Download - 583 Construction Management Rev i
-
7/25/2019 583 Construction Management Rev i
1/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 1 OF49
REG-5.8.3-001 Construction Management Version I
5.8.3 CONSTRUCTION MANAGEMENT METHODSTATEMENT
This method statement provides a detailed Construction Management Plan, indicatinghow the Project Agreement will manage the overall demolition, construction andrefurbishment works; specifically covering:
a) General approach to health and safety;
b) General approach to environmental management and sustainability;c) General approach to quality management;d) Management methodology including compound arrangements, storage, on and
off site support structures, logistics, etce) Organisation of staffing and resources;f) Operational integration of staff and operatives across the Participant organisation
and sub contracts;g) General security arrangements;h) Proposals for resident liaison throughout and in respect of all aspects of the
works.
Each of the points listed above are covered separately for the new build and refurbishment
works in the section that follows, with the exception of:
b) Environmental Management and Sustainability, and
h) Proposals for resident liaison
which have been collaboratively produced and agreed between the construction andrefurbishment contractors.
-
7/25/2019 583 Construction Management Rev i
2/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 2 OF49
REG-5.8.3-001 Construction Management Version I
Contents
Part 1 New Build Construction Management PlanPage 3
5.8.3 (a) General Approach to Health & Safety page 3
5.8.3 (b) General Approach to Environmental Management ..page 10
5.8.3 (c) General Approach to Quality Management ..page 18
5.8.3 (d) Management Methodology ..page 22
5.8.3 (e) Organisation of staffing and resources .. page 26
5.8.3 (f) Operational Integration of Staff .page 28
5.8.3 (g) General Security Arrangements ..page 29
5.8.3 (h) Resident Liaison page 31
Part 2 Refurbishment Works Construction Mgt Plan .Page 35
5.8.3 (a) General Approach to Health & Safety page 35
5.8.3 (b) General Approach to Environmental Management ..page 37
5.8.3 (c) General Approach to Quality Management ..page 37
5.8.3 (d) Management Methodology ..page 38
5.8.3 (e) Organisation of staffing and resources .. page 41
5.8.3 (f) Operational Integration of Staff .page 43
5.8.3 (g) General Security Arrangements ..page 46
5.8.3 (h) Resident Liaison page 48
Appendices
Appendix 01 - Higgins Health & Safety Policy & Procedures
Appendix 02 - Traffic Management Plan
Appendix 03 - Contract Quality Plan
Appendix 04 Higgins Quality Policy
Appendix 05 Rydon Maintenance H&S Policy
Appendix 06 Rydon Maintenance Quality Assurance Policy
-
7/25/2019 583 Construction Management Rev i
3/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 3 OF49
REG-5.8.3-001 Construction Management Version I
PART 1 - NEW BUILD CONSTRUCTION MANAGEMENT PLAN:HIGGINS CONSTRUCTION PLC
5.8.3 (a) General approach to Health & Safety
The Higgins Construction approach to Health and Safety management is paramount on all
construction projects, and is developed in such a way as to encourage everyone involved to
work together.
The core duty of all involved in the project will be to co-operate and co-ordinate with others.Every person involved in the project will have to seek co-operation from, and co-operate
with, others involved in the construction work on the same or adjoining sites in relation to
health and safety issues.
Below are the main criteria by which Higgins will approach the Myatts Field North Project:
Ensure that all statutory appointments and notices are in place.
The Project Management Team will ensure that Designers and Sub-Contractors who
may be engaged on the project are competent and adequately resourced.
Ensure suitable and sufficient welfare facilities are provided for the project from the startof the construction phase.
All Company Personnel are provided with information, instruction and training to ensure
they are competent to address the Health & Safety issues likely to be involved in the
management of the construction phase of the project.
A Higgins Construction Director will ensure that the construction phase of the project is
properly planned, managed and monitored, with adequately resourced competent Site
Management and support teams i.e. Resident Liaison Officers appropriate to the risks
and activities involved in this project.
Pre-tender/pre-start meetings will ensure that every sub-contractor who will be involved
on the project is informed of the minimum amount of time in which they will be allowedfor planning and preparation before they begin work on a site.
Suitable Construction Phase Plans will be prepared before construction works
commence and provided to the CDM co-ordinator.
The Project Management Team will provide copies of, or access to, relevant parts of the
Construction Phase Plan and other information to sub-contractors, including self-
employed, in time for them to plan their works.
-
7/25/2019 583 Construction Management Rev i
4/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 4 OF49
REG-5.8.3-001 Construction Management Version I
Information requests from sub-contractors will be met promptly and the Higgins project
team will oversee safe working, co-ordination and co-operation between the Project Sub-
Contractors.
The Project Management Team will liaise with the CDM co-ordinator on design carried
out during the construction phase of a project, including design by specialist Contractors.
Appropriate information will be included in the Construction Phase Plan.
The Project Management Team supported by experienced Health and Safety Advisers
shall ensure that all appropriate safety measures are implemented on the project.
The Project Management Team will ensure Construction Phase Health and Safety Plans
are to be kept up-to-date as projects progress.
All site personnel will be provided with suitable Health & Safety Induction, Informationand Training and site rules enforced as necessary and ensure the workforce is consulted
in relation to the projects Health & Safety matters.
The Project Management Team will provide the CDM co-ordinator promptly with any
information relevant to the Health & Safety File for the project
A copy of Higgins Health & Safety Policy & Procedures is provided at Appendix 01.
We acknowledge that the works will have an ongoing impact on the local environment during
the regeneration period. We therefore place the utmost importance on recognising theissues and identifying options to mitigate the impact of these issues.
Items which are considered to be of prime importance are:
Demolition, and new build construction works adjacent to tenanted properties
Traffic management and recognition of the impact of introduction of construction
traffic into a heavily populated public space
Site security and unauthorised access
Temporary and permanent utility services protection
Noise, dust and nuisance mitigation
Local community Health & Safety awareness
Well managed and appropriate temporary works
The regeneration programme will be carried out on a phased basis and as each Phase of
the works commences each construction area will be fully enclosed within a robust hoarding,
preventing any unauthorised access to the construction operations. The access gates to the
-
7/25/2019 583 Construction Management Rev i
5/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 5 OF49
REG-5.8.3-001 Construction Management Version I
works will be manned during construction working hours and movements in and out of these
areas closely controlled.
To ensure that the construction work is segregated from the public, vehicular movements will
be arranged to prevent disruption to the local residents. Where this is not possible traffic
movements are controlled and limited to non-sensitive periods (i.e. not during school runs).
Please refer to the Traffic Management Plan provided at Appendix 02.
All routes used by construction traffic leaving the construction site will be required to be
cleaned with wheel / under-carriage cleaning apparatus to mitigate against mud / debris
being transferred onto public roads.
Prior to the commencement of all phased works we will keep local residents and the local
Authority Representatives advised of operational programmes, methodology and the
proposed traffic management plan through the Residents Forum, the Resident Liaison
Officer, and newsletters. Any concerns or matters raised by local residents and the local
Authority Representative will be considered and where deemed appropriate will be
incorporated into the final approach.
All site roads, construction traffic routes etc. will be signposted with speed limits, direction
markers etc. Pedestrian routes and vehicular traffic routes for construction works will be
segregated by either demarcation fencing or physically sitting in different areas of the site.
When subcontractors from the database are selected at the enquiry stage for each project
they will be directed to their obligations in terms of health and safety legislation and our
procedures on site. Prior to letting a sub-contract award we hold a pre-order meeting to re-
emphasise the current legislation and our specific requirements. The pre-order meeting
minutes are signed by both parties and are used to formalise our contractual agreement with
the subcontractor. These minutes will be included within the form of subcontract agreement
and will be regularly referred to during meetings between our on site supervision team and
the subcontractor.
