CONSTRUCTION CONTRACTS
![Page 2: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/2.jpg)
2
CONTRACTS
“It is not the beauty of a building you should look at;
its the construction of the foundation that will stand the
test of time.”
- Unknown
![Page 3: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/3.jpg)
3
CONSTRUCTION CONTRACTS
Provides, based on what is known at the time of contract, for what is ultimately Deliverable, by
When and at what Price;
Deals with a relationship (not necessarily founded on good faith, mutual cooperation and trust)
just as much as it deals with the Deliverable.
Defines or restricts the extent to which the common law would otherwise govern the
relationship.
Defines the relationship - it is not a mere formality in the process.
![Page 4: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/4.jpg)
4
CONSTRUCTION CONTRACTS
The Deliverable: To define the Deliverable, with the degree of accuracy possible at the time,
and to allow the Deliverable to evolve in a controlled manner;
The Price: To define the Price of the Deliverable based on what is known and what ought to be
reasonably foreseeable to an experienced contractor at the time, and to provide for the Price to
change in a controlled manner;
![Page 5: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/5.jpg)
5
CONSTRUCTION CONTRACTS
The When: To define the Time for Completion of the Deliverable based on what is known and
what ought to be reasonably foreseeable to an experienced contractor at the time, and to allow
the Time for Completion to change in a controlled manner;
The Risks: To respectively allocate the foreseeable and unforeseeable / likely and unlikely risks
to each of the Parties; and
Possible Disputes: To provide a mechanism to principally avoid, but to otherwise effectively
deal with disputes.
![Page 6: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/6.jpg)
6
THOUGHT FOR THE DAY
- The type of contract form to be used will depend on the Employer’s preference as well as the Works to be executed
- Many employers use standard form contracts developed and published by industry-based organisations
- The idea of standard form contracts is to include provisions which are beneficial to both parties to the contract in accordance with good practice
- Some contracts are, however, not based on the approach of good practice
- Therefore it is important to know the three R’s:
![Page 7: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/7.jpg)
7
THOUGHT FOR THE DAY
- The type of contract form to be used will depend on the Employer’s preference as well as the Works to be executed
- Many employers use standard form contracts developed and published by industry-based organisations
- The idea of standard form contracts is to include provisions which are beneficial to both parties to the contract in accordance with good practice
- Some contracts are, however, not based on the approach of good practice
- Therefore it is important to know the three R’s:- Rights
![Page 8: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/8.jpg)
8
THOUGHT FOR THE DAY
- The type of contract form to be used will depend on the Employer’s preference as well as the Works to be executed
- Many employers use standard form contracts developed and published by industry-based organisations
- The idea of standard form contracts is to include provisions which are beneficial to both parties to the contract in accordance with good practice
- Some contracts are, however, not based on the approach of good practice
- Therefore it is important to know the three R’s:- Rights- Responsibilities
![Page 9: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/9.jpg)
9
THOUGHT FOR THE DAY
- The type of contract form to be used will depend on the Employer’s preference as well as the Works to be executed
- Many employers use standard form contracts developed and published by industry-based organisations
- The idea of standard form contracts is to include provisions which are beneficial to both parties to the contract in accordance with good practice
- Some contracts are, however, not based on the approach of good practice
- Therefore it is important to know the three R’s:- Rights- Responsibilities - Risks
![Page 10: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/10.jpg)
10
THOUGHT FOR THE DAY
- The type of contract form to be used will depend on the Employer’s preference as well as the Works to be executed
- Many employers use standard form contracts developed and published by industry-based organisations
- The idea of standard form contracts is to include provisions which are beneficial to both parties to the contract in accordance with good practice
- Some contracts are, however, not based on the approach of good practice
- Therefore it is important to know the three R’s:- Rights- Responsibilities - Risks
- Within standard form contracts you will find your three R’s within the General Conditions of Contract read together with the amendments thereto as set out in the Contract Data and Special / Particular Conditions
![Page 11: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/11.jpg)
11
THOUGHT FOR THE DAY
- The type of contract form to be used will depend on the Employer’s preference as well as the Works to be executed
- Many employers use standard form contracts developed and published by industry-based organisations
- The idea of standard form contracts is to include provisions which are beneficial to both parties to the contract in accordance with good practice
- Some contracts are, however, not based on the approach of good practice
- Therefore it is important to know the three R’s:- Rights- Responsibilities - Risks
- Within standard form contracts you will find your three R’s within the General Conditions of Contract read together with the amendments thereto as set out in the Contract Data and Special / Particular Conditions
- The obvious benefit of the standard form is common understanding and the resultant efficiency in Tender and Execution Phases.
