Performance Criteria for Tremie Concrete
Presenter: Martin Larisch
20th August 2013, Brisbane
22
Introduction
- Drilling is perceived to be the main scope of piling companies
(focus on big drilling rigs, state of the art drill tools, hard rock)
- Concrete placement is often perceived as the non critical activity
- In the past the slump was the almighty workability factor
- Did we (engineers) get involved into concrete mix design review?
- How did we determine if a mix is suitable or not?
- Did we review placement techniques CRITICALLY in the past
33
Introduction - DefinitionsTremie pipe:Steel pipe surmounted by a hopper or chute for concreting both under dry or wet conditions. For application in wet conditions a tremie pipe may comprise several joined lengths but must have watertight joints.
Schematics of a tremie pour:
44
Why should we use a tremie pipe?
Wet tremie:
- Ensure concrete is not placed through water (segregation)
- Ensure we don’t have inclusions
- Ensure concrete won’t hit cage (risk of segregation)- Control concrete placement (embedment of tremie, suitable
separator, no vibrator for SCC, etc.)
WE SHOULD NEVER REPLACE A TREMIE PIPE WITH
A CONCRETE BOOM PUMP SECTION!
NEVER POUR A BORED PILE USING ADDITIONAL
PRESSURE
55
Pouring dry holes
Dry pour (layflat tremie or direct discharge):- reduce fall height (segregation)- ensure concrete won’t hit reinforcement cage- control concrete flow
66
Why is pouring piles different to pouring structural concrete?
- Commonly up to 50 m deep
- Maybe deeper than 100m
- Subject to high pressure (at pile base)
- Concrete must displace fluid
- Concrete must be self-leveling
- Concrete must flow around cages
- Concrete must achieve bond with reo
Pouring piles & D-walls is a blind process
77
wet
Potential damage on piles and diaphragm walls due to use of
unsuitable concrete
88
Potential damage on piles and diaphragm walls due to use of
unsuitable concrete
wet
99
Potential damage on piles and diaphragm walls due to use of
unsuitable concrete
wet
Bleeding channels
1010
The Solution…
Recommended Practice “Tremie
Concrete for Deep Foundations”
Kindly supported by:Concrete Institute of AustraliaPFSFBauer Foundations AustraliaPiling ContractorsQLD Department of Main RoadsCSIROHyder Consulting University of QueenslandHolcim Australia
1111
The Solution…
Recommended Practice “Tremie Concrete for Deep Foundations”
Dr Karsten Beckhaus, Bauer Foundations Australia Pty LtdMartin Larisch, Piling Contractors Pty LtdPeter Ney, Holcim Pty LtdDr Habib Alehossein, CSIRO
Sherard Northey, Concrete Institute of Australia Professor Peter Dux, University of Queensland Stephen Buttling, Piling and Foundation Specialists Federation*Gary Lucas, Cement Concrete and Aggregates AustraliaLex Vanderstaay, Queensland Dep. of Transport & Main Roads*
* contributing the investigation program with 20,000 AUD each
1212
Purpose of the Recommended Practice:
- Provide guidance for those involved in the preparation of specs for the use of
tremie concrete for bored piles and diaphragm walls
- Cover special requirements for the mix design or properties of tremie concrete
with respect to its specific field of application
- Special attention should be given to the fact that the workability required has to be
achieved and maintained under considerable hydraulic pressure and for the total
time span until the last working step
- Provide recommendations on properties, constituents and proportioning, as well
as on testing of concrete; based on international and Australian experience
- Give advice on the usual range of application and to show principal measures to
achieve proper workability does not offer full prescriptive information!
1313
Areas of applications of the Recommended Practice:
This Recommended Practice
- refers to TC for bored piles, diaphragm walls and cut-off walls, min d = 400 mm
- applies to concrete for casting under both dry and wet conditions
- includes descriptions of suitable workability test methods
- refers to the Recommended Practice for Super-Workable Concrete
- generally applies to low, normal and high strength concrete on site or ready-mixed
But this Recommended Practice
- does not refer to the intended service life / not to specific durability needs etc.
- may not cover requirements as stated within particular project specification
(which may require additional measures or deviations from this guide)
- does not cover health and safety requirements …
1414
What makes a good mix - Risk of potential issues
1. Unsuitable Concrete at its plastic stage (prior to and during placement)
- e.g. insufficient flow-ability insufficient workability
- Insufficient fill-ability
- Insufficient water retention insufficient stability
- Insufficient retardation
2. Unsuitable placement techniques integrity issue of pile / D-wall
1515
Flowability The ease of flow of fresh concrete when unconfined by formwork or any other obstacles such as reinforcement.