Prior to the works commencing the Pre-Construction Information is developed into the
project specific Construction Phase Health and Safety Plan and is signed off at each stage
of the project prior to that work commencing. The subcontractors will be required to produce
the requisite method statements, risk and COSHH assessments in accordance with our
processes and procedures, and will not be allowed to commence work until these are in
place. This document is maintained on site and further developed by the addition of other
specific risk assessments, method statements, training information etc.
-
7/25/2019 583 Construction Management Rev i
6/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 6 OF49
REG-5.8.3-001 Construction Management Version I
The on site management of Health and Safety is controlled by our prevention is better
than cure ethos. All our supply chain partners are required to read and sign our current site
rules and regulations. Following this initial site induction there is a continuous process of
education by way of tool box talks relative to works being undertaken. These are signed off
by the Health & Safety Manager and records kept of all tool box talks given and which
operatives attended.
Regular site inspections are undertaken by our site management team and our health and
safety advisors to ensure that the works are being undertaken to the highest possible
standards and practices. These reports are published and available to all and will bediscussed with each subcontractor at regular progress meetings.
The health and safety performance of all subcontractors is monitored through Sub-Contract
Evaluations against the following performance indicators:
Quality of Workmanship
Submission of Records/Documentation
Adherence to Programme
Level of Work Supervision
Co-operation with Agent/Other Trades
Level of Technical Assistance/Expertise
Willingness to obviate Extra Costs
Attitude to Dayworks
Attitude to Site Cleanliness
Prevention of Waste
Protection of Works
Attitude to Health and Safety
Rectification of Defective Work
The results are fed back into our procurement database to inform selection of sub
contractors for future projects.
The nature of the works is such that all works will be notifiable under and require compliance
with the terms of the Construction (Design and Management) Regulations 2007 (CDM). In
order to comply with and surpass the regulations a CDM co-ordinator will be appointed at
the earliest possible opportunity after preferred bidder, and prior to the progression of
-
7/25/2019 583 Construction Management Rev i
7/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 7 OF49
REG-5.8.3-001 Construction Management Version I
detailed design. It will be the CDM co-ordinators responsibility to ensure that the Client is
aware of their duties and that relevant Pre Construction Information is passed to the
Principal Contractor and from there onto the trade sub-contractors. It is the responsibility of
the Principal Contractor to prepare a Construction Stage Health & Safety Plan in response to
the particular circumstances of the project and to ensure that the works are planned and
carried out in a safe manner with particular regard to the safety of the public, the works
operatives and future maintenance operatives.
The commencement of all work, regardless of the scale, will be subject to receiving a
satisfactory Method Statement and Risk Assessment. Only once these have been approved
by the Site Manager and H&S Manager will permission be granted to carry out the work.
The following provides an overview of day to day H&S practices which are enforced andfollowed on site:
All site operatives and visitors to the site will be suitably inducted by our ManagementStaff before being allowed onto the site.
All works to be undertaken will be carried out under the supervision of a permanent siterepresentative from Higgins Construction PLC namely our Project Manager. He willdiscuss with the site operatives the full extent of the works taking place and explain allthe restrictions applicable to this contract.
All subcontractor operatives on site will be experienced workers trained in theirrespective duties and conversant with the companys Health and Safety Policy andProject-specific Method Statements.
All trade operatives will be under the supervision of their Site Foreman, who if applicable,speaks the particular language of any non English speaking operatives and will translateall site induction/toolbox talks and emergency evacuation procedures. A signedstatement is obtained to ensure all operatives on site have received and understood allsuch safety instructions from Higgins Staff.
All operatives will be expected to use in the proper manner, the correct tools, equipmentand PPE for the task in hand.
Each operative shall demonstrate a concern for safety on site, for other workers, as wellas for themselves.
We will ensure that each operative wears the requisite personal protection equipment.The site will be designated a hi-viz and hard hat area and operatives will comply withthis.
All subcontractors will be required to undergo an on-site induction course to ensure alloperatives are conversant with the safe methods of working.
-
7/25/2019 583 Construction Management Rev i
8/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 8 OF49
REG-5.8.3-001 Construction Management Version I
Plant operatives will be CPCS holders and be responsible for the correct safe use of the
items of plant they are using and ensure that it is operated in accordance with themanufacturers instructions. All plant and equipment shall be the most appropriate foreach operation and the plant will be properly maintained and in good working order. Anynoisy plant shall be fully suppressed and when in intermittent use shall be shut downduring the periods of non-use.
Site personnel will maintain warning signs, barriers and safety measures etc, and reportany defects to their foreman for his immediate attention and action.
We will assess the requirements for First-Aid based on the numbers of operatives onsite, and together with the subcontractors, provide the necessary facilities on site.
Appointed members of Higgins Site Staff/Sub-contractors will be first-aiders. In the
event of any emergency on site, requiring attendance of the ambulance or fire fightingservices, once services have been informed, the Site Supervisor will take the appropriateaction.
A Fire Plan and emergency evacuation procedure will be in place and all operativesinformed of these by the Project Manager or other appointed site staff.
A traffic and pedestrian plan will also be agreed prior to implementing and clearlydisplayed on site. This will be regularly reviewed and amended as necessary.
Prior to commencing on site a full and detailed risk assessment will be carried out andissued to the Clients Agent for approval.
Access and Traffic Management
In recognition of the busy surrounding roads, traffic and pedestrian management needscareful consideration and consultation with the neighbouring residents and LambethsHighways Department.
A detailed Traffic Management Plan will be developed and implemented, taking intoaccount any requirements from planning conditions which may be specified further downthe line.
Temporary one way systems may need to be adopted for construction traffic together
with on site haul roads and temporary vehicular crossovers.
The estate and neighbouring residents together with Lambeths Highways Departmentwill be consulted at an early stage prior to implementing any traffic management planand updates as the works progress.
Access on and around the site, as shown on the annotated drawings, will depend on theparticular stage of the works.
A trained and dedicated Vehicle Banksman will supervise the access and egress ofdelivery vehicles within the confines of the hoarded off site areas. Refer to the annotatedphasing plans.
-
7/25/2019 583 Construction Management Rev i
9/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 9 OF49
REG-5.8.3-001 Construction Management Version I
Large delivery vehicles will be offloaded within the site boundaries using cranespositioned at appropriate locations to suit the build sequence.
Careful co-ordination and clear instructions for all deliveries will be given to suppliers andsubcontractors.
Direction signage on approach roads will clearly identify the new build construction sitesand the areas secured for demolition.
Appropriate directional signage and safety information will be displayed on the estate
warning pedestrians of the individual site access routes and construction traffic routes
The existing pedestrian and vehicle routes will be carefully considered when formulatingour traffic management strategy.
A member of Higgins Site Team will be responsible for supervising the trafficmanagement for each stage of the works and auditing and amending as appropriate.
Communication
Communication on site is essential, and the site team will have dedicated telephones/radios,faxes and email connections.
The Project Manager is the point of contact on site during working hours. We will have
emergency telephone numbers for matters arising out of working hours, weekends, and
public holidays.
As part or the Considerate Constructors initiative site contact numbers and the name of the
Project Manager will be displayed on notice boards.
-
7/25/2019 583 Construction Management Rev i
10/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 10 OF49
REG-5.8.3-001 Construction Management Version I
5.8.3 (b) General approach to Environmental Management
This section outlines our approach to sustainability during the demolition and constructionprocess. Full descriptions of our approach to sustainability are in the Sustainability MethodStatement (5.7.2) and associated documents.
In July 2008 Higgins Construction PLC, achieved accreditation under ISO 14001:2004(Certificate Ref EMS523870). In accordance with the requirements of the standard, theyhave developed and subsequently implemented an Environmental Management System
(EMS) which has been designed to systematically reduce the impact of their businessprocesses on the environment. This EMS forms the foundation for delivering pro-activeEnvironmental Management on all of their projects, and will be fully adhered to on the MyattsField PFI development.
