don lynch december 4, 2014. agenda december 4, 2014 2 babar magnet update outer hcal structural...

27
DON LYNCH DECEMBER 4, 2014 sPHENIX Engineering Meeting

Upload: hilda-rosamond-marsh

Post on 20-Jan-2018

214 views

Category:

Documents


0 download

DESCRIPTION

Present Magnet Status SC Solenoid Magnet is at SLAC Ready for shipment but shipping vendor screw up requires a re-bid of shipping contract – RFQ has been issued and bids are due tomorrow Expect to ship ~ mid January Valve box is also at SLAC and will ship separately Other ancillary equipment is crated, will also ship separately Still planning for ~May 2015 cold, low current test Planning for a full field test at some point Magnet review scheduled for 12/16 December 4, November 4,

TRANSCRIPT

Page 1: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

DON LYNCHDECEMBER 4, 2014

sPHENIX Engineering Meeting

Page 2: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

AGENDA

December 4, 2014

2

BABAR Magnet UpdateOuter HCal Structural Analysis (Assembly

and Support)sPHENIX Project Management

Page 3: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

Present Magnet Status

• SC Solenoid Magnet is at SLAC• Ready for shipment but shipping vendor

screw up requires a re-bid of shipping contract – RFQ has been issued and bids are due tomorrow

• Expect to ship ~ mid January • Valve box is also at SLAC and will ship

separately• Other ancillary equipment is crated, will

also ship separately• Still planning for ~May 2015 cold, low

current test• Planning for a full field test at some point• Magnet review scheduled for 12/16

December 4, 2014

3

November 4, 2014

3

Page 4: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

sPHENIX Global Design Concept

December 4, 2014

4

Up to 14 tall racks on upper platform

Ships stair access to mid and upper platforms

Valve box: cryo supply, magnet power connections, monitoring connections

2 500 liter dewars (1 permanent for top off, 1 temp during shutdown for cooldown transfers)

Mid level platform 2 racks? access

Up to 13 (7 short, 6 tall) racks on lower platform

Flux return end caps,Hinged

Page 5: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

Current sPHENIX model fits through shield wall opening

December 4, 2014

5

Page 6: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

Dimensions for Magnet Calculations

December 4, 2014

6

Page 7: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

Dimensions for Magnet Calculations

December 4, 2014

7

Page 8: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

Dimensions for Magnet Calculations

December 4, 2014

8

Page 9: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

December 4, 2014

9Dimensions for Magnet Calculations

Page 10: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

Outer HCal Assembly and Support Analyses

December 4, 2014

10

Anatoli’s slides showing analyses of the Outer HCal Assembly and Support have been reduced in the following slides. The full set of slides are linked on the agenda page.

Page 11: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

sPHENIX OUTER CALORIMETER ASSEMBLY STRUCTURAL ANALYSES.

1. HALF BARREL, SUPPORTED BY 33.75 degree SUPPORT (3 modules)

11BNL, A.Gordeev, R.Ruggiero

5 DIFFERENTSITUATION

RELATED TO OUTER

CALORIMETERHAS BEEN STUDIED

3 module has fixed support

Page 12: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

sPHENIX OUTER CALORIMETER ASSEMBLY STRUCTURAL ANALYSES.

1. HALF BARREL, SUPPORTED BY 33.75 degree SUPPORT (3 modules)DEFORMATION

12BNL, A.Gordeev, R.Ruggiero

Page 13: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

sPHENIX OUTER CALORIMETER ASSEMBLY STRUCTURAL ANALYSES.

1. HALF BARREL, SUPPORTED BY 33.75 degree SUPPORT (3 modules)EQUIVALENT STRESS

13BNL, A.Gordeev, R.Ruggiero

Page 14: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

sPHENIX OUTER CALORIMETER ASSEMBLY STRUCTURAL ANALYSES.

