domino case study - pci · case studies 04. what‘s next 05. residential typical lower floors have...
TRANSCRIPT
Brooklyn, NYArchitect: CookFoxMaster Plan: shOp ArchitectsOwner: Two Trees Management Co.
MOVEMENT
CASE STUDYMOTION
SHAPED
CAST
CARVED
S C U L P T E D
COARSE
FRAGMENTORGANIC
C R A F TF A B R I C A T EM O D U L E S
Design Data saved in Revit Families• Cook Fox• Nate Brooks – Gate Precast BIM
Managing Director• Their collaboration produced a set of
parameter-driven panel models that could be easily modified to keep up with on-going design decisions
CookFox/GATE design assist For Construction ModelDetailing/Engineering
3D PrintingForms/Hardware/Reinforcement
Additive Manufacturing
TOPICS OF DISCUSSION
ABOUT GATE01.
PCI AWARDS02.
TIMELINE03.
CASE STUDIES
04.WHAT‘S NEXT05.
TOPICS OF DISCUSSION
ABOUT GATE01.
PCI AWARDS02.
TIMELINE03.
CASE STUDIES
04.WHAT‘S NEXT05.
RESIDENTIALTypical lower floors have 19 piecesComplete floor is 2 days
RESIDENTIALTypical upper floors have 28 pieces Complete floor is 4 days
COMMERCIALTypical floor has 22 pieces.Complete floor is 2 ½ days
We never explored traditional delivery . It’s Hard to quantify the time savings because you would have to figure distributing to every floor and staging in the apartments. It would have massively delayed our ability to start the interiors program. The use of the hoist alone would have prohibited other trades from doing their work not to mention the added duration to occupy each apartment and install the window which is probably an hour per window.
-Hale Everets, Two Trees
TIME SAVINGS:
• Off-Site Manufacturing can start while Permits and Site Work are still ongoing
• No delays due to weather conditions
• Better quality control with controlled installation conditions in the plants
• Lower labor cost for off-site installation
• Reduced liability in regards to contingency allocation.CONSTRUCTIONDETAIL DRAWINGS
DESIGN-ASSIST DELIVERY
TIME SAVED
PROJECT DURATION DESIGN-ASSIST DELIVERY
TRADITIONALDELIVERY
COST ESTABLISHED
DETAIL DRAWINGS
BID CONSTRUCTION
COST ESTABLISHED
POTENTIALREDESIGN
SHOP DRAWINGS
PRELIMINARYDRAWINGS
PRELIMINARYDRAWINGS
TRADITIONAL DELIVERY METHOD