CROSSTOWN LRTConstruction Liaison CommitteeBrentcliffe – Victoria ParkJune 1, 2017
![Page 2: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/2.jpg)
2
Agenda
• West At-Grade (East Portal to Victoria Park Stop) Update
• Science Centre Station Update
![Page 3: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/3.jpg)
3
What Are We Building
• 15 underground stations and 10 surface stops – 9 km below ground and 10 km above ground
• A maintenance and storage facility
• A 19-kilometre route separated from regular traffic
• Transit communications system
• Links to 54 bus routes, three subway stations, GO Transit, and a new UP Express station
![Page 4: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/4.jpg)
4
Safety First – Our #1 Priority
We train and direct staff to:
• Always have a site specific safety plan and site specific emergency plan.
• Ensure pre-work hazard assessments are complete and understood.
• Ensure job hazards analyses are complete and understood.
• Do everything possible to protect themselves, co-workers, and members of the public.
• Stop work if the safety of themselves, co-workers and members of the public cannot be assured.
• Identify and report unsafe behaviour and coach each other to make improvements.
• Be prepared and equipped to work safely.
![Page 5: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/5.jpg)
5
Crosstown Design Approach
Street Level – Contextual and Inviting
An International Signature for Toronto
Entrance – Bright & Secure
Concourse – Simple & Pristine Concourse – Transparent & Open Platform – Spacious & Animated
![Page 6: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/6.jpg)
6
Accessibility
Station and Stops are designed to be universally accessible, including satisfaction of the AODA, applicable City of Toronto Guidelines, the OBC, and CSA Standards.
Some of those features include:
• Barrier‐free paths from the entrance level to the station platform level
• Tactile warning strips and tactile walking surface indicators
• Signage systems with tactile indicators
• Passenger Assistance Intercoms (PAI)
• Low floor Light Rail Vehicles (LRV) with designated wheelchair locations
• Nominal gaps from platform edges to LRV entries
• Automated visual and audible stop announcements
• On-street and off-street paratransit passenger pick-ups and drop-offs
![Page 7: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/7.jpg)
7
Environment & Sustainability
During Construction
• Programs to minimize impact on wildlife, their habitats, watercourses and trees
• Reduce impact on our community neighbours through the management of dust,
noise and vibration
• Sustainable construction practices, including active management of construction
and demolition generated wastes, targeting 75% waste diversion from landfills;
and off-site beneficial reuse of excess soil.
Project Design Sustainability
• Project wide application of Toronto Green Standard
• LEED Certification at EMSF
• Bike parking for short- and long-term users
• Dedicated pedestrian routes
• High Solar Reflectance Index paving
• Green roofs
• Water use conservation/efficiency
• Fritted glazing (minimize bird collisions)
• Shielded exterior lighting (prevent off-site light trespass)
• Sheltered waiting areas
• Energy efficiency – LED lighting, heat recovery systems
• Landscaping – use of native, drought-tolerant plants and large trees
![Page 8: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/8.jpg)
8
How We’re Building the Crosstown: Construction Overview
![Page 9: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/9.jpg)
9
The Crosstown: 2016 in Review
9
• Tunnels complete
• Construction activities at all 15 underground stations
• Utility relocations & support in place, underway or complete
• Shoring work underway or nearing completion at several stations
• All design through 60% completion
• Transit system definition for underground segments 60% complete
• Full Building Permit application packages being finalized for submission Q1-Q3
![Page 10: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/10.jpg)
10
The Crosstown: 2017 Construction Milestones
• Year of the Dig – 1 million tons to be excavated in 2017
• Start excavating main station boxes
• Shoring & utility relocations at interchange stations – Cedarvale, Eglinton, Kennedy
• Utilities Relocation
• Road Widening
• Start Guideway Install
• Track work – pour concrete base and first track installation
• Maintenance & Storage Facility buildings enclosed
10
![Page 11: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/11.jpg)
11
How we’re building the Crosstown:
Construction Overview
Distinct phases of construction:
• Preliminary works
• Utility relocations
• Handover of tunnel sections
• Support of excavation (shoring)
• Excavation & mining works
• Structural and architectural works
• Track work and systems installation
• Traction power system
• Signalling system
• Testing and commissioning
• Restoration works
![Page 12: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/12.jpg)
12
West At-Grade (Brentcliffe Portal to Victoria Park Stop)
Update
Brentcliffe Portal• Preparatory works are underway or complete
– Geotechnical Investigations
– Subsurface Utility Investigations
– Tree Protection and Removals
• Piling, the first stage for Support of Excavation (Shoring) almost complete
West At-Grade • Preparatory works are underway or complete
– Geotechnical Investigations
– Subsurface Utility Investigations
– Tree Protection and Removals
• Median Removals across Eglinton Avenue East scheduled to begin
![Page 13: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/13.jpg)
13
Brentcliffe Portal Aerial View (60% Rendering)
![Page 14: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/14.jpg)
14
Sunnybrook Park Stop Aerial View (60% Rendering)
![Page 15: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/15.jpg)
15
Aga Khan Park & Museum Stop Aerial View (60%
Rendering)
![Page 16: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/16.jpg)
16
Wynford Stop Aerial View (60% Rendering)
![Page 17: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/17.jpg)
17
Sloane Stop Aerial View (60% Rendering)
![Page 18: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/18.jpg)
18
O’Connor Stop Aerial View (60% Rendering)
![Page 19: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/19.jpg)
19
Science Centre Station Update
• Preparatory works are underway or complete
• Utility Relocation work continues
• Piling, the first step for Support of Excavation (Shoring), almost complete for Bus Depot, Pedestrian Entrance, Station Box and Portals. Main Entrance works scheduled to get underway as early as June 2017.
• Existing traffic set up installed in early May and expected to be in place for approximately three months. Traffic set up supports piling, utility works and road widening
• Next stage of work will include piling at the Main Entrance located at the southwest corner of Eglinton Ave. East and Don Mills Road and excavation in the centre of Eglinton Avenue to begin underground works: shoring, portals, station box, and track work
![Page 20: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/20.jpg)
20
Current Traffic Staging at Don Mills & Eglinton
Began early May. Scheduled to be in place for approximately 3 months.
![Page 21: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/21.jpg)
21
How we’re building Science Centre Station
Cut and Cover Methodology at Science Centre Station
![Page 22: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/22.jpg)
22
Science Centre Aerial View (90%)
Secondary Entrance
Main Entrance
Bus Terminal
![Page 23: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/23.jpg)
23
Science Centre Main Entrance Plaza (90%)
![Page 24: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/24.jpg)
24
Science Centre Main Entrance Dusk (90%)
![Page 25: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/25.jpg)
25
Science Centre West Portal (60%)
![Page 26: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/26.jpg)
26
Science Centre East Portal (60%)
![Page 27: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/27.jpg)
27
Science Centre Bus Terminal (60%)
![Page 28: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017](https://reader034.vdocument.in/reader034/viewer/2022052116/5a64e5977f8b9a88148b5dc7/html5/thumbnails/28.jpg)
28
Science Centre Bus Depot (60%)