Download - Arboricultural Method Statement
-
8/4/2019 Arboricultural Method Statement
1/13
- 1 -
Judith Moore 18-11-10
Arboricultural Method Statement
Revision - Preliminary
Site 63 Manor Road, Chigwell, Essex, IG7 5HP
Client Mr Imran UmraniContact Mr Imran Umrani, 59 Manor Road, Chigwell, Essex
07956 360331
To be read in conjunction with Tree Constraint Plan Drawing No. IU/MR01Tree Protection Plan Drawing No. IU/MR/03BS5937:2005 Tree Report, 63 Manor Rd, Rev A
Prepared by J M Moore B.Sc (hort) Tech Cert (Arbor A) M.Arbor.A
J M MOOREHope Cottage
40 Scotts Hill
Southminster
Essex CM0 7BG
Tel - 01621 772586
Mob - 07912 617939Email - [email protected]
-
8/4/2019 Arboricultural Method Statement
2/13
- 2 -
Judith Moore 18-11-10
Contents
1 Statement of Purpose
2- Arboricultural Impact Assessment
3 Sequence of events
4 Communication and Supervision
5 Works to existing trees
6 Protective Fencing
7 Additional Ground Protection for access
8 Storage
9 - Demolition
10 Ground levels
11 Pile and beams construction
12 Services and Rain Water Harvester
13 Removal of existing drive
14 Construction of new drive
15 Front boundary
16 Soft landscaping
17 General site care
Appendix 1 Protective fence detailAppendix 2 Ground protection
-
8/4/2019 Arboricultural Method Statement
3/13
- 3 -
Judith Moore 18-11-10
1 Statement of Purpose
1.1 This Method Statement has been written for Mr Umrani, tosatisfy the requirements of the Local Planning Authority (LPA).They have requested an arboricultural method statement, forconsideration in the discharge of conditions of the planningapproval.
1.2 The purpose of the method statement is to minimise the impactof the development and provide an adequate level of protectionfor the existing trees.
2 Arboricultural Impact Assessment2.1 Details of all trees can be found in appendix 1 of BS5837:2005
Trees in relation to construction report for 63 Manor Rd Rev A2.2 The location of all the trees are shown on drawing number
IU/MR/01 Tree constraints plan. The Root Protection area of alltrees to be retained is also shown.
Treeno.&class.
RPAm/sq
RadiofRPA(M)
Tree implicationsassessment
Mitigation to consider
T1
B
OakQuercus robur
127 6.36 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by thedevelopment
T2
B
OakQuercus robur
136 6.6 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by thedevelopment
T3
B
OakQuercus robur
240 8.76 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by thedevelopment
T4
B
OakQuercus robur
132 6.5 The development works areoutside the RPA (rootprotection area) and crown
spread
If the tree is protected inline with BS5837:2005,section 9, it should not be
affected by thedevelopment
T5
B
OakQuercus robur
234 8.6 CrownAccess to the site will be alongthe existing drive, below thecrown spread of T5
RootsThe existing drive, within thecrown spread, will be replaced
CrownRaise the crown on thesouth side by 2.5-3m to 5mabove ground level, toavoid accidental damage tocrown.
RootsDrive way to be constructedas detailed in theArboricultural method
statement (AMS)T6 Cherry Fell due to condition
-
8/4/2019 Arboricultural Method Statement
4/13
- 4 -
Judith Moore 18-11-10
RPrunus spp
T7
B
Cuppressusmacrocarpa
489 12.48 RootsThe existing drive within thecrown spread will be replacedand an area of new driveconstructed.
RootsDrive way to be constructedas detailed in theArboricultural method
statement (AMS)T8
R
CypressesCuppressusmacrocarpa
Fell due to condition
T9
C
Goat willowSalix caprea
8.2 1.6 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by thedevelopment
T10
C
CypressesCuppressusmacrocarpa
14.6 2.16 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by the
developmentT11
C
CypressesCuppressusmacrocarpa
65 4.5 RootsAn area of new drive will beconstructed within the RPA
RootsDrive way to be constructedas detailed in theArboricultural methodstatement (AMS)
T12
R
OakQuercus robur
Fell due to condition Plant a replacement tree
T13
R
CypressesCuppressusmacrocarpa
Fell due to condition
T14
B-C
OakQuercus robur
215 8.3 CrownThe existing building will needto be demolished on theperiphery of the Crown spreadThe new build is outside thecrown spread
RootsThe existing building will needto be demolished within theRPAThe new build will be within theRPA
RootsDemolition should be in linewith the AMSThe new building should beconstructed with a piledfoundation, to avoid therequirement for trenchfootings within the RPA.
