Page 1: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces

Brooklyn, NYArchitect: CookFoxMaster Plan: shOp ArchitectsOwner: Two Trees Management Co.

MOVEMENT

CASE STUDYMOTION

SHAPED

CAST

CARVED

S C U L P T E D

COARSE

FRAGMENTORGANIC

C R A F TF A B R I C A T EM O D U L E S

Page 2: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces
Page 3: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces
Page 4: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces
Page 5: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces
Page 6: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces

Design Data saved in Revit Families• Cook Fox• Nate Brooks – Gate Precast BIM

Managing Director• Their collaboration produced a set of

parameter-driven panel models that could be easily modified to keep up with on-going design decisions

Page 7: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces

CookFox/GATE design assist For Construction ModelDetailing/Engineering

3D PrintingForms/Hardware/Reinforcement

Page 8: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces

Additive Manufacturing

Page 9: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces
Page 10: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces
Page 11: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces

TOPICS OF DISCUSSION

ABOUT GATE01.

PCI AWARDS02.

TIMELINE03.

CASE STUDIES

04.WHAT‘S NEXT05.

Page 12: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces
Page 13: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces

TOPICS OF DISCUSSION

ABOUT GATE01.

PCI AWARDS02.

TIMELINE03.

CASE STUDIES

04.WHAT‘S NEXT05.

Page 14: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces

RESIDENTIALTypical lower floors have 19 piecesComplete floor is 2 days

RESIDENTIALTypical upper floors have 28 pieces Complete floor is 4 days

COMMERCIALTypical floor has 22 pieces.Complete floor is 2 ½ days

We never explored traditional delivery . It’s Hard to quantify the time savings because you would have to figure distributing to every floor and staging in the apartments. It would have massively delayed our ability to start the interiors program. The use of the hoist alone would have prohibited other trades from doing their work not to mention the added duration to occupy each apartment and install the window which is probably an hour per window.

-Hale Everets, Two Trees

Page 15: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces
Page 16: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces
Page 17: Domino case study - PCI · CASE STUDIES 04. WHAT‘S NEXT 05. RESIDENTIAL Typical lower floors have 19 pieces Complete floor is 2 days RESIDENTIAL Typical upper floors have 28 pieces

TIME SAVINGS:

• Off-Site Manufacturing can start while Permits and Site Work are still ongoing

• No delays due to weather conditions

• Better quality control with controlled installation conditions in the plants

• Lower labor cost for off-site installation

• Reduced liability in regards to contingency allocation.CONSTRUCTIONDETAIL DRAWINGS

DESIGN-ASSIST DELIVERY

TIME SAVED

PROJECT DURATION DESIGN-ASSIST DELIVERY

TRADITIONALDELIVERY

COST ESTABLISHED

DETAIL DRAWINGS

BID CONSTRUCTION

COST ESTABLISHED

POTENTIALREDESIGN

SHOP DRAWINGS

PRELIMINARYDRAWINGS

PRELIMINARYDRAWINGS

TRADITIONAL DELIVERY METHOD