A FIFA Soccer World Cup 2010 case study
Paul Inglesby,Telecoms/ICT Consultant
South Africa
Regional ITU Consultation on Conformance Assessment and
Interoperability for the Africa region (Nairobi, Kenya, 30-31 July 2010 )
Nairobi, Kenya, 30 – 31 July 2010 2
Background informationSouth Africa chosen to host the 2010 FIFA World CupSouth African Government signed contracts and provided guarantees to ensure that the event would be successfully executed The government requested Telkom to ensure that the bandwidth that was required will be available for FIFA 2010 ICT requirementsContract signed between DoC and Telkom to provide the infrastructure at the stadiums
The football challenge - building a next generation network for the World Cup 2010
Events considered in the scope of the IT Solution which required a formal operations support plan:
Preliminary Draw November 2007Confederations Cup June 2009 in selected stadiumsFinal Draw December 2009Team Workshop April 2010Referee Workshop April 2010FIFA Congress June 2010World Cup Finals 11 June through 11 July 2010 in ten stadiums
FIFA Confederation Cup and WC2010 critical timelines
Nov 2007Preliminary
Draw
Aug 2008LOC Office Operations
June 2009Confederations
CupApr 2010
World CupDec 2009
Final Draw
2008 2009 2010Jul 2009
IT&T Solution Evaluation
Apr 2010Global Integration
Testing &
Team/Referee Workshops
The communications requirement at the IBC and earmarked Stadiums for the FIFA 2010 World Cup matches can be broken up into (2) two groups:
Basic telecommunications infrastructure (WAN), andVenue distribution and access systems (LAN).
Strict rules apply to how the services should be provided, e.g.99.99% availability End-to-end service and performance management Dual homing
Communications requirement at an Earmarked stadium and the IBC only differ in scale
The FIFA combined IT&T communications requirements
Basic Communication Service required
Number of basic services required at a stadium
Number of basic communications services
required at the IBC STM-16 8 24 STM-1 11 110
E3 2 3 E1 and ISDN PRI 7 37
DSL 28 7 ISDN BRI 405 215
Analogue Telephony 12 8 IP Ports and VOIP ports ≈ 600 ≈ 2000
Example of initial network infrastructure action points/tasks/critical timelines
Estimated Timelines associated with Stadium and IBC Basic communications Infrastructure
Lo
cal In
fra
str
uctu
re a
t S
tadiu
ms a
nd
IB
C
No Further Progress possible in absence of:
Preparatory Phase
Release of FIFA Combined IT&T Communications
Specification
High Level Planning and Solution Design
Universal Communications
Services Architecture
Proposal
Finalized IBC location
Completed Telkom Carrier rooms at all venues including:
· All construction at venue to be completed
· Dual access to carrier rooms· Lockable entry· Rubbish removed· Municipal power available· Backup poweravailable
Finalized FIFA Combined IT&T Communications Specification
12 Month Process required to finalize the installation and integration of the FIFA 2010 Basic Communications solution at all earmarked Stadiums and the IBC upon completion off all venue
infrastructure i.e. handover of the last venue carrier rooms to Telkom
Detailed Network design, planning and Engineering
12 Months
Equipment Order and Delivery
Contractor Appointment
Equipment Installation
Equipment Commissioning
Site Preparation
Integration to National Network
(This step can only occur in 2009 after the
availability of the National DWDM
and ASTN Networks
Solution ready for service
1 Month 4 Months 3 Months 2 Months 2 Months
The football challenge - building a next generation network for the World Cup 2010
Example of FIFA Configuration Cup action points (Aps)
Confederations Cup Start
Satellite Earth
Station Testing of
Video
Network Operations
Centre NOC
Testing of Network
and Config of Services
NetworkEquipment
complete Installation of
Rooms at Stadiums
Mid June2009
Mid April
Mid March
End Feb2009
The football challenge - building a next generation network for the World Cup 2010
Where do you want your FIFA
2010 HD-TV feeds?
Nairobi, Kenya, 30 – 31 July 2010 8
Conformance testing and interoperability (C&I) challenges
Statement of Compliance(SOC) with standards
Always fully comply on a standalone equipment basis
Multi-vendor environmentInteroperability takes time and effort and becomes costly and delays the end-to-end services and performance testing procedures
Universal services provisioning infrastructure
Provisioning for the required video feeds are made by the dedicated NG-SDH and WDM infrastructureAny other basic communications service requirement, from Analogue telephony to High speed wireless LAN connectivity, is provided for by Telkom’s IP based NGN network.
