Earned Value
An Introduction to Earned Value Performance Management
1 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
What is Earned Value?
Managers at all levels in an organisation need to know the following key information about every project
and program, especially if the work is not running according to schedule:
• How much work has actually been performed?
• How much has it cost?
• What is the estimated final cost?
• What is the expected completion date of the planned work?
This problem is illustrated in Figure 1 which shows graphical representation of a time phased work
schedule. The blue line (Budget Cost) represents the cumulative planned value for the work. Without
additional data there is no information to help manage the work.
Figure 1
Work rarely runs exactly to plan, therefore to manage, the manager needs to know how work is actually
progressing compared with the plan. Many managers have access to the actual costs that have been
incurred for their work. This is shown as a red line in Figure 2. The red line (Actual Cost) represents the
cumulative actual costs for the work done to date.
Figure 2 shows the cost of the work is running under budget. This information by itself may give the
impression that the work will be completed under budget. However, the manager has very little idea of
how much work has actually been performed. The actual expenditure may have been on tasks outside the
original scope or it may have been spent inefficiently. To overcome this problem, the manager needs a
third piece of information. This information is known as the Earned Value.
![Page 2: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/2.jpg)
Earned Value
2 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
Figure 2
Earned Value is the value of completed work expressed in terms of the budget assigned for that work. This
is shown as the green line in Figure 3.
Figure 3
Figure 3 puts the work performance in a different light. The Earned Value (green line) is below the actual
cost (red line). This means the project is spending more than was budgeted to achieve the work performed
to date (ie, the work is being performed at a loss or is ‘running over cost’). This is contrary to the impression
given in Figure 2.
![Page 3: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/3.jpg)
Earned Value
3 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
Figure 3 also shows the Earned Value (green line) is below planned value (blue line). This shows the project
is running behind schedule. This information could not have been derived from Figure 2 and demonstrates
the importance of knowing the Earned Value of the work actually performed in addition to the budget
(planned value) and actual cost.
All of the above information is hindsight. What managers also need is a reliable forecast of when the work
will be completed and how much it will cost at completion. Earned Value enables these forecasts to be
made with a reasonable degree of accuracy. When the full set of Earned Value information is available, the
manager knows how much work has actually been performed and what it has cost. Since they know from
the original budget how much work there is in total, the amount of work remaining can be calculated and
used to forecast the eventual cost and (in conjunction with the schedule) the completion date of the work.
The forecast takes into account past performance rates and is shown as a yellow line in Figure 4.
Figure 4
By using a combination of schedule information (to project the remaining time needed to complete the
project) and applying the cost performance ratio achieved to date to all unexpended budgets, a reliable
projection of the cost and time to complete the project can be established.
The basic concepts of ‘time phased budgets’ and ‘earned value’
There are three keys to success in using Earned Value Performance Measurement:
1. Work must be planned in such a way that objective measurement of achievement is possible.
2. Objective techniques must be selected in advance to measure ‘achievement’ for each piece of
work.
3. Cost, schedule and technical achievement aspects of the project should be managed in a single
integrated management system.
Setting up a project for Earned Value Performance Measurement requires:
![Page 4: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/4.jpg)
Earned Value
4 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
• A suitable decomposition of the work using a Work Breakdown Structure1
• The identification of personnel to be assigned responsibility for accomplishing the work
• The scheduling the work and assignment of resources and corresponding costs/budget to the work.
In this example, it is assumed that the
Outline, Draft and Acceptance of the
Specification are scheduled to occur in
succeeding months and are assigned a
value of $1000 each (refer Blue). This
process has established a baseline in the
form of a time phased budget for each
element of work, the Planned Value (PV).
Once approved, this becomes the
Performance Measurement Baseline
(PMB).
When the Specification is completed, it can
be said that it Earned the Value of $3000
against the plan; or more simply, ‘Earned
Value equals $3000’ (refer Green). The
actual cost of the specification is not
required in order to determine the Earned
Value (EV), EV is directly aligned to the PV.
Note, ‘Outline’ started and finished on
time; it was planned to finish in month 1
and actually finished in month 1. ‘Draft’
started on time and finished one month
late. It was planned to finish in month 2
but actually finished in month 3. ‘Review
and Acceptance’ was performed in the
time planned, but was delayed one month;
it was planned to finished in month 3 but
actually finished in month 4.
The direct costs incurred in developing the
specification are collected separately,
these are called the Actual Cost (AC - refer
Red). Actual Costs need to be accumulated
in the same time periods as the Earned
Value but are not directly related to the EV.
Actual Costs may be higher or lower than
the budget for the work being
accomplished.
