dollo-ado shelter project
TRANSCRIPT
International Organization
for Migration
Objective………..
Construction of 1145 Transitional shelters
for the Year 2013
Funding source :- UNHCR / DFID
Brief description about IOM
Shelter design
Floor area - 6.0mx3.5m=21.0Sqm
Wall Height - 2.4m
Ridge Height - 3.4m
Main components of the shelter………
Eucalyptus timber frame work
Bamboo walling
CGI sheet roofing
Floor Plan of the shelter
Sequence of operation in shelter
construction……….
At workshop….
Preparing timber columns and components
for frames.
Preparing roof trusses .
Preparing doors and windows .
Slicing bamboo poles .
Preparing timber columns and
components for frames.
Preparing timber columns and
components for frames.
Preparing roof trusses
Preparing doors and windows
Slicing bamboo poles
Sequence of operation in shelter
construction……….
At site…..
Setting out and column erection.
Fabricating timber Skelton.
Fixing roof trusses.
Attaching bamboo slices.
Roofing
Fixing door and windows
Setting out and column erection
column erection
Fabricating timber Skelton
Attaching bamboo slices
Roofing
Materials and prefabricated items
delivered to the site for shelter
construction…..
From Workshop….
Transporting shelter components to
the site……
Materials and prefabricated items
delivered to the site for shelter
construction…..
From Store….
Quality Control monitoring…….
At workshop…….
Quality Controlling at workshop…...
Quality Control monitoring…….
At site….
Shelters completed per Zone
. ZONE # OF SHELTERS COMPLETED
ZONE A 26
ZONE B 69
ZONE C 51
ZONE D 51
ZONE E 54
ZONE F 29
ZONE G 35
ZONE H 50
ZONE I 55
ZONE J 59
ZONE K 62
ZONE L 56
ZONE M 50
ZONE N 54
ZONE O 77
ZONE P 73
ZONE Q 100
ZONE R 70
ZONE S 64
ZONE T 70
TOTAL 1155
Monthly Progress-2013
MELKEDIDA SHELTER CONSTRUCTION
PROGRAM & PROGRESS-2013
0.0
100.0
200.0
300.0
400.0
# O
F SH
ELTE
RS
ORIGINEL PROGRAM 100.0 120.0 140.0 140.0 140.0 140.0 140.0 140.0 85.0
PROGRESS 54.0 108.0 105.0 67.0 56.0 120.0 102.0 197.0 346.0
Apr- May- Jun- Jul-13 Aug-1 Sep- Oct- Nov- Dec-
A tool using to find the impact of IOM shelters and gathering beneficiary
details
Major challenges Encountered
Delay in Commencement of the project
Failure in supplying the materials in time by local
suppliers from Dollo-Ado
Poor quality materials by the local supplier
Delay in material supply due to road taxation
Delay in supplying the materials due to rain in
November.
Road condition between Dollo and Melkedida