demand levels and oversupply during off-peak hours,
contributing to unnecessary congestion, pollution and increased operating costs; (iv)
long bus routes, most of them crossing the city center and heavily used corridors; (v)
lack of integration between buses and the metro system, increasing travel costs and
reducing accessibility especially for the poor; and (vi) low passenger satisfaction with
the public bus system;
Limited inter-agency coordination at metropolitan level: incipient coordination
among the agencies dealing with transport and the absence of a transport coordinating
body at the metropolitan level;
High bus related accident levels: almost 25% of deaths on urban roads occurred in
accidents involving a bus; and
High air pollution levels, with transport as the major contributor to local emissions.
6. In response to these problems, the GoCH designed the PTUS, a comprehensive
and innovative multi-sector exercise comprised of 12 programs,1 of which a public
transport modernization program was by far the most important and complex one.
1 The PTUS included the following programs: (1) Public Transport Modernization focusing, among others, on (i)
replacing the informal owner-operation with gross-cost contracting to 14 relatively large operators; (ii) providing
incentives to operators to acquire high-standard low-polluting buses; (iii) redesigning the route network into a trunk and
feeder system and reducing the number of buses; (iv) introducing a unified fare system; (v) separately contracting fare
collection and a public transport management/information center to control bus flows; (vi) limiting the number of taxis,
and (vii) implementing a comprehensive infrastructure program to double the extension of the subway system and
construct segregated busways, bus stops, interchange stations, terminals, and underpasses. (2) Road Investments and
Traffic Control, including urban toll roads, allocating and managing road space to maximize social gains through traffic
![Page 17: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/17.jpg)
3
Rationale for Bank Assistance
7. The Bank’s support to the implementation of the PTUS, and in particular its
public transport program, was expected to help address the main issues affecting
transport and mobility in Santiago. This support came in a package of three instruments:
this TAL (P086689), the Santiago DPL, and the Sustainable Transport and Air Quality
Project for Santiago financed through a Global Environment Facility grant (GEF project
P073985).
8. The TAL was made to assist in the implementation of the public transport reform
arrangements. It was meant to provide the necessary technical assistance and advice to
support this difficult process of transformation.
9. The Santiago DPL supported the public transport reform, including the
institutional, organizational and managerial transformation of the system to ensure its
continuity and sustainability. It also emphasized fostering more integrated coordination
among transport, land-use and environmental issues, including social and participatory
elements, and supporting the difficult process of reallocating scarce street space to the
exclusive use of non-motorized transport and public transport.
10. The GEF project strove to accelerate the introduction of the PTUS as a whole by
concentrating on contributing to Green House Gas (GHG) emissions abatement with
different degrees of intensity and different implementation periods.
11. In these operations, the Bank was expected to act as catalyst for knowledge
generation and transfer. It was expected to provide value added because of its long-
standing involvement in urban transport operations in Latin America and its global
experience and knowledge in the field. The Bank was also expected to learn from the
innovative experience in Santiago for the benefit of its future urban transport operations.
12. This TAL was consistent with the goals and strategic approach set out in the 2002
Country Assistance Strategy (CAS). Indeed, while supporting the PTUS, it was expected
to (a) enhance sustained economic growth and social progress; (b) foster the inclusion of
the most vulnerable groups through improved access at affordable prices and reasonable
travel times, hence contributing to socially inclusive growth; (c) improve environmental
conditions; (d) promote public-private partnerships through a concession mechanism for
public transport services; and (e) modernize the State and build its technical capacity.
1.2 Original Project Development Objectives (PDO) and Key Indicators (as approved)
13. The PDO wording in the Project Appraisal Document (PAD) and the Loan
Agreement were different. The PDO as stated in the PAD referred to specific activities to
support the Borrower in improving Santiago’s urban transport system, i.e. ―to support the
management schemes with priority for public transport, pricing schemes, and parking restrictions. (3) Location of
schools and efficient management of school trips. (4) Promotion of New Commercial and Service Centers to reduce the
length of trips. (5) Change in Residential Land-Use Trends through, among others, mixed land-use and densification.
(6) Non-motorized Transport. (7) Immediate Actions to reduce environmental alerts. (8) Regulation of Urban Freight
Transport to rationalize freight traffic and reduce its environmental footprint. (9) Monitoring and Control. (10)
Financing. (11) Communication and Citizens’ Participation; and (12) Other Programs, including institutional aspects
and environmental aspects.
![Page 18: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/18.jpg)
4
implementation, monitoring, evaluation and continuous planning of the urban transport
reform and to strengthen the capacity and improve the procedures to mitigate potential
adverse impacts of transport infrastructure works‖. The wording in the Loan Agreement
was more general, namely ―to support the Borrower in achieving an efficient and
sustainable urban transport system for Metropolitan Santiago‖.
14. The PDO indicators were to (i) complete a survey to assess Transantiago’s impact
on transport demand; and (ii) design a monitoring system for Transantiago’s
environmental impact.
15. The expected intermediate outcomes were the following: (i) institutionalization of
Transantiago; (ii) mitigation of negative effects of Transantiago on low-income groups;
(iii) improved road infrastructure management; (iv) Transantiago users well informed
about the system; and (v) better coordination between transport and land use planning.
The respective indicators included: (i) prepared institutional framework for Transantiago;
(ii) designed action plan with mitigation measures for low-income users; (iii) completed
road infrastructure management plan; (iv) carried out dissemination campaign for
Transantiago; and (v) proposed land use and transport planning coordination
mechanisms.
1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and
reasons/justification
16. As already mentioned, following the launch difficulties of Transantiago, the
project needed to be restructured to realign the Bank assistance with the new operational
challenges of the system. It took over a year to redefine the project scope because of the
limited attention paid to the TAL during the Transantiago crisis. The restructuring was
completed in 2009 and at that time the project had only disbursed US$512,000.
Essentially the restructuring called for changes in the project activities, intermediate
outcomes, and indicators. Due to the difference in the PDO wording in the PAD and the
Loan Agreement, the wording of the Loan Agreement was adopted.
17. The revised PDO indicators were the following: (i) improvement measure
identified in the evaluation of Transantiago implemented and (ii) information on
Transantiago’s impact on air quality available.
18. The revised intermediate outcomes consisted of: (i) institutionalization of
Transantiago; (ii) mitigation of negative effects of Transantiago on street vendors; (iii)
improvement in quality and/or efficiency of Transantiago; and (iv) improvement of
Transantiago’s financial/fare control and management system. The respective indicators
were revised as follows: (i) prepared institutional framework for Transantiago; (ii)
designed action plan to mitigate the negative effects of Transantiago on street vendors;
(iii) evaluation of at least one pilot project showed potential for public quality and
efficiency improvements; (iv) real time information on Transantiago’s payment
obligations available; and (v) information on the system’s revenues, expenses, etc.
available on a daily basis.
![Page 19: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/19.jpg)
5
1.4 Main Beneficiaries
19. The primary target group included public transport users in Metropolitan
Santiago, who typically are people with lower incomes. Because of reduced externalities
from public transport, the primary target group also included people making trips to and
within the city, regardless of transport mode, and all inhabitants of the city. The
secondary beneficiaries were institutions like the Executive Secretary of the Committee
of Ministers for Urban Transport in Metropolitan Santiago (Transantiago-SE), which also
housed the Project Coordination Unit (PCU) and the Transport Planning Secretariat
(SECTRA). They benefited from capacity strengthening, improved analytical tools, better
data, and information.
1.5 Original Components (as approved)
20. The TAL had the following six components:
Component A. General Urban Transport to (i) obtain qualitative and quantitative
data on urban passenger movements; (ii) forecast urban transport demand by
incorporating socio-economic variables into ESTRAUS2
; (iii) lay the basis for
Transantiago’s long-term institutional design; and (iv) implement a road
infrastructure maintenance management system;
Component B. Public Transport to (i) obtain information to optimize fares; (ii)
design intermodal stations; (iii) design a graphic information system; (iv) obtain
information to optimize travel times; and (v) inform users of the new system;
Component C. Environment to provide regular data on air quality and noise levels
necessary to monitor and maximize the positive impacts expected from Transantiago;
Component D. Land Use to (i) update the sub-models of MUSSA3 and assess three
road pricing alternatives; (ii) promote activity concentration around transfer stations;
(iii) facilitate transport and land use planning coordination; and (iv) support the
implementation of the urban transport impact evaluation system (SEISTU) to ensure
that real estate developers pay for their negative transport externalities;
Component E. Social Aspects of Transport to (i) support a training program for
transit workers and (ii) analyze Transantiago’s impact on low-income groups; and
Component F. Mitigation of Potential Adverse Impacts of Transport
Infrastructure Works to (i) strengthen Chile’s capacity in the areas of involuntary
resettlements and (ii) harmonize environmental guidelines.
1.6 Revised Components
21. The restructuring eliminated the original Component F and changed several
project activities within the existing project components. It also ensured consistence in
substance and language between the components and project activities in the project
documents and the Loan Agreement. The revised components were the following:
2 ESTRAUS is the transport planning model of SECTRA http://www.sectra.gob.cl/metodologias_y_herramientas_de_transporte/metodologia/estraus_02.html. 3 MUSSA is a mathematical model to simulate the real estate market and make economic evaluations of the impacts
caused in the city (www.mussa.cl).
![Page 20: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/20.jpg)
6
Component A. General Urban Transport to (i) more precisely forecast urban
transport demand by incorporating socio-economic variables into ESTRAUS and (ii)
lay the basis for Transantiago’s institutional design over the long term;
Component B. Public Transport to (i) carry out evaluations of Transantiago’s
performance and identify measures to improve the public transport system; (ii)
improve Transantiago’s financial and fare management system; and (iii) improve the
quality and /or efficiency of public transport in Metropolitan Santiago;
Component C. Environment to monitor the impact of Transantiago on air quality;
Component D. Land Use to (i) update the sub-models of MUSSA and assess three
road pricing alternatives and (ii) support the implementation of SEISTU to ensure that
real estate developers pay for their negative transport externalities;
Component E. Social Aspects of Transport to analyze Transantiago’s impact on
street vendors; and
Component F. Project Management to strengthen the PCU and to carry out project
audits.
1.7 Other significant changes
22. The modification of the project components/activities required minor changes to
the implementation arrangements, the revision of the cost allocation among components,
and a closing date extension from December 31, 2009 to December 31, 2011. The project
also had a partial loan cancellation in the amount of US$1.4 million because the
Borrower financed several project activities totally or partially with local resources. The
reasons for the Borrower to do so included the following: (i) project activities, such as the
implementation of the financial and fare management system, were included in the scope
of ongoing contracts awarded according to local procurement rules and procedures; (ii) at
the end of certain fiscal years, Transantiago-SE had local resources available to finance
larger portions of project activities than envisaged; and (iii) some project activities were
completed after the loan closing date, so the respective payments could not be made with
loan proceeds.
2. Key Factors Affecting Implementation and Outcomes
2.1 Project Preparation, Design and Quality at Entry
23. The factors related to quality at entry that positively influenced project
implementation and outcomes included the following:
Sound technical background analyses, profound sector knowledge, participation
of multiple actors, and readiness. The project design and preparation benefited from
sound technical background analyses carried out during the preparation of the GEF
project and the Santiago DPL as well as GEF activities ongoing at the time of
appraisal. This contributed to the solid knowledge on the sector reflected in the
preparation documents. It also opened the doors to Santiago’s major urban transport
actors, who actively participated in the identification of the different project
components and activities. The terms of reference (TOR) for more than half of the
project activities were ready at appraisal. These TOR were technically sound and well
prepared.
![Page 21: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/21.jpg)
7
Fully operational PCU by project effectiveness. Transantiago-SE was also the
implementation agency of the GEF project, which meant that the PCU was fully
operational when the project became effective and that the staff had experience with
Bank rules and procedures.
24. The factors that negatively influenced project implementation included:
Lack of flexibility in the project description. All activities supported by the project
represented high local priorities and were fully defined at the time of appraisal.
Therefore, they were described in a precise and detailed manner, leaving no flexibility
for changes. With the change in government in 2006 and even more with the launch
difficulties of Transantiago, Transantiago-SE’s priorities shifted from a more strategic
and longer term perspective, to activities with immediate impact on the public
transport system. For that reason, and given the lack of flexibility in the project
description, project restructuring became necessary.
Shortcomings in risk identification and mitigation. The comprehensive risk
assessment for this project did not anticipate the launch difficulties of Transantiago
and the shift in project priorities due to these difficulties and the change in
governments. Since these risks were not identified, no mitigation measures were
designed and applied.
Shortcomings in the results framework. The shortcoming mentioned later in
section 2.3 made the precise assessment of the project outcomes more difficult.
2.2 Implementation
25. The factors that positively influenced project implementation included the following:
Highly committed and professional PCU and Transantiago-SE staff. The
commitment and professionalism of the people who worked on project issues was
exemplary despite frequent changes in the coordinator of Transantiago-SE, two
changes in PCU coordinator, and several changes in the technical staff throughout the
life of the project. This is illustrated by the fact that despite numerous obstacles, staff
managed to successfully complete studies (such as the ones on bus depots and
terminals, as well as the impact of street markets on Transantiago) that were essential
in the proper functioning of the public transport system.
Project restructuring. Project restructuring allowed realigning the project activities
with the changed needs and priorities of the Borrower and bringing the project back
on track to achieve its PDO.
Close follow up and monitoring. The Bank team practiced a hands-on follow up,
which included strong sustained implementation support and regular follow-up
conference calls to advise and assist the Borrower and regularly check the project
implementation progress. This enabled keeping the project activities on Transantiago-
SE’s priority list, except immediately after the launch of Transantiago, when all
efforts focused on remedying the severe launch problems.
26. The factors that negatively influenced project implementation included the following:
Crisis generated by the launch of Transantiago. The need to urgently solve the
difficulties resulting from the launch of the new public transport system created an
excessive work load in Transantiago-SE, which completely absorbed its entire staff,
including the PCU staff. During close to a year of this crisis situation, limited
![Page 22: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/22.jpg)
8
attention was paid to the TAL. This slowed down project implementation and shifted
the technical assistance needs and priorities.
Changes in authorities and Transantiago-SE’s leadership and staff. The project
spanned over three government terms, which contributed to, but was not the only
reason, for frequent changes in Transantiago-SE’s leadership and staff as well as PCU
staff. These changes had some normal negative impacts on the project
implementation pace and quality because new people needed to become familiar with
the project and with Bank procedures and rules.
Frequent changes in project activities. The changes in authorities and staff also
shifted project priorities, which led to the replacement of a considerable number of
project activities often already in an advanced bidding stage. The replacement mostly
occurred because of a shift in the priorities of the organization or the government as a
whole. In some cases, they happened because the commitment and ownership for an
activity was with an individual rather than the institution she or he belonged to. In
other cases, they stemmed from new needs that arose as the public transport system
evolved. These frequent activity changes consumed additional time and resources of
both the PCU and the Bank team.
Multiple and lengthy procedures and administrative hurdles. Bank projects in
Chile follow local and Bank review and control procedures for procurement and
contracting. In addition, because Transantiago-SE is not an autonomous entity with
legal personality, all processes were reviewed and authorized by both Transantiago-
SE and Ministry of Transport and Telecommunications (MTT), leading to the
duplication of activities and lengthy procurement and contracting processes. At times
the project also suffered from additional delays because the controllers’ office
(Contraloría) and MTT had little experience with Bank procurement procedures and
rules and the budgeting procedures to apply were not clear.
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization
27. M&E design. As already mentioned, the original PDO in the Loan Agreement
and in the PAD were different. Additionally, the PAD’s main text and results framework
showed one PDO, while the data sheet of the PAD included two PDOs. No indicators and
outcomes were related to the second PDO of the PAD, but it was linked to the activities
in the original Component 6. All PDOs were somewhat broad and subjective.
28. The original indicators were realistic in the light of the key project activities, but
not all of them adequately captured the level of achievement of the outcomes and the
PDO. For instance, carrying out a dissemination campaign does not necessarily mean that
the public transport users are well informed about Transantiago. Some outcomes were
also subjective, such as ―mitigating Transantiago’s negative impacts on low-income
groups‖ and the ―institutionalizing of Transantiago‖. Finally, the outcomes were mostly
related to one specific project activity only. Consequently, since the original project had
about 20 activities and only five outcomes, there were several implicit outcomes, which
contributed to the achievement of the PDO. For instance, the availability and use of new
planning tools facilitated the continuous planning of the urban transport reform program
and supported its implementation.
![Page 23: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/23.jpg)
9
29. In the framework of project restructuring the PDO wording of the Loan
Agreement was adopted since it was considered a better reflection of the intended
objective. Several indicators and outcomes were revised to align them with the project
modifications. The revision of the results framework neither eliminated the broadness and
subjectivity of the PDO and outcomes, nor did it fix the direct causal linkages between
some outcomes and the indicators. In addition, one of the indicators that measured the
improvements in the financial and fare management system was redundant.
30. The monitoring arrangements were simple and adequate for this type of technical
assistance loan. Data collection to assess the compliance with the indicator targets was
straightforward and required commensurate efforts and resources.
31. Implementation and usage. Data was regularly collected and presented in a
progress report discussed during supervision missions. The information collected during
project implementation was mainly used to track project progress.
2.4 Safeguard and Fiduciary Compliance
32. Safeguards. Originally, the environmental category of this project was C. In the
framework of project restructuring, the Borrower decided to change the project scope to
include the execution of pilot projects, which were to be defined in the course of project
implementation. Since these pilot projects could have required small works or have had
other negative environmental or social implications, the project’s environmental category
was changed to B and the Environmental Assessment safeguard policy (OP/BP 4.01) was
triggered. Transantiago-SE prepared, and the Bank approved, simplified environmental
guidelines. These guidelines included the description of the type of works envisaged in
the pilot projects and their potential environmental impacts, the applicable environmental
framework and norms, mitigation measures, institutional responsibilities, and a checklist
for screening, among others.
33. Transantiago-SE screened all pilot projects for potential negative environmental
and social impacts. For the pilot project to test colored road surface treatments for bus
lanes, Transantiago-SE provided the Bank with an assurance from the provider of the
road treatments that they did not have any negative environmental impact. In the case of
the pilot project to install solar lighting at bus stops, Transantiago-SE produced
satisfactory evidence on environmentally sustainable recycling procedures for batteries.
No negative social issues were anticipated or arose in these pilot projects.
34. The operation did not contribute to a wider agenda of strengthening the
environmental and safeguard capacity and procedures for public transport infrastructure
works because the relevant activities were cancelled during project restructuring.
35. Financial management (FM) and procurement. Fiduciary aspects overall were
handled in a satisfactory manner even though the project registered minor shortcomings
in FM and procurement. In terms of FM, the project maintained overall satisfactory
performance and low risk. Timely and reliable interim un-audited reports have allowed
managing and monitoring project implementation. Audit reports were by and large
![Page 24: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/24.jpg)
10
submitted on time and considered acceptable to the Bank.4
In the Independent
Procurement Review carried out in March 2009, procurement was considered moderately
satisfactory, mainly because of temporary weaknesses in internal controls and the
implementing agency’s low capacity to conduct procurement as per Bank guidelines.
This was due to a sudden departure of the then PCU head. The procurement post review
carried out at the end of 2010 considered procurement as moderately satisfactory because
of the limited amount of procurement activities carried out during the review period. The
last procurement post review at the end of 2011 considered procurement again fully
satisfactory.
