Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council
Edwards SalasSenior Vice President, Engineering and Operations, PG&E
February, 4, 2010
![Page 2: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/2.jpg)
2
Today’s Presentation from PG&EToday’s Presentation from PG&E
Coordinate with the Lifelines Council to:• Lifelines Partnership Opportunities
• Design System Standards
• Emergency Planning and Response Activities
![Page 3: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/3.jpg)
3
PG&E’s Coordination Goals with the PG&E’s Coordination Goals with the Lifelines CouncilLifelines Council
Coordinate with the Lifelines Council to:• Establish response and recovery priorities
• Facilitate Mutual Logistics Support
• Enhance Effective Communication
Formal acknowledgement that PG&E is a first responder organization
Identify restoration priorities regarding non-PG&E facilities for immediate electric/gas service
![Page 4: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/4.jpg)
4
System Map and Customers ServedSystem Map and Customers Served
PG&E Facts Regarding PG&E Facts Regarding Customers Served in Customers Served in CaliforniaCalifornia• 70,000 Square Miles
• 15 Million People Served
• 4.2 Million Gas Customers
• 5.1 Million Electric Customers
• 3,400 Buildings
![Page 5: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/5.jpg)
5
Earthquake Risk Management ProgramEarthquake Risk Management Program
![Page 6: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/6.jpg)
66
“Each utility shall withstand earthquakes to provide protection of life, limit damage to property, and provide for resumption of utility service in a reasonable and timely manner.” California Seismic Safety
Commission/CPUC Safety Branch
![Page 7: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/7.jpg)
7
Federal and State StandardsFederal and State Standards
• Federal Energy Regulatory Commission (FERC)
• Nuclear Regulator Commission (NRC)
• CPUC General Orders
![Page 8: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/8.jpg)
8
Design Standards (Examples)Design Standards (Examples)
• Department of Transportation (DOT)
• 2007 California Building Code
• Existing Building Retrofit Standards and Compliance
![Page 9: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/9.jpg)
9
Seismic Risk Management ApproachSeismic Risk Management Approach
• Evaluate Facilities and Operations
• Prioritize Selected Facilities for Mitigation
• Implement Mitigation
• Minimize Level of Earthquake Risk
![Page 10: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/10.jpg)
10
245 Market Street
![Page 11: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/11.jpg)
11Moss Landing 500kV SwitchyardDamage to Live Tank Circuit Breakers1989 Loma Prieta Earthquake
![Page 12: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/12.jpg)
12
Improving PG&E’s System PerformanceImproving PG&E’s System Performance
Gas Pipeline Replacement Program (GPRP) Seismic Tests on Replacement Breakers
![Page 13: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/13.jpg)
13
PG&E Seismic Investments PG&E Seismic Investments (1985 to Present)(1985 to Present)
Facilities
• Buildings
• Electric Substations
• Dams and Related Hydro Facilities
• Power Plants
• Gas T&D
• Loma Prieta Repairs
TOTAL BUDGET $2.54 Billion (estimate)
![Page 14: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/14.jpg)
14
Improving PG&E’s System PerformanceImproving PG&E’s System Performance
Iso-Base Vacaville Grid Control Center
![Page 15: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/15.jpg)
15
Post-Earthquake Emergency Response Post-Earthquake Emergency Response and Restoration Management and and Restoration Management and CoordinationCoordination
![Page 16: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/16.jpg)
16
Post-Earthquake Response ScenariosPost-Earthquake Response Scenarios“Expected” and “Extreme” Earthquakes“Expected” and “Extreme” Earthquakes
![Page 17: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/17.jpg)
17
Post-Earthquake AssessmentPost-Earthquake Assessment
• Strong Motion Instrument Program
• Post-Earthquake Building Inspection
• Gas and Electric Emergency Response Programs
• GIS
• USGS Shake Maps
• Dam Information Automated Seismic Hazard Assessment
![Page 18: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/18.jpg)
18
PG&E’s Emergency Planning and PG&E’s Emergency Planning and Response ActivitiesResponse Activities
• Primary and Alternate Emergency Operations Centers
• ICS/NIMS Incident Management
• Formalized Business Continuity Program – alternate headquarters, “tech down” plans, disaster recovery and resource recovery plans
• Integrated Training and Exercises with Federal, State, and Regional Agencies Including CCSF SFFD and Department of Emergency Management (DEM)
• California Utility Emergency Association (CUEA)
![Page 19: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/19.jpg)
19
Emergency Operations Center (EOC)Emergency Operations Center (EOC)
![Page 20: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/20.jpg)
20
Lifelines Comparison—DependenciesLifelines Comparison—Dependencies
What are PG&E’s Dependencies?What are PG&E’s Dependencies?• CommunicationsCommunications
• TransportationTransportation
• Public SafetyPublic Safety
• Emergency Medical ServicesEmergency Medical Services
Who’s Dependent on PG&E?Who’s Dependent on PG&E?• All other utilitiesAll other utilities
• All 18 Emergency Support Functions All 18 Emergency Support Functions (includes most city and county services)(includes most city and county services)
• BusinessesBusinesses
• ResidencesResidences
![Page 21: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/21.jpg)
21
Service Area OverviewService Area Overview
• PG&E's gas and electric network is interconnected throughout our service area.
• Restoration of lifelines in the San Francisco Bay Area will be impacted by the condition and capacity of the larger network after a major event.
![Page 22: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/22.jpg)
22
So What Can Residents Expect?So What Can Residents Expect?
• Minimum of 72 hours electric service interruption in red and orange areas of the Shake maps.
• Longer electric service restoration times where underground utilities are subject to liquefaction.
• Potentially weeks and months of gas service interruption in red and orange areas of the shake maps.
![Page 23: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/23.jpg)
23
Questions and AnswersQuestions and Answers
![Page 24: 1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,](https://reader036.vdocument.in/reader036/viewer/2022062500/5697c0141a28abf838ccd5b8/html5/thumbnails/24.jpg)
24
Thank You