Higgins Construction PLC is committed to protecting the environment and recognise thatmany of the operations and processes involved in delivering projects harbour the potentialfor environmental impact. Working to an ISO 14001-certified EMS helps to address this by;
Identifying the Environmental Aspects of all business activities
Identifying all legal and other regulatory requirements and ensuring that compliance with
them is maintained and regularly reviewed.
Ensuring all Environmental Objectives and targets (KPIs) are set and monitored.
In recognition of the evolving nature of Environmental Management, we pro-actively ensurethe continual improvement of our environmental performance. At the heart of this approachis their Environmental Policy, which contains the following key commitments;
1. To employ an Environmental Management System in accordance with BS EN ISO14001:2004 on all projects, and use this system to influence business decision makingprocesses.
2. To develop and achieve environmental objectives at Management Review Meetingswhich can be supported by measurable performance indicators, to manage all potentiallysignificant environmental aspects including resource use, waste, emissions andnuisance.
3. To work with supply chain partners to promote the sustainable sourcing of products andmaterials.
4. To maintain a consistent and transparent dialogue with all interested stakeholders inorder to identify and address key environmental issues affecting the business.
5. To seek out and apply innovative solutions to the delivery of projects.
-
7/25/2019 583 Construction Management Rev i
11/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 11 OF49
REG-5.8.3-001 Construction Management Version I
6. To regularly publish information on their environmental performance.
7. To the ongoing and structured training of staff, clients, suppliers and sub-contractors withthe aim of enhancing their awareness of relevant environmental issues and securingtheir effective participation in helping to minimise the environmental impacts.
8. To the reduction of the environmental impact of the final constructed product throughimproved specification and design.
9. To the promotion and demonstration of efficiency in the use of energy, water andmaterials, during the construction process including the use of definedmeasures/processes to minimise waste and re-use and maximise recycling outputs
As well as twice yearly auditing by BSi, their EMS is subject to more frequent internalauditing by a dedicated external consultancy. This ensures continuous improvement basedupon the Plan - Implement - Check, Correct and Present - Review feedback loop model.
In addition to improving Higgins general environmental performance, their EMS also helpsto score in several key areas under the Code for Sustainable Homes;
Higgins are Associate Members of the Considerate Constructors Scheme, and have aninternal KPI to achieve an average score in excess of 32 (denoting exemplarperformance) across all projects, helping to meet the requirements of Section MAN2 (2credits max)
In accordance with Clause 4.3.1 of ISO 14001, their EMS includes a Procedure toconsider and record each major construction activity and its Environmental Aspect on an
Aspects Register, together with the measures required to mitigate its potential effects.This includes best practice policies in respect of both air (dust) pollution arising from siteactivities, and water (ground and surface) pollution occurring on the site. They also haveProcedures in place to monitor, report and set target for CO2production / energy useand water consumption arising from site activities. All of these measures help to scoreunder Section MAN3 of the Code (2 credits max). This is also how we ensure that weadequately protect ecology during the demolition and construction process (Eco 3).
Based on our present policies and method statements, we will develop a ConstructionEnvironmental Management Plan (CEMP) for the project. The CEMP will be developed
throughout the planning, design and consultation processes with the aim to avoid, minimise
and mitigate any construction effects on:
The Environment
Existing surrounding Communities
New Residents of Myatts Field North
-
7/25/2019 583 Construction Management Rev i
12/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 12 OF49
REG-5.8.3-001 Construction Management Version I
A generic site-wide CEMP will define the general approach by which the project will be
undertaken and describe the environmental management system for the whole site. It will
show how best practice environmental performance will be achieved wherever practicable.
Site specific CEMPs will be prepared for each phase of the works. These will be written in
accordance with the generic site-wide CEMP and will detail the specific environmental
obligations and constraints (over the above those cove red in the generic CEMP) for that
area of the site. Both the generic and site specific CEMPs will include the following generic
documentation:
o A Management Structure, which includes an organisational chart encompassing allstaff responsible for environmental work. This will set out the respective roles andresponsibilities with regard to the environment and identify the nominatedenvironmental manager.
o An internal environmental audit programme, for example ISO 14001.
o An Environmental Risk Register and associated procedures, which show howenvironmental risks will be addressed.
o Procedures for environmental training of all permanent site staff, temporary staff willbe covered within the Toolbox Talk.
o Procedures setting out how internal communication will be programmed, managedand documented in respect of all environmental matters.
o
Procedures for handling external communications, liaison and complaints includingthe development and maintenance of a clear audit trail.
o Procedures for monitoring, recording and disseminating the environmentalinformation and performance.
o Procedures for addressing non-compliance and corrective actions.
o Procedures for dealing with major incidents, unexpected occurrences or finds duringconstruction, particularly related to:
Air quality (for example dust) Cultural Heritage (for example archaeological finds) Ecology (for example protected fauna/flora) Ground quality (contamination issues) Noise and Vibration Water resources
In addition, the CEMPs will include the following detailed information as appropriate.
Construction Works
o Location of the works, including a site plan, showing construction site boundaries,position of plant and any sensitive receptors, e.g. trees, water courses, localresidents etc.
-
7/25/2019 583 Construction Management Rev i
13/49
-
7/25/2019 583 Construction Management Rev i
14/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 14 OF49
REG-5.8.3-001 Construction Management Version I
o A register of permissions and consents required, with responsibilities allocated and a
programme for obtaining them.
Environmental Requirements
o Procedures for monitoring construction processes against the project environmentalobjectives and for the appropriate action if thresholds have been breached.
o Procedures for reporting any spillages/pollution incidents to the relevant authorities.
o Procedures for co-ordinating the monitoring results to ensure that the combinedeffect of the works in different locations does not trigger threshold levels.
o Schedule of potential significant environmental effects relating to each activity (thisshould draw upon the definitions of significant effects used in the ES and relate tothose effects identified).
o A specific Environmental Risk Register relating to each activity.
o Monitoring proposals, which shall include:
The receptors for which monitoring will be undertaken Frequency of monitoring Factors against which the monitoring results will be analysed Threshold levels Speed at which results will be analysed List of organisations/individuals to whom results will be distributed Actions to be taken in the event that thresholds are breached.
Management Plans
o Specific management plans relating to the following topics: Cultural Heritage Ecology Landscape Lighting Noise and Vibration Pollution incident control Topsoil Traffic Waste
-
7/25/2019 583 Construction Management Rev i
15/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 15 OF49
REG-5.8.3-001 Construction Management Version I
Communication
o External Consultation A list of those notified of the works and the date notified A list of proposed notifications and dates
o On-site mitigating measures for each effect and risk which will form part of thetoolbox talk for all site based staff.
A formal Code for Sustainable Homes Pre-Assessment has been undertaken, includingearly consideration of;
building orientation / massing target u-values
air permeability
low or zero carbon technologies (renewables)
This approach enables a strategy to be developed for meeting the requirements of the Codethrough;
Ensuring that building orientation optimises energy reduction, maximises passiveheating and reduces heat loss
Utilising an early renewables assessment to determine the most cost effective
approach to meet the site-specific renewables target taking on board any siteconstraints
Managing the production of typical SAP calculations to determine target u-values forthe development
Incorporation of the above to enable early establishment of the wall and floorconstruction to meet the requirements of Code Level 3. This is especially importantas these constructions can affect the choice of elevation materials, site setting out,acoustic and thermal performance, use of MMC, etc.)
As part of Higgins standard ISO 9001-accredited Quality Management procedures, a
detailed Contract Quality Plan (Appendix 03) will be developed, monitored and managedduring each stage of the design and construct process. The format of this Contract QualityPlan has been designed to integrate fully with the Environmental Management System, andaccordingly the Code for Sustainable Homes Assessment forms a key component of thisdocument. For Myatts Field North we are targetting 100% Forest Stewardship Council(FSC) timber, which will be incorporated into the management plan. Rydon Maintenancewill use the same contract quality plan format to achieve their targets.