2.5 Post-completion Operation/Next Phase
36. The prospects for the post-completion operation of the project vary. At the time of
ICR preparation, the pilot projects were in the process of being replicated at a large scale.
The results of most of the studies carried out under the project, such as the assessment of
the performance of the public transport system, the methodology to assess the financial
health of bus operators, the air quality monitoring exercise, and the organizational
improvement study for Transantiago-SE, were and still are likely to be extensively used.
The results and products of other activities, such as the SEISTU study did not yet find
practical applications. Similarly, some tools, such as the ESTRAUS model were and still
will be used, while others, such as the MUSSA model, still need further work to become
useful for practical applications.
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
37. The relevance is rated high. The original project design was adjusted to keep the
operation fully relevant in the light of changing circumstances largely attributed to the
severe launch difficulties of Transantiago and the cutting edge nature of the reform
supported by the operation. The original and revised PDO, which are similar in
substance, remained fully consistent with the development priorities of the GoCH. The
President’s Government Program5
advocates for a ―dignified and efficient public
transport‖. In the case of Santiago, this mainly means an improvement in public transport
service quality through (i) the construction of bus corridors and lanes; (ii) ticket pre-
payment areas; (iii) an improved bus network with fewer transfers; (iv) metro system
extensions; (v) an improved institutional structure for MTT; and (vi) objective and
efficient pricing to reduce subsidies. Transantiago is among the strategic objectives of the
Transport Minister,6 who promised substantial improvements in service quality to the 2.5
million bus users in Santiago.
4 The 2006 to 2008 audit reports had qualified opinions because the accrual basis was used to register a payment. This
was corrected afterwards. The 2009 to 2010 audit reports had unqualified opinions. 5 Programa de Gobierno para el Cambio, el Futuro y la Esperanza, Chile 2010 – 2014. 6 Cuenta Pública “Cumpliendo con las Personas, Cumpliendo con la Metas”, Ministro de Transporte y
Telecomunicaciones Pedro Pablo Errázuriz Domínguez, 2011.
![Page 25: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/25.jpg)
11
38. The PDO remained in line with the current Country Partnership Strategy (CPS)7,
which focuses on three results areas that broadly coincide with the government’s
development agenda: (i) public sector modernization; (ii) job creation and equity
improvement; and (iii) promoting sustainable investments. The project also meets the
current principles for Bank engagement in Chile, which concentrate on the provision of
technical assistance in areas in which the Bank has a comparative advantage and can
support the country’s drive to achieve its development goals. Moreover, for the Bank, this
project has been an important two-way investment, since the Transantiago experience is
highly valued among other Bank clients.
3.2 Achievement of Project Development Objectives
39. The assessment of the achievement of the PDOs presented some challenges. First,
as pointed out in section 2.3, the results framework had some shortcomings. Second, a
few outcomes were achieved by the Borrower on its own without contribution from the
project, such as ―Transantiago’s users being well informed about the new system‖, which
was accomplished through local contracts and finances. Third, according to ICR
guidelines, for projects with formally revised PDOs, the project outcome needed to be
assessed against both the original and the revised PDOs. This assessment is given below.
40. For details on project activities and outputs and their links with outcomes and the
achievement of the PDO, see annex 2. The ICR data sheet includes the revised PDO and
intermediate outcome indicators and annex 11 includes the original ones.
Original PDO and outcomes
41. The original PDO consisted of two objectives and its achievement was rated
moderately unsatisfactory. The project activities related to the objective of ―strengthening
the capacity and improving the procedures to mitigate potential adverse impacts of
transport infrastructure works‖ were cancelled and the objective was not achieved. The
second PDO of ―supporting the implementation, monitoring, evaluation and continuous
planning of the urban transport reform program‖ was partially achieved as follows (for
details see annex 2):
The project partially complied with the PDO indicators of ―designing an
environmental impact monitoring system for Transantiago‖ since it devised several
elements of such monitoring system, i.e. the methodology used to regularly monitor
Transantiago’s impact on air quality and a Web site to disseminate the results. In
addition, at the time of ICR preparation the Borrower was working to complement the
air quality monitoring system with a noise monitoring system.
The Borrower on its own and with local funds will achieve the second PDO indicator
of ―having Transantiago’s impact on transport demand assessed‖ once the origin-
destination (O-D) survey, ongoing at the time of ICR preparation, is completed.
The project also contributed to ―continuous planning of the urban transport system‖
by making transport planning instruments, such as ESTRAUS, more robust. This tool
was used to plan the extension of the metro system, among others.
7 IBRD and IFC Country Partnership Strategy for the Republic of Chile for the Period 2011-2016, January 11, 2011.
![Page 26: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/26.jpg)
12
The Borrower, entirely with local resources,8 also ―facilitated the implementation of
the urban transport reform‖ through (i) the implementation of a broad assistance
program for public transport workers and operators affected by the launch of
Transantiago; (ii) the revision of fare levels, structures, and the fare setting
mechanism after Transantiago’s launch; and (iii) the implementation of small and
medium sized transfer stations. All these activities were cancelled from the project
scope during restructuring because they had been ongoing or carried out.
42. Two of the five original intermediate outcomes were partially achieved by the
project, two by the Borrowers, and one was not achieved. The progress in achieving the
intermediate outcomes was the following:
Intermediate outcome 1 “Institutionalization of Transantiago”: The project complied
with the indicator of ―preparing an institutional framework of Transantiago‖ and laid
the basis for the transformation of Transantiago-SE into a more autonomous and
independent institution, likely to happen in the short to medium term;
Intermediate outcome 2 “Mitigation of the negative effects of Transantiago on low-
income groups”: The project only partially complied with the indicator of ―designing
an action plan with mitigation measures for low-income users‖ because it designed an
action plan only for street vendors, one specific group of low-income people. By
implementing this action plan and making several routes changes and service
improvements as a consequence of the project-financed evaluation of Transantiago by
a group of Brazilian experts, Transantiago-SE also partially reached this outcome
since low-income users normally have no alternative to public transport and thus
benefit most from service improvements. More improvements are expected under the
renegotiated contracts with the bus operators, which came into force between March
and June 2012 and provide the necessary flexibility to do so;
Intermediate outcome 3 “Transantiago’s users being well informed about the public
transport system”: Transantiago-SE, entirely with local resources, carried out a large
number of information and communications campaigns and activities and complied
with the indicator of ―implementing dissemination campaigns‖. In the past,
Transantiago-SE did not collect information on how well its users are informed about
the system9 and several sources, including the review in annex 10, still consider user
information in buses and at stops a challenge for Transantiago. However, given (i) the
huge amount of resources spent by Transantiago-SE for information purposes,
especially if compared to the limited budget reserved by the project for information
campaigns, and the absence of any resources for information campaigns and
communications under the old public transport system; (ii) the large number of
information and communications campaigns and activities carried out by
Transantiago-SE; (iii) the manifold information sources available; and (iv) the
statistics on their use, it seems reasonable to assume that this outcome was at least
partially achieved;
8 The Bank team had a continuous policy dialogue on those issues and provided information on international practice,
especially as far as fare systems are concerned. 9 At the time of ICR preparation, Transantiago-SE was contracting a study to measure the effectiveness of their user
information campaigns.
![Page 27: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/27.jpg)
13
Intermediate outcome 4 “Improved road infrastructure management system”:
Transantiago-SE, on its own and with local resources, created a simple road pavement
management system and so partially achieved the indicator of ―completing a Road
Infrastructure Management Plan‖ and this outcome; and.
Intermediate outcome 5 “Better coordination of transport and land use planning”:
The indicator of ―proposing a land use and transport planning mechanism‖ and the
respective outcome were not achieved.
Revised PDO and outcomes
43. After the serious launch problems outlined in the ICR of the Santiago DPL, the
public transport system underwent important changes. Despite several remaining
challenges, at the time of the preparation of this ICR, Transantiago has become one of the
best quality public transport systems in Latin America. Most notably, it managed to: (i)
provide high accessibility at a reasonable fare; (ii) fully integrate the bus and Metro
services in the city; (iii) introduce a contactless smart card with 100% penetration; (iv)
formalize and professionalize bus operations; and (v) drastically reduce the significant
externalities that Santiago used to face in terms of pollution, accidents and noise (for
details see annex 10). These achievements were huge and by far and large directly
attributable to the GoCH.
44. The project contributed within its limits of scope. It achieved and is still likely to
achieve the revised PDO of ―supporting the Borrower in achieving an efficient and
sustainable urban transport system for Metropolitan Santiago‖ with moderate
shortcomings and was considered moderately satisfactory. The achievements were the
following (for details see again annex 2):
The project exceeded the first PDO indicator and contributed and is still likely to
contribute to Transantiago’s efficiency and/or sustainability. As a result of Brazilian
experts evaluating the public transport system, Transantiago-SE implemented a few
service improvements (with more improvements expected), increased fares, applied
measures against fare evasion, and renegotiated contracts with bus operators. Among
other benefits, this led to reduced transfers for those users who benefitted from the
service improvements, enhanced network coverage, and increased operating cost
coverage. More positive impacts are expected under the renegotiated contracts with
bus operators and the implementation of the results of the study on bus depots and
terminals.
The project assessed Transantiago’s air quality impacts and complied with the second
PDO indicator of having ―information on the impact of the implementation of
Transantiago on air quality available‖. The information on Transantiago’s air quality
impacts was used to revise and make environmental standards of public transport
vehicles more stringent. These standards led and are still likely to lead to particulate
matter (PM) and Nitrogen Oxide (NOx) emission reductions.
The project developed more robust planning tools, such as ESTRAUS and MUSSA,
and the former was already used in several occasions.
45. Two of the four revised intermediate outcomes were fully and two were partially
achieved by the project:
![Page 28: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/28.jpg)
14
Intermediate outcome 1 “Institutionalization of Transantiago”: The project complied
with the indicator of ―preparing an institutional framework of Transantiago‖ and laid
the basis for the transformation of Transantiago-SE into a more autonomous and
independent institution, likely to happen in the short to medium term;
Intermediate outcome 2 “Mitigated the negative effects of Transantiago on street
market vendors”: The project complied with the indicator of ―designing an action
plan to mitigate the negative effects on street vendors‖ and by changing bus routes
and services during operating hours of street markets to avoid interferences and
conflict situations achieved the intermediate outcome;
Intermediate outcome 3 “Improvement of the quality and/or efficiency of public
transport in Santiago”: The evaluation of both pilot projects showed a potential for
public transport quality and efficiency improvements. Therefore, the project achieved
the respective indicator and this outcome. In addition, at the time of ICR preparation,
the Borrower had taken measures to replicate the results of the pilot projects on a
large scale; and
Intermediate outcome 4 “Improvement of Transantiago’s financial/fare control and
management system”: The project did not comply with the two indicators related to
the improvement of the financial/fare control and management system. However, the
information on the financial situation of bus concessionaires obtained through the
project financed study and some initial enhancements to Transantiago’s financial and
payment system carried out with local recourses somewhat contributed to the
achievement of the intermediate outcome.
46. As shown in the table below and following the ICR guidelines, overall the
achievement of the PDO for this formally revised project was also rated moderately
satisfactory.
Calculation of Outcome Rating for Formally Revised Projects
Against
original PDO/
outcomes
Against revised/
current PDO/
outcomes
Overall Comments
1. Rating Moderately
unsatisfactory
Moderately
satisfactory
- Reasonable
improvement
after
restructuring
2. Rating value 3 4
3. Disbursement (before
and after restructuring
and at project end)
US$ 512,000 US$ 1,858,199 US$2,370,199
4. Weight (% disbursed
before/after PDO/
outcome change)
0.22%
0.78%
100%
5. Weighted value (2*4) 0.65 3.14 3.78
6. Final value (rounded) Moderately
satisfactory
3.3 Efficiency
47. Given the nature of a TAL, no economic and financial analysis was carried out at
appraisal. This type of quantitative analysis was not considered appropriate to assess
![Page 29: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/29.jpg)
15
whether the cost of studies and other technical assistance activities was reasonable to
achieve the PDO.
48. In an ex-post perspective, it can be highlighted that the price of the studies carried
out was generally below the respective cost estimates. The studies, once contracted, were
quickly implemented and there were no cost overruns and only few contract
modifications. In the case of Components A and C, the cost overruns were due to the
inclusion of additional activities not originally budgeted. The overall project cost was
considerably lower than the appraisal and restructuring cost estimates for the following
reasons (i) lower prices paid for studies mainly in the case of Components D and E; (ii)
the fact that when preparing the restructuring cost estimates it was not yet clear how
many and what type of pilot projects would be carried out; (iii) to planned pilot projects
could finally not be carried out because the loan closed; (iv) Transantiago’s fare and
financial management system was improved but not fully redesigned; and (v) project
management and supervision was done as part of the normal operation of Transantiago-
SE and only required limited additional resources.
3.4 Justification of Overall Outcome Rating
Rating: Moderately satisfactory
49. The overall rating is moderately satisfactory. The original and revised PDO and
the revised project design remained highly relevant, the implementation of the project
appeared reasonably efficient, and the achievement of the PDO was rated moderately
satisfactory as a result of the evaluation of the original and the revised PDO.
3.5 Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
50. By contributing to the improvement of the public transport system conditions, the
project had positive impacts on the poor, the majority of whom use the public transport in
Santiago10
.
51. In terms of gender aspects, the evaluation of the pilot project which tested
photovoltaic lighting at bus stops showed that both women and men highly valued good
quality bus stops, but women considered the quality of bus stops more important (74.8%
of women considered it as extremely important versus 70.2% of men). When evaluating
the improvements at bus stops, women and men gave the improved lighting the highest
rating, with women providing a slightly higher score (6.1 on a scale from 1 to 7 versus 6).
Women also gave improved access a slightly higher score (5.4 versus 5.3), while men
rated improved information slightly higher (4.2 versus 4.1). When asked about the
priorities for bus stops improvements, both women and men picked safety and security,
the bus stop roof and lighting. However, women ranked safety and security highest, while
men considered the roof more important.
10 In 2010, 91% of the Metro users were low and middle class people, with 15% of users belonging to the two lowest
socioeconomic groups E and D. Information on the socio-economic group of bus users is not available. Given the
geographic coverage of the Metro system and the higher fare, its users tend to be better off than bus users.
![Page 30: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/30.jpg)
16
(b) Institutional Change/Strengthening
(particularly with reference to impacts on longer-term capacity and institutional development)
52. One project subcomponent directly focused on institutional development for the
urban transport sector (for details and results see annex 2, Component A.2). Additionally,
it is worth highlighting that the project contributed to institutional changes in the
following way:
Financing study trips for urban transport specialists to Bogota and Spain. These study
trips were highly successful for a number of reasons pointed out in section 6 -
Lessons Learned;
Supporting the development of new tools for urban transport planning (see annex 2,
Components A and D); and
Strengthening the PCU’s capacity to carry out Bank operations.
(c) Other Unintended Outcomes and Impacts (positive or negative)
53. At the time of ICR preparation, the Ministry of Economy was drafting a law on
street market vendors and used the results of the project financed study on street market
vendors as input. It is likely that this new law will lead to the implementation of measures
to improve the general conditions of street market vendors. These measures were
proposed in the study, but their implementation is outside Transantiago-SE’s
responsibility.
54. In addition, the study on bus depots and terminal, carried out specifically for
Transantiago, led to similar studies in other cities and is likely to culminate in a change of
the legal framework on the topic.
3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
55. No beneficiary survey or stakeholder workshops took place.
4. Assessment of Risk to Development Outcome Rating: Low or Negligible
56. The revised PDO of the project was to support the Borrower to achieve an
efficient and sustainable urban transport system for Metropolitan Santiago. Such a system
is essential for a thriving and competitive city like Santiago, and it is highly unlikely that
the Borrower will forgo it. Such a system is also fully in line with what is spelt out in the
current Presidential and Ministerial Programs.
57. The risk that the different project outcomes will not be maintained and/or further
pursued is also low. The project helped to lay the basis for the institutional framework of
Transantiago, and strengthened Transantiago-SE. At the time of ICR preparation, there
was a political will to provide Transantiago-SE with more autonomy. The negative
impacts of Transantiago on street market vendors were mitigated. The results of the
project-financed study on this subject enable Transantiago-SE to take street markets into
account whenever making changes to routes and operating schedules. It is unlikely that
the improvements to the quality and efficiency of public transport deriving from the large
scale implementation of the pilot projects will be reversed. Additionally, the project
provided Transantiago-SE with data, information and tools that will enable them to
![Page 31: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/31.jpg)
17
further improve the system. Finally, it is unlikely that the improvements made to
Transantiago’s financial and payment system will be reversed, especially considering that
by ICR preparation Transantiago-SE was preparing the bidding documents to further
improve the system.
5. Assessment of Bank and Borrower Performance
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry
Rating: Moderately Satisfactory
58. The Bank team involved in project preparation had a broad skill mix, including
various seasoned and experienced transport and urban transport specialists,
environmental and social specialists as well as safeguard and fiduciary specialists. The
preparation lasted approximately two years and was done together with the preparation of
the Santiago DPL. Frequent preparation missions were carried out and documented in the
Aide-Mémoires. The PAD is concise, but comprehensive in its coverage. It shows an in-
depth knowledge of the sector issues at the time of appraisal.
59. The technical design of the operation benefited from the Bank’s involvement in
the GEF project and in the parallel Santiago DPL. The technical preparation was
thorough. The TORs for more than half of the activities were ready at the time of
appraisal. The Bank team also adequately handled the fiduciary and safeguard aspects.
60. In hindsight, the project description was too rigid, leaving no space for changes in
the project activities. The results framework also had limitations as indicated in section
2.3 and not all risks were anticipated and mitigated (see paragraph 24). Consequently,
although the technical preparation was thoroughly carried out, due to these shortcomings,
Bank performance in terms of ensuring quality at entry was rated moderately satisfactory.
(b) Quality of Supervision
Rating: Satisfactory
61. During project supervision, the Bank team maintained an adequate skill mix,
including transport, environmental and fiduciary specialists. The team had a high level of
involvement throughout the lifetime of project implementation. Supervision missions
took place twice a year. In addition, the team was in constant contact with the PCU to
provide international experience, good practice examples and technical advice, review
and comment on TORs and project reports, and help address implementation issues.
Because of the rigid description of the project activities and the great need for flexibility
in this operation, the team showed creativity to solve implementation problems and adapt
the project activities to changed local conditions.
62. After the introduction of Transantiago, which almost completely stopped project
implementation during one year, Bank supervision was even more intensified through
monthly virtual supervisions via conference calls documented in detailed minutes. This
together with project restructuring brought project implementation under control again.
63. During the last few years of project implementation, Bank supervision put a lot of
effort in defining the pilot projects and pushing for their implementation before project
![Page 32: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/32.jpg)
18
closure. Safeguard and fiduciary aspects throughout the project implementation period
were adequately taken into account.
64. Because of the strong involvement in and constant support to this operation, the
performance of the Bank in supervising was considered satisfactory even if the team fell
short of fixing some of the shortcomings of the results framework during restructuring.
(c) Justification of Rating for Overall Bank Performance
Rating: Moderately Satisfactory
65. The Bank performance at entry was rated moderately satisfactory and the quality
of supervision was rated satisfactory. Therefore, the Bank’s overall performance was
considered moderately satisfactory.
5.2 Borrower Performance
(a) Government Performance
Rating: Moderately Satisfactory
66. The GoCH involved a broad range of sector agencies in project preparation,
assigned the necessary staff and resources, and put an enabling environment into place.
