14 April 2008 - LTQ5R5 1
LHe Q5R5New Calibrated probe
Reported by Juan CASAS
AT – ACR - IN
![Page 2: 14 April 2008 - LTQ5R5 1 LHe Q5R5 New Calibrated probe Reported by Juan CASAS AT – ACR - IN](https://reader036.vdocument.in/reader036/viewer/2022070309/551d9db6497959293b8db1ca/html5/thumbnails/2.jpg)
14 April 2008 - LTQ5R5 2
Q5R5New Level gauge LT831
• Calibrated
• Centered
• Raised by 20mm (5%) Pressure oscillations reduced Level can be measured with warm by-pass CLOSED!
Opening warm-bypass => 10% level reduction
Cols capillary & thermal load 30mm (7.5%) underestimation
![Page 3: 14 April 2008 - LTQ5R5 1 LHe Q5R5 New Calibrated probe Reported by Juan CASAS AT – ACR - IN](https://reader036.vdocument.in/reader036/viewer/2022070309/551d9db6497959293b8db1ca/html5/thumbnails/3.jpg)
14 April 2008 - LTQ5R5 3
LT qualification procedure
1- Mettre en régulation de niveau pendant 24 heures ou plus l’aimant avec une consigne entre 30 et 50%.
2- Augmenter la consigne de niveau en incréments de 5% jusqu’à atteindre le débordement. Chaque palier doit être stable pendant au moins 30 minutes
3- Démarrer boil-off avec chauffage 25W
4- Si lors du boil-off le niveau n’est pas stable
=> Laisser décroitre le niveau jusqu’à obtenir de nouveau la stabilité sur la lecture de niveau => Augmenter le niveau jusqu’à une consigne 5% inférieure de celle du débordement (point -2-) => Aller à -3- qui est boil-off 25W
5- Attendre augmentation de 0.2K ou plus de la température masse froide (TT831)
6- Remplir au niveau de débordement – 5%
7- Démarrer boil-off naturel
8- Attendre augmentation de 0.2K ou plus de la température masse froide (TT831)
9- Remettre niveau en régulation à une consigne “stable”
![Page 4: 14 April 2008 - LTQ5R5 1 LHe Q5R5 New Calibrated probe Reported by Juan CASAS AT – ACR - IN](https://reader036.vdocument.in/reader036/viewer/2022070309/551d9db6497959293b8db1ca/html5/thumbnails/4.jpg)
14 April 2008 - LTQ5R5 4
Natural Boil-off
![Page 5: 14 April 2008 - LTQ5R5 1 LHe Q5R5 New Calibrated probe Reported by Juan CASAS AT – ACR - IN](https://reader036.vdocument.in/reader036/viewer/2022070309/551d9db6497959293b8db1ca/html5/thumbnails/5.jpg)
14 April 2008 - LTQ5R5 5
25W Boil-off
![Page 6: 14 April 2008 - LTQ5R5 1 LHe Q5R5 New Calibrated probe Reported by Juan CASAS AT – ACR - IN](https://reader036.vdocument.in/reader036/viewer/2022070309/551d9db6497959293b8db1ca/html5/thumbnails/6.jpg)
14 April 2008 - LTQ5R5 6
Temperature Along Warm by-pass
![Page 7: 14 April 2008 - LTQ5R5 1 LHe Q5R5 New Calibrated probe Reported by Juan CASAS AT – ACR - IN](https://reader036.vdocument.in/reader036/viewer/2022070309/551d9db6497959293b8db1ca/html5/thumbnails/7.jpg)
14 April 2008 - LTQ5R5 7
Preliminary Conclusions
New level support avoid use of thermal by-pass
Thermo-acoustic oscillations still present as indicated by too low LT head temperature
Above 75-80% level oscillates:
• LT temperature head much reduced
• Start of pressure oscillations
• Level stabilizes after vaporizing and going to ca 40%
Maximum level corresponds to piping
Vaporized volume still to be calculated but vaporizing times are typical