T15
B
OakQuercus robur
152 6.9 CrownAccess to the site will be alongthe existing drive, below thecrown spread of T5
RootsThe existing drive within thecrown spread will be replaced
CrownRaise the crown on thesouth side by 2.5-3m to 5mabove ground level, toavoid accidental damage tocrown.
RootsDrive way to be constructedas detailed in theArboricultural methodstatement (AMS) Remove
the section of drive to thewithin the northern sector ofthe RPA.
-
8/4/2019 Arboricultural Method Statement
5/13
- 5 -
Judith Moore 18-11-10
T16
C
Purple leaved plumPrunus pissardii
41.8 3.65 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by thedevelopment
T17
B-C
Hornbeam
Carpinus betulus
91.6 5.4 The proposed house is outside
the RPA.
If the tree is protected in
line with BS5837:2005,section 9, it should not beaffected by thedevelopmentAdditional groundprotection will be required,for access to the sideelevation of the houseduring construction.
T18
B
OakQuercus robur
113 6 The proposed house isperipheral but outside theRPA.
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by the
developmentAdditional groundprotection will be required,for access to the sideelevation of the houseduring construction.Change the length ofgarden wall shown on thedrawing to fence, to negatethe need to excavate atrench footing through theroot area.
T19 Pear
Pyrus comunis
Fell to facilitate the
developmentT20 Pear
Pyrus comunis
Fell to facilitate thedevelopment
T21
C
AppleMalus domestica
84 5.2 Fell to facilitate thedevelopment
T22
B
Hornbeam 104 5.76 RootsThe existing building will needto be demolished within theRPAThe new build will be within theRPAThere is the potential for the
loss of approximately 9 m sqor 9% of the RPA.
RootsDemolition should be in linewith the AMSThe new building should beconstructed with a piledfoundation, to avoid therequirement for trenchfootings within the RPA.Additional groundprotection will be required,for access to the sideelevation of the houseduring construction, toreduce the area of RPA thatcould be lost.
G1
C
3x hornbeamcarpinus betulus
9 1.6 CrownThe crown of the trees will beclose to the proposedswimming pool room
CrownReduce back the crown onthe south west side by 2m,to reduce the potential foraccidental damage. Thetrees are young and wouldbe expected to recover
-
8/4/2019 Arboricultural Method Statement
6/13
- 6 -
Judith Moore 18-11-10
from any punning.
T23
R
AppleMalus domestica
Fell due to condition
T24
B
HornbeamCarpinus betulus
91 5.4 RootsThe new build will be within the
RPAThere is the potential for theloss of approximately 5 m sqor 5% of the RPA.
RootsThe new building should beconstructed with a piledfoundation to avoid therequirement fro trenchfootings within the RPA.Additional groundprotection will be required,for access to the sideelevation of the houseduring construction, toreduce the area of RPA thatcould be lost.
T25
R
AppleMalus domestica
Fell due to condition
T26
R
AppleMalus domestica
Fell due to condition
T27
C
AppleMalus domestica
24 2.76 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by thedevelopment
T28
C
Cherry plumPrunus cerasifera
60 4.4 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not be
affected by thedevelopment
T29
R
AppleMalus domestica
Fell due to condition
T30
B
OakQuercus robur
140 6.7 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by thedevelopment
T31
B
OakQuercus robur
165 7.3 The swimming pool will be inthe RPA and result in the lossof around 20% of the root area
Fell, to facilitate thedevelopment.Plant replacement semi
mature tree of samespecies.
T32
B
OakQuercus robur
160 7.14 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by thedevelopment
T33
B
HornbeamCarpinus betulus
117 6.12 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by thedevelopment
T34
B-C
Oak
Quercus robur
196 7.9 The development works are
outside the RPA (rootprotection area) and crownspread
If the tree is protected in
line with BS5837:2005,section 9, it should not be
-
8/4/2019 Arboricultural Method Statement
7/13
- 7 -
Judith Moore 18-11-10
affected by thedevelopment
T35
B
OakQuercus robur
179 7.56 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by the
developmentT36
B
CypressesCuppressusmacrocarpa
32 3.18 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by thedevelopment
T37
B
CypressesCuppressusmacrocarpa
91 5.4 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by thedevelopment
T38
171
CypressesCuppressus
macrocarpa
171 7.4 The development works areoutside the RPA (root
protection area) and crownspread
If the tree is protected inline with BS5837:2005,
section 9, it should not beaffected by thedevelopment
T39
R
OakQuercus robur
Fell due to condition Plant a replacement tree
T40
B
HornbeamCarpinus betulus
109 5.9 The development works areoutside the RPA (rootprotection area) and crownspread
If the tree is protected inline with BS5837:2005,section 9, it should not beaffected by thedevelopment
3 Sequence of Events3.1 Pre- commencement site Meeting3.2 Tree Works and tree removal3.3 Erect permanent tree protection fencing3.4 Installation of additional ground protection3.5 Demolition3.6 Construction of the building3.7 Installation of services3.8 Hard landscaping works3.9 Removal of protective fencing around all other trees
3.10 Soft landscape works
4 Communication and Supervision4.1 Prior to commencement of works, a site meeting between all
relevant parties should take place, to clarify responsibilities andparticular site issues. This meeting should include, but is notlimited to, arboricultural consultant, site manager, tree surgeon,engineer and if applicable the Councils Arboricultural Officer.