Hence, the GoCH’s contribution to project preparation was adequate.
67. During project implementation, the GoCH provided more counterpart funds than
agreed upon and stuck to the institutional arrangements defined at appraisal. The GoCH
showed a high level of commitment in the creation of an efficient and high quality public
transport system and consequently to the achievement of the PDO. The commitment to
Transantiago grew even stronger after the launch of the new system, which had caused
enormous distress to users and risked government collapse. At that time, the GoCH did
everything possible to correct the launch mistakes and make Transantiago work. This
exclusive dedication to fix Transantiago’s problems affected the resource priorities within
Transantiago-SE, led to several changes of Transantiago-SE’s coordinator and key staff,
and heavily slowed down project implementation for at least a year. Once the initial
difficulties of Transantiago were overcome, the GoCH was determined to use the
restructured TAL as a tool to improve the public transport system and build capacity and
skills within Transantiago-SE.
Although the commitment of the GoCH to Transantiago was exemplary, especially after
the launch problems occurred, it temporarily and understandably distracted the attention
from the implementation of the project activities. Consequently, the overall government
performance was rated moderately satisfactory.
(b) Implementing Agency or Agencies Performance
Rating: Satisfactory
68. Transantiago-SE, SECTRA, MTT, MINVU, SERVIU, and SEREMITT-RM were
all involved in project preparation. Their technical knowledge and experience was
fundamental in preparing a technically robust and sound operation.
69. The PCU had a small, well-qualified and highly committed team in charge of both
the TAL and the GEF projects. In technical matters, the PCU was supported by technical
staff from other areas of Transantiago-SE, SECTRA, and MTT. Together they did an
exemplary job in terms of preparing TOR and technical specification and supervising the
![Page 33: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/33.jpg)
19
studies and project activities. Study reports were thoroughly reviewed normally by at
least three people. The team provided excellent comments and high-quality technical
contributions. For most studies, they requested further analyses, which implied additional
supervision work. The team also provided valuable technical input to project
restructuring and was highly committed to the successive design of the pilot projects.
70. In safeguard and fiduciary terms, the performance of the PCU was also
satisfactory, except for minor accounting errors, not implying any accountability issues,
and some shortcomings in procurement mainly due to the temporary unfamiliarity of the
team with Bank procurement rules and procedures after the sudden departure of the head
of the PCU in 2009.
71. Given (i) the excellent technical performance of the project implementation
agencies; (ii) a largely satisfactory performance of the PCU in fiduciary and safeguard
terms; and (iii) the fact that most factors that slowed down project implementation
pointed out in section 2.2 were outside the direct control of the implementation agencies,
the performance of the implementation agencies was considered satisfactory.
(c) Justification of Rating for Overall Borrower Performance
Rating: Moderately Satisfactory
72. Since the government’s performance was moderately satisfactory and the
performance of the implementation agencies was satisfactory, the overall Borrower
performance was rated moderately satisfactory.
6. Lessons Learned
73. The technical lessons stemming from the implementation of the urban transport
reform are outlined in detail in the ICR of the Santiago DPL. Other lessons relevant for
the design and implementation of future operations in Chile or similar operations
elsewhere are the following:
In upper-middle-income countries, especially the ones with high technical
capacity, Bank involvement in transport constitutes a true two-way investment.
The Bank involvement in the Santiago urban transport reform not only provided the
GoCH with international experiences and practices, the opportunity for a continuous
policy dialogue, and some funds, but was also an exceptional learning experience for
the Bank team. Accompanying the whole reform process, from its design to the
solution of the launch problems, was highly instructive and the lessons learned from
this experience are greatly valued among other Bank clients.
In upper-middle-income countries, access to international experiences and
flexibility are more valued than the Bank’s financial resources. To successfully
implement a Bank project in a country like Chile, the Bank’s financial resources
constitute little incentive and other elements must be in place. First, the project
activities must continuously stay highly relevant for the current business needs of the
client. This requires great flexibility in the formulation of the project activities and a
willingness to make changes or drop them and start anew. It is especially important if
a government change occurs in the early years of project implementation. Since the
TAL supported a cutting edge reform in a fast changing environment and spanned
over three government periods, this was particularly true. Flexibility is also required
![Page 34: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/34.jpg)
20
in the application of Bank’s procurement rules and procedures to avoid imposing any
additional burden. Moreover, upper-middle-income countries highly value
international experiences and good practices. Therefore, the focus should be on
activities where the Bank can bring global knowledge.
It is difficult to design a good results framework for a TAL or an institutional
strengthening component. This operation showed that it is difficult to design a good
results framework for a TAL since institutional and capacity strengthening activities
do not easily lend themselves for precise outcome indicators. It also confirmed that it
remains a challenge to make all projects fit into the same results framework template,
which is better suited to the structure of infrastructure investments and projects with
precise physical outcomes. Consequently, particular focus needs to be placed on the
formulation of the PDO and the design of the results framework during quality
enhancement meetings not only for new projects, but also for project restructurings.
Additionally, mid-term reviews should be systematically used to critically review the
PDO and results framework and capacity strengthening should be provided.
A TAL that accompanies a Development Policy Loan (DPL) needs careful
planning. When the project was prepared, it was standard practice to have a TAL
accompanying a DPL. Nowadays DPLs without TALs are accepted. That said, the
operation confirmed that a TAL can be valuable to provide the Borrower with
resources and technical assistance to accompany a reform program. In countries
where Bank funds are additional to the general budget, it also constitutes an incentive
for sectoral agencies, which do not receive funds from a DPL. However, time and
careful planning are of essence. If the TAL and the DPL become effective together
and considering that it may take a year to contract a consulting firm, the technical
assistance will become available when the reform is on its way and the DPL is
disbursed. In Santiago this was not sufficiently factored in. Several activities meant to
prepare for the introduction of the reform were carried out by the GoCH and were
later cancelled from the project. Additionally, once the launch problems occurred, a
quick reaction was needed. With the Bank team in Washington and given our
procurement rules and procedures, such quick response was difficult.
Best practice study trips. The project-financed study trips for urban transport
specialists to Bogota and Spain were highly successful for the following reasons: (i)
thorough planning and organization of the trips (the project hired a consulting firm to
do research on the areas of interest and plan and organize the trips in close
collaboration with Transantiago-SE); (ii) participation of people that were doing the
job and likely to stay in the organization; (iii) a requirement for participants to report
back to their peers; (iv) excellent presentations to the peers with lots of photos, which
were extremely interesting also for the Bank team; and (v) the consideration of
several foreign practices, especially in the area of user information and attention, for
replication in Santiago. This could potentially be a model for the Bank’s global
knowledge capture efforts and the south to south exchanges.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners (a) Borrower/implementing agencies
74. The Borrower comments received on May 16 and 21, 2012 were incorporated in
the report.
![Page 35: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/35.jpg)
21
(b) Cofinanciers
75. Not applicable.
(c) Other partners and stakeholders
76. Not applicable.
![Page 36: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/36.jpg)
22
Annex 1. Project Costs and Financing
(a) Project Cost by Component (in USD Million equivalent)
Components Appraisal
Estimate (USD
millions)
Estimate at
Restructuring
(USD
millions)
Actual/Latest
Estimate (USD
millions)
Percentage
of
Appraisal
Percentage of
Restructuring
A. General Urban Transport 1.07 0.67 0.80 75% 120%
B. Public Transport 1.81 4.26 2.34 129% 55%
C. Environment 0.23 0.12 0.43 188% 360%
D. Land Use 0.89 0.63 0.57 64% 90% E. Social Aspects of
Transport 1.00 0.23 0.21 21% 92%
F. Mitigation of Potential
Impacts 0.28 0.00
0.00 0% 0%
G. Project Management 0.50 0.08 0.02 4% 27%
Total Baseline Cost 5.78 5.99 4.37 76% 73%
Physical Contingencies 0.00 0.00 0.00 Price Contingencies 0.20 0.00 0.00 0% 0%
Total Project Costs 5.98 5.99 4.37
73%
73%
Front-end fee PPF 0.00 0.00 0.00
Front-end fee IBRD 0.02 0.012 0.012 60% 100%
Total Financing Required 6.00 6.00 4.38 73% 73%
(b) Financing
Source of Funds Type of
Cofinancing
Appraisal /
Restructuring
Estimate (USD millions)
Actual/Latest
Estimate (USD
millions)
Percentage of
Appraisal /
Restructuring
Borrower 1.20 2.01 168%
International Bank for Reconstruction
and Development 4.80 2.37 49%
6.00 4.38 73%
![Page 37: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/37.jpg)
23
Annex 2. Outputs/Outcomes by Component Component A. General Urban Transport
Cost: US$0.8 million, which corresponds to 120% of the cost estimation revised during project restructuring
Activities carried out, outputs and outcomes Actual or likely contribution to
original indicators, intermediate
outcomes and PDO
Actual or likely contribution to
revised/current indicators,
intermediate outcomes and PDO
Current Subcomponent A.1. Carrying out an analysis and developing a socio-economic sub-model for SECTRA’s transport planning model
ESTRAUS.
This subcomponent was meant to analyze the socio-economic aspects
related to ESTRAUS and develop a tool to forecast the income,
motorization rate, and household size for Metropolitan Santiago.
The activities were carried out and the forecast tool was developed. This
tool is crucial in transport planning to more precisely forecast travel demand
since the socioeconomic characteristics of passengers determine their travel
behavior. SECTRA used the tool to plan the extension of the Santiago metro
system and to follow up on the 2006-2012 development plans for the
transport system in Metropolitan Santiago.
SECTRA will update the forecast tool with the results of the origin-
destination (O-D) survey ongoing at the time of ICR preparation.
Since the tool developed under the
project was used to plan the extension of
the Santiago metro system and to follow
up on the 2006-2012 development plans
for the transport system in Metropolitan
Santiago, this subcomponent contributed
to the original PDO of ―facilitating the
continuous planning of the urban
transport reform program‖.
Since the tool developed under the
project was used to plan the
extension of the Santiago metro
system and follow up on the 2006-
2012 development plans for the
transport system in Metropolitan
Santiago, it seems reasonable to
assume that this subcomponent
contributed to the revised PDO of
―increasing the efficiency and
sustainability of the urban transport
system‖.
Further contributions are still likely
because SECTRA will update the
tool and use it for future transport
planning in Metropolitan Santiago.
Current Subcomponent A.2. Designing of an institutional framework for Transantiago.
This project subcomponent envisaged to finance a study to analyze possible
institutional structures for Transantiago, propose a new institutional
framework, and devise an action plan to implement it.
Since the Borrower carried out an institutional analysis in-house, the project
complemented this activity by supporting the organization of an
international conference on Metropolitan Transport Authorities. Based on
the institutional analysis and the results of the conference, in 2007, the
Borrower submitted a draft law on the creation of a Metropolitan Transport
By supporting the preparation of a draft
law on the creation of a Metropolitan
Transport Authority for Santiago and
preparing the basis for organizational
improvements within Transantiago-SE
(which took place) the project complied
with the indicator target of ―preparing an
institutional framework for
Transantiago‖.
By supporting the preparation of a
draft law on the creation of a
Metropolitan Transport Authority
for Santiago and preparing the basis
for organizational improvements
within Transantiago-SE, the project
complied with the indicator target of
―preparing an institutional
framework for Transantiago‖.
![Page 38: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/38.jpg)
24
Authority for Santiago to Congress. At the time of ICR preparation, the
draft law was still pending. In this context it is necessary to point out that
creating a Metropolitan Transport Authority is no easy process (there are
few success stories outside the developed world) since it affects different
entities that have to give up individual powers for the benefit of the greater
Metropolitan Transport Authority.
Transantiago-SE commissioned a study to restructure MTT, to which
Transantiago-SE belongs as a temporary program. The study recommended
various changes to the structure and organization of MTT as well as the
transformation of Transantiago-SE into an autonomous agency with legal
personality. The responsibilities of this new agency would be broader than
Transantiago-SE’s current responsibilities, including the role of
coordinating all public transport modes in Santiago. While the changes to
MTT and the formalization of the new responsibilities of Transantiago-SE
can be made in the short run through a ministerial resolution, the
transformation of Transantiago-SE into an autonomous agency will need to
be made official through a law. At the time of ICR preparation, the GoCH
was carrying out the preparatory activities to implement these changes.
The project also supported an organizational study that reviewed the
internal organization, processes, systems and resources of Transantiago-SE,
defined a strategy, functions, staffing and other needs, and redesigned the
business processes. The results of the study were the basis for numerous
improvements in terms of processes, procedures, management control,
project management, system architecture, and human resources. For
instance, as a consequence of the study, the process to generate performance
indicators was fully automated. The revision of the internal processes also
helped to eliminate duplications, such as in the generation of operational
indicators, which were collected by the operations unit and an external
consultant. This strengthened Transantiago-SE as an entity in charge of the
urban transport system in Santiago.
These activities also helped to lay the
groundwork to achieve the original
intermediate outcome of
―institutionalizing Transantiago‖ as an
―autonomous agency‖, which is likely to
happen in the short to medium term.
Finally, by strengthening Transantiago-
SE as an entity in charge of the urban
transport system in Santiago, the
subcomponent also contributed to the
original PDO of ―implementing,
monitoring, evaluating and continuous
planning of the urban transport reform‖.
These activities also helped to lay
the groundwork to achieve the
current intermediate outcome of
―institutionalizing Transantiago‖ as
an ―autonomous agency‖, which is
likely to happen in the short to
medium term.
Finally, by strengthening
Transantiago-SE as an entity in
charge of the urban transport system
in Santiago, it is assumed that the
subcomponent contributed to the
―efficiency and sustainability of the
Santiago’s urban transport system‖
(revised PDO).
Previous Subcomponent. Analyzing the impact of Transantiago on transport demand.
This subcomponent was expected to collect, through household panels,
qualitative and quantitative data on mobility patterns and analyze the
changes in these patterns in the light of different urban transport projects
and policies.
Although the activity was cancelled, the
O-D survey ongoing at the time of ICR
preparation is expected to provide data
and information on the impact of
Not applicable since the
subcomponent was cancelled during
project restructuring.
![Page 39: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/39.jpg)
25
The study was cancelled and the respective resources were allocated to
more urgent activities because at the time of project restructuring the
Borrower was contracting an O-D survey with local resources. This O-D
survey was expected to collect the same data and information as the study.
The contracting of the O-D survey was delayed. At the time of ICR
preparation, the survey was still ongoing.
Transantiago on transport demand.
Therefore, the PDO indicator target of
―completing the survey to assess
Transantiago’s impact on transport
demand‖ is likely to be achieved before
the end of 2012.
This will also contribute to the original
PDO of ―monitoring, evaluating and
continuous planning of the urban
transport reform‖.
Previous Subcomponent. Carrying out a road infrastructure conservation and management study.
This subcomponent was expected to result in the implementation of a
planning system for urban road maintenance.
The activity was cancelled because at the time of project restructuring the
planning system was no longer a priority for the Borrower. The respective
resources were allocated to more urgent activities.
With the preparation of the Infrastructure Master Plan for Public Transport
2011–2015, which places strong emphasis on road maintenance and traffic
management measures, Transantiago-SE created a simple information
system in Excel spreadsheet format with the pavement status and
maintenance needs. The system is maintained with information received
from bus operators, the municipalities and collected by Transantiago-SE
through field visits. The system is the basis for the decisions on pavement
maintenance carried out by SERVIU.
Although the subcomponent was
cancelled, Transantiago-SE created a
simple pavement management system.
Therefore, Transantiago-SE complied
partially with the original indicator of
―completing a road infrastructure
management plan‖ and the original
intermediate outcome of ―improving
road infrastructure management‖.
This also contributed at least somewhat
to the achievement of the original PDO
of ―monitoring, evaluating and
continuous planning of the urban
transport reform‖.
Not applicable since the
subcomponent was cancelled during
project restructuring.
Component B. Public Transport
Cost: US$2.34 million, which corresponds to 55% of the cost estimation revised during project restructuring
Activities carried out, outputs and outcomes Actual or likely contribution to
original indicators, intermediate
outcomes and PDO
Actual or likely contribution to
revised/current indicators,
intermediate outcomes and PDO
Current Subcomponent B.1. Carrying out evaluations of Transantiago’s performance and identification of measures to improve the public transport
system (Previous Subcomponent: Estimation of public transport travel times and proposal for actions).
Originally this subcomponent was entitled “Estimation of public transport Transantiago-SE implemented the By implementing all assessment
![Page 40: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/40.jpg)
26
travel times and proposal for actions‖. It envisaged the proposal of low cost,
high-impact solutions to reduce total travel times, especially in critical routes
of the public transport network. During project restructuring, the scope of
this subcomponent was expanded to include assessments of other key
variables that influence the performance of Transantiago and propose
improvement measures. This was necessary because the introduction of
Transantiago led to severe difficulties, which needed to be evaluated and
resolved.
The revised subcomponent financed an assessment by internationally
renowned Brazilian experts of the public transport system with the aim to
improve it. The main recommendations from this assessment pointed to (i)
fare increases, (ii) operational/service improvements, mainly to reduce the
excess supply, short routes and transfers, (iii) changes in the contracts with
the bus operators to create incentives to provide good quality services, and
(iv) fare evasion reduction. The assessment also made it clear that
Transantiago-SE lacked the tools to adequately monitor the service offer and
demand. As a follow up, Transantiago-SE, with their own funds, contracted
the consulting firm of the previously mentioned Brazilian experts to (i)
develop a model to assess the profitability of the bus concessions, (ii)
develop a transport model with data on load profiles, origins and destinations
obtained from ticket validation information, (iii) simulate the profitability of
the contract modifications negotiated with the bus operators, and (iv)
generate the data to plan new operational improvements.
All the recommendations of the assessment were taken into account. (i)
Between 2010 and the time of ICR preparation, bus fares increased from
CLP400 to CLP580, Metro fares during off peak hours from CLP400 to
CLP600, and Metro fares during peak hours from CLP460 to CLP660.
These fare increases reduced the operating subsidies from 49% and 47% of
the system’s total costs in January 2009 and 2010, respectively, to 35% and
37% in January 2011 and 2012, respectively.
(ii) More than 70 operational improvements to reduce transfers and overall
travel times and to optimize public transport supply were identified. A few
of these improvements to increase coverage and reduce transfers were
implemented. For instance, the creation of the direct bus service 118 from
recommendations of the assessment by the
Brazilian experts. Some of the measures,
such as the operational/service
improvements, increased network
coverage and reduced transfers.
More service improvements are planned
under the renegotiated contracts with the
bus concessionaires, which provide the
necessary flexibility to do so.
Consequently, this subcomponent
contributed and is still likely to contribute
to the original intermediate outcome of
―mitigating the negative effects of
Transantiago on low-income groups‖.
Public transport users belonging to the
lowest income groups normally have no
alternative to public transport. Therefore,
they benefit most from reductions of
transfers, increased coverage, and other
service improvements.
The conclusions of the Brazilian experts
also led to the development of tools to
monitor and evaluate the performance of
Transantiago. These tools were used to
plan the service improvements. Therefore,
it seems reasonable to assume that the
subcomponent contributed and is still
likely to contribute to the original PDO of
―monitoring, evaluating and continuous
planning of the urban transport reform‖.
recommendations of the public
transport experts, the PDO
indicator target of ―implementing
at least one improvement
measure identified in the
evaluation of Transantiago‖ has
been exceeded. Additionally,
more improvement measures are
highly likely under the
renegotiated contracts with the
bus concessionaries and as a
result of the study on bus
terminals and depots.
