AGILE ESTIMATION & RELEASE PLANNING
Alok Guha, CSM
![Page 2: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/2.jpg)
PRODUCT BACKLOG
![Page 3: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/3.jpg)
ESTIMATE EACH ITEM (PART 1)
How long it is going to take ?
- 1 hour- 1 day- 1 week- Forever…
T1
![Page 4: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/4.jpg)
ESTIMATE EACH ITEM (PART 2)
is T2 T1Likely to take longer than
?
![Page 5: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/5.jpg)
HOW LONGER ?
=T2
?
?
?
T1 T1
T1 T1 T1
T1T1T1 T1
![Page 6: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/6.jpg)
T2 = 3 TIMES T1 ? MAY BE YES..
=T2
?
✔
?
T1 T1
T1 T1 T1
T1T1T1 T1
![Page 7: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/7.jpg)
LETS CREATE AN UNIT..
=T1 2
=T2 6
then
![Page 8: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/8.jpg)
THIS UNIT IS CALLED “STORY POINTS”
How long a user story will take (effort)
Influenced by complexity, uncertainty, risk, volume of work, etc
.Relative values are what is important: A login screen is a 2.
A search feature is an 8.
Basic math properties should hold 5+5 = 10
![Page 9: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/9.jpg)
TWO BIG ADVANTAGES TO STORY POINTS
Story points are additive, time-based estimates may not be.
Story points help avoid problems with unit confusion
![Page 10: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/10.jpg)
ESTIMATE EVERY TASK..
5
2 8
5
5
8
2
5
![Page 11: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/11.jpg)
YES, YOU SHOULD ESTIMATES EVERY TASK..
User stories will change anytime.
Everyone estimates… you, me, customer..
Points are not unit of time.
Lets be consistent than accurate.
Your estimates must include uncertainty.
Honesty is still the best policy.
![Page 12: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/12.jpg)
LETS PRIORITIZE
5
2 8
3
5
8
2
5
![Page 13: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/13.jpg)
VALUE YOUR TASKS..
5
2 8
3
5
8
2
5✪
✪✪
✪✪
✪✪
✪✪
✪ ✪✪
✪
✪✪
✪
✪✪
![Page 14: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/14.jpg)
ARRANGE
3
2 85
3
8
2 5✪
✪✪
✪✪
✪✪✪
✪
✪✪
✪
✪✪
✪
✪✪
![Page 15: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/15.jpg)
PRIORITIES…
Its very important to consider customer priorities.
And customer is the GOD, who is having final call.
Priorities changes over time.
Technical decencies are not irrelevant.
![Page 16: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/16.jpg)
PLANNING POKER
An iterative approach to estimating
Steps Each estimator is given a deck of cards, each card has a valid
estimate written on it.
Customer/Product owner reads a story and it’s discussed briefly.
Each estimator selects a card that’s his or her estimate.
Cards are turned at the same time.
Discuss differences (especially outliers).
Re-estimate until estimates converge.
![Page 17: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/17.jpg)
GENERAL RULES
Planning poker combines expert opinion, analogy, and disaggregation into an enjoyable approach to estimating that results in quick but reliable estimates.
Participants in planning poker include all of the developers on the team Planning Poker.
The product owner / business owner / business analyst participates in planning poker but does not estimate
![Page 18: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/18.jpg)
GENERAL RULES
At the start of planning poker, each estimator is given a deck of cards.
Each card has written on it one of the valid estimates 0, ½, 1, 2, 3, 5, 8, 13, 20, 40, and 100
You may also use a ? And {coffee} card Planning Poker
![Page 19: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/19.jpg)
LETS PLAY A GAME !!
![Page 20: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/20.jpg)
ESTIMATE THESE..Product backlog Items Estimate
Read and understand a densely written 5-page research paper about agile software development in an academic journal.
Your uncle owns a grocery store and now wants to sell over the internet too. Write a basic product backlog for him covering what he’ll need his website to do.
Recruit, interview, and hire a new member for your team.
Create a 60-minute presentation about agile software development for your coworkers.
Wash and wax your boss’ Volkswagen.
Read (and understand) a 150-page book on agile software development.
Write a 5-page summary of this conference for your Manager
![Page 21: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/21.jpg)
ACCESS VELOCITY
Points = Efforts involved
Duration = ?
![Page 22: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/22.jpg)
2
2
2
2
2
2
2
5
3
2
2
8
2
3
1
5
1
5
5
2
2
2
3
2
2
2
3
2
8
2
10 14 16 18 11 17
![Page 23: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/23.jpg)
VELOCITY
10 14 16 18 11 17
![Page 24: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/24.jpg)
ACCESS VELOCITY
What’s our average Velocity likely to be?
![Page 25: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/25.jpg)
ACCESS VELOCITY
Planned Velocity is useful only until we have real data - just an educated guess.
“Yesterday’s weather” is more important than average
Iterations must create production-quality increments
Velocity is specific for a team.
![Page 26: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/26.jpg)
RESOURCE SCHEDULE
Say planned velocity is 9.
Backlog points are 61.
So resource/candidate schedule will be
61/9 = 7 iterations
![Page 27: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/27.jpg)
2
2
1
2
2
8
1
5
1
1
1
1
5
1
1
2
2
2
2
2
1
5
3
1
9 9 9 11 9 9
![Page 28: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/28.jpg)
INSPECT & ADAPT
Plans are not important, Planning is.
![Page 29: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/29.jpg)
RELEASE BURNDOWN CHART
![Page 30: Aglie estimation and planning](https://reader034.vdocument.in/reader034/viewer/2022042817/55a6194d1a28abd1098b459b/html5/thumbnails/30.jpg)
CONCLUDING..
This is just a framework - there are multiple variants
The customer is a partner during estimation and planning
Don’t try to change the world, change your plans