![Page 12: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/12.jpg)
12
THOUGHT FOR THE DAY
• The role players are:
• Employer
• Main Contractor
• Sub-contractor
• (Designer / Supplier / Manufacturer etc)
• Importantly:
• Familiarise yourself with the contract
• Be aware of all changes to standard form contracts
• Strict compliance
![Page 13: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/13.jpg)
Integrity,quality,consistency.
![Page 14: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/14.jpg)
14
Standard Forms
![Page 15: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/15.jpg)
15
AVAILABLE STANDARD FORMS
What Standard Forms are available for use (and required to be used by State Owned Entities):
Construction
FIDIC
NEC
JBCC
GCC
CIDB standard forms
Professional Services
NEC PSA
CIDB Standard Forms
![Page 16: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/16.jpg)
16
AVAILABLE STANDARD FORMS
The FIDIC Suite (latest is 1999)
• Silver Book – EPC;• Yellow Book – Design & Build;• Red Book – Construction Work; and• Green Book – Minor Work.
![Page 17: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/17.jpg)
17
AVAILABLE STANDARD FORMS
• New Engineering Contract:
![Page 18: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/18.jpg)
18
AVAILABLE STANDARD FORMS
• New Engineering Contract • Engineering and Construction Contract
![Page 19: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/19.jpg)
19
AVAILABLE STANDARD FORMS
• New Engineering Contract • Engineering and Construction Contract• Construction Short Contract
![Page 20: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/20.jpg)
20
AVAILABLE STANDARD FORMS
• New Engineering Contract • Engineering and Construction Contract• Construction Short Contract
• Joint Building Contracts Committee Series 2000 (5th Edition 2007):
![Page 21: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/21.jpg)
21
AVAILABLE STANDARD FORMS
• New Engineering Contract • Engineering and Construction Contract• Construction Short Contract
• Joint Building Contracts Committee Series 2000 (5th Edition 2007):• Principal Building Agreement;
![Page 22: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/22.jpg)
22
AVAILABLE STANDARD FORMS
• New Engineering Contract • Engineering and Construction Contract• Construction Short Contract
• Joint Building Contracts Committee Series 2000 (5th Edition 2007):• Principal Building Agreement;• N/S Subcontract
![Page 23: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/23.jpg)
23
AVAILABLE STANDARD FORMS
• New Engineering Contract • Engineering and Construction Contract• Construction Short Contract
• Joint Building Contracts Committee Series 2000 (5th Edition 2007):• Principal Building Agreement;• N/S Subcontract
• General Conditions of Contract for Construction (2004)
![Page 24: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/24.jpg)
24
AVAILABLE STANDARD FORMS
• The standard forms of contracts can, and usually will, be changed to fit the different requirements for different projects or to suit the requirements of a particular employer
• These conditions may change the rights and responsibilities of the employer and contractor
![Page 25: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/25.jpg)
Global reach;local specialistknowledge.
![Page 26: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/26.jpg)
26
Before Signing
![Page 27: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/27.jpg)
27
BEFORE SIGNING
• Completion Date
![Page 28: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/28.jpg)
28
BEFORE SIGNING
• Completion Date
• Contract Price:
• Lump Sum / Re-measurable
• CPA?
• Cost Plus
![Page 29: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/29.jpg)
29
BEFORE SIGNING
• Completion Date
• Contract Price:
• Lump Sum / Re-measurable
• CPA?