The improvement measures
implemented, among others, led
to reduced transfers, increased
network coverage, and improved
operating cost coverage.
Therefore, the project contributed
and is still likely to contribute to
the achievement of the revised
PDO of ―increasing the efficiency
and sustainability of the urban
transport system‖.
![Page 41: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/41.jpg)
27
Maipú to La Florida in 2011 provides nearly 3 million annual passengers
with a direct origin-destination connection. The new direct bus service 125
from Lo Espejo y PAC to the center of Santiago decreased transfers on this
route by 38% annually. Additionally, the total length of bus routes increased
from 2,672 km in 2010 to 2,737 km in 2012 (by 2.4%), thus enhancing
network coverage. More operational improvements will be implemented in
the framework of the renegotiated contracts with the bus operators.
(iii) The contracts with bus operators were renegotiated and came into force
between March and June 2012. These contracts introduced incentives for
improved service quality (e.g. new remuneration criteria for bus operators,
which are 70% based on passengers transported and 30% based on km
provided, remuneration linked to service quality indicators and a bonus for
good service quality), gave operators a stronger role in the fight against fare
evasion, and provided the necessary flexibility to make additional
operational improvements (the results of these contract modifications are
expected to be noticeable on the ground in the beginning of the second part
of 2012 with the introduction of the new operational program and 800 new
buses). The information on the profitability of the contract modifications
with the bus operators was also fundamental in the contract renegotiations
since it enabled a reduction in the contract price.
(iv) Finally, many campaigns against fare evasion and more strict controls
were carried out. However, at the time of ICR preparation, this had not yet
led to reduced fare evasion.
The project also financed a study to evaluate the bus depot and terminal
infrastructure, its management, and prepare an integral management plan.
This study was concluded after project closure. It provided interesting
recommendations to create a stable and quality network of bus depots and
terminals and reduce the non-commercial kilometers of bus operators. At the
time of ICR preparation, Transantiago-SE set up a unit to deal with this
topic. This unit will be in charge of implementing the study
recommendations.
Current Subcomponent B.2. Improving Transantiago’s financial and fare management system through background studies and the design and
implementation of the new system.
This subcomponent was introduced during project restructuring and aimed at Not applicable since the subcomponent Transantiago-SE made some
![Page 42: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/42.jpg)
28
improving Transantiago’s fare and financial management system. This was
expected to be done through technical assistance to analyze the financial
strength of operators and the design and implementation of a new financial
management/payment system.
The project financed a study to develop a methodology to assess the
economic and financial health of the bus operators. The methodology
enables Transantiago-SE to anticipate a critical financial situation of one or
more bus operators and avoid sudden interruptions in the public transport
supply due to an unexpected bankruptcy. This methodology was used to
develop a model to assess the profitability of bus concessions, which as
previously mentioned helped to reduce the contract price paid to bus
operators.
In the course of project implementation, Transantiago-SE contracted the
development of a technological platform for the organization as a whole.
They decided to include the design and development of this fare and
financial management system within the scope of this contract. This was
expected to provide time and cost savings and facilitate system integration.
A new financial management and payment system for feeder services was
developed. The development was brought to a halt because the contract
renegotiations with the bus operators drastically changed the remuneration
formula and eliminated the distinction between feeder and trunk services.
In the meantime, Transantiago-SE hired a consultant to make urgent short
term improvements to the fare and financial management system, which
among others consisted of protocols for data import, automation of
processes, and the traceability of manual data changes. Those improvements
made the system more reliable and stable. At the time of ICR preparation,
Transantiago-SE was preparing the bidding documents for a second study
mainly to adapt the fare and financial management system to the new
payment mechanism in the renegotiated contracts with bus operators.
In the future, it is likely that the data regarding the system’s revenues and
expenses will become available in real time. According to the renegotiated
contracts, however, data on some of the penalties or the quality bonus is only
assessed at certain intervals. Therefore, it will not be possible to make the
was introduced during project
restructuring.
initial improvements to the fare
and financial management system
and at the time of ICR
preparation was about to contract
additional services to continue
with these efforts. Despite this,
the two indicators of ―having the
availability of real time
information on payment
obligations/penalties‖ and
―information on total revenues,
expenses, deficits/ surpluses, etc.
on a daily basis‖ were not
complied with.
Nevertheless, the initial and
forthcoming improvements to the
fare and financial management
system and the information on the
financial health of operators
contributed and are still likely to
contribute to the current
intermediate outcome of
―improving its financial/fare
control and management system‖
and the current PDO of
―increasing the public transport
system’s efficiency‖.
![Page 43: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/43.jpg)
29
information on the systems deficits/ surpluses and payment obligations
available in real time/on a daily basis.
Current Subcomponent B.3. Improving the quality and /or efficiency of public transport in Metropolitan Santiago by identifying international
experiences, designing pilot projects, implementing en evaluating them.
This subcomponent was introduced during project restructuring. It aimed at
improving the quality and/or efficiency of public transport in Santiago by
financing activities to identify international good practices in terms of public
transport improvements and apply some of them on a pilot project basis.
The project financed the identification of international good practice cases in
public transport and two highly successful study trips of urban transport
professionals from Santiago to Colombia and Spain. It also financed a visit
of an expert on urban redevelopment from Bilbao to Santiago. These visits
revealed a wealth of experiences and good practices, which culminated in
the design of several pilot projects.
Two pilot projects were completed and evaluated at the time of ICR
preparation. One pilot project tested different colored pavement surface
treatments for permanent bus lanes. It showed a 10% increase in bus speed
because private vehicles no longer invaded the bus lanes. It also helped to
select the most cost-effective pavement treatment product and application
procedure. At the time of ICR preparation, Transantiago-SE was preparing
the bidding documents to apply the colored pavement surface treatment on
50 km of permanent bus lanes. Transantiago-SE was also testing the
effectiveness of applying intermittent signs on the pavement to better signify
bus lanes which only function during certain hours of the day.
The second pilot project consisted of photovoltaic lighting installation at 263
bus stops. It showed that the equipment is resistant to vandalism and that
users highly value improved illumination (75.2% of the interviewees gave it
a rating of 6 or 7 on a scale from 1 to 7, with 7 being the best). The
evaluation also found that for 72.3% of the interviewees, the quality of bus
stops is extremely important and that illumination, the bus stop roof, security
and safety are the main features to be considered. Photovoltaic lighting is
considerably cheaper than conventional lighting if investment and operating
costs are considered. In addition, the photovoltaic illumination at 263 bus
stops leads to annual CO2 emission reductions of about 36.51 tons. At the
Not applicable since the subcomponent
was introduced during project
restructuring.
Both completed pilot projects
showed potential for public
transport quality and efficiency
improvements. Therefore, the
indicator target of ―having at least
one evaluation showing a
potential for improvements‖ was
achieved.
Since the evaluations of both
implemented pilot projects
showed potential for quality
and/or efficiency improvements
and Transantiago-SE was about
to replicate their results on a large
scale, the intermediate outcome
of ―improving the quality and/or
efficiency of the public transport
system‖ was achieved in the case
of photovoltaic lighting and will
be further achieved with the large
scale implementation of the
results of both pilots.
Similarly, this contributed and is
still likely to contribute to the
revised PDO of ―increasing the
public transport system’s
efficiency‖. Further contributions
are likely when the remaining
pilots are implemented and
replicated.
![Page 44: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/44.jpg)
30
time of ICR preparation, Transantiago-SE signed a contract for the
installation of photovoltaic lighting at 1,000 additional bus stops.
Transantiago-SE also planned to pilot test the use of the excess energy from
the system to operate a real time information system on bus arrivals.
The third pilot project to test traffic signs with variable speed information in
school areas could not be carried out because Transantiago-SE received only
one offer in the procurement process for equipment and the respective
process had to be cancelled. There was not sufficient time left to launch the
procurement process again. Transantiago-SE will carry out the pilot project
with its own resources.
Similarly, the pilot project to test efficient driving was postponed because
the application of the colored pavement treatment and the control cameras in
bus corridors to be used for this test will only be ready in the second half of
2012.
Finally, also at the time of ICR preparation, a number of foreign practices,
especially in the area of user information and attention, were under
consideration to be replicated in Santiago.
Previous Subcomponent: Fare optimization in Transantiago during full operation.
This subcomponent envisaged to review the fare system after the
introduction of Transantiago. The study was eliminated from the project
scope because the O-D data and information on travel patterns, essential to
carry out the study as originally planned, was not expected to become
available in time to complete the study before loan closure.
Although the study was not carried out, immediately after the introduction of
the new public transport system, Transantiago-SE analyzed and revised the
fare system on its own. As a first step to cope with the crisis, Transantiago
reduced the fare level, eliminated the separate charge portion for feeder
services, deactivated the automatic fare increase mechanism, and increased
the validity time window of tickets. This time window was reduced again
later. Fare increases were no longer automatically triggered as envisaged in
the bus service concessions. Instead, since 2009, an independent ad hoc
committee has been determining fare increases based on the cost of the
system and the available subsidies. The Bank team maintained a policy
Although the subcomponent was
cancelled, Transantiago-SE adjusted its
fare system to the new circumstances on
the ground. Therefore, Transantiago-SE
contributed at least somewhat to the
achievement of the original PDO of
―facilitating the continuous planning of the
urban transport reform‖.
Not applicable since the
subcomponent was cancelled
during project restructuring.
![Page 45: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/45.jpg)
31
dialogue on these issues and provided information on different fare systems,
especially the ones in Europe with weekly and monthly tickets.
Previous Subcomponent: Design of intermodal stations.
This subcomponent meant to prepare a design guide for small and medium
sized transfer stations. The activity was eliminated from the project scope
because the Borrower implemented small and medium sized transfer stations
before the guide was commissioned.
Although the activity was cancelled, the
Borrower implemented small and medium
sized transfer stations and gained
experience in doing so. These stations
supported the implementation of the public
transport system. Therefore, Transantiago-
SE contributed at least somewhat to the
achievement of the original PDO of
―facilitating the implementation of the
urban transport reform‖.
Not applicable since the
subcomponent was cancelled
during project restructuring.
Previous Subcomponent: Pilot testing of Transantiago’s information system.
This subcomponent envisaged to pilot test the design specifications for
Transantiago’s graphic information system on the ground before
implementing it. When this project became effective, Transantiago-SE had
already carried out the testing with local resources. This testing consisted of
observations through researcher participation and user surveys. Therefore,
the activity envisaged under this subcomponent was eliminated from the
project scope.
Although the activity was cancelled,
Transantiago-SE tested the graphic
information system and so supported the
implementation of the public transport
system. Therefore, Transantiago-SE
contributed at least somewhat to the
original PDO of ―facilitating the
implementation of the urban transport
reform‖.
Not applicable since the
subcomponent was cancelled
during project restructuring.
Previous Subcomponent: Transantiago’s communications plans I and II, inclusive Transantiago Express.
This subcomponent envisaged to finance information campaigns and
material to inform the public about the new public transport system. It also
envisaged the operation of a bus, called Transantiago Express, to carry out
information campaigns.
When the TAL became effective, Transantiago-SE had already contracted a
technology provider, who was in charge of the design and maintenance of
the system’s Web site, and other information activities. In addition,
Transantiago-SE created a service department, which carried out regular
communications activities, including street ad campaigns, information on
buses, in the media and on the Web site, information and complaints hotline
(call center), information on bus services at bus stops, information centers,
etc.
Transantiago-SE regularly carried out ad
campaigns, other information activities and
communications. They also devised
different tools to disseminate information
about the system. Consequently,
Transantiago-SE complied with the
―original project indicator of carrying out
the dissemination campaign for
Transantiago‖.
There is no evidence that the original
outcome of ―Transantiago’s users being
well informed about the system‖ was
Not applicable since the
subcomponent was cancelled
during project restructuring.
![Page 46: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/46.jpg)
32
Because of Transantiago-SE’s strong focus on communications and
information activities, the resources of the TAL to finance information
campaigns were no longer needed, and the activity was dropped from the
project scope. As for Transantiago Express, this activity was no longer part
of the communications strategy of the administration, which took over in
2006.
Transantiago-SE’s budget for communications and information activities
over the last three years was approximately US$20 million a year. Under the
old public transport system no resources were allocated to inform public
transport users.
In 2011, on a monthly basis, Transantiago-SE’s call center provided
information on routes, services, timetables and other service aspects to
approximately 20,000 to 24,000 users. Between January 2011 and February
2012, Transantiago-SE’s Web site with information on bus routes and
services received an average of 36,600 visitors.
In November 2011, Transantiago-SE launched a service to provide
information on bus arrival times at stops via cell phones
(http://web.smsbus.cl/web/). Users have two free inquiries on bus arrival
times per day. In March 2012, the system received approximately 9,600
daily inquires relating to bus arrival times. The bidding for the study to
evaluate the progress and finalize the design of the system which provides
this service started in the framework of this TAL. The bidding was
subsequently cancelled because the 2010 earthquake in Chile shifted the
country’s priorities. The system was later implemented with local resources.
achieved and the information provision in
Transantiago still needs strengthening.
However, given (i) the huge amount of
resources spent for information purposes,
(ii) the number of information and
communications campaigns and activities
carried out, (iii) the manifold information
sources available, (iv) the statistics on their
use, and (v) considering that the project
budgeted about US$1 million for
communications and information activities
and under the old system no formal
information and communications activities
took place, it seems reasonable to assume
that this outcome was at least partially
achieved.
In the same way, it seems likely that these
activities contributed to the original PDO
of ―facilitating the implementation and
continuous planning of the urban transport
reform‖.
Component C. Environment
Cost: US$0.43 million, which corresponds to 360% of the cost estimation revised during project restructuring
Activities carried out, outputs and outcomes Actual or likely contribution to
original indicators, intermediate
outcomes and PDO
Actual or likely contribution
to revised/current indicators,
intermediate outcomes and
PDO
Current Subcomponent C.1. Monitoring of Transantiago’s impact on air quality in Santiago (Previous Subcomponent: Design of an information
system for the environmental monitoring of Transantiago).
![Page 47: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/47.jpg)
33
This subcomponent was originally meant to finance the design of a system to
inform the public of Transantiago’s impact on air quality and noise. In 2007, after
the new public transport system launch, Transantiago-SE had an immediate need to
inform the public about the air quality benefits of Transantiago. Therefore, the
scope of this subcomponent was changed to air quality impact monitoring instead
of designing a full environmental monitoring system.
The project financed the design of a methodology and a first study to assess
Transantiago’s impact on the air quality in Santiago. This study showed that
Transantiago was responsible for important decreases in particulate matter (PM),
Nitrogen Oxide (NOx), and soot at street level11
. In 2009, Transantiago-SE
financed the follow up study with their own resources. This study showed that the
positive impacts in terms of PM reductions continued to increase, while the
benefits in terms of NOx emissions reduction went slightly down. Transantiago-SE
created a Web page to disseminate this and other information on the environmental
performance of the system
(http://www.transportedesantiago.cl/LACIUDAD/MEDIOAMBIENTE/index.htm).
The results of the study were also extensively divulgated in the press and other
publications, especially immediately after the launch of Transantiago. In addition,
the results of these studies were used to make the environmental requirements of
public transport vehicles more stringent. The requirements are set out in the
Environmental Prevention and Clean-Up Plan (Plan de Prevención y
Descontaminación Ambiental) and in the MTT emission norms revised in 200912
.
They led to additional NOx and PM reductions. In 2011, Transantiago emitted 77.2
tons/year of PM and 4,211.7 tons/year of NOx, which was 19.9% less in PM and
1.7% less in NOx compared to 201013
.
At the time of ICR preparation, Transantiago-SE was in the process of contracting
Although the project did not design a
full environmental monitoring system
for Transantiago as envisaged by the
original PDO indicator, it devised
several elements of such a monitoring
system, i.e. the methodology used to
regularly monitor Transantiago’s
impact on air quality and the Web site
to disseminate the results. In addition,
the Borrower is likely to complement
the air quality monitoring system with
a noise monitoring system in the near
future. As such, the subcomponent
contributed and is still likely to
contribute to the original PDO of
―facilitating monitoring and evaluating
of the urban transport reform as well as
its continuous planning‖.
The project complied with the
PDO indicator of ―having
information on the impact of
the implementation of
Transantiago on air quality
available‖. Since this
information was used to make
the environmental
requirements of public
transport vehicles more
stringent, the subcomponent
contributed and is still likely to
contribute to the system’s
environmental sustainability,
and hence the achievement of
the revised PDO.
11 For instance, in 2007, after the introduction of the new system, public transport reduced its ultrafine PM (PM2.5) by 30% and the NOx levels by 50%. 12 ―Proyecto de Revisión, Reformulación y Actualización del Plan de Prevención y de Descontaminación Atmosférica para la Región Metropolitana (PPDA)‖, Comisión Nacional
del Medio Ambiente Región Metropolitana de Santiago, Santiago, January, 2009 and ―Normas de emisión de monóxido de carbono (CO), hidrocarburos totales (HCT),
hidrocarburos no metánicos (HCNM), metano (CH4), óxidos de nitrógeno (NOx) y material particulado (MP), para motores de buses de locomoción colectiva de la Ciudad de
Santiago‖, Subsecretaria de Transportes, published in the Official Gazette of March 13, 2002, modified with D.S. Nº 58/2003 (MSGP); D.S. 153/2005; and D.S. 42/2009. 13 ―Programa de Seguimiento Ambiental: Emisiones Atmosféricas del Sistema de Transportes Publico de buses de Santiago año 2010-2011‖, Secretaria de Transportes (SECTRA)
del año 2011. Este documento responde al Seguimiento del Plan de Prevención y Descontaminación de Santiago (PPDA).
![Page 48: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/48.jpg)
34
the third air quality impact assessment. Transantiago-SE was also planning to carry
out these studies in two to three year intervals in the future. Additionally, at that
time, the Ministry of Transport and the Ministry of Environment were preparing an
agreement to create noise maps for Santiago and other cities. For Santiago, this will
mean developing a methodology to single out Transantiago’s impact on noise
levels and to regular monitor it.
Component D. Land Use
Cost: US$0.57 million, which corresponds to 90% of the cost estimation revised during project restructuring
Activities carried out, outputs and outcomes Actual or likely contribution to original
indicators, intermediate outcomes and
PDO
Actual or likely contribution to
revised/current indicators,
intermediate outcomes and PDO
Current Subcomponent D.1. Updating the Land Use Model for Santiago (MUSSA)14
based on results of the 2001 O-D survey and the 2002 population
and housing census, and carrying out of a social assessment of three congestion pricing alternatives in the framework of Transantiago.
This subcomponent consisted of two parts. The first included an update of
MUSSA for Santiago together with the validation of its predictive capacity.
The second part, included simulations with MUSSA, ESTRAUS, and the
Methodology for Vehicle Emission Calculation (MODEM)15
to assess three
road pricing alternatives in the framework of Transantiago.
The planned activities were carried out. The simulation of three congestion
pricing alternatives showed that MUSSA needs further improvements to be
used for strategic transport planning. This will be done once the ESTRAUS
model has been updated with the results of the O-D survey.
By developing a tool for strategic transport
and land use planning, the project laid the
basis for better urban transport planning.
Once MUSSA is improved, it also seems
reasonable to assume that it will ―facilitate
continuous planning of the urban transport
system in the future‖ (original PDO).