As work progresses schedule and cost
variances can be measured from the plan
in dollar terms. Deviations from the plan identified, and the results reported in tables and charts.
1 For more on the WBS see: https://www.mosaicprojects.com.au/WhitePapers/WP1011_WBS.pdf
![Page 5: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/5.jpg)
Earned Value
5 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
The Effect of ‘Objective Measures2’ and Aligning Costs
The shape of the graphs in the previous section can change significantly depending on the ‘Objective
Measures’ chosen for the project or tasks. The charts in the previous section are based on the Earned Value
being achieved on a progressive basis (ie, when a task is half done, 50% of the EV is accomplished).
However, accurately assessing the status of documentation is notoriously difficult. Therefore, it would be
quite reasonable to make the objective measure for these tasks ‘100% on completion’, ie, no earned value
is achieved until the task is complete. This would mean no Earned Value is achieved during ‘Month 2’
because no task was finished during that month.
Aligning Actual Costs (AC) with Earned Value (EV)
To keep the performance reporting
accurate, the Actual Costs included in each
period (month) needs to be accumulated on
the same basis as the Earned Value.
Accumulating Actual Costs in ‘Month 2’ for
the preparation of the “Draft” would show
a large negative Cost Variance (because
there is no corresponding EV); this would be
incorrect. All of the Actual Costs for
preparing the “Draft” need to be
accumulated in Month 3, at the same time
the EV for preparing the “Draft” is
accumulated.
In addition to the fundamental need to
align AC with EV by using the same
‘Objective Measures’, two administrative
issues need to be considered on most
projects:
• Prepaid costs (eg annual insurance premiums) need to be deferred to align with the work that is
generating the EV
• Some form of “accrual” process is needed to account for costs incurred in generating the EV (ie,
doing the work) for which accounts have not been received and/or paid.
The effect of these changes is shown in the Chart above. The difference in the shape of the curves between
the two charts is the fundamental reason why it is important to establish the way EV will be calculated (the
‘Objective Measures’) before work commences on the project and for this information to be widely
communicated.
2 Objective measures for a single work package may be based on: - Discrete effort, measuring the units produced - Weighted milestones, based on the accomplishment of distinct phases of the work - Fixed formula (percentages attributed at the start and end), typically 0/100, 50/50, or 100/0 - Percent complete - ‘Apportioned effort’ or ‘level of effort’, where the work cannot be measured directly.
![Page 6: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/6.jpg)
Earned Value
6 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
Earned Value – Stages of Development
1 Decompose the Project Scope Decompose the entire project scope of work into manageable elements
using a Work Breakdown Schedule (WBS).
2 Assign Responsibility Assign responsibility for the accomplishment of each element of the
work at an appropriate management level. An Organisation Breakdown
Structure (OBS) may be used to identify the organisational hierarchy
responsible for work accomplishment. A Responsibility Assignment
Matrix (RAM) may be used to map WBS elements to the OBS elements.
3 Schedule the Work Create a schedule for all the work. Tasks are created at or below the
level of work packages in the WBS. The goal of the schedule is to provide
a vehicle for evaluating actual progress (in time) against predefined
objective measures of achievement. All tasks and milestones within the
project should be linked with dependencies to produce a logic network
that will allow the critical path, free float and total float for every task
and milestone to be calculated3.
4 Develop a Time-Phased Assign resources (and costs) to work packages or schedule tasks and
Budget establish the time-phased budget. The assigned budget value is
distributed over the activity duration based on the ‘objective measure’
and is expressed in terms of dollars, labour hours, or other measurable
units. Budgets should be assigned to all work elements (tasks or work
packages4) within a project. This time-phased budget defines the
Planned Value (PV) curve. The total budget at the completion of the
project is termed the Budget at Completion (BAC).
Once approved, the time phased representation of the total Planned
Value (PV) for all tasks (or WBS elements) becomes the Performance
Measurement Baseline (PMB). The PMB represents the formal plan for
the project manager to accomplish all of the project work in the time
allocated and within the amount of budget authorised for that work.
Generally, additional funds are set aside as a Management Reserve (or
contingency) for any unanticipated tasks that are within the scope of the
project.
The total budget for resources assigned to the project is required to
equal the Budget At Completion (BAC) of the Performance
Measurement Baseline. The budget at completion plus management
reserve should equal the Project Budget (PB).
5 Assign Objective Measures The accomplishment of tasks is ultimately expressed in terms of their
of Performance budgetary values (Earned Value). Objective measures of performance,
are used to quantify the degree of completion of tasks or work packages
in progress. These measures of performance should be established in
such a way that they correctly measure accomplishment of progress.