FIFA 2010 Stadium Telkom Carrier Room
IMAX Metro Ethernet NG-SDH WDM
(ROADM)
IP Router
DSLPRIBRI
Analogue
WiMAX
GbE
EFE
RemoteCisco
CatalystSwitch
GbE
GbE
VPN
STM-1/4/16E1/E3
STM-16/64/OTN10GbE
Wireless DSL
Optical FibreLink to Telkom
Exchange10GbE
STM-64
Optical FibreLink to Second
Carrier Room
FE
Possible Services
Splice Rack Mini OMDF Test & Patch
MDF AC & IsolationRectifiers Batteries
AirconDPAM
Computer & Maintenance Area
Ethernet Frame
Spares Storage Fire Protection
FIFA 2010 Venue Telkom Carrier Room Proposal
Remote Ethernet Switch
Nairobi, Kenya, 30 – 31 July 2010 10
Conformance testing and interoperability (C&I) challenges
Interoperability challenges between IMAX (Multi-Service Access Node) and the Softswitch in a multi-domain environmentNetwork operator is expected to resolve the interoperability and systems integration issues/problemsA global C&I program which is acceptable to the entire ICT industry is required
Network Solution
National Network
Regional Network
Regional Network
Regional Network
Regional Network
Regional Network
Regional Network
Primary Telkom Regional Exchange
Regional and National networksresilience, auto restoration and manageability
ASTN Grooming Node Transparent Lambda HandoverLH DWDM Metro/RegionalDirect Fibre ConnectivityInternational LinkFIFA 2010 Stadium
SAT-2
SAT-3
SAFE
Pretoria 2
Kimberly
Durban 1
Durban 2
Nelspruit 1
SAFE
KP
PC
Upington
Melkbos Strand
CapeTown 1
CapeTown 2
Port Elizabeth 1
Port Elizabeth 2
Mtunzini
Bloemfontein 1
Bloemfontein 2
Jo’burg 1
Johannesburg 2Johannesburg 3
Pretoria 1
Rustenburg 1Rustenburg 2
Polokwane 1 Polokwane 2
Nelspruit 2
• Overhead fibre replacement to reduce “accidental” fibre/route damage & ensure network stability
• “Legacy” DWDM replacement – gearing for 10Gbit/s service capability on National Network
• Regional network enhancement – providing managed capacity & consolidated network infrastructure
• Intelligence – managed control of restoration schemes across multiple fibre routes
Telkom National Network enhancements
Nairobi, Kenya, 30 – 31 July 2010 13
Conformance testing and interoperability (C&I) challenges
Minimised C&I issues/concerns by adopting a single vendor strategy for national/regional optical fibre transport technology platform
Not the most optimum solution from a Total Cost of Ownership (TCO) CAPEX+OPEX+ all other hidden costs perspective
Dedicated DWDM Infrastructure utilised for Video Distribution
Telkom Transport Network
Telkom Services and IP Networks
Communications Architecture for FIFA 2010 – high level model
Stadium
Hotel, Press Office, Media Centre,…
High Definition Contribution Video
Voice
Fax
Internet
Voicemail
Video Conferencing
Call Forwarding
…IBC
Inte
rnat
iona
l Redundant Fibre Connectivity
Backup WirelessConnectivity
Redundant Fibre Connectivity
Backup WirelessConnectivity
Redundant Fibre Connectivity
Backup WirelessConnectivity
Telkom Current & NGN Services Networks utilised for standard Communication Services
Nairobi, Kenya, 30 – 31 July 2010 15
ConclusionSupport and adopt a global C&I program which is acceptable to all ICT role players
Ultimately need to reduce Total Cost of Ownership (TCO) with more affordable ICT services for all and in particular in developing countries
Nairobi, Kenya, 30 – 31 July 2010
Thank you for your attention