By developing a tool for strategic
transport and land use planning, the
project laid the basis for better
urban transport planning. Once
MUSSA is improved, it also seems
reasonable to assume that it will
contribute to a ―more efficient and
sustainable urban transport system‖
(revised PDO).
Current Subcomponent D.2. Carrying out a study to update the graphic information system of the one-stop process (Ventanilla Única) information
system (Sistema de Información Ventanilla Única SIVU) and identify the needs to revise the legal framework to allow for the application of the Urban
Transport System Impact Evaluation System (Sistema de Evaluación de Impacto sobre el Sistema de Transporte Urbano SEISTU) and SIVU’s
functioning as means to mainstream procedures (Subcomponent entitled “Technological and legal support for the development of the “one-stop
process” (Ventanilla Única) project” in the PAD).
This subcomponent aimed at strengthening SEISTU by carrying out a study By providing the blueprint to improve By providing the blueprint to
14 MUSSA is a software and a mathematical model, that represents the urban real estate market and allow planners to forecast and simulate its economic equilibrium under
different demographic, macroeconomic and regulatory scenarios. With MUSSA, the user can simulate the real estate market for these scenarios and make economic evaluations of
the impacts caused in the city. It can interact with most transport models as to assess the impacts of land use and transport projects and policies (www.mussa.cl). 15 MODEM is a tool which uses inputs from ESTRAUS to simulate pollutant emissions from the transport system for Santiago as a whole and for single neighborhoods
(http://www.sectra.gob.cl/metodologias_y_herramientas_de_transporte/metodologia/transporte_medioambiente/estimacion_emisiones_fuentes_moviles_modem.html).
![Page 49: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/49.jpg)
35
to improve its legal framework and information system. Only the title of the
activity was changed during project restructuring to align it with the title in
the Loan Agreement.
The study was carried out and the blueprint to strengthen SEISTU was
prepared. A working group was set up with representatives of the Ministry
of Housing, MTT and SECTRA to implement a new legal framework for
SEISTU. The activities of the working group were suspended because the
revision of the legal framework was no longer a government priority at the
time of ICR preparation.
SEISTU, the project laid the basis for
better urban transport planning. As such, it
may ―facilitate continuous planning of the
urban transport system‖ (original PDO) in
the future.
improve SEISTU, the project laid
the basis for better urban transport
planning. As such, it may
contribute to a ―more efficient and
sustainable urban transport system‖
(revised PDO) in the future.
Previous Subcomponent: Analysis of and recommendations for the urban, architectonic, and operational planning in the influence area of transfer
stations.
This subcomponent aimed at promoting the concentration of activities and
investments around transfer stations and recommending urban design
standards to foster sustainable urban development. No activity was carried
out and, in the framework of project restructuring, the subcomponent was
eliminated from the project scope because it no longer was a priority for the
government, which took over in 2006.
Since the Borrower did not carry out any
activity to promote the concentration of
activities and investments around transfer
stations and the subcomponent was
cancelled, it did not contribute to the
achievement of the original PDO.
Not applicable since the
subcomponent was cancelled
during project restructuring.
Previous Subcomponent: Diagnostic of the transport and urban planning entities and design of instrument to facilitate inter-institutional coordination.
The objective of this subcomponent was to develop tools and procedures to
facilitate transport and land-use planning coordination. No activity was
carried out and, in the framework of project restructuring, the subcomponent
was eliminated from the project scope because it no longer was a priority
for the government, which took over in 2006.
Since the Borrower did not carry out any
activity to facilitate land-use and transport
planning coordination and the
subcomponent was cancelled, the
respective indicator was not complied with
and the subcomponent did not achieve the
original expected outcome or PDO.
Not applicable since the
subcomponent was cancelled
during project restructuring.
Component E. Social Aspects of Transport
Cost: US$0.21 million, which corresponds to 92% of the cost estimation revised during project restructuring
Activities carried out, outputs and outcomes Actual or likely contribution to original
indicators, intermediate outcomes and
PDO
Actual or likely contribution to
revised/current indicators,
intermediate outcomes and PDO
Current Subcomponent E.1. Assessment of the impact of Transantiago on street market vendors and preparation of a social mitigation program for
the benefit of such vendors (Previous Subcomponent: Social assessment of the impact of Transantiago on low-income groups in Metropolitan
Santiago).
This subcomponent was originally meant to assess the impact of The activity under this subcomponent was The revised indicator of ―designing
![Page 50: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/50.jpg)
36
Transantiago on low-income groups in Metropolitan Santiago. The scope of
the subcomponent was redirected to one specific group of low-income
users, i.e. street market vendors. This change was justified by the fact that,
on the one hand, the new system considerably decreased the average fare
level and so had large positive impacts on low-income users in monetary
terms. On the other hand, in several cases, the new bus routes and services
passed in places where street markets were held and negatively affected
their operation. Therefore, Transantiago-SE needed an urgent tool to
manage and mitigate these conflict situations with street markets.
The assessment carried out under this subcomponent showed the magnitude
of the phenomenon in Santiago, where about 1,200 street markets take place
on a weekly basis. The study produced a geo-referenced database with the
size, location, operating days/hours, and other characteristics of these street
markets. It prepared an action plan for the mitigation of conflict situations
with the public transport system as well as recommendations of a more
general nature, such as in hygienic, institutional and organizational terms.
The results of the study were used to modify bus routes and bus services
during the operating hours of street markets. Knowing the location of street
markets was also useful to identify the places to carry out public
information campaigns about Transantiago, especially concerning service
changes. Finally, at the time of ICR preparation, the Ministry of Economy
was drafting a law that used the results of the project financed study of
street market vendors as input. It is likely that this new law will lead to the
implementation of measures to improve the general condition of street
market vendors, which were proposed in the study but are outside the
responsibility of Transantiago-SE.
not carried out as originally planned.
Instead of focusing on low-income users in
general, the activity only focused on one
particular group of low-income people.
Therefore, the respective indicator of
―designing an action plan with mitigation
measures for low-income users‖ was only
partially complied with. By reducing the
negative impacts of Transantiago on street
vendors, which are one specific group of
low-income people, the subcomponent
contributed somewhat to the expected
original outcome of ―mitigating the
negative effects of Transantiago on low-
income groups‖.
Finally, the information gained from the
study on street market vendors was used to
make service changes and disseminate
information on the system. Therefore, it is
reasonable to assume that this
subcomponent contributed to the
―monitoring and evaluation as well as the
continuous planning of the urban transport
system‖ (original PDO).
an action plan to mitigate the
negative effects of Transantiago on
street vendors‖ was complied with.
By using the results of the study to
modify bus routes and bus services
during the operating hours of street
markets, the expected outcome of
―mitigating the negative effects on
street market vendors‖ was also
achieved. By the same token, it
seems reasonable to assume that
the subcomponent contributed to
the ―efficiency/sustainability of the
system‖ (revised PDO).
Previous Subcomponent: Capacity building, business creation and reconversion of the transport system workers.
This subcomponent envisaged the design and implementation of a training
program for public transport workers affected by the introduction of the
new system.
The Borrower, on its own, carried out a comprehensive program to assist,
train and reconvert displaced public transport workers and operators. It
trained 254 union leaders in the preparation of business plans, 217 public
transport workers who were over 55 years old in setting up a small business,
and 480 public transport workers who were between 40 and 54 years old
The GoCH, on its own, trained and
reconverted displaced public transport
workers and operators. As such, it
contributed to the original PDO of
―facilitating the implementation of the
urban transport reform‖. The
subcomponent was cancelled from the
project scope because it became
superfluous.
Not applicable since the
subcomponent was cancelled
during project restructuring.
![Page 51: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/51.jpg)
37
and 129 public transport workers who were under 40 years old in acquiring
a new profession. The training courses included a living allowance for three
to four months, transport costs, reimbursements and other benefits. The
program also supported 427 drivers in obtaining and homologating driver
licenses for the new system and supported a program to help small bus
owners prepare a business plan. Finally, in addition to training and direct
benefits, the program provided information on access to general benefits,
such as unemployment benefits, health insurance, etc.
Since the GoCH had carried out a comprehensive reconversion program,
this project subcomponent became superfluous and was dropped from the
project scope.
Component F. Mitigation of Potential Adverse Impacts of Transport Infrastructure Works (component cancelled in the framework of project
restructuring)
Budgeted Cost: US$0.28 million (budget reallocated to other activities)
Activities carried out, outputs and outcomes Actual or likely contribution to original
indicators, intermediate outcomes and
PDO
Actual or likely contribution to
revised/current indicators,
intermediate outcomes and PDO
Previous Subcomponent F.1. Institutional capacity strengthening in the area of involuntary resettlements.
This subcomponent envisaged to strengthen the capacity of the entities
responsible for resettlement, devise tools to facilitate the execution of
involuntary resettlement, and lay the framework for a revised compensation
scheme.
The subcomponent was cancelled from the project scope because
institutional collaboration and strengthening in the area of resettlement was
carried out at local level in the Territorial Management Commission
(Comisión de Gestión Territorial). This Commission was comprised of all
actors involved in the construction of transport infrastructure in Santiago,
including SECTRA, the Ministry of Public Works (MOP), Transantiago-
SE, SEREMITT-RM, and MTT. Its aim was to harmonize MOP’s and
SERVIU’s expropriation procedures and strengthen these entities in their
implementation. This was not achieved, but SERVIU improved its
consultation procedures. A change in Chile’s resettlement laws was no
longer envisaged.
The subcomponent was cancelled and did
not contribute to the achievement of the
original PDO.
Not applicable since the
subcomponent was cancelled
during project restructuring.
![Page 52: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/52.jpg)
38
Previous Subcomponent F.2. Upgrading of the guidelines for environmental management plans for urban infrastructure works.
This subcomponent envisaged the revision and harmonization of the two
sets of environmental guidelines used for public infrastructure projects in
Chile. The subcomponent was cancelled from the project scope because it
was no longer a priority for the newly elected government, which took over
in 2006.
Since the subcomponent was cancelled and
the Borrower did not revise and harmonize
the two sets of environmental guidelines,
the subcomponent did not contribute to the
achievement of the original PDO.
Not applicable since the
subcomponent was cancelled
during project restructuring.
Component F. Project Management (component envisaged in the Loan Agreement but not in the PAD and therefore formalized during project
restructuring in the RPP to ensure consistency)
Cost: US$0.02 million, which corresponds to 27% of the cost estimation revised during project restructuring
Activities carried out, outputs and outcomes Actual or likely contribution to original
indicators, intermediate outcomes and
PDO
Actual or likely contribution to
revised/current indicators,
intermediate outcomes and PDO
Original/Revised Subcomponent F.1. Strengthening the Project Coordination Unit (PCU) to carry out its obligations under the project through the
provision of technical assistance, training, operating costs, financing and equipment, as well as through project audits.
This component aimed at strengthening the PCU through training, technical
assistance, equipment, and operating costs. It also aimed at financing the
project audits.
The component financed the participation of Transantiago-SE staff in
procurement and financial management training courses. Project audits and
operating costs were financed by the Borrower.
Not applicable. Not applicable.
![Page 53: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/53.jpg)
39
Annex 3. Economic and Financial Analysis
Not applicable.
![Page 54: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/54.jpg)
40
Annex 4. Bank Lending and Implementation Support/Supervision Processes
(a) Task Team members Names Title Unit Responsibility/
Specialty Lending Judy L. Baker Lead Economist WBIUR Poverty Specialist
Antonio Leonardo Blasco Sr Financial Management (FM)
Specialist
LCSFM FM Specialist
Margarita Rosa De Castro Illera Consultant LCSUW Safeguard Specialist
Elisabeth Goller Sr Transport. Specialist LCSTR Transport Specialist
Pierre Graftieaux Sr Transport. Specialist AFTTR Co-TTL
Jorge Rebelo Consultant LCSTR TTL
Kenneth M. Gwilliam Consultant ECSS5 Transport. Economist
Juan Lopez-Silva Consultant CESSF Environmental
Specialist
Gerhard Menckhoff Consultant LCSTR Transport. Specialist
Slobodan Mitric Consultant SASDU Transport. Specialist
Zeinab Partow Sr Country Economist AFTP1 Economist
Richard C. Podolske Consultant ECSS5 Peer Reviewer
Jitendra J. Shah Lead Environmental Specialist ECSS3 Peer Reviewer
Anna Wellenstein Country Program Coordinator SACIA Peer Reviewer
Andres Mac Gaul Senior Procurement Specialist LCSPT Procurement Specialist
Solange Van Veldhuizen Program Assistant ECSHD Program Assistant
Luz Mesa-Bartrina Senior Counsel LEGAF Senior Counsel
Supervision/ICR Natalia Cecilia Bavio Financial Management Analyst LCSFM FM Specialist
Antonio Leonardo Blasco Sr Financial Management Specialist LCSFM FM Specialist
Flavio Chaves Natural Resources Mgmt. Specialist AFTEN Environmental
Specialist
Oscar Emilio Chinea de Leon Consultant LCC7C Procurement Specialist
Elisabeth Goller Sr Transport. Specialist LCSTR TTL
Pierre Graftieaux Sr Transport. Specialist AFTTR Co-TTL
Jorge Rebelo Consultant LCSTR TTL
Delia Beatriz Grisolia Consultant LCSFM FM Specialist
Ana Maria Grofsmacht Procurement Specialist LCSPT Procurement Specialist
Juan Lopez-Silva Consultant CESSF Environmental
Specialist
Andres Mac Gaul Senior Procurement Specialist LCSPT Procurement Specialist
Alejandro Roger Solanot Sr Financial Management Specialist LCSFM FM Specialist
Francisco Rodriguez Procurement Specialist LCSPT Procurement Specialist
Ana Lucia Jimenez Financial Management Specialist LCSFM FM Specialist
Raul Tolmos Environmental Specialist LCSEN Environmental
Specialist
Paloma Lopez Diez Extended Term Temporary LCSTR Assistant
Heike Spichal Consultant LCSTR Editor
Juan Carlos Munoz Abogabir Consultant LCSTR Consultant
![Page 55: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/55.jpg)
41
(b) Staff Time and Cost
Stage of Project Cycle Staff Time and Cost (Bank Budget Only)
No. of staff weeks USD Thousands (including
travel and consultant costs)
Lending
FY05* 9.13 40.75
Total: 9.13 40.75
Supervision/ICR
FY06 6.09 32.70
FY07 7.44 34.43
FY08 10.19 43.17
FY09 17.17 81.13
FY10 20.75 86.41
FY11 15.09 65.36
FY12 11.50** 60.00**
Total: 88.23 403.20 * Project preparation started in FY04, but costs were not charged to this project (they were likely charged
to the parallel Santiago DPL).
**Estimates
![Page 56: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/56.jpg)
42
Annex 5. Beneficiary Survey Results
No beneficiary survey was carried out.
![Page 57: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/57.jpg)
43
Annex 6. Stakeholder Workshop Report and Results
No stakeholder workshop was held.
![Page 58: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/58.jpg)
44
Annex 7. Summary of Borrower’s ICR and/or Comments on Draft ICR
Coordinación General de Transportes de Santiago
COMPLETION REPORT
SANTIAGO URBAN TRANSPORT TECHNICAL ASSISTANCE LOAN (TAL)
N°7316-CH
BORROWER CONTRIBUTION
Coordinación General de Transportes de Santiago
May 22, 2012
1. INTRODUCTION
In tribute to the Bicentennial of Chile’s Independence, the Government of Chile
(GoCh) developed the Santiago Urban Transport Plan 2000 - 2010 (PTUS) to help
solve Santiago’s mobility problems. These problems derived from rapid economic
growth, increased car use, general mobility indicators. The Plan was meant to
achieve substantial improvements in the quality of life for Santiago’s citizens. In the
Plan the main activity was Program 1 ”Modernization and Integration of Public
Transport Services“, which ultimately culminated in the Transantiago Plan to
incorporate high levels of competitiveness, efficiency and quality in urban transport.
The GoCh requested financial and technical support from the World Bank to
implement Santiago’s public transport system (Transantiago) reform. The World
Bank approved the Santiago Urban Transport Technical Assistance Loan (TAL), which
aimed at supporting the GoCh in achieving a sustainable urban transport system for
Santiago. The TAL was accompanied by the Santiago Urban Transport Development
Policy Loan (DPL) to support policy and institutional reforms envisaged to put
Transantiago into full operation.
Due to the complexity and scope of the Transantiago Plan, it was implemented in two
stages. Between October 2005 and February 2007, Transition Phase 1 was
implemented. It marked the beginning of the operation of public transport services
through concession contracts, i.e. consisting of a corporation of transport operators
with the gradual integration of new buses with high efficiency standards. In Phase 2
of the reform scheme, which started in February 2007, new trunk and feeder
services and fare integration were introduced, among others.
Since the beginning of Phase 2, Transantiago has experienced constant adjustments
in order to become a high-quality transport system. In this way, the priorities of
Transantiago-SE changed toward activities with immediate impact on Transantiago-
SE’s management capacity and the quality and efficiency of the Transantiago Plan.
![Page 59: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/59.jpg)
45
Consequently, in 2009, it was essential to restructure the different project
components of the TAL. This was due to changes in the original needs and priorities.
Component restructuring was directed towards new areas, which continued to be a
priority until the end of the project.
2. BACKGROUND OF TRANSANTIAGO AND THE ROLE OF THE TAL
More than five years after the implementation of Phase 2 of the Transantiago Plan, it
is possible to conclude that it was an unprecedented pioneering initiative in nature
and scope, which necessarily has a high level of risk, resulting in complex
implementation.
Today, it is possible to say with certainty that the new system is more efficient than
in was at the start and much better than the old system ("yellow buses"). In addition,
the system has achieved a level of stability and is on track to become one of the best
in the region.
For example, compared to the old system ("yellow buses"), bus accidents have been
reduced by more than 50 percent. Eighty percent of the current Transantiago fleet is
accessible to disabled people, which was not possible before. Air pollution caused by
public transport has been reduced by one third and travel times have decreased,
despite the increase in number of cars and congestion.
It is important to highlight that the system started with a little more than 200
services and has now evolved to more than 370 services. The system increased the
number of bus stops by 300 percent, 80 percent of which have shelters. The system
has more than 200 kilometers of exclusive bus lanes, corridors and bus-only lanes,
which is more than double compared to the previous system. Finally, coverage was
improved, reaching almost 12,000 kilometers, which is almost double of what was
initially offered.
In this process of implementation and constant system improvement, the TAL
provided a fundamental contribution both in its initial definition and in its role
supporting the system’s implementation.
Some activities were not implemented under the project as planned due to
unexpected circumstances. Despite this, at the moment of project closure, it became
evident that these activities were important for the system since they were carried
out with local funds. This happened for instance in the case of the information
campaigns and the design of the road infrastructure management mechanism.
Therefore, it is a good reflection that the initial project design was adequate.
As far as the support to the implementation of the Transantiago Plan is concerned,
on the one hand, project restructuring aimed at proving a better response to the
system’s changing priorities and Transantiago-SE’s organization. On the other hand,
the difficulties in the implementation of Transantiago severely affected the project,
almost paralyzing it. This meant limited implementation progress and a mismatch of
the initially defined components with the actual needs.
Moreover, the adjustments made during project restructuring paved the way for the
renegotiation of the concession contracts with bus operators. These renegotiations
![Page 60: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/60.jpg)
46
mark the first major milestone after the start of Phase 2 in 2007. The results of
these renegotiations have already started to become visible.
