Assigning Setup Times to Resources
Trigger:
Concept
You can create a performance model for machine and resource setups to include time from one
setup to another, including the time required to perform the work. If one of your scheduling
objectives is to sequence or group jobs based on their required setup, you can also include a
penalty factor in the scheduling calculation.
Any two setup types within a resource can have a transition time and a transition penalty, which
means that the scheduler needs the specified time for transition from the former setup to the latter.
In this topic, you will assign setup times to resources.
Required Field(s) Comments
Output - Result(s) Comments
Additional Information
Last changed on: 1/18/2010 09:35:00 AM Page 1
-
8/14/2019 Assigning Setup Times to Resources_SPD
2/29
System Process DocumentAssigning Setup Times to Resources
Procedure
Step Action
1. Begin by navigating to the Resources page.
Click the vertical scrollbar.
Page 2 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
3/29
System Process DocumentAssigning Setup Times to Resources
Step Action
2. Click the Manufacturing and Distribution Manager link.
Last changed on: 1/18/2010 09:35:00 AM Page 3
-
8/14/2019 Assigning Setup Times to Resources_SPD
4/29
System Process DocumentAssigning Setup Times to Resources
Step Action
3. Click the vertical scrollbar.
Step Action
4. Click the Resources link.
Page 4 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
5/29
System Process DocumentAssigning Setup Times to Resources
Step Action
5. Use the Organizations page to select your organization.
Last changed on: 1/18/2010 09:35:00 AM Page 5
-
8/14/2019 Assigning Setup Times to Resources_SPD
6/29
System Process DocumentAssigning Setup Times to Resources
Step Action
6. Click the M1 Seattle Manufacturing list item.
Step Action
7. Click the OKbutton.
orPress [Alt+O].
Page 6 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
7/29
System Process DocumentAssigning Setup Times to Resources
Step Action
8. Use the Resources page to find the resource that you had already defined.
Last changed on: 1/18/2010 09:35:00 AM Page 7
-
8/14/2019 Assigning Setup Times to Resources_SPD
8/29
System Process DocumentAssigning Setup Times to Resources
Step Action
9. Click in the Resource field.
Step Action
10. Press [F11].
Page 8 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
9/29
System Process DocumentAssigning Setup Times to Resources
Step Action
11. Enter the desired information into the Resource field. Enter "CDMOLD".
Last changed on: 1/18/2010 09:35:00 AM Page 9
-
8/14/2019 Assigning Setup Times to Resources_SPD
10/29
System Process DocumentAssigning Setup Times to Resources
Step Action
12. Press [Ctrl+F11].
Step Action
13. Click the Setups button.
Page 10 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
11/29
System Process DocumentAssigning Setup Times to Resources
Step Action
14. Use the Setups page to select the setups for which you want to define changeovers.
Use the arrow button to move the setup from the Available column to the Selectedcolumn.
Use the double arrow button to move all setups from the Available column to the
Selected column.
Last changed on: 1/18/2010 09:35:00 AM Page 11
-
8/14/2019 Assigning Setup Times to Resources_SPD
12/29
System Process DocumentAssigning Setup Times to Resources
Step Action
15. Click the CM66711 list item.
Page 12 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
13/29
System Process DocumentAssigning Setup Times to Resources
Step Action
16. Click the > button.
Step Action
17. Click the CM66712 list item.
Last changed on: 1/18/2010 09:35:00 AM Page 13
-
8/14/2019 Assigning Setup Times to Resources_SPD
14/29
System Process DocumentAssigning Setup Times to Resources
Step Action
18. Click the > button.
Page 14 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
15/29
System Process DocumentAssigning Setup Times to Resources
Step Action
19. Click the CM66713 list item.
Step Action
20. Click the > button.
Last changed on: 1/18/2010 09:35:00 AM Page 15
-
8/14/2019 Assigning Setup Times to Resources_SPD
16/29
System Process DocumentAssigning Setup Times to Resources
Step Action
21. Click the Save button.
Page 16 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
17/29
System Process DocumentAssigning Setup Times to Resources
Step Action
22. Click the Changeovers button.
orPress [Alt+C].
Step Action23. Use the Changeover Times page to enter the time it will take to perform the
changeover and assign a penalty to the changeover if there is one.
Last changed on: 1/18/2010 09:35:00 AM Page 17
-
8/14/2019 Assigning Setup Times to Resources_SPD
18/29
System Process DocumentAssigning Setup Times to Resources
Step Action
24. Click the Select button.
orPress [Alt+S].
Page 18 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
19/29
System Process DocumentAssigning Setup Times to Resources
Step Action
25. Use the Select Setup Types page to select the setup from the list of available setup
types.
Step Action
26. Click the >> button.
Last changed on: 1/18/2010 09:35:00 AM Page 19
-
8/14/2019 Assigning Setup Times to Resources_SPD
20/29
System Process DocumentAssigning Setup Times to Resources
Step Action
27. Click the OKbutton.
orPress [Alt+O].
Page 20 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
21/29
System Process DocumentAssigning Setup Times to Resources
Step Action
28. Click the Select button.
orPress [Alt+c].
Step Action
29. Click the >> button.
Last changed on: 1/18/2010 09:35:00 AM Page 21
-
8/14/2019 Assigning Setup Times to Resources_SPD
22/29
System Process DocumentAssigning Setup Times to Resources
Step Action
30. Click the OKbutton.
orPress [Alt+O].
Page 22 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
23/29
System Process DocumentAssigning Setup Times to Resources
Step Action
31. Use the Refresh List of Changeovers button to automatically generate a list of all
potential changeover combinations in the From and To fields.
Step Action
32. Click the Refresh List of Changeovers button.
orPress [Alt+R].
Last changed on: 1/18/2010 09:35:00 AM Page 23
-
8/14/2019 Assigning Setup Times to Resources_SPD
24/29
System Process DocumentAssigning Setup Times to Resources
Step Action
33. Click the Update option.
Page 24 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
25/29
System Process DocumentAssigning Setup Times to Resources
Step Action
34. Click the Update option.
Step Action
35. Click in the Duration field.
Last changed on: 1/18/2010 09:35:00 AM Page 25
-
8/14/2019 Assigning Setup Times to Resources_SPD
26/29
System Process DocumentAssigning Setup Times to Resources
Step Action
36. Enter the desired information into the Duration field. Enter "2".
Page 26 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
27/29
System Process DocumentAssigning Setup Times to Resources
Step Action
37. Click the Update option.
Step Action
38. Click in the Duration field.
Last changed on: 1/18/2010 09:35:00 AM Page 27
-
8/14/2019 Assigning Setup Times to Resources_SPD
28/29
System Process DocumentAssigning Setup Times to Resources
Step Action
39. Enter the desired information into the Duration field. Enter "2".
Page 28 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Assigning Setup Times to Resources_SPD
29/29
System Process DocumentAssigning Setup Times to Resources
Step Action
40. Click the Save button.
Step Action
41. You have completed the Assigning Setup Times to Resources procedure.