Including the Code toolkit and bespoke commitments into the Contract Quality Plan ensuresthat all decisions made during Pre-Construction are tracked and integrated into both sub-contractor and materials orders, and Higgins own management processes.
-
7/25/2019 583 Construction Management Rev i
16/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 16 OF49
REG-5.8.3-001 Construction Management Version I
Below are more details on key commitments to best practice in sustainable construction forMyatts Field North.
Materials
Materials is a significant section in the Code for Sustainable Homes in terms of available
credits, and there is a mandatory requirement for at least three of the five key elements to
achieve a relevant Green Guide rating from the 2007 version of The Green Guideof A+ to D
(roof, external walls, internal walls, upper and ground floors, and windows).
We commit to achieve levels in excess of these mandatory requirements;
80% of the materials utilised on the project will be A-rated (as defined in the GreenGuide 2008)
100% of timber used will be FSC (or equivalent) accredited
Using our extensive supply chain database we can source and specify cost-effective
materials which meet the required scoring criteria under the Code whilst still maintaining
architectural merit.
The above commitments will be formalised through their inclusion in the Code for
Sustainable Homes Assessment checklist included within the Contract Quality Plan and
accordingly incorporated within all sub-contract and material orders. As our constructor
partner procures all of their materials directly, we can guarantee that a full audit trail (as
required under the Code) for all materials i.e. FSC accreditation, Chain of Custody
Certificates, etc. will be supplied.
Waste Recycling
From January 2008, Higgins Construction PLC has operated Site Waste Management Planson all of its new schemes, helping to score under the mandatory requirement of Section
WAS2. Higgins partners with several licensed Waste Management Companies, who hold
Waste Carriers Licenses and operate ISO 14001-accredited Waste Transfer Stations. All
waste is removed unsegregated from site before being separated into individual waste
streams and recycled at the Waste Transfer Station.
Records are then issued to site by the Waste Management Company for inclusion in the Site
Waste Management Plan. An average recycling rate of 78% has been achieved across
recent project, and we believe that our commitment to increase this to 80% is practically
-
7/25/2019 583 Construction Management Rev i
17/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 17 OF49
REG-5.8.3-001 Construction Management Version I
achievable via on-site segregation of plasterboard waste and the subsequent recycling of
this element as a separate waste stream to the other unsegregated waste.
Transport
We confirm our commitment to produce, monitor and managed a detailed Transport Plan,
which will be initiated at Preferred Bidder Stage. These Plans have been successful
developed and utilised on previous schemes and have ensured that the number and length
of journeys are kept to a minimum, reducing emissions from transportation, and minimising
noise, fumes and general disturbance to local residents.
This Transport Plan will be incorporated within the overall Contract Quality Plan to ensure it
is continuous and regularly monitored and updated.
We believe that our proposal for the construction of Myatts Field PFI will minimise waste,
and transport movements.
Air Tightness
We do not believe that an air permeability rate of 3m3/m2/h is practically achievable on
panellised timber-framed forms of construction (excluding SIPs). Based on historical data we
believe that a predicted air permeability rate of 7m3/m2/h is more realistic (which is still a 30%
improvement over current Building Regulations), although we reaffirm our commitment to
reduce this level as far as practically possible.
Following completion of the Air Tightness Testing, copies of all test reports will be included
within the Contract Quality Plan and additionally distributed to the Code for Sustainable
Homes Assessor to ensure the post-completion audit requirements of the Code are met.
-
7/25/2019 583 Construction Management Rev i
18/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 18 OF49
REG-5.8.3-001 Construction Management Version I
5.8.3 (c) General approach to Quality Management
Higgins have a strong quality ethos. Each has successfully been granted or is in the
process of applying for Investor in People Status, and Quality Assurance accreditation
ISO9001:2000.
The following section details Higgins approach to matters related to quality management
which will be continually reviewed and developed to enhance their resource capabilities in
order to successfully execute their projects.
Commitment of Resources
Higgins Construction considers its primary resource capability to be its employees and
integrated supply chain and have recognised this through its commitment towards
Investors in People.
Higgins have a progressive and rigorous selection process for employment of both staff and
supply chain partners to ensure suitability and competence to deliver against our quality
management targets on the projects that we undertake. Thereafter all employees are
reviewed on a regular basis under a Company Training and Development Policy and all
supply chain partners are reviewed by our Procurement Knowledge Centre and any areas ofweakness addressed.
A copy of our construction partners Quality Control Policy is included in Appendix 04. The
key elements of the Quality Assurance system are detailed as follows:
Quality Control Policy
Higgins Construction PLC will manage and continue to improve the high quality of building
contracting services provided by the company;
Ensure that all contractual requirements between the company and its clients areconsistently achieved;
Ensure that health, safety and welfare requirements are properly applied and managed;
Continually try to improve the effectiveness of the quality management system.
The aims of the quality control policy are delivered through the Higgins Management System
which is audited by Directors and independently by the BSi.
-
7/25/2019 583 Construction Management Rev i
19/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 19 OF49
REG-5.8.3-001 Construction Management Version I
The Higgins Management System has been developed in accordance with the requirements
of BS EN ISO 9001:2000. Conformance with the requirements of the Higgins Management
System is mandatory for all members of staff engaged in the provision of building contracting
services. This quality policy will be reviewed at the annual management review to verify its
continuing suitability.
Quality Objectives
Higgins are founder members of the Governments Construction Best Practice programme
which is being managed through the offices of the DTI.
In accordance with the recommendations made by the Construction Task Force, which are
detailed in their report Rethinking Construction , Higgins have joined the following two
Benchmarking Clubs:-
Housing Forum Benchmarking Club which is managed by Achilles; and
Housing Industry Benchmarking Club which is managed by Building Software Limited.
Through the use of specific KPIs the companys performance is regularly monitored andmeasured and the results are compared with the industry average. The companys
performance will be reviewed by the Board of Directors, who are responsible for managing
the development and implementation of the improvements that they deem necessary to
address any deficiencies and/or weaknesses identified through this programme.
In addition to the above each department maintains a set of quality objectives which are
used to monitor performance.
Scope of the Quality Management System
The Higgins Management System is defined within the following key documents:
Quality Manual;
Procedures Manual;
Business Plan;
Monthly Board Reports; and
KPI Report
-
7/25/2019 583 Construction Management Rev i
20/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 20 OF49
REG-5.8.3-001 Construction Management Version I
The Higgins Management System has been developed to exceed the requirements of BS
EN ISO 9001:2000 as applicable to the provision of building contracting services.
The processes and quality control systems we have in place will ensure that the project is
managed for compliance with all contract requirements and required standards of
workmanship, cost and programme performance. The management tool we use, also
address key areas such as risk management, value management and supply chain
management all of which ensure the project and client delivery targets are met.
Our Supply Chain are required to work to the Higgins Management procedures unless they
are able to demonstrate to us that their own Quality Systems provide the equivalent
standard of quality control and management.
We develop Quality Plans for each project which we would involve the Client and the Supply
Chain in, to ensure that all parties buy into the key processes and sign-off stages, that will
ensure an audit trail is available to show quality checks have been adhered to.
We will establish a continuous improvement culture throughout the partnership. We will
encourage input from all stakeholders, including residents and the supply chain, to reviewwhat we are doing and how we can do it better. By establishing a forum team to look at
continuous improvement we would be able to establish a mechanism for reviewing
feedback, setting targets for improvement ensuring strategy is developed to encourage this
culture. On Myatts Field North Regenter will hold joint review and lesson learnt workshops
for both the refurbishment and new build contracts where we will include residents
comments to regularly evaluate areas that could be improved. We will then make sure that
we act on the lessons learnt on future phases of work.
