ATLAS LS1 infrastructure: Installation of a new 10’000 litre
LHe dewar for the SolenoidN. Delruelle on behalf of the TE/CRG groupLS1 Infrastructure Meeting – 16 Apr 2014
2
Outline
► layout of the new supply 10’000 litre LHe dewar Interconnecting valve box 2 Transfer Lines TL4 and TL5
► Planning of the new supply Manufacture Integration in UX15
TE/CRG/N.Delruelle – LS1 infrastructure – 16 Apr 2014
3
Layout of the new supply
TE/CRG/N.Delruelle – LS1 infrastructure – 04 Dec 2013
New transfer line TL4
New valve box
New 10’000 L dewar
New transfer line TL5
Existing transfer line TL1
Existing transfer line TL2
Courtesy of Jos Metselaar
4
Layout of the new supply
TE/CRG/N.Delruelle – LS1 infrastructure – 04 Dec 2013
New 10’000 L dewar
New valve box
New transfer line TL4
Existing transfer line TL2
Existing transfer line TL3 to solenoid
Courtesy of Jos Metselaar
5
Manufacture planning
► The valve box: Manufacturing: by week 12/2014 18/2014 Test of the electrical cabinet: by week 14/2014 18/2014
► Transfer lines TL4 & TL5: Manufacturing: by week 10/2014 ˅
► The 10’000 litre LHe dewar: Manufacturing inner & outer vessel: by week 5/2014 16/2014 Insulation: by week 7/2014 18/2014 Inner plumbing: by week 10/2014 21/2014 Test of the electrical cabinet: by week 10/2014 22/2014
TE/CRG/N.Delruelle – LS1 infrastructure – 16 Apr 2014
6
Installation planning in Point 1
► The valve box: Installation: week 20/2014 (12 May)
► Transfer lines TL5: Installation: from week 20 to week 23/2014 (from 12 May to
06 June) Leak test on TL5: week 24/2014 (09 June)
► The 10’000 litre LHe dewar & TL4: Handling & Installation: week 24/2014 (09 June) Connection between dewar and TL4: week 25/2014 (16 June) Leak test on TL4: week 26/2014 (23 June) Cutting & connection to existing TL3: from week 27 to
week 29/2014 (from 01 July to 18 July)
TE/CRG/N.Delruelle – LS1 infrastructure – 16 Apr 2014