Construction Construction Construction Construction Delays & Best Delays & Best Delays & Best Delays & Best
PracticesPracticesPracticesPracticesGene Wortham
Idaho Transportation Department
![Page 2: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/2.jpg)
“Time is Money”
![Page 3: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/3.jpg)
![Page 4: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/4.jpg)
Who pays the Who pays the Who pays the Who pays the
Money for the Money for the Money for the Money for the
Time?Time?Time?Time?
![Page 5: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/5.jpg)
Effects of Construction
Delays• Acceleration
• Schedule Change - Inefficiency
• Delayed project completion
• Missed intermediate completion dates
• Liquidated Damages
• Frustration – claims
• Increased Costs
![Page 6: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/6.jpg)
Delay Causes
• Labor Strikes
• Weather
• Third Party
• Plan Errors
• Change Orders
• Contractor Errors
• Suspension of Work
• Utilities
• Differing Site Conditions
• Archaeological Finds
• The list goes on
![Page 7: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/7.jpg)
Costs of Delays
• Delays in most cases always cause
additional costs
• Direct Costs
• Indirect Costs
• Impact Costs
![Page 8: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/8.jpg)
Delay
Excusable Non-Excusable
No TimeNon-Compensable
Entitlement for time
Compensable
Non-Compensable
![Page 9: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/9.jpg)
When a Delay Occurs
Time for delay needs
to be addressed
immediately
![Page 10: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/10.jpg)
Arbitration
Appeal
Claim
Disagreement
Problem
DRB
DRB
Project Level
Higher UpCRB
![Page 11: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/11.jpg)
Contract Clause for
Determination and Extension
of Contract Time
Most Owner’s contracts
have this clause giving
guidelines for time
requests
![Page 12: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/12.jpg)
Contractual Requirements for
Contractor Scheduling (CPM)• Without a Schedule, how does
Owner/Contractor determine how a delay affects time?
• Initial Schedule
• Schedule Updates
• Contract completion date
• Contractor’s scheduled completion date
• Substantial completion
• Float
![Page 13: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/13.jpg)
Types of Non-Excusable Delay
Non-Excusable (Within control of the Contractor)
– Under estimate of production rates
– Inadequate scheduling or management
– Construction mistakes
– Equipment problems
– Bad Luck
– Liquidated Damages or Termination of Contract
The list goes on
Bottom line - Construction is a risky business
![Page 14: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/14.jpg)
Types of Excusable Delay
• Unusually Severe Weather
• Changes and Extra Work
• Differing Site Conditions
• Delays from unforeseeable causes beyond control of the Contractor
• Labor Disputes
• Utilities
• Etc.
![Page 15: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/15.jpg)
•Foreseeability
•Beyond the Control
•Without fault or negligence
Excusable Delay
![Page 16: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/16.jpg)
Excusable Delay – Time
Consideration
• May entitle Contactor to an extension of time (refer to your contract specifications)
• Contractor not charged Liquidated Damages or terminated if the Delay is Excusable – Time should be forthcoming
• If time extension is requested by Contractor and not granted and proven to be excusable –Constructive Acceleration may exist and costs owed by Owner
• Above may be overturned by a “No Damage for Delay” clause in contract
![Page 17: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/17.jpg)
Excusable Delay
(Compensable or Non-
Compensable)
• Non-Compensable Delay – Unforeseeable and beyond the control and without fault or negligence by the Owner or Contractor (may be entitled to time)
• Compensable Delay – The Contractor is entitled to an adjustment for increases in costs to the performance of the contract
![Page 18: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/18.jpg)
Compensable Time Extensions
The following clauses are placed in the contract to prevent a breach by the Owner
• Changes and Extra Work clause
• Differing Site Condition clause
• Suspension of Work clause
• Utility Work clause
![Page 19: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/19.jpg)
Changes and Extra Work Clause
The Changes and Extra Work may be
compensable – time may be given if
proven to affect the critical path
![Page 20: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/20.jpg)
Differing Site Conditions Clause
• Direct Costs
• Indirect Costs (OH & profit)
Amount to be paid can be limited to Contract
wording.