We will maintain a clear induction process with all new team members to ensure lessons
learnt are shared and backward steps are not taken. By the development of clear audit trailsand Issue Resolution Logs we will be able to record and monitor the impacts of both radical
changes and fine tuning.
The Higgins Management Procedures is targeted in key areas: -
Before Contract:
Ensuring that the site management team has the correct composition and is the rightteam for the 'job' in terms of experience and expertise.
-
7/25/2019 583 Construction Management Rev i
21/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 21 OF49
REG-5.8.3-001 Construction Management Version I
Maintaining regularly audited data bases of quality suppliers and sub-contractors.
Ensuring that proposed suppliers meet the correct contract specification.
Ensuring that all proposed sub-contractors meet the Company's rigorous selectionprocedures and will deliver the correct product.
During Contract:
Quality monitoring will take various forms depending on several factors;
The type of work being carried out
The duration of the work being carried out
The complexity of the work being carried out and
The contractors previous performance.
The Contracts Manager will be responsible for monitoring the quality of both the work being
carried out and the information that is supplied by way of drawings, manuals and other data
needed to determine future maintenance and lifecycle.
Day-to-day monitoring of the work quality will be devolved down to operational technicalstaff. For larger projects these will take the form of regular scheduled, minuted meetings
with the contractor.
Other features of the contract period are;
The agreement and monitoring of a site specific Contract Quality Plan to achieve therequired quality objectives.
The purpose of the plan will be to identify key quality issues, incorporate them within the
plan and establish the means to measure monitor and achieve the required quality level.
The agreement of an effective handover procedure. The procedure will be extractedfrom the quality plan and translated into a handover programme. This programme
together with a procedure checklist will be utilised by the site management team to
achieve successful handover.
Post Contract support for a 12 month period for completed dwellings will be provided
by the following means:
-
7/25/2019 583 Construction Management Rev i
22/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 22 OF49
REG-5.8.3-001 Construction Management Version I
UItilising a professional, directly employed office based after care team led by a
construction director. The after care team will log problems and allocate resources as
appropriate.
Employing mobile, multi-skilled operatives supported by trade specialists where requiredto undertake repairs and maintenance.
On Myatts Field North we will include a quality plan that will be prepared in conjunction with
,and signed off by, key stakeholders and partners. The plan will indicate those stages of
works that require inspection, the timing/frequency/quality control parameters or
specifications, and the allocation of responsibility for inspection. Quality inspections will be
recorded in the appropriate customary manner and actions reviewed regularly within a
Supply Chain quality forum and the management of appropriate safety standards through an
independent safety group.
We will agree and monitor a specific Contract Quality Plan to achieve the requirements of
the scheme in terms of its quality objectives. This plan will be fully agreed after extensive
consultation and discussion with the residents and client to ensure that the plan includes for
all client inspection and review processes and milestones. The purpose of the plan will be to
identify key quality issues, incorporate them within the plan and establish the means to
measure monitor and achieve the required quality level.
5.8.3 (d) Management methodology, including compoundarrangements, storage, on and off site support structures,logistics
We believe transformation of this estate is only achievable through a fully integrated,
seamless and comprehensive approach to regeneration. We will achieve this by running the
practical aspects of our development on Myatts Field North in a fully incorporated way to
ensure the most efficient works programme for residents. We will ensure full integration of
compounds and all logistics in terms of deliveries and storage between all our delivery
partners. We will set up one site compound from which we will operate all our procurement,delivery and storage systems for both refurbishment and new build in order to minimise any
mess or disruption for residents.
The management of this process will be through Joint Project Meetings which will take place
weekly throughout the development programme. Residents will be invited to attend these
meetings to discuss any concerns they have with the management of the works.
-
7/25/2019 583 Construction Management Rev i
23/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 23 OF49
REG-5.8.3-001 Construction Management Version I
We also intend to appoint one team of Resident Liaison Officers that will serve the residents
whatever their position within the programme.
Management Methodology - Joint Working Structure
Refurbishment
Repairs & MaintenanceRegenter MFN DevCo
Regenter MFN SPV
General Manager
Joint Weekly PM
Team
Joint RLOs Team
Plan utilities /
roads / hoardings /
plant safety / demolition
All refurbishment
All repairs and maintenance
All lifecycle replacement
All New Build
Sales and Marketing
of new build
Plan respite /
re-housing /
cleaning / support
Refurbishment
Repairs & MaintenanceRegenter MFN DevCo
Regenter MFN SPV
General Manager
Joint Weekly PM
Team
Joint RLOs Team
Plan utilities /
roads / hoardings /
plant safety / demolition
All refurbishment
All repairs and maintenance
All lifecycle replacement
All New Build
Sales and Marketing
of new build
Plan respite /
re-housing /
cleaning / support
Site Access Arrangements All Parties
The main site compound for all of the works, new build and refurbishment, will be located in
the same location which will also contain resident liaison and neighbourhood management
facilities. However there will be a requirement for satellite offices adjacent to specific work
faces.
This office will comprise of:
Reception area
Meeting room
Offices for construction management staff Housing Office with resident access
Toilets and welfare facilities
Storage containers
Respite facilities
The majority of site project offices will be in a central compound. The offices will be modular
accommodation to suit flexible arrangements for the internal layouts.
-
7/25/2019 583 Construction Management Rev i
24/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 24 OF49
REG-5.8.3-001 Construction Management Version I
This will be fitted-out and furnished to a high standard to make any visitors feel welcome.
They will also project our corporate image, being professional in appearance and using
relevant colours and logos. They will be maintained and kept free from graffiti at all times.
The offices will be fully equipped with telephones and Internet connections, together with
smoke detectors and fire alarms. Water and electricity will be provided by tapping into the
mains supplies. The office will be welcoming and resident friendly as the bottom floor will be
the housing office.
In addition to the main project offices, satellite offices will be established adjacent to new
build site 13 and site 17.
Storage of materials will be in steel containers within the main compound and within satellite
compounds close to the works areas.
The area we propose for the central project offices is indicated on our phasing/traffic
management plan (Sides 1 & 2), close to Cowley Road.
This will remain for the duration of the project as this helps to maintain consistency, stability
and to build trust with the residents and other stakeholders. We also feel that due to lack of
space we will need to double stack with staircase access to the top level.
All operatives will adhere to the Myatts Field North dress code, including the wearing of
personal, protective equipment (PPE) and visible means of identification at all times.
Operatives will conduct themselves in a professional manner. Operatives will bring to thepremises, or have delivered, all tools, equipment and plant necessary to carry out the
programmed works.
Material Distribution and Storage
We will provide containers to store smaller and more vulnerable and valuable items of
material. We may in additional use separate storage areas within individual hoarded off
sites.
All disturbed areas will be reinstated at the end of the project, if not included as part of thenew works. We will ensure that pedestrian access to the site office for visitors to the housing
office and to the RLOs is safe and secure.
A combination of materials handler forklift, mobile crane visits, static tower crane visits, static
tower cranes and Mobile Elevated Work Platforms (MEWP) are proposed for this project.
The general principles of materials control will be followed at all levels:-
-
7/25/2019 583 Construction Management Rev i
25/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 25 OF49
REG-5.8.3-001 Construction Management Version I
Good schedule file systems used to give quick reference as to when, and from whom,
deliveries are required.
Planned deliveries utilised to ensure control of suppliers
Alternate sources made available if possible
Control of wastage of materials of site level optimised to ensure level kept to a minimum.Delivery schedules monitors and adjusted accordingly
Careful checking of orders and monitoring of planned delivery dates to ensure materialsdelivered can be properly stored and unnecessary double handling avoided
Standard quality of materials maintained throughout the contract period by checking
against agreed samples or specifications
Subcontractors will be encouraged to minimise any wastage of materials at the first instance
in line with our Environmental Policy. Proposals for use of modular components and ready
mixed mortar for example, may also help reduce wastage.
