TOPICS‐Changes to the SDDOT Org Chart
FAST Act
STP payouts
SIB Loans
Planning Grants
BIG Grants
Other Grants
2
SDDOT ORGANIZATIONAL
FAST ACTFixing Americas Surface Transportation Signed December 4, 2015
5 years of funding
$305 billion over fiscal years 2016 through 2020
Builds on MAP‐21
5% increase in funding the first year
Expands freight network
STP = Surface Transportation Block Grant (STBG) TAP = TA Transportation Alternatives http://www.fhwa.dot.gov/fastact/index.cfm
3
FAST ACTProgram 5‐Year Funding
(billions)
Federal Highway Administration $ 226.3
Federal Transit Administration 61.1
Federal Motor Carrier Safety Administration 3.2
Pipeline and Hazardous Materials Administration 0.4
National Highway Traffic Safety Administration 4.7
Federal Railroad Administration 10.3
Total $305.0
5
FAST ACTFixing Americas Surface Transportation TIGER Grants
Due April 29, 2016
$1M‐$100M
Rural = 100% funding
Urban = 80% funding (>50,000 people)
https://www.transportation.gov/sites/dot.gov/files/docs/2016%20TIGER%20NOFO.pdf
4
STP PAYOUTS
Surface Transportation Program (STP) (81.95% fed/18.05% State)
Class 1 Cities and Counties
Annual allocations
Includes 9.025% state match
July 1 October 31 December 30 Total
COUNTIES 7.97$ 10.90$ 13.10$ 31.97$
CITIES 5.39$ 3.78$ 8.80$ 17.97$
Total 13.36$ 14.68$ 21.90$ 49.94$
STP PAYOUTS
SIB Loan Projects stay in the STIP
Other STP projects – option to pay out accounts (4 cities and 9 counties)
https://apps.sd.gov/hc65subfundbalances/secure/default.aspx
5
SIB LOANS State Infrastructure Bank (SIB)
Federal Funds
Federal aid route
0% Interest
May repay using STP funds
Projects included in STIP
Full environmental coordination
SDDOT Bid letting
Contact: Chris Ott 605‐773‐4114 [email protected]
Applications
https://www.state.sd.us/eforms/secure/eforms/E2068v1‐1784‐SIB%20Application.pdf
State Highway Fund Loans State Funds
NOT eligible for SIB
Funding of Last Resort
Interest = Prime Rate
County or Class I City
May repay using STP funds
Local Bid letting
10 Year Max repayment
$200,000 minimum loan
Minimum of 5 new jobs created‐economic development
6
LOCALLY OWNED BRIDGES
7
CITY OWNED BRIDGES
241 total city owned structures
76 with a Sufficiency Rating less than 80
36 with a Sufficiency Rating less than 50
40 posted bridges
LOCALLYOWNEDBRIDGES
South Dakota is 4th
worse in the nation for bridge condition!
8
BIG GRANTS $7 M from SB 1
Additional $2M from SDDOT
Applications were due January 31, 2016
Applications will be due January 2, 2017
Received: 100 applications, $14.44M
9
Bridge Improvement Grant (BIG)
1. Preliminary Engineering
2. Preservation (Maintenance/Preventative Maintenance/Minor Rehab)
3. Rehabilitation/Replacement
Preliminary Engineering(PE) BIG1. Must be listed in 5 Year Plan (Counties)
a) Show year of PE in plan and show separately year of construction
b) Plan ahead – do PE as soon as possible
2. Must include an engineering cost proposal with application
3. Received 70 Applications, $2 M
10
Preservation BIG1. Must be listed in 5 Year Plan (Counties)
2. Must include an engineering estimate (design, construction, and construction engineering) with application
3. Not required to have plans with application but it is recommended to have as much detail as available to what work is intended to be done
4. Received 20 Applications, $7.8 M
Rehab/Replacement BIG1. Must be listed in 5 Year Plan (Counties)
2. Must include a complete TS&L package with application
3. Must include an engineering estimate (design, construction, and construction engineering) with application
4. Received 10 Applications, $8 M
11
Rehab/Replacement BIGRanking process 100 point system
Bridge Condition
Posting = 29 points
Substructure = 6
Superstructure = 6
Culvert = 12
Fracture Critical = 6
Scour Critical = 6
Emergency = 6
Sufficiency Rating = 1
Rehab/Replacement BIGRanking process
User Impact = 20 points
ADT vs Detour length
Wheel Tax = 0‐10 points
Shovel Ready = 10 points
Bonus points for additional financial commitment = 3 points for every 5% over the 20% match requirement
12
Cities/Towns 241 Structures Statewide
41 are Candidates for Major Rehab/Replace
Est. at $42,730,219 for replacement
Other 200 are eligible for Preservation
10 BIG applications from 7 Cities this year
2016 AwardsPE – Round 1 to Transportation Commission 2/25/16
40 grants worth $.9 M
2 Cities
17 Counties
Balance of Funding Awarded on April 28 Commission Meeting
13
BIG GRANTSImprovements for next year:
Applications must include design and construction engineering costs split out
Grants rounded to the nearest thousand dollars
Contingency ok to include
More information needed, include photos, include estimates
Repair the whole bridge, not just one part.
TRANSPORTATION ECONOMIC DEVELOPMENT GRANTS Community Access ‐ $2.5 million per year
Agri‐Business ‐ $1.0 million per year
Industrial Park ‐ $ 0.5 million per year
The total for the three programs is $4.0 million per year.
14
TRANSPORTATION ECONOMIC DEVELOPMENT GRANTSApplication Should Include:
Clear map showing the project location
Engineer's Estimate
Resolution of support from the local sponsor
TRANSPORTATION ECONOMIC DEVELOPMENT GRANTSCommunity Access Grants
Less than 5,000 population
Main roads
Less than 1 mile
Local bid letting
2 years to obligate the money
Grant Maximum is $400,000
60% of construction costs
Applications are due July 15
15
TRANSPORTATION ECONOMIC DEVELOPMENT GRANTSIndustrial Park Grants
Inside or to an industrial park
5 new jobs
New or expanded industry
Local bid letting
2 years to obligate the money
Grant Maximum is $400,000
60% of construction costs
Applications are due April 15, July 15, October 15
TRANSPORTATION ECONOMIC DEVELOPMENT GRANTS
Plans and Specifications
Designed in accordance with the SDDOT Standard Specifications for Roads and Bridges
Must have plans and specifications stamped by a PE
SDDOT reviews and approves plans and bid documents
American's with Disabilities Act
Let to bids locally
SDDOT concurs in bid award
16
Culverts Small Structures Task Force
Less than 20’ opening (Bridge)
Greater than 16 Sq. Ft. (31‐14‐27)
January 28, 2016 Transportation Commission approval
Dick Howard, Jim Puffer, Bob Wilcox, Dirk Rodgers, Steve Williams, Duane Sutton, and Greg Vavra
Develop a process for consideration by the Transportation Commission for potential grants for township and county “small structures”
$2M
April 29
QUESTIONS
CONTACT INFO
Laurie Schultz [email protected] 605‐773‐8149