3 For more on good scheduling practice see: https://mosaicprojects.com.au/PMKI-SCH-010.php
4 In many situations, cost and EV are more efficiently managed at the work package level. Whereas the scheduling of work and the use of resources required a more detailed schedule. Integration between the two systems is essential.
![Page 7: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/7.jpg)
Earned Value
7 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
The measuring of Earned Value should be computed using the same
methodology as the original plan (budget).
6 Set the Performance The Work Breakdown Structure, the Schedule, the Budget for each task
Measurement Baseline and WBS element and the time-phased budget as developed in steps 1-5
shall be approved by the Project Manager or higher authority and
recorded as the Performance Measurement Baseline (PMB). This
baseline provides the reference points against which actual project
progress is compared, it should include the best estimates for task
duration, scheduling, resource allocation, costs, and the other project
variables required to be monitored.
To be valid a baseline, it should not only be logically constructed but it
should make sense when compared to available project resources. A
quick way to judge this is to plot an S-Curve. Observing the steepness of
the S-Curve can indicate if the baseline is feasible.
7 Perform the Work Formally authorise the work to be undertaken and perform the
authorised work. For the Project Manager to exercise proper control of
the project, the chain of authorisation for the commencement of work
should emanate from the Project Manager either directly or indirectly.
Each work authorisation should clearly identify:
• What is to be done
• Who is to do it
• When it is to be done
• The quantity of resources budgeted
• Who is the person responsible for acceptance of the work
• How progress and actual costs are to be measured and aggregated.
8 Accumulate and Report Record and accumulate schedule progress, earned value and actual cost
Performance Data for each element on a consistent and periodic basis. The Planned Value,
Earned Value, Actual Costs, Budget at Completion and Estimate to
Complete are calculated and logically summarised through the project
decomposition (WBS) to properly represent the status of the individual
tasks and the project in total. In addition, the current schedule needs to
be progressed to show achievement and to provide forecast completion
dates for the scheduled work.
The Earned Value (EV) is compared with the Planned Value (PV) to
establish the Schedule Variance (SV).
All costs actually incurred in the performance of the work (AC) should be
accumulated at a level which will identify the cost elements and factors
contributing to cost variances. The Actual Costs (AC) is compared with
the Earned Value (EV) to establish the Cost Variance (CV).
Forecasts at completion both in terms of cost and schedule are made for
comparison with current period status information and performance
Reports are distributed to appropriate management levels on a
consistent and periodic basis.
![Page 8: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/8.jpg)
Earned Value
8 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
9 Analyse Performance Identify and analyse variances from the Performance Measurement
Baseline (PMB).
Earned Values (EV) for tasks, elements, and totals are compared with
the corresponding Planned Value (PV) to identify any variance between
the amount of work accomplished and the amount of work scheduled.
The progressed (current) schedule is compared with the baseline
schedule to determine slippages and forecast completion dates.
Earned Value (EV) for tasks and work elements is compared with the
corresponding Actual Cost (AC) to determine the Cost Variance (CV).
Cost and schedule variances should be evaluated to determine their
cause and the likely impact on the project.
Estimates of the costs at completion should be routinely developed and
updated based on past trends and current knowledge and compared
with the corresponding Budget At Completion (BAC) to identify the
extent of the cost Variance at Completion (VAC). Forecasts of the
scheduled completion should also be routinely developed and updated
based on past trends and current knowledge for comparison with the
planned completion dates5.
10 Management Action Take management action to compensate for past deviations or to rectify
projected deviations from the Performance Measurement Baseline. The
required corrective action should be determined based on the source
and cause of the variance.
Variances may have several dimensions. They may arise from poor
planning, unforeseen scope changes, technical problems, equipment
failures or other exogenous factors such as supplier difficulties.
Regardless of the cause, corrective actions require either a change in the
baseline planning or the development of a short-term get-well plan that
is incorporated in the forecasts. In either case, revisions to planning
should only be accomplished prospectively. Retroactive changes to cost,
schedule or technical planning or accomplishment should not be allowed
other than to correct administrative or typographical errors.
11 Baseline Maintenance Changes to the Performance Measurement Baseline can originate either
internally through the identification of unforeseen scope changes or
resource requirements or where changes have been directed by other
stakeholders. Where there have been changes to the project, it will be
necessary to replan certain elements of the work. Due to the importance
of maintaining a valid baseline for performance measurement,
replanning should be accomplished:
• With proper authority
• In a systematic and timely manner
5 The various formulae used to calculate the EV metrics are details below, and in: https://mosaicprojects.com.au/WhitePapers/WP1081_Earned_Value.pdf
![Page 9: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/9.jpg)
Earned Value
9 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
• Should be carefully controlled, and
• Adequately and visibly documented.
