Recall
¤ Engineering Economy
¤ Engineering Economic Decision
¤ 7 Principles of Engineering Economy
![Page 2: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/2.jpg)
1. Problem recognition and evaluation.
2. Development of the feasible alternatives.
3. Development of the cash flows for each alternative.
4. Selection of a criterion ( or criteria).
5. Analysis and comparison of the alternatives.
6. Selection of the preferred alternative.
7. Performance monitoring and post-evaluation results.
7-step Engineering Economic Analysis procedure
![Page 3: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/3.jpg)
Cost Concepts and Design Economics I
CE22 Lecture 2
MA. BRIDA LEA D. DIOLA Institute of Civil Engineering College of Engineering University of the Philippines Diliman
![Page 4: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/4.jpg)
Discussion Topics
¤ Cost estimating
¤ Cost terminology
¤ General economic environment
![Page 5: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/5.jpg)
Cost vs Expenses
¤ "Expense" is a specific cash or other expenditure that can be followed in the accounting system
¤ "Cost" can refer to non-financial matters, such as lost time, aggravation, or pollution
![Page 6: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/6.jpg)
Used to describe the process by which the present and future cost consequences of engineering designs are forecast
Cost Estimating
Cost Estimating
![Page 7: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/7.jpg)
USES OF COST ESTIMATING
¤ Provide information used in setting a selling price for quoting, bidding, or evaluating contracts
¤ Determine whether a proposed product can be made and distributed at a profit (EG: price = cost + profit)
¤ Evaluate how much capital can be justified for process changes or other improvements
¤ Establish benchmarks for productivity improvement programs
Cost Estimating
![Page 8: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/8.jpg)
¤ Top-down Approach
¤ Bottom-up Approach
COST ESTIMATING APPROACHES
Cost Estimating
![Page 9: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/9.jpg)
¤ Uses historical data from similar engineering projects
¤ Used to estimate costs, revenues, and other parameters for current project
¤ Modifies original data for changes in inflation / deflation, activity level, weight, energy consumption, size, etc…
¤ Best use early in estimating process
TOP-DOWN APPROACH
Cost Estimating
![Page 10: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/10.jpg)
¤ Attempts to break down project into small, manageable units and estimate costs, etc….
¤ Smaller unit costs added together with other types of costs to obtain overall cost estimate
¤ Works best when detail concerning desired output defined and clarified
BOTTOM-UP APPROACH
Cost Estimating
![Page 11: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/11.jpg)
TOP-DOWN vs BOTTOM-UP
¤ TOP-DOWN – target costing
¤ BOTTOM-UP – design to price
![Page 12: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/12.jpg)
Example
¤ Forecast the expense of getting a Bachelor of Science (B.S.) degree from U.P. ( Four-year course)
¤ Top-Down Approach
¤ Bottom-Up Approach
![Page 13: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/13.jpg)
TOP-DOWN APPROACH
¤ Tuition fee/year + Other expenses/fees = total estimated cost
¤ Multiply by the number of years to finish the course
![Page 14: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/14.jpg)
BOTTOM-UP APPROACH
Total Cost of a B.S. at UP
Tuition and Other Fees
Tuition, Activities Fees,
Memberships, Medical, Lab fees
Books and Supplies
Books, Duplication, Supplies,
Computer rental, Software
Living Expenses
Rent, Food, Clothing,
Recreation, Utilities
Transportation
Gas, Maintenance, Insurance, Fare
Year 1, 2, 3 and 4
![Page 15: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/15.jpg)
Cash Cost vs Book Cost
¤ Cash cost is a cost that involves payment in cash and results in cash flow.
¤ Book cost or noncash cost is a payment that does not involve cash transaction; book costs represent the recovery of past expenditures over a fixed period of time.
Cost Terminology
![Page 16: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/16.jpg)
¤ Fixed costs are those unaffected by changes in activity level over a feasible range of operations for the capacity or capability available.
¤ Variable costs are those associated with an operation that vary in total with the quantity of output or other measures of activity level.
Fixed vs Variable Costs
Cost Terminology
![Page 17: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/17.jpg)
INCREMENTAL COST
¤ Incremental cost is the additional cost that results from increasing the output of a system by one (or more) units.
Cost Terminology
![Page 18: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/18.jpg)
Sunk Cost and Opportunity Cost
¤ A sunk cost is one that has occurred in the past and has no relevance to estimates of future costs and revenues related to an alternative course of action;
¤ An opportunity cost is the cost of the best rejected ( i.e., foregone ) opportunity and is hidden or implied;
Cost Terminology
![Page 19: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/19.jpg)
¤ Suppose the heating, ventilating and air conditioning (HVAC) system in your home has just experienced a major failure. You immediately call the Air Comfort Company for an estimate to replace your system. Their price is $4,200 and you gladly sign a contract and write a check for the required $1,000 down payment. At this point the weather warms and the urgency for replacement of your defunct system eases somewhat. You then get a second estimate for a new HVAC system. It is $3,000. You call Air Comfort back and they inform you that the $1,000 down payment is not refundable! What should you do? Explain.