Materials delivered to site will be packaged to prevent wastage at point of use e.g. shrink
wrapping and / or palletised. Careful ordering of type and quantity together with a selected
method of offloading will further prevent material wastage on site.
Careful co-ordination of material deliveries will be necessary to avoid potential congestion
with residents traffic and the local school start and end times. It is also important to have
the correct sizing of delivery vehicles to allow materials to be received offloaded / loaded
within the hoarded off site boundaries. This offload / load procedure will be supervised at all
times by an appointed Banksman as our Health and Safety Procedures.
Working Hours
Although the office will be open from 0900hrs until 1700hrs, all sub-contractors and employees
will be advised of the allowed working hours and will be adhered to. These times will be in
accordance with LBLs Code of practice for construction sites, i.e., 08.00hrs 18.00hrsMonday to Friday, and 08.00hrs 13.00hrs Saturday. No works will take place during UK
holidays
No work will be carried out on Sundays or Bank Holidays, unless necessary for minimising
potential disruption of utility services connections and / or diversions or installing / removing
tower cranes and having first been approved by Lambeth.
-
7/25/2019 583 Construction Management Rev i
26/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 26 OF49
REG-5.8.3-001 Construction Management Version I
Off Site Suppor t Structure
The site team will be supported by large off site support structure we have shown an
example of this in the off site support structure of Higgins. Each team is supported in this
way with a wealth of knowledge, expertise and staff that can be called upon at any time.
5.8.3 (e) Organisation of staffing and resources
We show below an organisation chart showing where each service delivery partner is placed
within the wider context of Regenter MFN. Each delivery partner is integrated into one team,
sitting in one office.
: Lambeth - All Teams Staffing Structure
Repairs &Maintenance
Manager
RefurbishmentManager
Repairs TeamRefurbishment
Team
24/7 Helpdesk
Estate Services
ManagerHousing Manager
Housing Team
(including Leasehold)
Regenter DevCo
Project Manger and
support staff
HigginsSenior Project
Manager
Regenter MFNSPV Manager
Resident Liaison Officers
Higgins
New Build Team
New HomesSales and Marketing
Team
Pinnacle ContractManager and
support staff
Equipe Contract
Manager and
support staff
Repairs &Maintenance
Manager
RefurbishmentManager
Repairs TeamRefurbishment
Team
24/7 Helpdesk
Estate Services
ManagerHousing Manager
Housing Team
(including Leasehold)
Regenter DevCo
Project Manger and
support staff
HigginsSenior Project
Manager
Regenter MFNSPV Manager
Resident Liaison Officers
Higgins
New Build Team
New HomesSales and Marketing
Team
Pinnacle ContractManager and
support staff
Equipe Contract
Manager and
support staff
-
7/25/2019 583 Construction Management Rev i
27/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 27 OF49
REG-5.8.3-001 Construction Management Version I
Jointly
We will jointly appoint a team of Resident Liaison Officers (RLOs). We will ensure this team
meets the Resident Forum, as it is crucial they understand the community and what
individuals experiencing refurbishment and decanting are going through.
The RLO Team will be in place prior to Financial Close to prepare for Service
Commencement.
New Build
Our New Build Team reports to the SPV General Manager, and will include, although not
exclusively, the following roles:
Project Manager
Site Managers
Managing Surveyor
Community Development Manager
Senior Project Co-ordinator
-
7/25/2019 583 Construction Management Rev i
28/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 28 OF49
REG-5.8.3-001 Construction Management Version I
5.8.3 (f) Operational integration of staff
The diagram below shows how we intend to ensure all our work streams are integrated. As
well as sharing an office, one of the most effective ways of operational integration, we will
ensure that joint weekly meetings feed into the working stream groups, so that everyone
knows exactly what is happening at all stages of the program.
: Operational Integration of Staff
Design Team
Working Group
Refurb Team
Working Group
New Build Team
Working Group
RLO Team
Weekly JointStrategic Meeting
Design Team
Working Group
Refurb Team
Working Group
New Build Team
Working Group
RLO Team
Weekly JointStrategic Meeting
-
7/25/2019 583 Construction Management Rev i
29/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 29 OF49
REG-5.8.3-001 Construction Management Version I
5.8.4 (g) General security arrangements
When undertaking construction and/or refurbishment work we will address the following
aspects of security:
Compound Security: we will install CCTV on the compound that has high quality hard drive
recording. This recording is of a good enough quality and date stamped to be able to use in
court action if required
Site Security: each site will be made secure by the erection of solid hoarding prior to any
work commencing, so that no unauthorised access is possible
Site Personnel:will wear high visibility jackets and hard hats, and will be expected to wear
ID badges at all time.
Resident Safety: we will assist in keeping residents safe by holding Health and Safety
briefings. All operatives who enter resident homes will only do so with ID badges.
Resident Belongings:resident belonging will be inventoried before work begins within their
home, and anything that the resident feels is of value will be placed in secure storage.
The access to the project offices shall be controlled at all times and all personnel and visitors
will report to the site office. A separate dedicated access will be provided for the residents to
access the housing management/RLO offices.
The vehicular and pedestrian access into the construction areas will be controlled by anappointed gate man employed by Higgins Construction, who will be in radio contact withthe other members of the Higgins and Rydon Maintenance site management team.
All site personnel will wear photographic/controlled access identification badges at all times
on site and a register shall be kept in the Project Managers office. They will be surrendered
and cancelled on completion of work stage works and or employment and the register
amended accordingly.
All visitors shall wear visitor badges when on site.
All operatives will wear Myatts Field branded Hi -Viz vests for security and safety. These will
be issued with the ID badges.
Security issues will be integral to the sub-contract documents and discussed and agreed at
all pre-commencement meetings.
-
7/25/2019 583 Construction Management Rev i
30/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 30 OF49
REG-5.8.3-001 Construction Management Version I
CCTV cameras will be erected as a security measure to monitor the site and it may be
necessary to augment these cameras with out of hours static guards, should the need
arise.
During out of hours periods the detailed security measures will be augmented within the
works compound with the use of security personnel/wardens, both in a static monitoring and
mobile capacity.
Public safety is paramount and that safe access is assured to and from dwellings and
around the site with appropriate areas securely fenced off with notices and signs as
required. We will assist in keeping residents safe by holding Health and Safety briefings; we
will be visiting local schools to talk about the work that is being undertaken and the health
and safety risks that this may pose. We will ensure the all residents and the Client are
aware of the out of hours designated emergency contact number.
Prior to works starting, the site areas will be segregated from the residents with 2m high
solid hoardings with vision panels if required. These will be moved/adapted to suit the
phasing of the project. We propose to use 2m high heras fencing for the completion of the
works for the landscaping, car parking, new below ground services and new roads.
Existing fire escape route/access points to occupied buildings/shops will be maintained with
appropriate signage for any temporary diversion routes and with suitable temporary
illumination.
The site access will be protected by pedestrian and vehicular security gates which will be left
closed during the working day and securely locked out of hours.
The hoarding will need to be adjusted and adapted during the later stages of work for the
completion of the external landscaping and car parking.
Stair tower access to scaffolding will be made safe on a daily basis and all mechanical plant
will be immobilised at the end of each working day, whilst un-attended or for periods of non -
use.
At the start and on completion of the daily works, the site will be inspected to ensure it is
secure and safe.
-
7/25/2019 583 Construction Management Rev i
31/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 31 OF49
REG-5.8.3-001 Construction Management Version I
-
7/25/2019 583 Construction Management Rev i
32/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 32 OF49
REG-5.8.3-001 Construction Management Version I
5.8.3 (h) Resident Liaison throughout and in respect of all aspects ofthe work
Resident liaison throughout all aspects of the works is critical to deliver a successful
programme of works on time and with the support of the local community and residents
throughout a period of tremendous upheaval and disturbance. We understand how
important it is for residents to understand what is being proposed, contribute towards the
proposals and feel that they have been able to voice concerns, ideas and questions. We
have an approach that has a proven track record and enables residents to have direct
access to the teams delivering the works programmes to ensure the maximumtransparency, honesty and performance against our delivery commitments.
