![Page 1: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/1.jpg)
Minnesota State
ACEC PresentationMay 19, 2017
Heidi Myers
System Director, Design and Construction– Facilities
![Page 2: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/2.jpg)
2
➢Background➢Project funding sources➢Designer selection methods➢Project Forecast➢Project Schedule➢Project Requirements➢Resources
AGENDA
![Page 3: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/3.jpg)
3
New name
MINNESOTA STATE
New webpage
minnstate.edu
BACKGROUND
![Page 4: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/4.jpg)
4
BACKGROUND
30 Colleges and 7 Universities54 Campuses28.5M GSF of building area
![Page 5: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/5.jpg)
5
63%GO Bond Fund
6% HEAPR
21% RevenueFund
3% GESP
7% Other
$341.5 million in major capital projects active in either design or construction as of 12/31/2016
PROJECT FUNDING
Capital Project Funding Sources
![Page 6: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/6.jpg)
6
2017 PROJECT FUNDING REQUEST
$141,916,800 GO Bond
$110,000,000 HEAPR
$251,916,800 Total
![Page 7: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/7.jpg)
7
2017 PROJECT FUNDING REQUESTGreen boxes indicate A/E selection needed
![Page 8: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/8.jpg)
8
2017 HEAPR PROJECT FUNDING REQUEST
![Page 9: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/9.jpg)
9
2017 HEAPR PROJECT FUNDING REQUEST (CONTINUED)
![Page 10: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/10.jpg)
10
2017 HEAPR PROJECT FUNDING REQUEST (CONTINUED)
![Page 11: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/11.jpg)
11
DESIGNER SELECTION METHODS
Quote
Facilities PT Master Contract
State Designer Selection Board
Public Notice
![Page 12: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/12.jpg)
12
SOLICITATION • Request by Campus Project Manager • Threshold: Under $50K
PROJECT TYPES• Typically simple projects funded with campus funds• Construction often occurs during summer
Inform campus project manager your firm is interested in work
DESIGNER SELECTION METHODS
Quote
ACTION
![Page 13: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/13.jpg)
13
PROGRAM SOLICITATION FOR MASTER CONTRACT
• New Master Contract Program
• Based on qualifications for 29 services
• To be implemented June 1, 2017
• RFQ announced in State Register for annual submission
Next occurrence early 2018
Monitor State Register
DESIGNER SELECTION METHODS
Facilities PT Master Contract
ACTION
![Page 14: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/14.jpg)
14
PROJECT SOLICITATION FOR PO (against Master Contract)
• Requested by Campus Project Manager • Threshold: Under $100K
PROJECT TYPES• Typically simple projects funded with campus or HEAPR funds• Construction often occurs during summer
DESIGNER SELECTION METHODS
Facilities PT Master Contract
ACTION Inform campus project manager your firm is interested in work
![Page 15: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/15.jpg)
15
SOLICITATION • RFP announced in State Register
• RFP materials posted on SDSB webpage
PROJECT TYPES• Required for GO Projects over $2 Million
Monitor 2017 legislative session
Monitor State Register
DESIGNER SELECTION METHODS
State Designer Selection Board
ACTION
![Page 16: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/16.jpg)
16
SOLICATIONRFP announced in State Register • RFP materials posted on Minnesota State solicitation webpage
PROJECT TYPES• Typically used for fees over $100,000• Pilot program for Campus Architect & Owner’s Rep• Campus Engineer under consideration
Monitor State Register
DESIGNER SELECTION METHODS
Public Notice
ACTION
![Page 17: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/17.jpg)
1717
PROJECT REQUIREMENTS
SWEEP
State
• State Statues https://www.revisor.mn.gov/search/
• Building Codes http://www.dli.mn.gov/ccld/codes.asp
• B3 http://www.b3mn.org/guidelines/
Minnesota
State
• Board Policies http://www.mnscu.edu/board/policy/index.html
• System Procedures
Facilities
• e-Builder https://idpstarid.mnscu.edu/idp/Authn/UserPassword
• Design Standards http://www.minnstate.edu/system/finance/facilities/design-
construction/pdf/Updated%20Design%20Standards%207th%20Edition%207.21.16.pdf
• eManual documents http://www.minnstate.edu/system/finance/facilities/design-
construction/pm_emanual/index.html
![Page 18: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/18.jpg)
1818
PROJECT SCHEDULE
SWEEP
Typical HEAPR Project
Legend
![Page 19: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/19.jpg)
1919
Contingency Funds
Construction Administration
PROJECT SCHEDULE
PreDesignFunding secured
Select & hire A/E
Final Review
Kick off Meeting
InterviewsInfoMeeting
e-Builder
Meeting with A/E
Legend
e-Builder
![Page 20: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/20.jpg)
2020
PROJECT SCHEDULE
Schematic Design
Design Development
Construction Documents
Design KickOff Meeting
Tech Review Meeting
Tech Review Meeting
Tech Review Meeting
Issue for bids
Recieve Bids & review
Award & hire
contractor
Pre-Bid Info Meeting
Bid Opening
e-Builder
e-Builder
![Page 21: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/21.jpg)
2121
PROJECT SCHEDULE
Pre-Con Construction
Pre-Con Meeting
Substantial Completion
Progress Meetings
Final Completion
Transfer Balance Warranty
Final Walk Thru
e-Builder
e-Builder
10 Month Review
e-Builder
![Page 22: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/22.jpg)
22
State Registerhttps://mn.gov/admin/bookstore/
Facilities Solicitations & Vendor Opportunitieshttp://www.minnstate.edu/system/finance/facilities/design-construction/announcements/index.html
State Designer Selection Board https://mn.gov/admin/government/construction-projects/sdsb/
Campus Facilities Contactswww.minnstate.edu/system/finance/facilities/about/staffdirectory/web-facilities-contacts-3.24.17.pdf
Please note that Minnesota State websites will soon be restructured and links will change
RESOURCES
![Page 23: ACEC Presentation96bda424cfcc34d9dd1a-0a7f10f87519dba22d2dbc6233a731e5.r41.cf2.… · ACEC Presentation May 19, 2017 Heidi Myers ... Design Kick Off Meeting Tech Review Meeting Tech](https://reader031.vdocument.in/reader031/viewer/2022022011/5b15a4757f8b9a8b288d3299/html5/thumbnails/23.jpg)
23
Facilities Design Guidelineshttp://www.minnstate.edu/system/finance/facilities/design-construction/pdf/Updated%20Design%20Standards%207th%20Edition%207.21.16.pdf
e-Builderhttps://connect.mnscu.edu/sites/ebuildervendor/SitePages/General.aspx
eManualhttp://www.minnstate.edu/system/finance/facilities/design-construction/pm_emanual/index.html
CIP Reporthttp://www.minnstate.edu/system/finance/facilities/design-construction/cip/index.html
Please note that Minnesota State websites will soon be restructured and links will change
RESOURCES