Replanning should not be used as an alternative to proper initial
planning, nor should it be used to mask legitimate variances.
Maintenance of the Performance Measurement Baseline is required to
ensure that baseline changes are properly recorded and visible and can
be examined to determine their causes and potential impact on
completion dates and costs. In order to maintain the integrity of the
Performance Measurement Baseline the project manager should not
transfer scope or budgets independently of one another.
Earned Value Presentation, Definitions & Calculation
The S-Curve Charts are derived
from tabulated project data and a
defined set of formulae6.
Basic EV Data
Planned Value (PV) Otherwise called Planned Budget or (now outdated term) Budgeted Cost of
Work Scheduled (BCWS). The authorised budget for the project work
6 For more on Earned Value Formulae see: https://mosaicprojects.com.au/WhitePapers/WP1081_Earned_Value.pdf
![Page 10: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/10.jpg)
Earned Value
10 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
scheduled. Distributed over time (cumulative) using the Performance
Measurements Baseline (PMB) schedule to generate the baseline S-Curve.
Earned Value (EV) Otherwise called (now outdated term) Budgeted Cost of Work Performed
(BCWP). The authorised budget for the project work actually accomplished
based on the values in the PMB.
EV is calculated by applying the agreed performance measures to tasks in
progress. EV is 0% for tasks not started and 100% for tasks that are
completed.
Actual Cost (AC) Otherwise called (now outdated term) Actual Cost of Work Performed
(ACWP). The actual cost of work performed as recorded in the organisations
cost accounts. It is important that the actual costs are gathered “as at” the
same date as the Earned Value data and are the total authorised costs
incurred at that date.
Budget At Completion (BAC) The total authorised budget for accomplishing the scope of work as
documented in the PMB. (Management Reserve is not included.) BAC can
refer to a task, an element of the WBS (at any level) or the whole project.
Estimate At Completion (EAC) The estimated total cost to complete the project’s scope. It is the Actual
Cost to Date + Estimate To Complete. EAC can refer to a Task, an element of
the WBS (at any level) or the whole project.
Estimate To Complete (ETC) Otherwise called Forecast Cost. The anticipated cost to complete all
unfinished work on the project. This can simply be the unexpended budget
(ie BAC - EV) or the unexpended budget adjusted by a factor to allow for
trends experienced to date (see IEAC).
Independent Estimate IEAC is a cost estimate generated by an independent process to calculate an
At Complete (IEAC) adjusted completion cost based on trends to date. Options for calculating
the IEAC include:
Assuming future cost performance will be the same as the past
IEAC = ACWP + (BAC-EV) = BAC
CPI CPI
Assuming future cost performance will be influenced by factors of 80% past
cost and 20% past schedule performance
IEAC = ACWP + ( BAC - EV ) .
0.8 x CPI + 0.2 x SPI
Assuming future cost performance will be influenced by the last 3 months
cost performance
IEAC = ACWP + 3 x (BAC - BCWP)
CPI1+ CPI2+ CPI3
Assuming future cost performance will be influenced by past cost and
schedule performance
IEAC = ACWP + (BAC - BCWP)
CPI x SPI
Simply repricing (Re-estimating) the incomplete portion of the project’s
work is NOT an acceptable option for EV calculations.
![Page 11: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/11.jpg)
Earned Value
11 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
EV Variances
Cost Variance (CV) The value of work performed less the cost of performing the work.
CV = EV - AC
Illustration: Developing the detailed design has a budgeted value of $20
000. The job is now complete (100%), therefore the EV is $20 000. The
designer has invoiced $19 500 for the whole of the work (AC = $19 500, It
does not matter if the invoice has actually been paid yet, the costs have
been incurred).
The Cost Variance is: CV = $20 000 - $19 500 = +$500
Note: to calculate the cost performance during a particular period, it is not
necessary to know how much work was originally planned to be achieved in
that period.
Schedule Variance (SV) The difference between the value of work planned to be completed in a
period and the value of work actually completed in the period (measured in
PMB units).
To measure schedule performance during a specific period, the value of the
work planned to be achieved during that period must be known, ie, the
Planned Value (PV). Then schedule performance is determined by
comparing Earned Value (EV) with Planned Value (PV). Any difference is
referred to as a Schedule Variance (SV).
SV = EV - PV
Illustration: $20 000 worth of work was scheduled for the month of January
(PV = $20 000). For whatever reason, only $18 000 worth of work was
achieved (EV = $18 000).
