Transcript
Page 1: 2010 TIGER II Recipient · 2010 TIGER II Recipient ... TIGER Application Process . Use of Funds . Project Progress . Author: Garett Ballard-Rosa Created Date: 8/3/2011 7:52:07 PM

2010 TIGER II Recipient

Page 2: 2010 TIGER II Recipient · 2010 TIGER II Recipient ... TIGER Application Process . Use of Funds . Project Progress . Author: Garett Ballard-Rosa Created Date: 8/3/2011 7:52:07 PM

  The City of Fort Valley and Fort Valley State University

  “CommUniversity”

  Need for Redevelopment

  State University Drive Master Plan

  Vision for Enhanced Streetscape

Page 3: 2010 TIGER II Recipient · 2010 TIGER II Recipient ... TIGER Application Process . Use of Funds . Project Progress . Author: Garett Ballard-Rosa Created Date: 8/3/2011 7:52:07 PM

  Available Funding

  Six Livability Principles

  Rural Area- No Match

  Consistency with Plans

  Program Outcomes

  Performance Measures

Page 4: 2010 TIGER II Recipient · 2010 TIGER II Recipient ... TIGER Application Process . Use of Funds . Project Progress . Author: Garett Ballard-Rosa Created Date: 8/3/2011 7:52:07 PM

  Project specifics

  Rural communities want the same amenities as large cities   Sidewalks- accessibility   Bike lanes- alternative modes of

transportation

  Landscaped Medians- safety and aesthetics   Distinguished neighborhoods   Connectivity- between Downtown and FVSU

Page 5: 2010 TIGER II Recipient · 2010 TIGER II Recipient ... TIGER Application Process . Use of Funds . Project Progress . Author: Garett Ballard-Rosa Created Date: 8/3/2011 7:52:07 PM

  Environmental Review Complete

  Term Sheet signed between City and FHWA

  Currently Finalizing Drawings

  Currently Collecting Initial Performance Measures

  Construction projected to begin October 2011

  Construction complete July 2012


Top Related