New McCoy Elementary
Pricing History for Conceptual Phases
SchematicDesign Package
50% DDEstimate
95% CDEstimate
Final Budget onBid Set
Variance FromOriginal
Original Budget $14,898,998
J Jacobs Construction N/A $14,118,687 5/6/2011 TBD -$780,311
Pricing Entity 1 N/A $14,325,769 N/A N/A -$573,229
Pricing Entity 2 N/A $13,305,876 N/A N/A -$1,593,122
Pricing Entity 3 N/A $13,992,812 N/A N/A -$906,186