The new contracts aim exclusively to achieve a quality of service that would meet the
users’ needs. Changes are meant to be incorporated gradually, with the ultimate goal
of achieving a profound system transformation. These changes aim at eliminating the
fixed payments to bus operators which force them to stop at bus stops. It also aims
to improve frequency, as well as reduce and control fare evasion. Moreover, they will
decrease the number of transfers and protect workers, including the obligation to
pay US$1 million in the form of a performance bond for labor law violations.
3. COMPLIANCE WITH THE OBJECTIVES AND MAIN ADVANCES IN THE
DIFFERENT AREAS
This project is discussed in detail in the Implementation Completion and Results
Report (ICR) prepared by the World Bank. Therefore this section only describes the
main aspects regarding compliance with the stated objectives and the main
achievements.
The difference in the degree of achievement of the project objectives and its
implementation before and after the 2009 restructuring was mainly due to the
complex circumstances related to the implementation of the Transantiago Plan and
organizational priorities. This implied a temporary reassignment of the professional
Project Coordination Unit (PCU) staff with tasks that supported the implementation of
Transantiago. It also caused important changes in direction throughout the life of the
project. As a consequence, various activities already in progress were dropped. New
activities were incorporated, not all of which could be implemented due to the timing
of the project.
There were originally defined project objectives that remained unchanged after the
restructuring. One was the need to improve the institutional structure of
Transantiago, both fundamental and strategic. The improvement needs are both
internal to the organization and external, related to its role as planning agency of a
more sustainable urban transport in Santiago. While the project’s respective
indicator was complied with and the objective was achieved, there is clearly a long
way the Ministry of Transport and Telecommunications (MTT) has to go towards
building this institution.
Moreover, the objectives in terms of a communications strategy gained greater
importance towards the project end. This is reflected in the substantial investment of
local resources in its implementation, making it a central axis of the system. In part
this responds to the lessons learned from the system’s implementation, which now
enables Transantiago-SE to better define the target audience and the messages to
communicate.
Another key component refers to the transition from one system to another, which
involves significant social impact. A lot of effort was put into a locally funded
assistance program for workers and former transport operators to integrate them
into the new system or to help them convert to other activities.
As for the sustainability of the system, significant progress was made in the
methodology that measured the impact on air quality, which has been updated with
![Page 61: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/61.jpg)
47
local resources and has been given a permanent status through the Decontamination
Plan.
Finally, a major outstanding issue is the coordination between transport planning and
land use. This is recognized as a central focus in the overall improvement of cities.
However, since it involves actors outside Transantiago-SE and requires structural
reform, which goes beyond the transport portfolio, the related objective could not be
achieved within the framework of the project. The MTT, through the Unit for
Sustainable Transport and Urban Development, has launched a related activity aimed
at implementing this kind of improvements. A standard methodology for planning
and management with an integrated transport and urban development view was
developed, which can be replicated nationwide.
As for the objectives set during project restructuring, the most important ones relate
to the measures associated with the assessments of the Transantiago Plan. These
measures were best aligned with the project’s operational objective of supporting the
implementation of the system. The measures paved the ground for: (i) the
renegotiation of contracts with bus operators and in the future with the financial
service and technology provider (AFT); (ii) the foundations for a policy on
Transantiago’s bus terminals/depots and for legal improvements at the national
level; (iii) the implementation of pilot projects to make operational and service level
improvements, which have a high replication potential in Santiago and in the
surrounding regions; and (iv) the completion of the database for the future
construction of the financial system, which will only be possible once the new
contracts are fully operational.
Another more specific objective achieved under the project refers to interference of
transport routes and services with street markets. The study results on this subject
led to direct improvements in the system’s operation. The results enable constant
incorporation and adjustments to operational plans for bus services. In addition, the
results serve as input to the communications strategy of Transantiago. Finally, it is
the only study on the subject carried out by the public sector and is useful for other
sectors that deal with street markets.
In short, although not all objectives were fully achieved, especially in the initial stage
of the project, the experience was successful since (i) it provided great value to the
Transantiago Plan and (ii) contributions to achieve the most important objectives
have continued after project closure.
4. BANK PERFORMANCE
Since the beginning of the project, the World Bank assigned a highly qualified team
to the project. This led to a robust project design. During project implementation,
the team provided support in order to adjust the project to new priorities.
In particular, the team in charge of the project showed a high level of commitment
and was proactive, which together with the efforts of the local team led to the
successful completion of the project. This was no easy task considering the difficult
implementation of Transantiago and obstacles encountered in local processes and
institutions.
Finally, the Bank team always showed their full support in the light of difficulties
faced by the public transport system reform, the low initial implementation rate and
![Page 62: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/62.jpg)
48
project adjustments as well as contingencies, such as the earthquake on February 27,
2010.
5. BORROWER PERFORMANCE
It is important to note that due to several Bank projects under parallel
implementation (DPL, GEF and TAL) and the decision of Transantiago-SE to give
these projects continuity despite the difficulties in implementing the Transantiago
Plan, a permanent team (PCU) with highly qualified professionals in different areas
(transport, urban planning, social, environmental and financial) was created. These
professionals also managed to obtain thorough knowledge of World Bank rules. This
experience helped to solve the difficulties encountered during the execution of the
project in a timely, creative manner and to take advantage of the opportunities that
arose in the concrete context.
Additionally, the technical support provided by institutions outside the MTT, such as
SECTRA (before it became part of the MTT) and CONAMA, was fundamental. This
helped to maintain continuity throughout the project and after its completion.
6. LESSONS LEARNED
A general lesson learned from this project experience is that while thorough technical
preparation before starting is highly relevant, the definition of the objectives and
indicators needs to be in line with what can reasonably be expected and must show a
certain degree of flexibility.
Since this was a project supporting the implementation of a reform as important and
comprehensive as the Transantiago Plan, the existing risks had to be rigorously
assessed. In light of this analysis, it was necessary to define flexible and feasible
objectives in order to adjust the project within reasonable periods of time to the
needs of the objectives it supported.
Also, the indicators associated with the objectives had to be very precise and
achievable within the scope of the project and the Implementation Agency
responsibilities. For example, on the one hand, using indicators which required the
support of actors outside the Implementing Agency was risky. On the other hand,
indicators which did not allow measuring the achievements in a concrete way left
much room for interpretation, which ultimately affected the evaluation of the project.
In operational terms, it was essential that the actors involved in the project
implementation process were adequately trained in the World Bank rules. It was also
important to ensure continuity of knowledge, making sure that at least one trained
professional always integrated the teams. In this context, it was important to
highlight the efforts related to the preparation of a more didactic and concise
operating manual, carried out in the framework of project restructuring. This
facilitated the work of the actors involved in the processes, who did not have the
required thorough knowledge.
In short, in terms of the project implementation, the following aspects are highlights:
Project objectives need to be realistic with respect to the project scope and
the responsibilities of the implementing agency, and must consider the local
institutional reality.
![Page 63: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/63.jpg)
49
Project objectives need to be flexible so that the project can be adjusted to
meet its ultimate objective.
Indicators need to be feasible in the light of the proposed activities, the
project scope and the responsibilities of the implementing agency, and must
consider the local institutional reality.
Indicators need to be specific and measurable.
The actors involved in project implementation must continually be trained in
order to get a common understanding and thus accelerate administrative
processes. In this particular case, training needs were provided to the PCU
and the legal areas of Transantiago-SE, MTT and the Controller General’s
Office (CGR).
Continuity of knowledge and management of World Bank rules must be
ensured among the actors involved in project implementation to avoid delays
in processes due to changes in professional teams.
Finally, it is important to note that an important lesson learned in the
implementation of Transantiago-SE was the need for greater autonomy. This would
have avoided the duplication of administrative processes, which led to slower project
implementation and a high risk of outdated information regarding the immediate
needs.
7. CONCLUSIONS
Given the previous consideration and in line with what the World Bank concluded in
its ICR, the Borrower agrees with a final project rating of “Moderately Satisfactory”.
This is mainly due to the implementation difficulties before project restructuring.
Despite the difficulties encountered during project implementation, it is essential to
highlight Transantiago-SE’s commitment in providing continuity to the project. In
addition, the Bank and PCU staff played a fundamental role, demonstrating a
committed and proactive approach in achieving the proposed objectives.
Finally, the value added in the Bank’s support of initiatives with the scope and
complexity of the Transantiago Plan should be highlighted. Especially since no
comparable external benchmarks exist to derive lessons, the knowledge and
expertise of the Bank are critical.
8. FINAL COMMENTS
In 2012, Transantiago faces the consolidation of its new regulatory and contractual
structure. In June, the CGR is expected to formalize the seven concession contracts
with bus operators. Additionally, the responsibility to provide certain services will be
transferred from some of the current operators to other operators and the thousand
oldest buses will be replaced with new ones.
A complementary and vital step is the renegotiation of the current contractual
relationship between the AFT, the MTT and between the AFT and other actors in the
Transantiago system. The situation is expected to be solved in general terms in July
2012. This should lead to the first signs of improvements for users and the system in
the last quarter of 2012.
![Page 64: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/64.jpg)
50
Consequently, 2013 will start with new contractual arrangements for Transantiago,
leading to a healthy bus industry and the ability to address the continuing challenges
of the city.
In 2013 the objective is to continue the pursuit of continuous improvements to the
services provided by the bus operators. In addition, the new integrated vision of a
public transport system will be approached in full, especially the information and
infrastructure management. This new challenge will focus on a harmonious vision of
public transport, the city and its approach from the angle of overall user experience.
This requires, for example, a new relationship with Metro, the structural backbone of
the system. It also requires collaboration with Metrotren, the interurban train
operator, to create the first interurban train service with fare and operational
integration within Transantiago.
This change process with tangible improvements in service quality will also be
accompanied by the consolidation of the organization that regulates, manages and
monitors the system, i.e. Transantiago-SE or Coordination of Transantiago
(Coordinación Transantiago). Discussions are ongoing regarding the need to create
an entity responsible for public transport in Santiago. It is expected that a proposal
to create a new institutional framework will be ready by 2013 and under
implementation in 2014.
![Page 65: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/65.jpg)
51
Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders
There were no cofinanciers or other partners.
![Page 66: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/66.jpg)
52
Annex 9. List of Supporting Documents
IBRD and IFC Country Partnership Strategy for the Republic of Chile for the Period
2011-2016, January 11, 2011
Project Appraisal Document and Aide Memoires of preparation and supervision missions
in IRIS
Santiago Urban Transport Project Programmatic Development Loan ICR
GEF Sustainable Transport and Air Quality for Santiago Project ICR
Programa de Gobierno para el Cambio, el Futuro y la Esperanza, Chile 2010 – 2014.
Cuenta Pública ―Cumpliendo con las Personas, Cumpliendo con la Metas‖, Ministro de
Transporte y Telecomunicaciones Pedro Pablo Errázuriz Domínguez, 2011.
―Proyecto de Revisión, Reformulación y Actualización del Plan de Prevención y de
Descontaminación Atmosférica para la Región Metropolitana (PPDA)‖, Comisión
Nacional del Medio Ambiente Región Metropolitana de Santiago, Santiago, January,
2009
―Normas de emisión de monóxido de carbono (CO), hidrocarburos totales (HCT),
hidrocarburos no metánicos (HCNM), metano (CH4), óxidos de nitrógeno (NOx) y
material particulado (MP), para motores de buses de locomoción colectiva de la Ciudad
de Santiago‖, Subsecretaria de Transportes, published in the Official Gazette of March
13, 2002, modified with D.S. Nº 58/2003 (MSGP); D.S. 153/2005; and D.S. 42/2009
Pilot on efficient lighting of bus stops, User perception survey, Service Department of
Transantiago-SE, April 2012.
Informe Financiero de Transantiago, Coordinación de Transportes de Santiago, Period
June 2007 – January 2012.
―Evaluación de infraestructura existente de terminales y depósitos de buses de
locomoción colectiva urbana de Santiago y Plan de Mejoramiento Integral‖, Study
Conclusions, March 2012.
―Programa de Seguimiento Ambiental: Emisiones Atmosféricas del Sistema de
Transportes Publico de buses de Santiago año 2010-2011‖, Secretaria de Transportes
(SECTRA), 2011.
![Page 67: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/67.jpg)
53
Annex 10. Status of Transantiago at the Time of ICR Preparation
Transantiago, five years after its launch
Report prepared by Juan Carlos Munoz for the World Bank in 2012
1. Introduction
In this document we review the current state of Transantiago, the fully integrated public
transport system covering the whole of Santiago in Chile. The system is comprised of bus
services provided by private operators and a Metro system owned by the government.
Bus services were originally structured as a trunk and feeder network in which nine
feeder operators enjoyed the exclusive provision of services in an area of the city, while
five trunk operators enjoyed the exclusive provision of services in a set of corridors.
A private consortium led by the most important banks in Santiago and a technological
operator compose the Technological and Financial Administrator of Transantiago (AFT)
which provides the magnetic payment card, its charging network and the card validating
devices in all of the buses, and is responsible for the management of the funds gathered
through the fares.
The system captured worldwide attention after its premature implementation in February
2007, before most of the infrastructural and systems conditions required by its designers
were in operation. For a thorough revision of the design and implementation of
Transantiago we refer to Munoz et al, 2008.
Section 2 of this document summarizes the current state of Transantiago focusing on the
evolution of the services offered, the infrastructure available, performance indicators, the
main features of the contracts between the authority and the operator’s and the financial
situation of the system. Sections 3 and 4 present the main achievements and challenges of
the plan at present.
2. Current state of Transantiago
2.1 Public transport services
In this section we focus on the characteristics of the services offered, the state of the fleet
and the total number of kilometers driven. We distinguish bus services from Metro
services.
2.1.1 Buses
The tendering documents of Transantiago considered an operational fleet of only 4,600
buses. However, before the inauguration of Transantiago the government requested 1,000
extra buses, so the initial operational plans considered a fleet of 5,600 buses. The system
started with 1,375 new buses that had already been operating for the pre-launch or
transition phase. Transantiago’s inauguration in midst of the 2007 summer holidays was
extremely rough, with notorious lack of bus services citywide and unacceptably low
levels of service to users. The actual number of initially operating buses was clearly
insufficient—so during the first year of Transantiago the authorities focused on
significantly increasing the effective supply of bus services in the city. Table 1 displays
![Page 68: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/68.jpg)
54
the kilometers driven, the number of registered fleet, and number of services offered by
the end of years 2008 to 2011, while Figure 1 displays the evolution of the monthly
commercial kilometers offered in 2009-2011.
Year Commercial
km
(million)
Number of
Fleet
Services
2007
(starting Feb 10) 371.1 4,489 223
2008 481.4 6,399 322
2009 487.2 6,572 334
2010 512.4 6,564 357
2011 483.0 6,165 370
Table 1: Evolution of public transport commercial kilometers, number of fleet
and services after Transantiago (the fleet and services reported for 2007 reflect
figures at the time Transantiago was inaugurated; they increased significantly
later during that year). (Source: Transantiago)
Figure 1. Evolution of the monthly kilometers offered from January 2009 to December 2011
Figure 1 shows an increasing trend of the kilometers offered, peaking in March 2010, the
month when the national government changed office. During most of 2010, the
government made an effort to reduce the total kilometers offered as a way to reduce the
needed subsidy to finance the system.
The current fleet of more than 6,000 buses has been in permanent renewal to gradually
displace the old style buses (actually converted lorries) inherited from the previous
system. During 2009 and 2010 a total of 1,151 new buses joined the system. By the end
of 2013, Transantiago plans to replace 1,108 extra buses. Table 2 shows the fleet
composition in terms of 160-passenger articulated buses, standard 95-passenger buses
30,000,000
32,000,000
34,000,000
36,000,000
38,000,000
40,000,000
42,000,000
44,000,000
46,000,000
48,000,000
Jan
/09
Fe
b/0
9
Mar
/09
A
pr/
09
M
ay/0
9
Jun
/09
Ju
l/0
9
Au
g/0
9 Se
p/0
9
Oct
/09
N
ov/
09
D
ec/0
9
Jan
/10
Fe
b/1
0
Mar
/10
A
pr/
10
M
ay/1
0
Jun
/10
Ju
l/1
0
Au
g/1
0 Se
p/1
0
Oct
/10
N
ov/
10
D
ec/1
0
Jan
/11
Fe
b/1
1
Mar
/11
A
pr/
11
M
ay/1
1
Jun
/11
Ju
l/1
1
Au
g/1
1 Se
p/1
1
Oct
/11
N
ov/
11
D
ec/1
1
![Page 69: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/69.jpg)
55
and the rest of the old fleet with capacities ranging between 50 and 80 passengers (these
capacities assume a rather high 6 passengers/m2 density). The aggregated capacity of the
fleet in terms of seats/standings and the average age of the fleet are also displayed. Table
2 shows that the authority has reduced the emphasis on adding large articulated buses to
the new fleet, focusing more in renewing standard medium-sized buses.. The 2011
capacity drop is due to the extension of the Metro network which triggered a reduction in
the number of buses operating in the vicinity of the new lines.
Year Fleet Articulated Standard Rest Capacity
Avg.
Age
2008 6,399 23% 20% 58% 607,178 8.4
2009 6,572 22% 26% 52% 626,527 7.4
2010 6,564 22% 40% 38% 650,003 5.9
2011 6,165 24% 45% 31% 626,647 5.3
2012 6,167 23% 46% 31% 627,695 5.2
Table 2: Distribution of bus types and their aggregated capacity in Transantiago (Source:
Registro Nacional de Transporte Público)
The registered fleet has better environmental standards. Figure 2 shows the evolution of
the percentage of buses satisfying different (and progressively more stringent)
international environmental standards. By May 2012, 92% of the fleet was Euro III, of
which one third was also equipped with a Diesel Particulate Filter (DFP in Spanish).
Figure 2: Evolution of bus technological standards after Transantiago (Source: Registro Nacional
de Transporte Público)
Until recently, the newly added services kept most of the original trunk and feeder
structure under which the system was initially organized. These new services aimed at
reducing the average number of transfers per trip by joining and extending some services,
and relaxing the stringent exclusivity of feeder zones and corridors. However, this
flexibility could not be extended as much as desired since the original contracts were
quite rigid.
30%
10% 3% 1%
38%
37%
30% 27%
10% 9% 8%
32%
53%
65% 68%
59% 58% 58%
2% 5%
31% 33% 34%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2006 2007 2008 2009 2010 2011 2012
EURO III + DFP
EURO III
EURO II
EURO I
![Page 70: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/70.jpg)
56
Although the newly signed contracts do not change the services operating in Transantiago,
they eliminate the trunk and feeder logic by not distinguishing between both types of
services. Thus, it is expected that this trunk and feeder structure will become more
blurred in the future. The new contracts with bus operators shift from giving them
exclusive to preferential use of streets. With the recently negotiated contracts, some
previously trunk and feeder concessions have merged giving birth to larger firms whose
services are a mixture of feeder and trunk services. In addition, the system has shifted its
image from clear geographic areas (based on exclusive feeder concessions or trunk
operations over exclusive corridors) to assigning each operator of these new sets of
services its own brand recognition.
When Transantiago started, a significant issue was the number of times that the operators
did not provide the services that were committed or planned. A key change came when
the authority decided in mid-2007 to link payment of firms to the buses actually seen
operating in the city. As noted in Figure 3, this change had a dramatic impact increasing
the operating fleet from 4,600 to 5,800 buses in only three months.