Our approach to resident liaison during this period is outlined below. A separate method
statement detailing our approach to resident consultation during the planning process is
included in our Planning method statement 5.4.4
Resident Forum
This will be the representative body on behalf of residents in the monitoring of our
compliance and performance against the Project Agreement including our performance in
relation to execution of the construction, refurbishment and demolition works.
Design Consultation
The design consultation process will take place prior to each planning application. This will
provide residents with full access to the drawings and surveys and a genuine ability to
influence the evolution of the design. This process has already commenced and we have
already revised our design and masterplan solution on the basis of the feedback received
from residents e.g. we have reduced building heights and incorporated replacement
bungalows. Further revisions can also be incorporated to address concerns over heights of
the buildings surrounding Fountains Place. We can also ensure that the final selection ofmaterials and colours for the community centre, parks furniture, play equipment are directly
influenced by the choices and preferences of residents throughout the design consultation
process.
Service Delivery Solution
We will consult with residents during our first 100 days in order to find out what it is important
to them in regard to the service proposals and tailor our solution as a result of this
consultation. We will walk the estate with residents and collectively identify the composition
of the Environmental Blitz action programme. Other areas including the nature of support
-
7/25/2019 583 Construction Management Rev i
33/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 33 OF49
REG-5.8.3-001 Construction Management Version I
and consultation that is offered throughout the construction and refurbishment period will be
particularly tailored to the preferences and requirements of residents e.g. weekend
meetings, composition of meetings, nature of representation and agenda items.
Establishing Key Groups
Because the project has different elements, different residents require different information.
We will establish working groups with the residents covering demolition, decanting, new
build and refurbishment so that we can address and fully meet the requirements of each
group. The requirements of the residents experiencing refurbishment works to their homes
are unlikely to be consistent with those residents that will be moving to a new home or to that
of a homeowner. All of these needs will be different to the needs and requirements of thevarious community groups and local businesses and surrounding residents. We will set up
resident liaison groups and activities that are specifically tailored to the different groups.
Wider Consultation
We propose to hold open community meetings once a month for the first 100 days on site. If
the community feel that these need to continue we will make sure that they do. This will
enable wider representation and liaison to be established.
Published Consultation
We will regularly distribute a newsletter throughout the construction and refurbishment
period. Newsletters will be issued on a quarterly basis during the services period.
Resident Liaison Officers
We will have dedicated Resident Liaison Officers (RLOs) responsible for the individual, one-
to-one consultation with each resident/family prior to refurbishment, construction and decant
works. The RLOs will be responsible for assessing the individual needs of the residents and
ensuring that the works are undertaken in such a way that respects these individual
circumstances.
The RLOs will undertake all initial discussions with residents concerning appointments and
programming of the necessary works, support available to assist throughout the process
(e.g. respite facilities, moving assistance etc.) and take time to explain and illustrate the
various choices that are available to residents and assist with their selection (e.g. kitchen
design).
The RLOs, together with the Helpdesk will also undertake survey work with residents
following completion of the works to monitor resident satisfaction and feedback that will be
-
7/25/2019 583 Construction Management Rev i
34/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 34 OF49
REG-5.8.3-001 Construction Management Version I
published in our reporting material and newsletters and also inform the approach we take in
future stages of the works.
Single Site Office
We will establish a combined site office within the Myatts Field North Community from which
the construction, refurbishment and service teams will operate. It will be co-located with the
Neighbourhood Management Office providing a One Stop Shop for all aspects of the
contract. This will enable more effective communication and will provide a better service to
the residents.
The site office will be open extended hours during the construction and refurbishment period
from 9am and 5pm . The site office will enable us to display material relevant to residents
such as the various works programmes, masterplan model for the new Myatts Field
Community, performance and feedback information and the team responsible for delivery of
the works and services to the residents.
The site office will also provide confidential interview rooms where residents can talk openly
to our team in private and confidential surroundings. We will have a suggestions box and
complaints box, together with access to translation services to ensure that all residents feel
able and capable of accessing information and participating in consultation and liaison.
Show Homes
We will provide and make available show homes on each phase of the new build
construction works so that residents are able to view the new homes that are being provided
and the choices available to them on the various fixtures and fittings. The show homes will
be a key tool in promoting interest and excitement among residents that are required to
decant and move home through the project.
-
7/25/2019 583 Construction Management Rev i
35/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 35 OF49
REG-5.8.3-001 Construction Management Version I
Promotion of Resident Safety & Visits to Local Schools
Public safety is paramount and safe access is assured to and from dwellings and around the
site with appropriate areas securely fenced off.We will effectively guide the public on safe
routes using notices and signs as required.
Part of our overall all plan for safety will be to visit local schools to explain what work is being
undertaken and the health and safety risks that this may pose. We will ensure the all
residents and the Client are aware of the out of hours designated emergency contact
number.
We will ensure that accesses to existing blocks of flats are maintained, as well as ensuring
that there is good access to the newly occupied homes as they are built.
Staff Livery & Identification
We intend all staff to have easily recognisable staff livery, making them more obvious,
accessible and approachable to residents whilst undertaking their duties. All our operatives
will wear identification badges at all times, and we will encourage residents to refuse entry if
a badge is not shown. Residents can call the Helpdesk to check the identification of any of
our staff if there is any doubt or concern at all.
-
7/25/2019 583 Construction Management Rev i
36/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 36 OF49
REG-5.8.3-001 Construction Management Version I
PART 2 - REFURBISHMENT WORKS CONSTRUCTIONMANAGEMENT PLAN - BY RYDON MAINTENANCE
The section below provides responses from our refurbishment partner, Rydon Maintenance,
to the question raised in the ISDS and covers the following matters.
a) General approach to health and safety;b) General approach to environmental management and sustainability;c) General approach to quality management;
d) Management methodology including compound arrangements, storage, on andoff site support structures, logistics, etc
e) Organisation of staffing and resources;f) Operational integration of staff and operatives across the Participant organisation
and sub contracts;g) General security arrangements;h) Proposals for resident liaison throughout and in respect of all aspects of the
works.
5.8.3 (a) General approach to Health & Safety
Our approach to refurbishment is guided by the fact that we are working in peoples homes.
Health and Safety and the security of residents and neighbours will be the first priority of
Rydon Maintenance.An important issue for us is the organisation of works to ensure that
multi trade working is carried out simultaneously, minimizing disruption and speeding up the
refurbishment.
We will address those through risk assessment, vigilance, monitoring, feedback,
consultation and best practice advice. We will also negotiate and agree a Residents Charter
with the Steering Group which will guide all our actions.
We are dedicated to the development, investment, management and operation of housing
projects. This includes the management, operation and maintenance of client premises and
equipment, and the provision of support services. We build teams involving all parties in a
project and centred on a close working relationship with the client together with a
commitment to health, safety, quality, and environmental objectives. Rydon Maintenance
has an up-to- date health and safety policy manual in compliance with legal requirements.
-
7/25/2019 583 Construction Management Rev i
37/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 37 OF49
REG-5.8.3-001 Construction Management Version I
To ensure its risks are adequately managed and its standards maintained, we carry out
regular internal and external audits of itself and its suppliers. We can access financial
resources, staff with suitable skills and appropriate technology for implementation and
continual improvement of our policy.