Passing ability (blocking resistance)The ability of fresh tremie concrete to flow through tight openings such as spaces between steel reinforcing bars without segregation and blocking.
Water retention ability (filtration resistance)The ability of fresh tremie concrete to retain its water despite being subject to pressure caused by supporting fluid or fresh concrete above.
Slump retention ability (flow maintenance)The ability of fresh tremie concrete to maintain its flow characteristic, measured by slump test, over a certain period of time, possibly controlled by appropriate admixtures.
w o
r k
a b
i l i
t ys
t a b
i l i
t y
1616
Background:
Unsuitable Concrete at its plastic stage,
may have insufficient rheological properties, characterised by ...
Viscosity In general viscosity describes a fluid's
internal resistance to flow and may be
thought of as a measure of fluid friction;
here simplistically the flow resistance of
fresh tremie concrete once flow has started.wet
Velocity Profile inside a “pipe” or similar!
What about the shearing zone inside the pile?
1717
How concrete flows
during a wet tremie
pour (theory):
wet
concrete must flow and pass obstacles easily
1818
How concrete flows during a wet tremie pour (theory):
1919
Flowability The ease of flow of fresh concrete when unconfined by formwork or any other obstacles such as reinforcement.
Passing ability (blocking resistance)The ability of fresh tremie concrete to flow through tight openings such as spaces between steel reinforcing bars without segregation and blocking.
Water retention ability (filtration resistance)The ability of fresh tremie concrete to retain its water despite being subject to pressure caused by supporting fluid or fresh concrete above.
Slump retention ability (flow maintenance)The ability of fresh tremie concrete to maintain its flow characteristic, measured by slump test, over a certain period of time, possibly controlled by appropriate admixtures.
w o
r k
a b
i l i
t ys
t a b
i l i
t y
2020
wet
Tremie concrete in Australian standards and specifications:
Review of Australian codes, standards and specifications included but was not limited to:
AS 3600: Concrete StructuresAS 1379: Specification and Supply of ConcreteAS 2159: Piling — Design and Installation
MRTS 63: Cast-in-Place PilesMRS11.70: Concrete
RTA B58: Permanent Cased PilesRTA B59: Cast in Place PilesRTA B80: Concrete Work for Bridges
2121
wet
Tremie concrete international standards and specifications:
Review of international codes, standards and specifications included but was not limited to:
ACI 301: Specifications for Structural ConcreteACI 336: Specification for the Construction of Drilled Piers EN 206-1: Concrete — Part 1: Specification, Performance, ProductionEN 1536: Execution of Special Geotechnical Work — Bored PilesEN 1538: Execution of Special Geotechnical Work — Diaphragm Walls
2222
Summary of review:
Summary of the detailed review of standards, codes and specifications and of investigations in terms of addressing fresh concrete criteria on Tremie Concrete:
- Only solitary specific recommendations for tremie concrete are given:- slump / slump tolerance- materials, proportioning and testing- production and control
- Modern concrete’s rheology can’t be described by slump only , but can be well described by special tests (e.g. as for super-workable concrete)
wet
2323
Characteristic performance of Tremie Concrete:
wet
“Normal” Concrete compacting by vibrating after placing
Tremie Concrete (self) compacting, only by help of hydraulic head
Super-Workable Concrete self-compacting
Independent of the required hardened concrete properties, by looking at viscosity of concrete, and on viscosity of the paste, there are some important differences in the mixture composition as well.
2424
Characteristic performance of Tremie Concrete:
wet
2525
Characteristic performance of Tremie Concrete:
wet
2626
Why is the slump test alone not suitable to determine workability?
Samples with similar slump values can have different flow behaviour
wet
2727
The slump alone is not good enough…
wet sufficient slump ?!
but
can’t pass through 80-mm grid !!
2828
wet
Backup by investigations on more than 40 trial mixes
2929
Laboratory testing (pre-production):
wet
distinctive slump: for correlation on site (only!)
Required workability
to be confirmed by
L-Box and/or slump flow test
f i l m !