• Cost Plus
• Payment Structures: Progress / milestone based
![Page 30: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/30.jpg)
30
BEFORE SIGNING
• Completion Date
• Contract Price:
• Lump Sum / Re-measurable
• CPA?
• Cost Plus
• Payment Structures: Progress / milestone based
• Bond Requirements
• Performance
• Retention
• Advanced Payments
![Page 31: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/31.jpg)
31
BEFORE SIGNING
• Completion Date
• Contract Price:
• Lump Sum / Re-measurable
• CPA?
• Cost Plus
• Payment Structures: Progress / milestone based
• Bond Requirements
• Performance
• Retention
• Advanced Payments
• Penalties
![Page 32: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/32.jpg)
32
BEFORE SIGNING
• Completion Date
• Contract Price:
• Lump Sum / Re-measurable
• CPA?
• Cost Plus
• Payment Structures: Progress / milestone based
• Bond Requirements
• Performance
• Retention
• Advanced Payments
• Penalties
• Material Terms
![Page 33: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/33.jpg)
33
BEFORE SIGNING
• Completion Date
• Contract Price:
• Lump Sum / Re-measurable
• CPA?
• Cost Plus
• Payment Structures: Progress / milestone based
• Bond Requirements
• Performance
• Retention
• Advanced Payments
• Penalties
• Material Terms
• Programming Requirements
![Page 34: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/34.jpg)
34
BEFORE SIGNING
• Completion Date
• Contract Price:
• Lump Sum / Re-measurable
• CPA?
• Cost Plus
• Payment Structures: Progress / milestone based
• Bond Requirements
• Performance
• Retention
• Advanced Payments
• Penalties
• Material Terms
• Programming Requirements
• Entitlements to Extension of Time and Additional Costs
• Variation Orders
• Omissions
• Delays
![Page 35: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/35.jpg)
35
BEFORE SIGNING• Completion Date
• Contract Price:
• Lump Sum / Re-measurable
• CPA?
• Cost Plus
• Payment Structures: Progress / milestone based
• Bond Requirements
• Performance
• Retention
• Advanced Payments
• Penalties
• Material Terms
• Programming Requirements
• Entitlements to Extension of Time and Additional Costs
• Variation Orders
• Omissions
• Delays
• Limitation of Liability
![Page 36: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/36.jpg)
36
BEFORE SIGNING• Completion Date
• Contract Price:
• Lump Sum / Re-measurable
• CPA?
• Cost Plus
• Payment Structures: Progress / milestone based
• Bond Requirements
• Performance
• Retention
• Advanced Payments
• Penalties
• Material Terms
• Programming Requirements
• Entitlements to Extension of Time and Additional Costs
• Variation Orders
• Omissions
• Delays
• Limitation of Liability
• Resolution of Anticipated Disputes
![Page 37: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/37.jpg)
Integrity,quality,consistency.
![Page 38: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/38.jpg)
38
Contract Phases
![Page 39: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/39.jpg)
39
CONTRACT PHASES
![Page 40: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/40.jpg)
40
CONTRACT PHASES
![Page 41: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/41.jpg)
41
CONTRACT PHASES
![Page 42: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/42.jpg)
42
CONTRACT PHASES
![Page 43: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/43.jpg)
43
CONTRACT PHASES
![Page 44: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/44.jpg)
Global reach;local specialistknowledge.
![Page 45: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/45.jpg)
45
It’s not just a contract
![Page 46: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/46.jpg)
46
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
An evolving “merx” against a backdrop (very often over an extended period of time) of
evolving circumstances (both unforeseeable and foreseeable, albeit not always predictable).
Reasonable programming.
Breach (albeit not material) is expected. A degreed of breach is the rule rather than the
exception and events or circumstances giving rise to disputes are common place; not because
of the nature of the industry players but rather the nature of activity.
Risk is considered (not avoided at all costs), understood and allocated.
![Page 47: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/47.jpg)
47
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Principal Drivers: Traditional: Time, Cost and Quality – modern approach includes Health
&Safety.
