Progress Report
March 19, 2013
San Angelo City Council
2
Agenda
1. Progress & Schedule Update:a. Transmission Main
b. Booster Pump Station & Well Field
c. Treatment
d. New Groundwater Wells
2. Questions & Discussion
3
Transmission Main
NTP January 23, 2012 Substantial Completion: July 16, 2013 Final Completion: September 14, 2013 Current status: Dig-Lay-Bury is approximately
80% complete
4
Progress As of March 4, 2013
5
Progress Summary
3rd dig-lay-bury crew added through March 14, 2013 to expedite production in BCV areas before nesting season.
Work progressing in both directions Valves and appurtenance work ongoing with dig-
lay-bury Pressure testing starting soon
6
Laying Pipe in Rock
7
Gate Valve Installation
8
Booster Pump Station & Well Field
NTP: June 18, 2012 Substantial Completion: June 18, 2013 Final Completion: July 17, 2013 Current Status: Approximately 50% complete
9
Progress Summary Booster pump cans set, backfill underway Foundations for all well buildings underway, most
complete High point and well 6 tank foundations underway. Well cleaning underway Potential delay to current schedule mainly due to
longer than expected time needed to clean and retrofit existing wells
10
Hickory Wells 1-9 Background
Wells drilled in the 70s Potential obstructions or items identified by the
initial video survey at some wells TCEQ required cleaning of the well casing at
each well along with the removal of debris or obstructions noted in the initial video survey followed by a new video survey to confirm conditions of wells
11
Conditions of Well
Obstruction in Well 4 has been identified as a packing plug. Contractor trying drill and air purge it out of the well.
Obstruction removal and repairs to 3 wells 5 holes in well 7 casing: 1 at 64 feet, 3 at 1,128 feet, and 1
at 2,062 feet. A sleeve can be swaged in at 64 feet and possibly at 1128 feet, but not at 2062 due to the pressure at that depth. Hole at 2062 is completely sealed with grout.
Well 1 liner casing slipped. Attempt will be made to remove the slipped casing.
12
Setting block for booster pump station electrical building
13
Booster Pump Cans
14
Looking East PS & Electrical Building
15
Underground electrical at Well 1
16
Groundwater Treatment Plant
Groundwater Treatment Facility Disinfection Facility Associated civil work and piping Project Status:
• RRSS Selection and Design NTP: February 6, 2013
• Overall final design: Anticipated completion completion April 30, 2013
17
Site Layout
Disinfection Facility Groundwater Treatment Facility
18
Disinfection Facility
19
Groundwater Treatment Facility
20
Groundwater Treatment Facility
Building Dimensions: 208’ – 0” x 133’ – 4”
21
Groundwater Treatment Facility
22
Disinfection Facility
Building Dimensions:
105’ – 4” x 64’ – 44”
23
Disinfection Facility
24
Post Design Key MilestonesAnticipated Dates or Schedule
TWDB/TCEQ Review May 1, 2013 through June 30, 2013
Advertise Project May 16, 2013
Bid Project July 9, 2013
Recommendation of Award & Council Approval
July 9 through July 16, 2013
TWDB Release of Funds and NTP August 1, 2013
Substantial Construction Completion for GWTF
July 31, 2014
Final Construction Completion of Project
October 30, 2014
25
New Wells
Regulatory hurdle cleared and clearing, grubbing and grinding of cleared material of new wells and ROW complete.
Phase 1: Engineering for “Drilling New Wells” underway. Expected design completion and submittal to TCEQ April 30, 2013
Phase 2: Engineering for “Site Civil, Piping and Equipping New Wells” will start in May 2013
Questions?
March 19, 2013