Then: SV(January) = $18 000 - $20 000 = -$2 000
Note: in order to calculate the schedule performance during a particular
period, it is not necessary to know the cost of the work achieved (AC) only
the budgeted cost for that work (from the PMB).
Note also that Earned Value data does not give a direct expression of days
ahead or behind schedule. The schedule variance is expressed in terms of
value of the work. Either an update (or status) of the project schedule is
necessary to relate this to a calendar, or the use of Earned Schedule7 to
predict the overall delay is required.
Understanding the nature of the work causing the SV is important. For
example, a negative SV due to nonreceipt of material might be recovered
very quickly (the material is delivered); while a similar negative SV due to
loss of production due to weather is unlikely to be recovered without
management intervention. A negative SV indicates the project is behind
schedule, the quantum of the slippage can only be accurately determined
analysing actual progress data on the project schedule.
Lastly, note that Earned Value (EV) is essential to derive cost and schedule
7 For more on Earned Schedule see: https://www.mosaicprojects.com.au/Mag_Articles/N003_Earned_Schedule.pdf
![Page 12: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/12.jpg)
Earned Value
12 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
performance: the other two elements – Planned Value (PV) and Actual Cost
(AC) render no useful performance information without Earned Value.
EV Performance Indices
Cost Performance Index (CPI) The cost efficiency ratio of Earned Value (EV) to Actual Costs (AC) over a
specified period. A value greater than 1 indicates the work is being
performed in a more cost-effective way than planned. A value less than 1
indicates actual costs are higher than the budgeted allowance for the work
performed.
CPI = EV
AC
Schedule Performance Index The schedule efficiency ratio of Earned Value (EV) to Planned Value (PV)
(SPI) over a specified period. A value greater than 1 indicates more work is being
performed than planned. A value less than 1 indicates less work is being
performed than planned (ie, the project is behind schedule).
SPI = EV
PV
Cost Variance % (CV%) The Cost Variance expressed as a percentage of Earned Value.
CV% = CV x 100
EV
Schedule Variance % (SV%) The Schedule Variance expressed as a percentage of Planned Value.
SV% = EV x 100
PV
Interpreting EV Data
Note - EV does not have to be
measured in $
A typical EV Chart (S-Curves)
produced by most competent
software packages encapsulates a
vast amount of data to provide
management with a complete
overview of the project. A vertical
dashed line positioned at the date
of the last update separates actual
data input by the project team from
forecast data
![Page 13: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/13.jpg)
Earned Value
13 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
Overall Project Completion Data
The vertical line positioned at the date of the
last update separates actual data input by
the project team from forecast data. The
blue line plots the original planned
expenditure on the project from its start to
its original projected end date (Planned
Value or PV). The red line plots the actual
expenditure to date, and the yellow line the
expenditure required to complete the
unfinished portion of the project. Traditional
Earned Value can predict the cost overrun (or
underrun), the forecast delay has to be based
on information contained in the schedule, of
from Earned Schedule calculations.
The horizontal difference between the end of
the blue line and the end of the yellow line is the slippage (gain or loss) between the current expected
completion date for the project and the original planned date.
Current Performance Data
Information at ‘Time Now’ compares the
amount of work accomplished compared
to the plan (SV or SPI) and the cost of
completing that work compared to the
estimate (CV or CPI)
These two variances result in nine
possible scenarios with varying degrees of
magnitude in both dimensions. The
‘ahead of schedule, under budget’ and
‘behind schedule, over budget’ options
are shown below.
![Page 14: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/14.jpg)
Earned Value
14 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
Note: in both of these graphs, the ‘actual cost’ is about the same, what differs is the amount of work
accomplished as measured by the Earned Value (blue line in these charts).
The complete picture is a comprehensive status of the project. Research suggests the cost performance
information is more reliable than any other predictive method from around the 20% complete stage of the
project, improving in accuracy as more work is accomplished. Using Earned Schedule, a similar level of
accuracy is derived for the forecast completion date.
_____________________________
![Page 15: An Introduction to Earned Value Performance Management...This problem is illustrated in Figure 1 which shows graphical representation of a time phased work schedule. The blue line](https://reader036.vdocument.in/reader036/viewer/2022090611/60759fc7f932647a8d0ad1d0/html5/thumbnails/15.jpg)
Earned Value
15 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more papers in this series see: https://mosaicprojects.com.au/PMKI.php
Downloaded from Mosaic’s PMKI Free Library.
For more papers focused on Earned Value see: https://mosaicprojects.com.au/PMKI-SCH-040.php Or visit our PMKI home page at: https://mosaicprojects.com.au/PMKI.php
Creative Commons Attribution 3.0 Unported License.