Quality: Workmanship and Performance (as appropriate).
Time and Cost are moving targets - One of the Parties has to accept the risk. The extent / lack of
planning and the proper allocation of risk are a key factors in Time and Cost optimisation.
Health & Safety: statutory requirements and corporate policy considerations. The concept of
best practice and zero harm is most often required and/or adopted in mature jurisdictions and
by responsible corporations.
![Page 48: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/48.jpg)
48
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Rights:
Timeous Payments
![Page 49: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/49.jpg)
49
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Rights:
Timeous Payments
Variations or alterations
![Page 50: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/50.jpg)
50
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Rights:
Timeous Payments
Variations or alterations
Extensions of Time
![Page 51: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/51.jpg)
51
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Rights:
Timeous Payments
Variations or alterations
Extensions of Time
Access to the Employer
![Page 52: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/52.jpg)
52
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Rights:
Timeous Payments
Variations or alterations
Extensions of Time
Access to the Employer
Dispute Resolution Mechanisms
![Page 53: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/53.jpg)
53
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Rights:
Timeous Payments
Variations or alterations
Extensions of Time
Access to the Employer
Dispute Resolution Mechanisms
Termination of the Contract
![Page 54: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/54.jpg)
54
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Rights:
Timeous Payments
Variations or alterations
Extensions of Time
Access to the Employer
Dispute Resolution Mechanisms
Termination of the Contract
Appointment of sub-contractors
![Page 55: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/55.jpg)
55
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Responsibilities:
Completing and Maintaining Works
![Page 56: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/56.jpg)
56
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Responsibilities:
Completing and Maintaining Works
Guarantees and insurances
![Page 57: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/57.jpg)
57
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Responsibilities:
Completing and Maintaining Works
Guarantees and insurances
Administrative procedures
Reporting on progress
Updated programmes
Substantiation of claims
Contemporaneous documents
![Page 58: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/58.jpg)
58
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Responsibilities:
Completing and Maintaining Works
Guarantees and insurances
Administrative procedures
Reporting on progress
Updated programmes
Substantiation of claims
Contemporaneous documents
Notifications
Early Warning
Notice of Claim – Time periods
Fully detailed claim
![Page 59: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/59.jpg)
59
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Responsibilities:
Completing and Maintaining Works
Guarantees and insurances
Administrative procedures
Reporting on progress
Updated programmes
Substantiation of claims
Contemporaneous documents
Notifications
Early Warning
Notice of Claim – Time periods
Fully detailed claim
Security
![Page 60: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/60.jpg)
60
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Main Contractor Responsibilities:
Completing and Maintaining Works
Guarantees and insurances
Administrative procedures
Reporting on progress
Updated programmes
Substantiation of claims
Contemporaneous documents
Notifications
Early Warning
Notice of Claim – Time periods
Fully detailed claim
Security
Instructions
![Page 61: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/61.jpg)
61
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Main Contractor Responsibilities:
Completing and Maintaining Works
Guarantees and insurances
Administrative procedures
Reporting on progress
Updated programmes
Substantiation of claims
Contemporaneous documents
Notifications
Early Warning
Notice of Claim – Time periods
Fully detailed claim
Security
Instructions
Subcontracts
Claims
![Page 62: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/62.jpg)
62
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Main Contractor Responsibilities:
Completing and Maintaining Works
Guarantees and insurances
Administrative procedures
Reporting on progress
Updated programmes
Substantiation of claims
Contemporaneous documents
Notifications
Early Warning
Notice of Claim – Time periods
Fully detailed claim
Security
Instructions
Subcontracts
Claims
Compliance
![Page 63: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/63.jpg)
63
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Main Contractor Risks:
Financial Loss
Errors in calculations
Poor management
Delays
