do's & dont's of mee related.ppt

31
ENERCON Compiled By: Service & Installation Quality Assurance I N D I A Presentation On “Technical Review of Existing Project Execution” Date: 20th July, 2011

Upload: asr-reddy

Post on 04-Jun-2018

241 views

Category:

Documents


0 download

TRANSCRIPT

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 1/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

Presentation

On

“Technical Review of Existing

Project Execution”

Date: 20th July, 2011

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 2/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

TOPICS TO BE COVERED

1. Observations And Non-compliancesi) Internal Lines (Feeders 3 & 5).

ii) VCBs (Feeders 3 & 5).iii) Store Yard Contractor Side.

2. Do’s And Don’t’s

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 3/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

Internal Lines

Observations Related To Internal Lines Feeder 3 & 5

1. Poles.2. Stay Wire.3. Earthing.

4. Insulators.5. Hardwares Of Structures.6. Mounting Structures.7. Foundations.8. Conductors.9. Jumpers And Connections.10. Cut-Points.

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 4/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

Mounting And Hardware

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 5/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 6/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 7/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

Do’s & Don'ts Of Hardware Mounting

• Mounting hardware size shouldbe as per the standard drawings.

• Ensure that all the hardware aretightened at all places like PINinsulator, Strain insulators,Jumpers etc.

• Proper alignment of hardwarebetween equipment andmounting frame.

• Mounting hardware holes inframe should be done as per theparticular hardware size.

• Avoid using hardware of lowergrades.•Don’t make Gas cutting as apractice for alignment of mountinghardware.

•Don’t use Corroded hardware formounting .

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 8/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

Earth System

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 9/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 10/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

Do’s & Don'ts Of Earthing connection.

Do’s

• Bituminous paint should beprovided 150mm above theground and 150mm below theground to avoid corrosion, toprovide low resistive andmaintain potential Gradient.

• Ensure the Pole earthing shouldbe provided before the stringingof conductor to avoid theconductor and insulator damage.

• Insulator should be providedbetween LA structure earthing

and structure.• Isolator structure earthing withisolator handle should beprovided for the safety ofoperation

Don’ts

• Don’t make overlaping with lesscontact area in between twoearth strips

• Don’t use LA and Neutralearthing overlapped to providelow resistance and equipotentialsurface.

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 11/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

Stay Wire Arrangement

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 12/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

ENERCON

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 13/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

VCB Structure Feeder 5

ENERCON

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 14/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

ENERCON

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 15/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I ADo’s & Don'ts Of Stay Arrangement.

Do’s • Diameter of G.I. Stay Wires shall

be as per the EIL Standards .• Minimum tensile strength 700 kN

/ mm2

• Minimum breaking force ofsingle wire and strand shall beas per IS: 214 – 2000.

Don’ts • Don’t use the stay wire with

loosen condition. Ensure propertightening.

• Don’t use stay wire with out guy

insulator of EIL standard ratings.

ENERCON

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 16/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

Foundation

ENERCON

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 17/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I ADo’s & Don'ts Of Foundation activity.

Do’s

• Foundation (shape and size) should as per standard drawing• Foundation cement sand and aggregate ratio should be 1:2:4 or

1:4:8• Provide proper curing time (at least two days)• Surface of foundation should be same level at all sides• It should be assured the cement grade (53 grade)• All raw material of civil work (foundation or construction work)

should be checked by EIL employee

Don’ts

• Do not utilize non standardraw material.

• Do not use the rejectedtemplates for the civil work

in case of foundations.

ENERCON

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 18/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

Paint Work

ENERCON

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 19/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I A

ENERCON

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 20/31

ENERCON

Compiled By: Service & Installation Quality Assurance

I N D I ADo’s & Don'ts Of painting activity.

Do’s

• Transmission line pole’s surfacepreparation should be done (Can beuse sand blasting, wire brush, emerypaper)

• After cleaning, apply the coating ofred-oxide paint through out thesurface area and dry it, it providesustainability against corrosion.

• After applying the red-oxidecompletely apply another coat ofaluminum paint.

• After erection second coat ofaluminum paint should be apply.

Don’ts

• Do not apply the red-oxide paintwithout surface preparation ofthe poles.

• Do not erect poles withoutpainting , it will decrease the lifeof the poles and get corrodedeasily.

ENERCON

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 21/31

Compiled By: Service & Installation Quality Assurance

I N D I A

Jumpers And Connections

ENERCON

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 22/31

Compiled By: Service & Installation Quality Assurance

I N D I A

ENERCONI N D I A

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 23/31

Compiled By: Service & Installation Quality Assurance

I N D I A

Do’s & Don'ts Of Jumpers , conductor & Connections.

Do’s • Laying of jumpers should be

done per drawing.• Binding should not be loose.• Avoid Fraying of conductor.

• Bending of lug at conductorshould avoid.

• Avoid conductor joint in manyplaces between two cut points.

• Clearance between conductor toconductor and conductor to poleshould be as per standard.

• Sag should be as per standard.

Don’ts • Don’t Cut of conductor during

lugging. Ensure proper lugging.• Don’t make Nick mark in

conductor.

• Don’t put the conductor instress. Ensure proper length toavoid stress.

ENERCONI N D I A

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 24/31

Compiled By: Service & Installation Quality Assurance

I N D I A

Yard Condition

ENERCONI N D I A

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 25/31

Compiled By: Service & Installation Quality Assurance

I N D I A

ENERCONI N D I A

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 26/31

Compiled By: Service & Installation Quality Assurance

ENERCONI N D I A

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 27/31

Compiled By: Service & Installation Quality Assurance

ENERCONI N D I A

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 28/31

Compiled By: Service & Installation Quality Assurance

ENERCONI N D I A

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 29/31

Compiled By: Service & Installation Quality Assurance

ENERCONI N D I A

Do’s & Don'ts For Yard and Material Preservation

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 30/31

Compiled By: Service & Installation Quality Assurance

Do s & Don ts For Yard and Material Preservation

• Specification of all materials,equipment and various channelsshould be available in yard.

• Identification and traceability of allmaterials should be available.

• Acceptance criteria for Isolator shouldbe checked when the material indent.

• Painting process on materials shouldbe done as per specification.

• Assembling of DO fuse should be donecorrectly.

• Corrective action for scrap materialshould be done.

• Corroded Nuts should be scraped anddisposed.• Corrective action for scraped clamps

should be done.

• Do not misalign the assembly of DOfuse.• Do not place the relay panel and VCB

over abrupt surface and protect themfrom dust and other foreign particles.

• Ensure that there is no oil leakagefrom CT’s ,PT’s.

• Do not mix good materials withscrap.

• Ensure the life cycle and functioningof all panel batteries.

ENERCONI N D I A

8/14/2019 Do's & Dont's of MEE related.ppt

http://slidepdf.com/reader/full/dos-donts-of-mee-relatedppt 31/31

Compiled By: Service & Installation Quality Assurance

Thank You