4.2 If changes should arise the site manager will inform thearboricultural consultant who will assess the situation and make
the appropriate recommendations. The consultant will liaise with
-
8/4/2019 Arboricultural Method Statement
8/13
- 8 -
Judith Moore 18-11-10
and advise the LPA if changes to the method statement arerequired.
4.3 A copy of the method statement will be retained on site and thesite manager will be responsible for ensuring operatives adhereto the methodologies.
5 Removal andworks to existing trees5.1 Trees to be removed.
Due to condition T6, T8, T13, T12, T23, T25, T26 and T36To facilitate the development T19, T20, T21 and T31Trees are to be felled inline with BS3998 and roots are to beremoved using a stump grinder, if they need to be removed.
5.2 Works to existing treesT5 OakRaise the crown on the western side, over the driveway, to aheight of 4m. This will allow access for construction vehicles. Allthe branches are to be cut back to appropriate pruning points.T15 OakRaise the crown on the western side, over the driveway, to aheight of 4m. This will allow access for construction vehicles. Allthe branches are to be cut back to appropriate pruning pointsT18 OakReduce back secondary growth on the south western side of thecrown by 1.5m. This should provide adequate clearance for thescaffold, and reduce the potential for accidental damage to the
crown during the construction process.T22 HornbeamReduce back secondary growth on the south western side of thecrown by 1.5m. This should provide adequate clearance for thescaffold, and reduce the potential for accidental damage to thecrown during the construction process.
Any pruning works required will be carried out by a competentarborist, in line with BS3998:1989
6 Protective Fencing6.1 All trees to be retained will be protected by a total exclusion
zone, the boundaries of which will be defined by protectivefencing. This is to be carried out prior to the developercommencing on site
6.2 The fencing is to be set out in line with drawing numberIU/MR/03, tree protection plan.
6.3 The fencing is to be of 1.8m steel mesh, wired to a framework ofsteel scaffold poles as detailed in BS5837:2005 section 9.3figure 3. (See appendix 1)
6.4 Once erected, the fencing will have all weather notices attached
to the barrier worded Construction Exclusion Zone Keep out6.5 There is to be no access within the protected area, with the
-
8/4/2019 Arboricultural Method Statement
9/13
- 9 -
Judith Moore 18-11-10
6.6 The fencing will not be removed until all construction of buildingsand hard surfaces are complete
7 Additional ground protectionsee also drawing number LSI/HG/02
7.1 The area between the eastern wall of the proposed house andtrees, number T17, T18, T22, G1 and T24, will require additionalground protection, for the area that lies within the RPA of thesetrees. For pedestrian access this should be protected with geo-textile, laid over the existing soil level. Over this should be laidabutting scaffold boards, to reduce potential ground compactionfrom pedestrian access, in line with BS5837:2005 section 9figure 3. Scaffold will be required to be erected over this area,adjacent to the outside of the tree protection fencing.
7.2 However, this will also be a main access to the rear of thebuilding during the construction process and, if wheeled ortracked vehicle access is required, the ground protection willneed to be designed by an engineer, to take into considerationthe potential loading of the area.
7.3 An area, between the flank wall of the western wing of the houseand the protective fence around T14, will require additionalground protection, as above, within the RPA of T14.
8 Storage of Materials8.1 There will be adequate room for the storage of material, both to
the front and rear of the property, without encroaching into theRoot Protection Areas
9 Demolition9.1 The buildings will be demolished, where possible, into the
existing foot print of the buildings. Particular care will need to beimplemented when demolishing the main building, adjacent toT14, where the building is close to the periphery of the crown ofthe tree. Netting should be fixed to the outside of the scaffoldsection, running through the crown spread of T14, to minimise
the potential for damage to the trunk from debris.9.2 The western section of the building, within the RPA of T14, will
be demolished to a depth of 250mm below existing ground level.The area above this, out side the foot print of the new building,will be made up with good quality topsoil, to provide asatisfactory rooting environment for T14.
10 Ground levels10.1 For the majority of the root protection areas, ground levels will
not be changed. The exception is the area within the RPA of
trees T5, T7 and T15, where the new driveway will beconstructed. See section 14 and 15 of this document.