Figure 3: Number of operating buses in Transantiago from July to December 2007
(Source: Beltran et al., 2011)
The efforts of the authority to force operators to effectively comply with the operational
program they prepared became more and more sophisticated. Indeed, several new
indicators were linked to the operators’ revenues. We now present the evolution of three
of them.
a) ICPH: this indicator measures the number of seats/standing places offered by an
operator aggregated for all its services. It is calculated as the number of buses
effectively operating every half an hour multiplied by their seating/standing
capacity, divided by the theoretical figure indicated by the operational program.
Figure 4 displays the evolution of this indicator once it was incorporated into the
contracts.
![Page 71: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/71.jpg)
57
Figure 4. Evolution of the ICPH (Source: Beltran et al., 2011)
The indicator presents the fraction of buses expected versus actual buses operating during
a 30-minute period. However, the indicator did not capture if vehicles operated during the
full 30 minutes or only a fraction of the time. Thus, Transantiago modified the indicator
to capture the fraction of all kilometers actually driven from those expected during the
30-minute period. This new indicator, called ICPKH, was computed for every service in
every direction and was linked to the revenues received by operators. The average
percentage obtained with this indicator directly affected the revenues obtained by an
operator.
b) ICF: this indicator measures the frequency effectively fulfilled by each service in
each direction. It is calculated as the percentage of programmed bus trips
effectively offered. Figure 5 displays the evolution of this indicator once it was
incorporated into the contracts.
Figure 5. Evolution of the ICF (Source: Beltran et al., 2011)
c) ICR: this indicator measures the regularity of the services offered by each service
in each direction. The index is based on the coefficient of variation (CV) of the
![Page 72: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/72.jpg)
58
observed headways (unfortunately measured only at the dispatching terminal).
The CV is transformed into an index of 0 (minimum) when the CV exceeds 1.5
(this is indicative that the headway variability is huge), and 1 (maximum) when
the CV is lower than 0.4 (meaning little variability across bus headways). For
values of CV between 0.4 and 1.5, the ICR decreases linearly until 0. Figure 6
displays the evolution of this indicator once it was incorporated into the contracts.
Figure 6. Evolution of the ICR (Source: Beltran et al., 2011)
As can be observed from the three graphs, the three indicators have impacted the
performance of the operators. However, in the case of ICR, this impact has been
considerably weaker. Indeed, reliability is still one of the main complaints of
Transantiago users. In addition, even though these indicators succeeded in getting the
operators to comply with the operational program, they also induced some undesirable
behaviors such as having drivers not stopping at certain stops simply to improve the
performance indicators that were part of the contracts. The authority expects that the
incentives added in new contracts (discussed later in this document) will address these
issues effectively.
2.1.2 Metro
After Transantiago was launched, Metro adapted its services to improve the level of
service offered to users. We must recall that Metro almost doubled its ridership when
Transantiago started due to several reasons: i) fare integration allowed users to take
Metro without paying a second fare, ii) information on the new bus system was
inadequate, so users opted to take Metro as the more familiar service, iii) the bus system
was providing a very poor level of service, and iv) the card payment network lacked
coverage, so Metro appeared to be the only place to load fare cards. Since 2007 the fleet
of train cars and the kilometers driven has grown as shown in Table 3. Also, a very
innovative skip-stop operation was implemented in three of the four lines during peak
periods. This operation allows the system to provide a higher level of service to
passengers, increases the capacity of the system by approximately 10% and reduces the
operational costs per kilometer. Finally, since Transantiago started, Metro has extended
its operations starting earlier and ending later in the day compared to before 2007. An
order for 108 extra train cars will start arriving by mid 2012 and should significantly
![Page 73: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/73.jpg)
59
improve the level of comfort experienced by users during peak periods. These trains will
also be equipped with air conditioning which the current fleet lacks.
2005 2006 2007 2008 2009 2010 2011
Network length (km) 66.1 85.1 85.1 85.1 85.1 94.9 103.5
Number of stations 78 92 92 92 93 101 108
Number of train cars 636 666 751 751 751 967 967
Car kilometers
driven 51,782 71,192 94,199 105,346 106,001 119,064 131,143
Annual ridership
(million passengers) 267 331 601 642 608 621 640
Table 3: Evolution of the characteristics of Metro network, services and ridership (Source: Transantiago and
Metro)
2.2 Infrastructure
In this section we focus on the characteristics of infrastructure available for operating
Transantiago. Again, we distinguish between infrastructure for buses and Metro.
2.2.1 Buses
Transantiago was inaugurated with almost no specialized infrastructure for buses. This
lack of infrastructure had a very significant impact in increased travel times, reduced bus
productivity and capacity, increased waiting times, and eliminated the potential
advantages of a trunk and feeder system. It also damaged reliability which turned out to
be one of the main complaints of bus users. Since the inauguration of Transantiago the
number of segregated bus corridors has grown steadily as shown in Table 4. However,
the current network of high standard rolling infrastructure covers only a small fraction of
the citywide trunk network of Transantiago that is more than 1,500 kilometers long.
Year Segregated
corridors
Bus only
lanes
Exclusive streets
(peak hrs only)
2007 13 68 8
2008 16 77 31
2009 65 101 31
2010 90 101 31
2011 90 101 31
Table 4: Evolution of the infrastructure for buses (kms) (Source:
Transantiago)
The implementation of segregated corridors has been slow partly because local residents
and authorities (i.e. majors) oppose them. They perceive bus corridors delay expectations
of having a Metro line in their neighborhoods and fear significant property expropriations.
On the other hand, authorities argue that segregated corridors can only be built along
wide avenues. Thus, they have designated several lanes that were previously assigned for
mixed traffic as ―Bus only‖. The number of these lanes grew in the first two years of
Transantiago as shown in Table 4. However, these lanes have been quite ineffective since
they are too often used by private vehicles and not enough attention has been paid in
terms of priority for buses at their intersections. Twice the authority has implemented a
![Page 74: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/74.jpg)
60
kind of automatic enforcement through photographic evidence to prevent cars from
invading bus ways, with very good results in terms of bus speed improvements. Some bus
lanes have also been painted red to make them visually clearer. However, these efforts
have been quite focused on only the most utilized corridors. Finally, Table 4 also shows
the evolution of exclusive streets for buses implemented during 2008 (these are streets
devoted exclusively for buses during peak periods only), mainly in the central business
district. Its network has not grown since then.
According to Muñoz (2012), the average speed offered by the various types of corridor
infrastructure vary significantly. Table 5 shows the average speed observed in the
morning rush hour for downtown headed services using different corridor types. The
average feeder speed is approximately 17 kilometers/hour, but varies significantly among
different areas of Santiago reaching only 11 kilometers/hour in some other zones.
Segregated corridors
and exclusive streets
Bus
only
lanes
Mixed
traffic
Speed (km/hr) 25.88 17.21 15.09
Table 5: Average speed for downtown-headed services using different
infrastructure during the morning rush hour (Source: Muñoz, 2012)
The authority has also focused on providing adequate bus stops for the system. In 2007,
Transantiago had only 3,013 roofed stops that had grown to 8,580 by 2010 (from a total
of approximately 11,000 stops). Recently, Transantiago installed solar lighting at about
300 stops in the suburbs and signed a contract for an additional 1,000 of these stops.
Additionally, 129 of the stops operate with off-bus payment areas (stations) during peak
periods. Even though the off-bus payment areas are quite effective in terms of speeding
up dwell times, reducing fare evasion and loading buses homogeneously, they were
designed to play a transient role while a more definitive solution was underway. After
five years, the more definitive stations have not yet been installed, and the current ones
contribute very little to the expected harmony between the public transport infrastructure
and the urban space.
The 2011-2015 Infrastructure Master plan for Transantiago establishes that around
US$760 million will be invested in building 86 kilometers of extra bus corridors and
improving 16 kilometers of mixed traffic ways with a high proportion of buses. It also
includes US$210 million to improve the quality the stops and of the stations with off-bus
payment systems, and US$25 million to install 700 cameras for bus priority enforcement.
2.2.2 Metro
Two extensions of existing metro lines have been inaugurated since 2007. Like the rest of
the network, these run at high frequency (intervals of less than 3 minutes during peak
periods) and quite reliably. Thus, they were very well received, even though they did not
attract as many new passengers as planned. As should be expected, Metro is clearly
experiencing a decreasing marginal ridership contribution from new lines added to the
system. However, new lines have also contributed to improving comfort by reducing the
average density inside trains in some critical areas. Table 3 shows the evolution of the
network (kilometers and stations), the size of the fleet (train cars), the annual kilometers
![Page 75: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/75.jpg)
61
driven and the annual ridership. Last year two new lines were announced to be
inaugurated during 2016-2018, adding 37 extra kilometers to the network.
It is interesting to notice that Metro demand during the second year of Transantiago was
particularly high even though the network did not grow. Since demand later dropped to
its 2007 level, this rise and drop could be associated to the poor level of service offered
by the bus system at the beginning of Transantiago, and the lag taken for the bus demand
to recover, and for users to recognize it. Also, it could be associated to the difference in
Metro and bus fares starting in early 2009 as shown in Figure 8.
2.3 Demand
Users of Transantiago tap in to enter a bus or the Metro network, but are not required to
tap out neither in buses nor Metro (transfers within the Metro network are not registered).
The fare system allows passengers to take up to three legs to finish their trips (i.e. two
transfers at the most). The duration between the first and last taps cannot exceed two
hours. So, during two hours, passengers may make up to three single-leg trips paying a
single fare as long as they do not take Metro more than once or repeat the same bus line.
Thus, the ridership is estimated as the number of passengers entering the system paying
their fare (even if they make more than one trip). The public transit ridership (excluding
shared taxis) in Santiago dropped after Transantiago’s inauguration, by approximately
10% below the projected demand for 2007. On one hand this is due to the difficult
beginning of Transantiago, but it is also not unexpected as the country has continued
growing strongly and the car fleet in Santiago has increased by one third in five years as
shown in Table 6.
Year Cars Cars and
motorbikes
2006 918 943
2007 972 1013
2008 1027 1081
2009 1055 1113
2010 1128 1186
2011 1222 1285
Table 6: Car fleet Metropolitan Region (surrounding
Santiago) in thousands (Source: National Institute of
Statistics, INE)
Figure 7 shows the evolution of the monthly validated trip legs in bus feeder, bus trunk
and Metro services, showing a total number around 150 million trip legs. The graph also
shows the ridership that can be inferred from this information which, as is based on the
card validation of users, neglects the multiple trips that can be made within two hours and
the growing number of trips that evade the fare. High fare evasion has been observed in
bus services in several parts of the city (fare evasion in Metro is almost nonexistent) and
it has become alarmingly high according to some studies. The red curve of Figure 6
corresponds to the estimated percentage of passengers evading the bus fare which has
recently gone over 20%. The reasons for this evasion are manifold. Some people simply
do not want to pay (fares have increased by 50% in the last three years and for a
significant fraction of the population paying the fares twice on every workday represents
around 15% of their income), others enter through the back door as a convenient way to
![Page 76: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/76.jpg)
62
enter a densely loaded bus (validators are only located at the front door), while others
may not have a facility nearby to charge their cards (the network for charging the
payment card is still insufficient in some areas of the city, particularly during some
periods). Notice that in these last two cases, evaders may pay their fare in a subsequent or
previous leg of the same trip allowing Transantiago to receive its income, but not the
evaded operator. Evasion has become a regular habit in certain areas, as the probability
of getting a fine is still so low that it pays off to evade if a user wants to minimize his/her
trip costs. The figure shows a slightly diminishing number of trips which is probably
influenced by the notoriously long student strikes that affected public schools and higher
education in Santiago through the whole second semester of 2011.
Figure 7: Evolution of feeder, trunk and metro trip legs, total trips and evasion (Source:
Transantiago)
As was mentioned, one of the main drivers of the high evasion rates is the fare. During
the first three years of Transantiago operation the fare barely changed; however, the last
two years have seen a significant increase of almost 50%. Figure 8 shows the striking
correlation between fares and evasion rates. During this period the currency fluctuated
between US$1=$450 and $650. The bus fare jumped from approximately US$0.70 when
Transantiago started to approximately US$1.15 nowadays.
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
0
20
40
60
80
100
120
140
160
180
Jun
/07
Sep
/07
Dec
/07
Mar
/08
Jun
/08
Sep
/08
Dec
/08
Mar
/09
Jun
/09
Sep
/09
Dec
/09
Mar
/10
Jun
/10
Sep
/10
Dec
/10
Mar
/11
Jun
/11
Sep
/11
Dec
/11
Evas
ion
Trip
legs
an
d T
rip
s (m
ill.)
Feeder Trunk Metro Trips Evasion
![Page 77: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/77.jpg)
63
Figure 8: Evolution of a single bus trip fare, a single metro trip fare (peak period) and fare evasion (Source:
Transantiago)
2.4 Performance indicators
The operational performance of a public transport system as complex as Transantiago
must be characterized by many different dimensions and should consider the integrated
level of service provided by the system as a whole (Metro and buses). At least we should
consider: access times, waiting times, travel times and number of transfers. The
performance indicators of this section were obtained from Muñoz (2012), in which a
representative sample of 400 trips in Santiago was thoroughly analyzed (400 trips were
selected to provide a statistically significant estimation of the average travel time for the
whole city, however for a more disaggregated analysis the number of trips does not
guarantee the same level of statistical robustness). The background of Figure 9 displays a
histogram of the distance (measured over the network) travelled by different
Transantiago users. The same figure displays the average time spent by a traveler walking,
waiting, and riding inside the vehicle for each distance segment. According to this study,
during the morning peak, the average origin to destination distance corresponds to 11.4
kilometers, while the average walking, waiting and travelling times for Transantiago
users are 13.8, 8.2 and 28.6 minutes respectively.
8%
10%
12%
14%
16%
18%
20%
22%
24%
26%
300
350
400
450
500
550
600
650
700
Evas
ion
Fare
s ($
)
Bus Fare Metro Fare Evasion
![Page 78: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/78.jpg)
64
Figure 9: Average trip conditions across all public transport users. Background: histogram of the
distance traveled; front: access time, waiting time and in-vehicle time for each distance (Source:
Muñoz, 2012)
However, not only average indicators are relevant here; the performance is strongly
linked to the reliability of these indicators across different times when the same trip is
started. Indeed, even though the average door to door travel time across all trips
corresponds to approximately 50.6 minutes, its standard deviation has been estimated as
5.9 minutes. This means that once every 20 trips, the total travel time is more than 10
minutes longer than the average.
On the other hand, travel conditions vary greatly in different areas of the city. Figure 10
shows the average total travel time for all trips within a given distance interval (the
confidence interval is 95%). This means that while some 15 kilometer long trips may take
37 minutes on average, others will take 84 minutes on average. This explains why users
have such varying experiences throughout the city, with some people considering
Transantiago a modern and efficient system, while others criticize it as slow, crowded,
infrequent, and inaccessible.
Figure 10: 95% confidence interval for average travel time across all public transport users in
Santiago (Source: Muñoz, 2012)
0.0
20.0
40.0
60.0
80.0
100.0
120.0
0%
2%
4%
6%
8%
10%
12%
14%
2.5 5.0 7.5 10.0 12.5 15.0 17.5 20.0 22.5 25.0 Más
Tim
e (
min
)
Length of the trip (km) Trips Walking Waiting In-vehicle
More
0
20
40
60
80
100
120
140
0%
2%
4%
6%
8%
10%
12%
14%
2.5 5.0 7.5 10.0 12.5 15.0 17.5 20.0 22.5 25.0 Más
(min
)
Length of the trip (km) Trips Travel Time
More
![Page 79: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/79.jpg)
65
The study results of Muñoz (2012) are somewhat consistent with those reported by
Observatorio de Movilidad Urbana (OMU) (2009) and presented in Table 7 in which the
travel time for road and rail trips are compared across 15 Latin-American cities. The
document is not clear regarding how these travel times are computed. The travel times
collected in 2007 and reported in the document coincide with the worst period for
Transantiago. Even under those circumstances, the system appeared to provide a better
level of service than most of the other comparable cities considered in the sample.
In a parallel study, DICTUC, a branch of the Catholic University of Chile, (2011) was
measuring the same set of trips since the beginning of Transantiago. Figure 11 displays
the evolution of their measurements during the morning peak period. The study also
includes the average travel time obtained during two different studies developed during
2001 and 2006, yielding 46.7 and 52.6 respectively.
The average level of service (access time, waiting time, travel time, number of transfers,
comfort, reliability, etc.) in the city started significantly lower than the one offered by the
previous system. However, as can be observed from Figure 11, significant improvements
were already observed by the end of 2007 that have remained quite constant since then. It
can also be observed that nowadays the level of service offered by Transantiago is better
than the one offered by the previous system, especially if the impact of the projected level
of citywide congestion is considered. Notwithstanding, overcrowding inside the vehicles
has become a recurring complaint, especially in Metro, as can be inferred from Table 3,
since the demand doubled in a single year without a corresponding capacity increase.
City Country Travel time (min)
Road Rail All
Belo Horizonte Brazil 38.1 35.0 38.1
Bogotá Colombia 72.1 0.0 72.1
Buenos Aires Argentina 37.0 39.1 37.3
Caracas Venezuela 55.3 20.0 53.0
Ciudad de México México 45.5 40.0 45.1
Curitiba Brazil 36.5 0.0 36.5
Guadalajara México 47.8 35.0 47.4
León México 52.2 0.0 52.2
Lima Peru 60.0 0.0 60.0
Montevideo Uruguay 34.7 25.0 34.7
Porto Alegre Brazil 35.2 25.0 34.8
Río de Janeiro Brazil 41.6 35.7 41.4
San José Costa
Rica 57.0 43.0 57.0
Santiago Chile 47.0 29.0 43.6
São Paulo Brazil 46.1 41.4 45.6
Table 7: Travel times in different Latin-American cities in 2007 (Source:
"Observatorio de Movilidad Urbana - CAF", 2009)
![Page 80: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/80.jpg)
66
Figure 11: Evolution of average total travel time (walking+waiting+in-vehicle) and waiting
time for a sample of Transantiago trips (Source: DICTUC, 2011)
A very important element of the system’s bottom line performance is its evaluation by the
users. This has been a difficult battle for Transantiago since its evaluation is (almost) at
its lowest since it was inaugurated five years ago. Figure 12 shows the approval rating of
public transport issues in Chile since the inauguration of Transantiago. The graph
distinguishes individuals in Santiago from the rest of the country, but does not distinguish
users from non-users. On the other hand, Figure 13 shows the net satisfaction (defined as
the difference between approving and disapproving passengers) for frequent users of
Transantiago which is slightly higher than for the general citizen. Both graphs are
consistent, showing that approval peaked by the end of 2009, right before fares started to
increase systematically. Although the drop could be associated with the national
government election change in March 2010, it appears that its main driver was the fare
increase. Meanwhile, the level of service has remained constant (with the exception of
the period from March to September 2010 in which the volume of services dropped as
observed in Figure 1) and the fare evasion rate has grown.