![Page 64: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/64.jpg)
64
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Main Contractor Risks:
Financial Loss
Errors in calculations
Poor management
Delays
Penalties
![Page 65: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/65.jpg)
65
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Main Contractor Risks:
Financial Loss
Errors in calculations
Poor management
Delays
Penalties
Insolvency of Employer
![Page 66: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/66.jpg)
66
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Main Contractor Risks:
Financial Loss
Errors in calculations
Poor management
Delays
Penalties
Insolvency of Employer
Termination of the contract
Recovery of damages
![Page 67: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/67.jpg)
67
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Sub-Contractor:
Three R’s will mainly depend of Scope of Works
![Page 68: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/68.jpg)
68
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Sub-Contractor:
Three R’s will mainly depend of Scope of Works
Responsibility is towards Main Contractor
![Page 69: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/69.jpg)
69
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Sub-Contractor:
Three R’s will mainly depend of Scope of Works
Responsibility is towards Main Contractor
Weaker position
![Page 70: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/70.jpg)
70
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Sub-Contractor:
Three R’s will mainly depend of Scope of Works
Responsibility is towards Main Contractor
Weaker position
Similar rights to those in Main Contract
![Page 71: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/71.jpg)
71
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Sub-Contractor:
Three R’s will mainly depend of Scope of Works
Responsibility is towards Main Contractor
Weaker position
Similar rights to those in Main Contract
Warning lights in contract:
Reduction of / set-off from certified payments
Pay when paid
No DAB / Arbitration Procedure
![Page 72: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/72.jpg)
72
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Sub-Contractor:
Three R’s will mainly depend of Scope of Works
Responsibility is towards Main Contractor
Weaker position
Similar rights to those in Main Contract
Warning lights in contract:
Reduction of / set-off from certified payments
Pay when paid
No DAB / Arbitration Procedure
Retention percentages
![Page 73: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/73.jpg)
73
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Sub-Contractor:
Three R’s will mainly depend of Scope of Works
Responsibility is towards Main Contractor
Weaker position
Similar rights to those in Main Contract
Warning lights in contract:
Reduction of / set-off from certified payments
Pay when paid
No DAB / Arbitration Procedure
Retention percentages
Defects liability periods
![Page 74: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/74.jpg)
74
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Sub-Contractor:
Three R’s will mainly depend of Scope of Works
Responsibility is towards Main Contractor
Weaker position
Similar rights to those in Main Contract
Warning lights in contract:
Reduction of / set-off from certified payments
Pay when paid
No DAB / Arbitration Procedure
Retention percentages
Defects liability periods
Changes to notification periods
![Page 75: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/75.jpg)
75
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT” Sub-Contractor:
Three R’s will mainly depend of Scope of Works
Responsibility is towards Main Contractor
Weaker position
Similar rights to those in Main Contract
Warning lights in contract:
Reduction of / set-off from certified payments
Pay when paid
No DAB / Arbitration Procedure
Retention percentages
Defects liability periods
Changes to notification periods
Time barring
![Page 76: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/76.jpg)
76
CONSTRUCTION CONTRACTS – IT’S NOT “JUST A CONTRACT”
Important:
Notification Procedure Time barring
Strict Compliance
![Page 77: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/77.jpg)
Integrity,quality,consistency.
![Page 78: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/78.jpg)
78
DISPUTE: NOW WHAT?
![Page 79: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/79.jpg)
79
DISPUTE: NOW WHAT?
• Claims procedure
• Determination
• Dispute
• DAB / Arbitration
• Court
![Page 80: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/80.jpg)
80
DIFFERENCE IN APPROACHPRACTICAL EXAMPLE
Contractor 1
Realistic Tender
Guarantees and finance
Signed Contract
Took possession
Timeous notice: delays
Contemporaneous documents
![Page 81: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/81.jpg)
81
DIFFERENCE IN APPROACHPRACTICAL EXAMPLE
Contractor 1
Kept to progress chart
Reported regularly
Completed snag list
Completed work
Received final payment
![Page 82: CONSTRUCTION CONTRACTS](https://reader035.vdocument.in/reader035/viewer/2022062309/56815290550346895dc0b24f/html5/thumbnails/82.jpg)
82
QUESTIONS?