-
8/4/2019 Arboricultural Method Statement
10/13
- 10 -
Judith Moore 18-11-10
11 Pile and beam construction.11.1 The foundations for the eastern wall of the extension, are to be a
pile and beam construction as detailed by the structuralengineer. This will negate the need for a trench footing within
the RPA of T14.11.2 The foot print of the new house is outside the crown spread of
all the retained trees.11.3 The pile machine will be the smallest practicable machine, to
access the site under the crowns of T5 and T15. It should be atracked vehicle, to reduce ground pressure, and is not toencroach within the protected RPA area.
11.4 Pile and beam will negate the need to excavate deep trenchfootings at this close proximity to tree T14. The maximumexcavation will be 300mm for the ground beam.
12 Service Trenches and Rain Water Harvester12.1 A rain water harvester will be installed, out side the RPA of any
tree. However, if any of the access pipes encroach into the RPAof a tree, the excavation must comply with the following.
12.2 The exact service runs are not known at the time of thisstatement. Again, if there is the need for access into any existingservice runs that are within the RPA of any tree, it must complywith the following.
12.3 The drain will be carefully excavated by hand. Any roots over50mm, which can practically be retained and dug under, will be
retained and protected by wrapping in damp Hessian. Any rootsover 25mm in diameter, which can not be preserved, will bepruned cleanly with a sharp saw or seceteurs by a suitablyqualified person. Exposed roots will be covered with dampHessian and sharp sand.
12.4 The drains will be plastic pipe work, with the minimum possiblenumber of connections within the RPA. The trench will be linedwith a root barrier, to reduce the potential for root encroachmentinto the drains. This will be a proprietary flexible barrier, such asthe Terram root guard or Greenleaf Reroot materials, or similar,installed inline with the manufacturers specification.
13 Removal of existing driveway13.1 The existing driveway is higher than the surrounding soft
landscape areas. Removal of the existing drive way hardsurfacing, within the RPA of T5, T7, T14 and T15, will be carriedout using hand tools only.
13.2 Excavations will extend no deeper than the existing depth of subbase. A hand held pneumatic breaker will be used to break upthe surface. All spoil will be removed from the area in wheelbarrows along scaffold boards, to avoid unnecessary ground
compaction.
-
8/4/2019 Arboricultural Method Statement
11/13
- 11 -
Judith Moore 18-11-10
13.3 Any roots over 25mm in diameter will be pruned cleanly with asharp saw or secutuers by a suitable, qualified person. Exposedroots will be covered with damp Hessian and sharp sand, untilthe new base is laid.
14 Construction of new Driveway14.1 The new drive way will encroach into the RPA of T5, T15, T7
and T14. It will be a no dig construction, with a porous surfacetreatment.
14.2 For the areas that are existing grass, existing ground vegetationwill be killed using a translocated, glyphosate based herbicide.The dead vegetation will be removed by hand.
14.3 The drive will be laid on a geo-grid base, backfilled with MOTtype 1, with no fines or similar. This should not be tipped on tothe grid but spread from one end, by hand. The surfacetreatment should be a porous tarmac or block paving, designedby an engineer to meet loading requirements.
14.4 All edging for these areas should be tanilised timber edging,secured with wooden stakes, as concrete kerb edgings wouldrequire damaging excavations into the root area.
15 Front boundary15.1 The front boundary is to be railings, supported on brick piers.
The footings for the piers will be dug within the RPA of the trees,along the front boundary with Manor Road.
15.2 The footings for the piers will be hand dug, to minimise the
damage to the root area.
16 Proposed Landscape Works16.1 Cultivation under the crown spread of protected trees is to be
carried out by hand only, and care paid not to damage existingroots. No mechanical cultivation is to be permitted within the rootprotection areas.
16.2 There is to be no change in soil levels within the RPA of theretained trees.
16.3 New 18-20cm extra heavy standard oak trees (quercus robur)
will be planted as replacements for T14, T31 and T36. They willbe planted in the locations shown on landscape drawing numberIU/MR/02.
17 General Site Care17.1 Site offices will not be located within 3m of the protective fencing17.2 No materials will be stored within 2m of the protective fencing17.3 No transferring of fuels will be permitted within 5m of the
protective fencing.17.4 No fires are permitted within 2m of the protectivefencing.
-
8/4/2019 Arboricultural Method Statement
12/13
-12-
Judith
Moore
18-11-10
Appendix1Treeprotectionfencing
-
8/4/2019 Arboricultural Method Statement
13/13
-13-
Judith
Moore
18-11-10
Appendix2Groundprote
ctionforpedestrianac
cess