3030
Laboratory testing (pre-production):
wet
Required stability
to be confirmed by Visual Stability Index (VSI) test in one procedure with slump flow test
VSI “Class 0”:- no indication of segregation or separation- very good aggregate distribution- no bleeding
(Class 1: starting to exhibit a mortar halo)
3131
Laboratory testing (pre-production):
wet
5 bar
non-permeable soilpermeable soil
++ < 15 l/m³ water loss + < 30 l/m³ water loss (plus requirements to filter cake)
Filtration loss (l/m³)Filter cake thickness (mm) Proof of sufficient stability
(high hydraulic head pressure)
3232
Testing on site:
wet
proof of “characteristic” slump and spread
should confirm laboratory resultsgood flowability & passing abilityof concrete with same composition!
No EXTRA EFFORT on site
3333
Workability trialscement 390 kg 390 kg 390 kg 420 kgwater 168 l 179 l 191 l 181 lw/c 0.43 0.46 0.49 0.43
slump 230 mm 220 mm 240 mm 230 270 mm
visually excellent good excellent good / excellent
Slump dia 380 mm 350 mm 500 mm 450 570 mm
L-Box Dh (170 mm)* (220 mm)* 60 mm 40 20 mm *) did not reach the end of L-Box
312 l 335 l323 l 335 l very
stable mix!
3434
Recommended concrete testing for future projects
Pre-production tests (spend $1-2k in advance to get a suitable mix)
- L-Box (time and ratio)
- Slump flow (time and diameter)
- Slump (height)
- VSI (visual)
- Filtration press (bleed water & filter cake thickness)
Site tests (correlate to pre-production test)
- Slump flow (time, diameter and VSI)
- Slump (height)
NO EXTRA EFFORT ON SITE!
3535
wet
Test Methodand properties assessed
Suggested value for structural element of length land for optional pouring conditions
Dry Wet, flow distance
- < 1.2 m ≥ 1.2 m
Slumph (mm) ≥ 140* ≥ 180 ≥ 220
Slump flowDfinal (mm)Tfinal (sec)
--
400 - 600≤ 5
450 - 650≤ 3
L-BoxTravel distance from bars (mm)Filling RatioTend (sec)L-Box Passability (mm)
> 200
--
≤ 40
(full)
≥ 0.2≤ 12≤ 40
(full)
≥ 0.4≤ 8
≤ 20
Bauer filtrationFiltration loss (l/m³)Filter cake thickness (mm)
≤ 30≤ 150
≤ 30 @ l ≤ 15 m / ≤ 15 @ l > 15 m≤ 150 @ l ≤ 15 m / ≤ 100 @ l > 15 m
3636
Potential Issues
Bleeding channels
- Free water can’t be retained by fines in the concrete mix and escapes
How to avoid it:
- Limit free water to max 180l/m3
- Carry out pre-production tests (filtration test)
- Use experienced concrete supplier who can respond quickly
3737
Potential Issues
Insufficient concrete cover
- Mostly insufficient workability or placement technique
How to avoid it:
- Ensure concrete spacers are in place
- Ensure sufficient concrete flowability (spread, slump, L-Box)
- Review & discuss methodology prior to implementing new procedures
3838
Potential Issues
Inclusions
- Insufficient flowability, placement techniques or cleaning of pile base
How to avoid it:
- Ensure pile base is free of drill sludge
- Ensure sufficient concrete flowability (L-box & slump flow)
- Ensure tremie pipe remains 3m inside the concrete throughout pour
3939
Potential Issues
Others:
- Anchor ducts
- Concrete supply by others (specification)
- Tremie pipe lifted out of concrete during pour
- Pouring under pressure (concrete pump)
- Leaving too much tremie inside concrete
- Understand behaviour of drilling fluid
- Insufficient separator
- Fully cased piles (bleeding)
- Inexperienced concrete supplier
- Lack of resources / commitment of supplier
4040
Concrete for CFA piles
Similar requirements as for tremie concrete, in addition consider:
- Carry out pre-production tests whenever possible
- Use max aggregate of 10mm to ensure sound cage installation
- Focus on stability of the mix (filtration press)- Focus on L-Box and slump flow (low viscosity)- Increase workability to 4 hours (project specific)
- Avoid cage vibrator whenever possible, rather use excavator and push cage into concrete carefully under steady pressure
- Ideally, cages should be plunged into concrete under gravity
- Use experienced and capable concrete supplier (value for $)
4141
The Way Forward…
YOUR ACTIVE INPUT & INVOLVEMENT IS CRITICALTO ACHIEVE EXCELLENT ENDPRODUCTS AND TO INCREASE INDUSTRY STANDARDS