Download - 10/19/20151 Building a Legacy Rebuilding Providence Public Schools 2008 Q1 Report Volume III
04/20/23 2
Overview
• Required by School Board Resolution.
• Timely Information to the School Board and Public.
• Historical Reference for the Program.
• Overall Focus will be on Phase I projects, estimated present value cost - $384MM.
• Targeted Focus on Active Projects.
Keys for Review
• Strikethrough means outstanding issue has been resolved.
• Project comments may be updated and not show comments from previous report.
• Checkmark means action has been completed.
04/20/23 3
04/20/23 4
Active Projects
• Adelaide Avenue High School.• Central High School.• Hanley Vocational School.• Career and Technical Educational Facility.• Free Standing Athletic Complex.• Nathan Bishop Middle School.• West Broadway Elementary School.
04/20/23 5
Active ProjectsAdelaide Avenue High School
Comments
• Opened on time September 2007
• 575 students in grades 9-11
Outstanding Issues
• Access route to the Building still pending.
04/20/23 6
Active ProjectsCentral High School
Comments
• Estimated Cost of $36MM.
• Final stages of multi year renovation.
• Interior and Exterior.
• Building Codes.
• Temporary relocation of students.
04/20/23 7
Active ProjectsHanley Career and Technical School
Comments
• Estimated cost is $22MM
• Part of RIDE’s $90 M approval which includes the Hanley facility, CTE and Athletic Complex.
• Hanley programming - Culinary, Cosmetology, Graphic Arts, Automotive.
04/20/23 8
Active ProjectsCareer and Technical Education (CTE)
Comments
• Estimated cost of $50 MM.• Part of RIDE’s $90 M
approval which includes the Hanley facility, CTE and Athletic Complex.
• CTE Programming - Masonry, HVAC, Electrical, Plumbing, Carpentry.
• Completion in Sept. 2009.
04/20/23 11
Active ProjectsAthletic Complex
Comments
• Estimated Cost of $18 MM.
• Part of RIDE’s $90 M approval which includes the Hanley facility, CTE and Athletic Complex.
• Will house track and field and other indoor sports events.
04/20/23 12
Active ProjectsNathan Bishop Middle School
Comments
• Estimated cost of $35 MM.
• Program designed with community advisement.
• First facility proposal approved under State’s revised review process.
04/20/23 13
Active ProjectsWest Broadway Elementary School
Comments
• Students and Faculty relocated to Pell Complex.
• Options Development Community Group.
• Work of the Community Group will be submitted to School Board.
Outstanding Issues
• No timetable set for this project to date.
Warm, Safe and Dry Projects
• $12.4 million in FY 2006.
• $11.5 million in FY 2007
• Unknown in FY 2008– No work currently authorized.
– Potential for minor fire compliance expenditures.
04/20/23 14
Phase I Projects
04/20/23 15
Phase I Projects
School Facility
Ade
laid
e
Cen
tral
FSP
EF
Han
ley
Bis
hop
CT
E
W B
road
way
Mt.
Ple
asan
t
Wes
t
Fei
nste
in
Asa
Mes
ser
Mes
ser
Ann
ex
Lau
rel H
ill
L.H
.Ann
ex
1 Included in Rebuilding a Legacy Phase I2 Options Currently Under Review3 School Board Approval4 Building Committee Recommendation NA NA NA NA5 Final School Board and City Council Approval6 Facility Architects Identified7 RIDE Phase I Approval 8 RIDE Phase II Approval 9 Board of Regents Approval10 General Assembly Approval NA NA NA NA NA NA11 Bonds Sold12 Construction Underway13 Construction Complete14 Outstanding Final Issues Resolved
= Complete = Ongoing = Has not Begun
Act
ion
Step
s
04/20/23 16
Action StepsApril to October 2008
• School Board Approval– Capital Plan– Phase I Next Steps
• RIDE/Board of Regents Approval– Nathan Bishop - Building Trades CTE
• Bonds Sold– 2007 Series A, $75MM -2007 Series B, $75MM
• Projects Started– Nathan Bishop - Building Trades CTE
• Projects Completed– Outstanding Issues at Adelaide resolved