• The Changes and Differing Site Conditions clauses are not generally referred to as delay or suspension of work
![Page 21: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/21.jpg)
Suspension of Work Clause
Delays by the Owner for an unreasonable time fall under this clause and are most likely compensable. Very risky for liability on the Owner
• The Suspension of Work clause should provide contractual guidance for an equitable adjustment to the Contractor for time and money excluding profit
• Ground rules for Delay generally come from Contract Law. The Owner is liable for their actions/inactions that result in unreasonably delaying or disrupting the Contractor
• There is an implied obligation on the part of the Owner not to delay, interfere with or hinder the Contractor’s performance of their contract
![Page 22: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/22.jpg)
Utility Facilities clause
Refer to your State contract requirements to determine your rules for compensation and time the Owner is liable to the Contractor for a Utility delay. Should exclude profit.
![Page 23: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/23.jpg)
Burden of Proof for Damage
Must be Proven by
Contractor (Time and Money)• The contract performance was delayed
• Delay was excusable
• Delay was for unreasonable period of time– Unreasonable means not originally
anticipated, customary or inherent in the construction industry
– Some States define this unreasonable time by days
• Contractor did incur additional expenses
![Page 24: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/24.jpg)
Defective Plans and Specifications
• Contractor does not have to prove unreasonable time delay
• Any Delay due to Defective Plans/Specifications is unreasonable
![Page 25: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/25.jpg)
Third Party Delay
• This is a delay without the fault or negligence of either the Owner or Contractor
• Generally eligible for time but not compensable
![Page 26: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/26.jpg)
Concurrent Delay
• Both Owner and Contractor are contributing to the Delay time
• Neither Party can recover damages (non-compensable)
• Contract time may be extended
![Page 27: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/27.jpg)
Delay Costs
The cost of the delay must be traced directly to the claimed delay in a clear cause and effect relationship
![Page 28: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/28.jpg)
Acceleration
Acceleration is action taken by the Contractor in order to speed up the progress of the project to accomplish early completion or to make up for lost time
• Voluntary
• Constructive (not ordered by the Owner but attributed to the Owner
• Direction from the Owner
![Page 29: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/29.jpg)
Constructive Acceleration
• Constructive Acceleration occurs when the Contractor is induced by the actions/inactions of the Owner to complete the work in accordance with schedules not updated to include all time extensions from excusable delays.
![Page 30: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/30.jpg)
Contract Completion
The contract must be specific in terms of the time required to perform the work
![Page 31: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/31.jpg)
Contractor’s Scheduled Completion
• This is the date the Contractor presents on his schedule as to when the work will completed.
![Page 32: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/32.jpg)
Substantial Completion
• Most contracts define what constitutes substantial completion
• Substantial completion is primarily used to stop time accounting
![Page 33: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/33.jpg)
No Damage for Delay cause
• An effort to reduce claims for delay• Exculpatory Language – precludes damages for delay
• Generally, the Contractors sole remedy is only a time extension if so stated in the contract
• Validity of this clause varies from State to State
• Clause must be very clear and unambiguous• Enforceable – with following exceptions
– Jurisdiction allows the clause– Delay was not contemplated by the parties to the contract– Delay caused by fraud, gross negligence, active interference– Delay is so unreasonable that it is tantamount to an
abandonment of the Contract by the Owner– All of the above have been completely reversed by the courts
and rulings made in various ways
![Page 34: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/34.jpg)
Best Practices
Survey Says ………..
![Page 35: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/35.jpg)
Owner caused suspension or delay
for unreasonable period of time
Excusable – 100%
Compensable – 100%
![Page 36: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/36.jpg)
Unavoidable Utility Delay
Excusable – 95%
Compensable – 56%
![Page 37: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/37.jpg)
Unusual Severe Weather
Excusable – 95%
Compensable – 8%
![Page 38: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/38.jpg)
Unavoidable area-wide material
shortage that occurs after bid
Excusable – 90%
Compensable – 0%
![Page 39: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/39.jpg)
Labor strikes that occur after bid
Excusable – 81%
Compensable – 9%
![Page 40: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/40.jpg)
Unforeseeable and unavoidable;
such as fires, floods, and natural
disasters
Excusable – 100%
Compensable – 29%
![Page 41: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/41.jpg)
Third party delay without fault or
negligence of either Owner or
Contractor
Excusable – 88%
Compensable – 31%
![Page 42: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/42.jpg)
Differing Site Conditions
Excusable – 100%
Compensable – 95%
![Page 43: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/43.jpg)
Damage to permanent work prior to
acceptance
Excusable – 64%
Compensable – 47%
![Page 44: Construction Delays & Best Practices](https://reader036.vdocument.in/reader036/viewer/2022070300/6157db99ce5a9d02d46fe8cc/html5/thumbnails/44.jpg)