Building for Learning ProjectPhoto Progress Report
October 2009
Project commencement 21st September 2009
![Page 2: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/2.jpg)
New roof going up (over rooms 4 and 5)
If you look closely, you will see the old
wooden shingles which were the original roof dating back to the late
1890’s
1st Oct 2009
![Page 3: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/3.jpg)
Admin empty ready for refurbishment to begin by 19th Oct2nd Oct 2009
![Page 4: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/4.jpg)
New roof being added to original school building dating back to 1874 – 2nd Oct 2009
![Page 5: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/5.jpg)
Major roof works completed – 5th Oct 2009
![Page 6: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/6.jpg)
Internal Demolition Begins 6th Oct 2009
![Page 7: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/7.jpg)
Classrooms 6-9 Demolition continues Oct 2009
Rooms emptied, carpets, ceilings, all electrics wiring removed ready for 1st storey construction and concrete slab floor
![Page 8: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/8.jpg)
Racking construction for refurbishment storage 14th Oct 2009
![Page 9: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/9.jpg)
Demolition continues Oct 2009
![Page 10: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/10.jpg)
Corporate Services area refurbishment 19th Oct 2009
Windows removed Ceiling Fans replaced
![Page 11: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/11.jpg)
Floor demolition 19th Oct 2009
![Page 12: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/12.jpg)
Graeme Connelly supervising wall demolition 21st Oct 2009
![Page 13: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/13.jpg)
Internal framing and windows being cut in 27th Oct 2009
![Page 14: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/14.jpg)
Framing and floors added 28th Oct 2009
Staff inspections of works
![Page 15: Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009](https://reader037.vdocument.in/reader037/viewer/2022110304/5518afe0550346c31f8b4e83/html5/thumbnails/15.jpg)
Outside area demolition ready for major works to begin 29th Oct 2009