Figure 12. Transantiago approval ratings among Santiago citizens (Source: Adimark, 2010; 2012)
0
10
20
30
40
50
Jan/07 May/08 Sep/09 Feb/11 Jun/12
![Page 81: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/81.jpg)
67
Figure 13. Net satisfaction among Transantiago’s frequent users (Source: Collect Gfk, 2011)
2.5 Contracts
It is difficult to imagine a set of contracts that have been amended as often as those of
Transantiago’s operators. Since February 2007 they have been changed 17 times, four of
them quite structural. Even though all these amendments kept the structure of the original
contracts, several of them imposed new incentives to the operators. The original contracts
aimed at providing a low risk operation in which changes in ridership had a minimal
effect in revenues captured by the firms. This reduced demand risk faced by bidding
firms helped to attract new and international operators to Transantiago and to guarantee a
very competitive bidding process. The contracts specified substantial fines and revenue
deductions for operators who did not provide the services that were agreed in the
operational plan. However, the contracts also established that once an operator
accumulated a certain (fairly low) number of fines, its contract would expire. Very soon
the authority realized that this contract was not working to its advantage, since getting rid
of the operators did not help to improve the system. Thus, the fines were useless and the
authority was unable to enforce high quality service. This proved quite catastrophic. In
the beginning it meant that the operators kept most buses at the terminals, thereby
providing very insufficient services. Even though this was solved by the contract’s first
amendment, the mismatch between the incentives of operators and the goals of the
authority remained. By mid 2011, this discrepancy materialized in the form of operators
being insensitive to passengers evading the fare or drivers skipping some bus stops in
order to reach the performance indicators associated with the operational plan (although
hard to believe, this last issue has become a quite frequent passenger complaint about
Transantiago).
The authorities and operators have recently signed a new set of contracts (they are not
amendments to previous ones) imposing a new regulatory framework that significantly
increases the impact of ridership captured by operators in their revenues. The new
contracts improve and increase the indicators that relate revenues to the quality of service
being offered. The contracts also incorporate a cap to the potential subtractions in
revenues when the effective supply of services differs from the plan or if the regularity of
-70%
-51% -51% -57% -48% -50% -51% -52% -58%
-51% -43% -46%
-39% -39% -31%
-38% -28% -26%
-17% -7% -4%
4% 3% 2%
-30% -32% -30%
-100%
-50%
0%
50%
100%
Mar
-07
Ap
r-0
7
May
-07
Jun
-07
Jul-
07
Au
g-0
7
Sep
-07
Oct
-07
No
v-0
7
Dec
-07
Jan
-08
Feb
-08
Mar
-08
Ap
r-0
8 /
May
-08
Jun
-08
/ J
ul-
08
Sep
-08
/ O
ct-0
8
No
v-0
8 /
Dec
-08
Jan
-09
/ F
eb-0
9
Mar
-09
/ A
pr-
09
May
-09
/ J
un
-08
Jul-
09
/ A
ug-
09
Sep
-09
/ O
ct-0
9
Dec
-09
/ J
an-1
0
Mar
-10
/ A
pr-
10
Au
g-1
0 /
Sep
-10
Mar
-11
/ A
pr-
11
Jun
-11
/ J
ul-
11
![Page 82: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/82.jpg)
68
services drops below a certain standard. In total, the operators face a higher demand risk
with the new contracts. The authorities expect that in this new scenario operators will be
more worried about the quality of service being offered and will fight fare evasion since
it affects their own pockets. The authorities are also confident that the new incentives will
not bring on-the-street wild competition for passengers, which is one of the main
achievements of Transantiago in relation to the previous system since quite few firms are
operating, service overlapping from different firms has been kept quite limited, and the
operators cannot choose their services freely.
Finally, it is worth mentioning that in this last renegotiation of contracts the authority also
tried to keep financially sustainable firms operating in the system. It did this by including
some stabilizing mechanisms for firms revenues, limiting the maximum revenue
discounts that can be applied (Transantiago can intervene with a firm that repeatedly
provides unsatisfactory service), and establishing mechanisms to adapt to unpredictable
urban and economic conditions.
Since Transantiago started, three feeder operators went bankrupt and had to leave the
system. This created a significant headache to the authorities and damaged the level of
service to users. Thus, one of the outcomes of the negotiation process was to merge
service areas under fewer and larger players.
2.6 Financial situation
Transantiago was designed to operate without subsidies and to offer a similar average
fare per trip than the previous system; however it was launched at a slightly reduced
average fare. Even though this constraint implied fewer and larger buses, this goal was
never achieved. In the first place, the operation of a formal public transport system is
considerably more expensive than an informal one, for instance, because it entails
considerably higher labor costs. Secondly, an integrated fare is more expensive to
manage. Additionally, the new system allows for more than one trip per fare within the
120-minute time window.
It soon became clear that Transantiago would need significant subsidies to operate. In
fact, the system’s annual costs have reached approximately US$1.700 million, which is
significantly higher than the costs originally planned. The government raised funds for
Transantiago with two purposes. The first was to use central funds to subsidize students
who pay only one third of the regular fare instead of recuperating the difference from the
rest of the system’s users. The second has been to employ central funds to cover
Transantiago’s operational deficit. The total subsidies are significant and have reached
over US$50 million per month (around 40% of the total costs). Figure 13 shows the
evolution of the monthly deficit expressed in US$. Furthermore, the government also
decided that every peso spent as a subsidy in Transantiago must be mirrored in some
other Chilean city. Thus, the total national subsidy for public transport is actually double
the figure required by Transantiago.
![Page 83: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/83.jpg)
69
Figure 13: Monthly deficit (in US$) from June 2007 to January 2012
An integrated public transport system like Transantiago should be subsidized for several
reasons. On one hand, it causes significantly less congestion, pollution and accidents than
cars. On the other, subsidies allows the provision of more and more frequent services
reducing access times and waiting times for all users of the system. These efficiency
gains have been highlighted as one of the more relevant reasons justifying subsidies.
Finally, they can hardly been accused of being regressive since the large majority of
public transport users belong to the poorest sectors in the city.
3. Achievements
The main achievements of Transantiago can be listed as follows:
a) The industry has been formalized. It has moved from thousands of small operators to a
group of seven firms corresponding to only five different financial groups which are
easier to inspect, monitor and coordinate. Also, drivers now have formal contracts
which must obey labor legislation.
b) Transantiago has reduced transit externalities significantly. As shown in Figure 14,
accidents involving buses dropped by half for several reasons: drivers no longer work
insanely long shifts nor compete for passengers in the streets, vehicles are more
reliable since they are better maintained, and vehicles no longer move with their doors
open. Also, bus-based pollution and noise has reduced significantly. According to a
study developed by the Mario Molina Centre in 2009, Transantiago has contributed in
reducing the concentration of ultrathin particles (mainly associated to buses) by
cutting the number of kilometers driven and requiring buses to be equipped with
higher technological standards. For example, in Alameda, the main street in Santiago,
the concentration of ultrathin particles dropped by 25%. Environmental emergencies
are less frequent than before even though the city, its activities, and the vehicle fleet
have continued to grow.
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
May/07 Sep/08 Jan/10 Jun/11
![Page 84: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/84.jpg)
70
Figure 14: Annual number of accidents involving urban buses in Santiago (Source:
CONASET)
c) Low floor buses (80% of the fleet) equipped to handle users with reduced mobility,
fulfilled a strong need for this group.
d) Fares in the system are fully integrated. Passengers perceive the total set of public
transport services as a system and can take the most advantage out of the full network.
The introduction of the magnetic touchless card Bip! has been considered a great
success, reaching a 100% penetration among Santiago’s citizens and being one of the
few elements well evaluated by users from the beginning of the plan.
e) Metro moves twice as many passengers as before while still providing a good level of
service. The firm has proven very dynamic and innovative to deal with such a
challenge without a proportional increment in its fleet. In early 2012, it got the ―Best
Metro of the Americas‖ award.
f) Also, two social conflicts which used to happen inside buses have been eradicated:
student discrimination by drivers (since operators are paid the same by all types of
passengers) and drivers’ assaults (since new buses run cash-less).
g) Finally, the introduction of subsidies for the public transport system can also be
considered a success as long as these funds end up improving the quality of service
beyond what users can finance with their own fares, instead of financing the fares of
those users that refuse to pay.
4. Challenges
Transantiago faces, however, several challenges in different areas.
Operational
The main challenges here are the following:
a) Improve bus headway control. Regular service not only increases reliability, it also
reduces waiting times and improves comfort (Delgado et al., 2012). Unreliability in
bus service is one of the most common complaints of Transantiago.
0
1000
2000
3000
4000
5000
6000
7000
2005 2006 2007 2008 2009 2010
![Page 85: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/85.jpg)
71
b) Improve bus speeds which are quite low in several corridors of the city (Muñoz,
2012). Increasing speed reduces cycle times which in turn increase the frequency and
capacity offered. Thus, higher speeds improve travel times, waiting times and comfort.
Transantiago should expand its bus infrastructure as this has proven to increase bus
speeds significantly, as well as extend and strengthen bus priority enforcement in bus
lanes and corridors. It could also implement an extensive bus priority program at
traffic signals and formalize (using proper buses and scheduled services) its ―super
expresos‖ services which use the urban highways to join very distanced and dense city
areas. As the level of service in Transantiago varies significantly across the city, the
authorities should focus their efforts in those areas where the service is worst.
c) Fight fare evasion. This has implications that transcend the public transport system.
Evasion has become so massive in certain areas that it could affect the morals of the
city. The government is now relying on operators to fight it, but should not step back
in its own responsibility to bring evasion back to international standards.
d) Transantiago already has five years of experience. The demand patterns involved in
everyday trips are well understood. However, this knowledge has only recently been
processed and is now being used for developing operational plans or making
decisions. It seems that there is still a gap to be filled which should benefit the
unavoidable trade-off between user level of service and system costs.
Infrastructure
The government has prioritized the infrastructure for Metro over buses. Even though
Metro offers a very high level of service which will probably improve even further with
the newly added fleet (and may capture more demand to fill those trains instead of
providing more comfortable trips), it is clear that new lines will suffer from the
inescapable network effect of decreasing marginal productivity. If we add to the above
the high cost of Metro infrastructure, it is clear that Transantiago should direct investment
toward bus infrastructure, particularly BRT. Since its beginning, Transantiago has had a
bus infrastructure master plan that has been continuously delayed. The authorities should
implement this infrastructure plan, even if it implies removing some privileges for car
drivers. Congestion in the city during peak periods is reaching high levels and some areas
urgently require public transport services that could attract car owners. Bus infrastructure
is a key player in this fight. To win this battle, the corridors and lanes already built for
buses must be respected by cars. The government has started an enforcement project in a
few corridors based on automatic photo evidence and red painted bus lanes which should
be extended to the whole city. Also, very often the intersections of these bus corridors are
not well designed. This means that the interaction between buses, pedestrians, and/or cars
is so inefficient that the travel time savings gained from the high speeds experienced at
the corridor are lost.
The system started without pre-payment stations for buses. This mistake was corrected
quite quickly through a series of temporary fence-based prepayment stations operating
during peak periods only. The temporary stations were very successful in terms of
speeding up dwell times, reducing evasion and improving the boarding experience for the
![Page 86: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/86.jpg)
72
user. However, after five years, the city has not turned this transitory infrastructure into
something definitive that could add value to the urban landscape as is observed in many
other Latin-American cities.
Another relevant issue that should be addressed is the infrastructure for pedestrians and
bikers. Every transit user has to overcome an initial and a final distance through a non
motorized mode. In Santiago, even though in most Latin American cities the situation is
worse, pedestrians are exposed to uncomfortable conditions (e.g. crowdedness at
sidewalks, poor illumination, wet sidewalks during rains, etc.).
Information
The public transport system that preceded Transantiago lacked a user information system.
Transantiago has made some progress by implementing a call center, a web-based trip
planner for users, a real-time system informing the arrival time of the next few buses to
each stop based on text messages, and some information at most stops. However, the
information provided to users at buses and stops is still notably poor. The main hurdles
here have been vandalism and bureaucracy. More devices that provide online information
about the arrival time for the coming buses should be installed at the most relevant stops
(only one of these devices has been installed and has worked very well for more than two
years). Certainly, having better infrastructure in the most visited stations would help to
implement such a system there.
Also, even though Metro is the spinal chord around which Transantiago was built, the
users perceive Metro and Transantiago as separated entities. Metro has a big
responsibility with this issue since very little of its information system has changed from
when it was a fully independent transport mode. Metro should consider that its
responsibility starts much earlier than the moment a user steps in one of its stations.
Finance
Transantiago has brought subsidies that were strongly needed to public transport.
However, the total amount of subsidies assigned has not been the result of a rational
decision, balancing the social short- and long-term benefits of these subsidies with those
that could be obtained in alternative investments. Instead, the bulk of the subsidies are
needed to prevent fares from escalating. In addition, some effort should be made to
allocate subsidies to the socioeconomic groups that need them most.
Institutions
Even though Transantiago is a fully integrated system, too many agencies are involved in
key aspects of the plan. This has often prevented important decisions from being made.
Thus, one of the main problems of Transantiago is the lack of a single authority that
could simplify the decision process by looking at the system as a whole. Such an
authority should look at all transport modes in Santiago, not just at public transport. In
the last five years, the functions of the Ministry of Transport have been strengthened, and
a permanent public transport subsidy has been approved. The next step should be a
citywide authority as those that have been successfully implemented in London, Madrid
or New York.
![Page 87: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/87.jpg)
73
Contracts
New contracts with operators have been signed recently and their consequences are hard
to predict. However, one important concern is that the number of firms operating in
Santiago has been reduced to only seven, and relate to only five economic groups (with
one of them operating one third of the Transantiago fleet), so these firms will face the
authority with a much stronger hand. Another concern is that this situation could escalate
the consequences in already conflictive relations between driver unions and firms. Finally,
in the future, the authority should reduce the length of the contracts signed with the
operators. Their current length of more than 10 years is unnecessary long.
A second issue is the relation between the authority and the Technological and Financial
Administrator of Transantiago (AFT). The performance of this entity, controlled by the
most relevant banks in Chile, has been disappointing. The AFT has provided a very weak
charging network for the payment card, it has been very static in developing new
financial opportunities for this card that has 100% penetration in Santiago, etc. The AFT
has become an obstacle for the evolution of the system. The authority has announced that
the AFT will be next in the set of contracts to be revised.
As a final comment, Transantiago needs to earn the trust of citizens who have not
forgiven its catastrophic beginnings and its later consecutive fare increases. Transantiago
has made significant achievements, which many cities worldwide would consider almost
impossible. However, it still lacks some key elements that a public transport system
should provide; some of these elements, such as the infrastructure, have been quite well
solved in several cities in neighboring countries.
5. References
Adimark (2010) Encuesta: Evaluación Gestión del Gobierno a Enero 2010.
http://www.adimark.cl/es/estudios/documentos/Ev_Gob_Ene2010.pdf
Adimark (2012) Encuesta:Evaluación Gestión del Gobierno a Marzo 2012.
http://www.adimark.cl/es/estudios/documentos/003_ev_gob_3_mar12.pdf
Beltran, P., Gschwender, A. and Palma, C. (2011). The impact of compliance measures
on the operation of a bus system: the case of Transantiago. 12th International Conference
on Competition and Ownership in Land Passenger Transport (Thredbo12), Durban,
South Africa.
Collect GfK (2011) Transantiago Estudio Tracking Calidad de Servicio Nº 5, Junio-Julio
2011.
DICTUC (2011) Medición de Indicadores de Desempeño del Sistema de Transporte
Público de Santiago, 2007–2011. Subsecretaría de Transportes, Ministerio de Transporte
y Telecomunicaciones.
Delgado, F., J.C. Munoz and R. Giesen (2012) How much can holding and/or limiting
boarding improve transit performance? Transportation Research B (in press).
Munoz, J.C. (2012) Indicadores críticos en la percepción del nivel de servicio ofrecido a
usuarios. II Congreso Las Mejores Prácticas SIBRT en América Latina. Léon, México;
April 25-26, 2012.
![Page 88: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/88.jpg)
74
Munoz, J.C., Ortúzar, J. de D. and Gschwender, A. (2008) Transantiago: the fall and rise
of a radical public transport intervention. In W Saleh and G. Sammer (eds.), Travel
Demand Management and Road User Pricing: Success, Failure and Feasibility. Chapter
9, 151-172. Ashgate Publishing Limited, Farnham.
![Page 89: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/89.jpg)
75
Annex 11. Original Indicators and Degree of Achievement (a) PDO Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target
Values
Actual Value Achieved
at Completion or
Target Years
Indicator 1 : Survey to assess Transantiago’s impact on transport demand completed
Value Quantitative or Qualitative)
Survey to assess
Transantiago’s impact on
transport demand not
carried out
Survey to assess
Transantiago’s
impact on
transport demand
completed
Origin-Destination
survey ongoing with
local resources
Date achieved 05/11/2005 12/31/2009 04/06/2012
Comments (incl. % achievement)
Target likely to be met in the future with local resources
Indicator 2 : Design of a monitoring system for the environmental impacts of Transantiago
Value Quantitative or Qualitative)
No monitoring system for
the environmental
impacts of Transantiago
designed
Monitoring system
for the
environmental
impacts of
Transantiago
designed
Several elements of such a
monitoring system devised,
i.e. the methodology used
to regularly monitor
Transantiago’s impact on
air quality and the Web site
to disseminate the results;
noise monitoring system
likely to be implemented in
the near future with local
resources
Date achieved 05/11/2005 12/31/2009 04/06/2012
Comments (incl. % achievement)
Target partially met
(b) Intermediate Outcome Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Preparation of an institutional framework for Transantiago
Value (Quantitative or Qualitative)
Institutional framework
not yet existing
Preparation of an
institutional
framework for
Transantiago
Seminar on
metropolitan transport
authorities organized;
draft law to create
such an authority
pending;
Transantiago-SE
strengthened from an
organizational point of
view; initiative to
![Page 90: Document of The World Bank · Transantiago-SE into autonomous entity ongoing Date achieved 05/11/2005 12/31/2009 04/06/2012 Comments (incl. % achievement) Target met Indicator 2 :](https://reader034.vdocument.in/reader034/viewer/2022051911/600154367033d50dfd266ba2/html5/thumbnails/90.jpg)
76
transform
Transantiago-SE into
autonomous entity
ongoing
Date achieved 05/11/2005 12/31/2009 04/06/2012
Comments (incl. % achievement)
Target met
Indicator 2 : Design of an Action Plan for the proposed mitigation measures for low-income
users, including an implementation schedule
Value (Quantitative or Qualitative)
Action Plan not yet
available Action Plan
available
Action Plan only for one
particular group of low-
income people devised,
i.e. street market vendors
Date achieved 05/11/2005 12/31/2009 04/06/2012
Comments (incl. % achievement)
Target only partially met
Indicator 3 : Completion of Road Infrastructure Management Plan
Value (Quantitative or Qualitative)
No Road Infrastructure
Management Plan
Road
Infrastructure
Management Plan
completed
Transantiago-SE created
a simple pavement
management system
Date achieved 05/11/2005 12/31/2009 04/06/2012
Comments (incl. % achievement)
Target partially met with local resources
Indicator 4 : Implementation of the dissemination campaign for Transantiago
Value (Quantitative or Qualitative)
No dissemination
campaign for
Transantiago
Implementation of
the dissemination
campaign for
Transantiago
Transantiago-SE
implemented many
dissemination campaigns
and communications
activities
Date achieved 05/11/2005 12/31/2009 04/06/2012
Comments (incl. % achievement)
Target met with local resources
Indicator 5 : Proposal of land use and transport planning coordination
Value (Quantitative or Qualitative)
No proposal Proposal prepared No proposal
Date achieved 05/11/2005 12/31/2009 04/06/2012
Comments (incl. % achievement)
Target not met