![Page 20: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/20.jpg)
Recurring vs Nonrecurring Costs
¤ Recurring costs are repetitive and occur when a firm produces similar goods and services on a continuing basis. (i.e. variable cost)
¤ Nonrecurring costs are those that are not repetitive, even though the total expenditure may be cumulative over a relatively short period of time;
Cost Terminology
![Page 21: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/21.jpg)
Direct vs Indirect Costs
¤ Direct costs can be reasonably measured and allocated to a specific output or work activity
¤ Indirect costs are difficult to allocate to a specific output or activity
Cost Terminology
![Page 22: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/22.jpg)
Life-Cycle Cost
Life-cycle cost is the summation of all costs, both recurring and nonrecurring, related to a product, structure, system, or service during its life span.
Life cycle begins with the identification of the economic need or want ( the requirement ) and ends with the retirement and disposal activities.
Cost Terminology
![Page 23: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/23.jpg)
Lifecycle Cost: Example
Source: MIT Opencouseware Project evaluation notes
![Page 24: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/24.jpg)
Capital and Investment
¤ Investment Cost or capital investment is the capital (money) required for most activities of the acquisition phase;
¤ Working Capital refers to the funds required for current assets needed for start-up and subsequent support of operation activities;
¤ Operation and Maintenance Cost includes many of the recurring annual expense items associated with the operation phase of the life cycle;
¤ Disposal Cost includes non-recurring costs of shutting down the operation;
Cost Terminology
![Page 25: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/25.jpg)
The General Economic Environment
![Page 26: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/26.jpg)
Consumer and Producer Goods and Services
¤ Consumer goods and services are those that are directly used by people to satisfy their wants;
¤ Producer goods and services are those used in the production of consumer goods and services: machine tools, factory buildings, buses and farm machinery are examples;
General Economic Environment
![Page 27: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/27.jpg)
General-Price Demand Relationship
Price
Units of Demand
General Economic Environment
![Page 28: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/28.jpg)
General-Price Demand Relationship
Price (p)
Units of Demand (D)
a p = a - bD for 0 ≤ D ≤ a/b and a>0, b>0
D = (a – p)/b b ≠ 0
Where p = price per unit D = demand for the product or service (# of units) a = base (maximum) price (intercept on the price axis) b = slope of the price-Demand line 1/b = amount by which demand increases for each unit decrease in price
General Economic Environment
![Page 29: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/29.jpg)
Total Revenue (TR) Function
TR = p * D Total Revenue = price per unit * demand
Units of Demand (D)
TR TR = aD – bD2 for 0 ≤ D ≤ a/b
Max TR
a/(2b)
General Economic Environment
p = a - bD
dTR = a – 2bD = 0 dD
![Page 30: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/30.jpg)
Cost, Volume and Breakeven Point Relationships
Total Cost = Fixed Cost + Variable Cost
CT = CF + Cv
For the linear relationship assumed
Cv = cv * D
Where cv is the variable cost per unit
General Economic Environment
![Page 31: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/31.jpg)
Cost, Volume and Breakeven Point Relationships
Cost and Revenue
Volume (Demand)
CT
CF
CV
D’1 D’2 D*
Profit
Maximum Profit
PROFIT (loss) = Total Revenue – Total Costs
General Economic Environment
Breakeven Points
![Page 32: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/32.jpg)
Profit Maximization
In order for the profit to occur, the following must be met:
1. The price per unit that will result in no demand has to be greater than the variable cost per unit. ( a – cv) > 0
2. Total revenue must exceed total cost
Occurs where total revenue exceeds total cost by the greatest amount
General Economic Environment
![Page 33: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/33.jpg)
Example 2-6: Optimal Demand when Demand is a Function of Price
A company produces an electronic timing switch that is used in the consumer and commercial products made by several other manufacturing firms. The fixed cost is $73,000 per month and the variable cost is $83 per unit. The selling price per unit is p = $180 – 0.02D. For this situation:
a. Determine the optimal volume for this product
b. Confirm that profit (instead of loss) occurs at the demand in (a)
c. Range of profitable (volume) demand in units per month
General Economic Environment
![Page 34: Cost Concepts and Design Econ 1](https://reader030.vdocument.in/reader030/viewer/2022020102/563db8ee550346aa9a985c1b/html5/thumbnails/34.jpg)
Next Meeting: Cost-Driven Design Optimization Present Economy Studies Reference: Sullivan et al, Engineering Economy