2. HALF BARREL, SUPPORTED BY 101.25 degree SUPPORT (11 modules)

14BNL, A.Gordeev, R.Ruggiero

11 modules have fixed support

(101.25 degree)

LASTSUPPORTED

MODULE

FIRSTSUPPORTED

MODULE

Page 15: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

sPHENIX OUTER CALORIMETER ASSEMBLY STRUCTURAL ANALYSES.

2. HALF BARREL, SUPPORTED BY 101.25 degree SUPPORT (11 modules)3D DEFORMATION

15BNL, A.Gordeev, R.Ruggiero

Page 16: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

sPHENIX OUTER CALORIMETER ASSEMBLY STRUCTURAL ANALYSES.

2. HALF BARREL, SUPPORTED BY 101.25 degree SUPPORT (11 modules)EQUIVALENT STRESS

16BNL, A.Gordeev, R.Ruggiero

Page 17: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

sPHENIX OUTER CALORIMETER ASSEMBLY STRUCTURAL ANALYSES.

3. QUARTER BARREL, SUPPORTED BY 1 (one) MODULE BOTTOM

17BNL, A.Gordeev, R.Ruggiero

FIXED SUPPORTS

8 MODULES TOTAL

Page 18: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

sPHENIX OUTER CALORIMETER ASSEMBLY STRUCTURAL ANALYSES.

3. QUARTER BARREL, SUPPORTED BY 1 (one) MODULE BOTTOMDEFORMATION

18BNL, A.Gordeev, R.Ruggiero

X = 1.75mm

Y = 1.6 mm

Page 19: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

sPHENIX OUTER CALORIMETER ASSEMBLY STRUCTURAL ANALYSES.

3. QUARTER BARREL, SUPPORTED BY 1 (one) MODULE BOTTOMEQUIVALENT STRESS

19BNL, A.Gordeev, R.Ruggiero

Page 20: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

4. FULL ASSEMBLY WITH NO TOP MODULEDUE TO VERY LARGE MODULE MODEL HAS BEEN SIMPLIFIED

SUPPORTED BY 120 degree support

20BNL, A.Gordeev, R.Ruggiero

4 x 120 degree supports

Page 21: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

4. FULL ASSEMBLY WITH NO TOP MODULEDUE TO VERY LAGE MODULE MODEL HAS BEEN SIMPLIFYED

SUPPORTED BY 120 degree support. MODULE

21BNL, A.Gordeev, R.Ruggiero

Page 22: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

4. FULL ASSEMBLY WITH NO TOP MODULEDUE TO VERY LAGE MODULE MODEL HAS BEEN SIMPLIFYED

SUPPORTED BY 120 degree support.TOTAL DEFORMATION

22BNL, A.Gordeev, R.Ruggiero

Page 23: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

4. FULL ASSEMBLY WITH NO TOP MODULEDUE TO VERY LAGE MODULE MODEL HAS BEEN SIMPLIFYED

SUPPORTED BY 120 degree supportEQUIVALENT STRESS

23BNL, A.Gordeev, R.Ruggiero

Page 24: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

5. FULL ASSEMBLY DUE TO VERY LAGE MODULE MODEL HAS BEEN SIMPLIFIED

SUPPORTED BY 120 degree support

24BNL, A.Gordeev, R.Ruggiero

Page 25: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

5. FULL ASSEMBLY DUE TO VERY LAGE MODULE MODEL HAS BEEN SIMPLIFIED

SUPPORTED BY 120 degree supportDEFORMATION

25BNL, A.Gordeev, R.Ruggiero

Page 26: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

5. FULL ASSEMBLY DUE TO VERY LAGE MODULE MODEL HAS BEEN SIMPLIFYED

SUPPORTED BY 120 degree supportDEFORMATION

26BNL, A.Gordeev, R.Ruggiero

Page 27: DON LYNCH DECEMBER 4, 2014. AGENDA December 4, 2014 2 BABAR Magnet Update Outer HCal Structural Analysis…

5. FULL ASSEMBLY DUE TO VERY LAGE MODULE MODEL HAS BEEN SIMPLIFYED

SUPPORTED BY 120 degree supportEQUIVALENT STRESS

27BNL, A.Gordeev, R.Ruggiero