The occupational health and safety policy manual states the responsibilities of managers,
methods to control hazards and how employees are informed. The company will attempt to
minimise the occurrence of all workplace risks. For this purpose regular safety meetings will
be held to provide occupational health and safety advice for all employees and the setting
and review of objectives. Rydon Maintenance will ensure systems exist to maintain a safe
place of work at clients sites for all employees, suppliers, visitors and other interested
parties. The Rydon Maintenance compliance manager is responsible for providing
information on the company health and safety performance and reporting results to the
General Manager on a regular basis and the designated H&S Site Manager as appropriate.
All employees have a personal responsibility for their own occupational health and safety
and that of other people. This includes anything we do or fail to do. Consultation will be
carried out with all employees who must co-operate fully on any matter relating to
occupational health and safety or face disciplinary measures.
The initial refurbishment works will require compliance with the Construction (Design andManagement) Regulations (CDM). In order to comply with the regulations a CDM Co-
ordinator will be appointed at, or just prior to, contract commencement by Regenter. It will be
the CDMCs responsibility to ensure that any proposed works are planned and carried out in
a safe manner with particular regard to the safety of the public, the works operatives and
future maintenance operatives.
The commencement of all work, regardless of the scale, will be subject to receiving a
satisfactory Method Statement and Risk Assessment. Only once these have been approved
will permission be granted to carry out the work.
A copy of our H&S policy is enclosed at Appendix 05.
-
7/25/2019 583 Construction Management Rev i
38/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 38 OF49
REG-5.8.3-001 Construction Management Version I
5.8.3 (b) General approach to Environmental Management
Refer to section under Part 1 of this method statement where applicable to refurbishment
works.
5.8.3 (c) General approach to Quality Management
We are conscious of the need to sustain and improve the high quality of our service toensure that all standards and specifications are consistently achieved throughout the
contract. We have a total commitment to the philosophy of customer care. Our experience of
working within the community sector has resulted in a belief that success is achieved only by
recognising and providing a quality response to the needs of residents, our partners and the
council. We have underlined our commitment to quality customer care with the achievement
of Quality Assurance accreditation ISO 9001:2008 which will ensure:
The high quality of the products we use
The efficiency of installations and refurbishment works we carry out
The effectiveness of the co-ordination and communication among the stakeholdersof the project.
This process will involve the pooling and dissemination of formal structured feedback, in the
form of responses to survey questionnaires, as well as regular stakeholder workshops in
which feedback is discussed and potential improvements are identified and evaluated. For a
sub-contractor to be working on our project, the quality monitoring aspect of their
performance will be included in the terms and conditions of their contract.
Quality monitoring will take various forms depending on several factors:
The type of work being carried out The duration of the work being carried out
The complexity of the work being carried out
The contractors previous performance.
The Refurbishment Contract Manager will be responsible for monitoring the quality of both
the work being carried out and the information that is supplied.
-
7/25/2019 583 Construction Management Rev i
39/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 39 OF49
REG-5.8.3-001 Construction Management Version I
Day-to-day monitoring of the work quality will be flowed down to operational technical staff.
For larger works, this will take the form of regular scheduled, minuted meetings. For small
repair works a proportion of the works will be post-inspected to ensure compliance. This will
be fed back into the SPV monitoring meetings.
The information obtained through these processes is then used to identify actions and
feedback.
The practices and procedures which are implemented in achieving our quality policy
emanate from the company objective to achieve Zero Defects at completion.
Our Contract Managers are charged with the responsibility of ensuring that a high quality,
right-first-time product is delivered in every dwelling.
The process we will follow is:
Snagging: The scope of works for each package will identify the provision of benchmarks,
samples and snagging teams. Subcontractors will be required to detail the extent of their
input and staff commitment to these items.
Completion, Handover and Certification: Works will not be offered up to the Independent
Certifier until we are satisfied that they meet our own stringent standards and fully comply
with the requirements of the Project Agreement.
A copy of our QA policy is enclosed at Appendix 06.
5.8.3 (d) Management methodology, including compoundarrangements, storage, on and off site support structures,logistics
We believe transformation of this estate is achievable through a fully integrated, seamless
and comprehensive approach to regeneration. One aspect of how we will achieve this is by
running the practical aspects of our development on Myatts Field North in a fully
incorporated way to ensure the most efficient works programme for residents. We will
ensure full integration of compounds and all logistics in terms of deliveries and storage
-
7/25/2019 583 Construction Management Rev i
40/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 40 OF49
REG-5.8.3-001 Construction Management Version I
between all our delivery partners. We will set up one site compound from which we will
operate all our procurement, delivery and storage systems, in order to minimise any mess or
disruption for residents.
Site Access Arrangements All Parties
It is our intention to manage all works in Lambeth, refurbishment, new build construction and
neighbourhood management from a centrally located site office and compound.
This office will comprise of: Reception area
Meeting room
Offices for construction management staff
Housing Office with resident access
Toilets and welfare facilities
Storage containers
Respite facilities
All the site office accommodation and storage will be in steel portacabin type units. This will
be fitted-out and furnished to a high standard to make any visitors feel welcome. They will
also project our corporate image, being professional in appearance and using relevant
colours and logos. They will be maintained and kept free from graffiti at all times. The offices
will be fully equipped with telephones and Internet connections, together with smoke
detectors and fire alarms. Water and electricity will be provided by tapping into the mains
supplies. The office will be welcoming and resident friendly as the bottom floor will be the
housing office.
For the first three to six months the temporary site establishment will be located in a shop
unit in Foxley Square until the interim site set up is available off Cowley Road. On
completion of the new community centre the establishment will relocate to this permanent
location for the remainder of the PFI term. We would prefer to reduce any moves to the
absolute minimum as this helps to maintain consistency, stability and to build trust with the
residents and other stakeholders.
All operatives will adhere to the Myatts Field North dress code, including the wearing of
personal, protective equipment (PPE) and visible means of identification at all times.
Operatives will conduct themselves in a professional manner. Operatives will bring to the
-
7/25/2019 583 Construction Management Rev i
41/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 41 OF49
REG-5.8.3-001 Construction Management Version I
premises, or have delivered, all tools, equipment and plant necessary to carry out the
programmed works.
.
Material Distribution and Storage
We will provide containers to store smaller and more vulnerable and valuable items of
material. We may in additional use separate storage areas within individual hoarded off
sites.
All disturbed areas will be reinstated at the end of the project, if not included as part of the
new works. We will ensure that pedestrian access to the site office for visitors to the housing
office and to the RLOs is safe and secure.
The general principles of materials control will be followed at all levels:-
Good schedule file systems used to give quick reference as to when, and from whom,deliveries are required.
Planned deliveries utilised to ensure control of suppliers Alternate sources made available if possible Control of wastage of materials of site level optimised to ensure level kept to a minimum.
Delivery schedules monitors and adjusted accordingly
Careful checking of orders and monitoring of planned delivery dates to ensure materialsdelivered can be properly stored and unnecessary double handling avoided
Standard quality of materials maintained throughout the contract period by checkingagainst agreed samples or specifications
Subcontractors will be encouraged to minimise any wastage of materials at the first instance
in line with our Environmental Policy. Proposals for use of modular components, timber
frame, brick slips, and ready mixed mortar for example, may also help reduce wastage.
Materials delivered to site will be packaged to prevent wastage at point of use e.g. shrink
wrapping and / or palletised. Careful ordering of type and quantity together with a selected
method of offloading will further prevent material wastage on site.
Careful co-ordination of material deliveries will be necessary to avoid potential congestion
with residents traffic and the local school start and end times. It is also important to have
the correct sizing of delivery vehicles to allow materials to be received offloaded / loaded
-
7/25/2019 583 Construction Management Rev i
42/49
LAMBETH MYATTS FIELD NORTH REGENTER RESPONSE5.8.3 CONSTRUCTION MANAGEMENT
PAGE 42 OF49
REG-5.8.3-001 Construction Management Version I
within the hoarded off site boundaries. This offload / load procedure will be supervised at all
times by an appointed Banksman as per our Health and Safety Procedures.
Working Hours
Although the Rydo