S.l. No. Description Work Program of 1st Nov. 2011 Achievement of 31th Oct.2011 Remarks
Drainage pipe installation Drainage pipe installation in progress
CC casting of pipe fixing CC casting of pipe fixing in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for Surcharge material placement Sand bagging in progress
PVD Driving PVD Driving in progress
Wall casting 2nd lift CH 800-840/Country side Rebar fabrication & shuttering executed
Rod binding 2nd lift CH 840-860/Country side Rebar fabrication in progress
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
7 Sheet Pile Concrete Pouring Concrete Pouring in progress
8 RCC Drainage Pipe Concrete Pouring of Pipe Concrete Pouring of Pipe in progress
9 Electric Substation Concrete Pouring of Colun & Grade beamConcrete Pouring of Column & Grade beam in
progress
10 Wasa Relocation Connection work of relocated line Connection work of relocated line in progress
11 Electric Relocation Connection of relocated line in processCircuit (33/33/11/0.44 KV ) overhead cable fixing
complete
12 Laboratory
13 Interlocking Block ILB production (2 Plant) ILB production in progress
14 Dismantling work CC/RCC Dismantling work at Segment 2 & 3 CC/RCC Dismantling work at Segment 2 & 3 inprogress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
3
Road Work5
Segment 1A1
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,1st Nov, 2011
Open deep drain4
Segment 1
-
8/13/2019 Daily Program Nov-2011
2/19
S.l. No. Description Work Program of 2nd Nov. 2011 Achievement of 1st Nov.2011 Remarks
Drainage pipe installation Drainage pipe installation in progress
CC casting of pipe fixing CC casting of pipe fixing in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for Surcharge material placement Sand bagging in progress
Surcharge material placement Surcharge material placement in progress
Pre-cast Bracing installation
Concrete pouring of 3rd lift CH 840-860/Country
sideRebar fabrication & shuttering executed
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
7 Sheet Pile Concrete Pouring Concrete Pouring in progress
8 RCC Drainage Pipe Concrete Pouring of Pipe Concrete Pouring of Pipe in progress
9 Electric Substation Concrete Pouring of Column & Grade beamConcrete Pouring of Column & Grade beam in
progress
10 Wasa Relocation Finshing task for connection Finshing task for connection in progress
11 Electric Relocation Connection of relocated line in processCircuit (33/33/11/0.44 KV ) overhead cable fixing
complete
12 Laboratory
13 Interlocking Block ILB production (2 Plant) ILB production in progress
14 Dismantling work CC/RCC Dismantling work at Segment 2 & 3CC/RCC Dismantling work at Segment 2 & 3 in
progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
1
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,2nd Nov, 2011
Open deep drain4
Segment 13
Road Work5
Segment 1A
-
8/13/2019 Daily Program Nov-2011
3/19
S.l. No. Description Work Program of 3rd Nov. 2011 Achievement of 2nd Nov.2011 Remarks
1 Segment 1A Drainage pipe installation Drainage pipe installation in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for Surcharge material placement Sand bagging in progress
Surcharge material placement Surcharge material placement in progress
Pre-cast Bracing installation
Concrete pouring of 3rd lif t CH 840-860/Country
side
Rebar fabrication & shuttering executed
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
7 Sheet Pile Concrete Pouring Concrete Pouring in progress
8 RCC Drainage Pipe Concrete Pouring of Pipe Concrete Pouring of Pipe in progress
9 Electric Substation Concrete Pouring of Column & Grade beamConcrete Pouring of Column & Grade beam in
progress
10 Wasa Relocation Finshing task for connection Finshing task for connection in progress
11 Electric Relocation Connection of relocated line in processCircuit (33/33/11/0.44 KV ) overhead cable fixing
complete
12 Laboratory
13 Interlocking Block ILB production (2 Plant) ILB production in progress
14 Dismantling work CC/RCC Dismantling work at Segment 2 & 3CC/RCC Dismantling work at Segment 2 & 3 in
progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
5
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,3rd Nov, 2011
Open deep drain4
Segment 13
Road Work
-
8/13/2019 Daily Program Nov-2011
4/19
S.l. No. Description Work Program of 14th Nov. 2011 Achievement of 13th Nov Nov.2011 Remarks
1 Segment 1A Drainage pipe installation
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
4 Segment-2 PVD Driving PVD Driving in progress
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
7 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress
8 Wasa Relocation Newly installed line is functioning
Old line dismantling
9 Laboratory / Field Test
Field density test at segment-2 (150 mm local sand
layer)
10 Interlocking Block ILB production ILB production in progress
11 Dismantling work Mosque dismantling Mosque dismantling work in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
5
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,14th Nov, 2011
Segment 13
Road Work
-
8/13/2019 Daily Program Nov-2011
5/19
S.l. No. Description Work Program of 15th Nov. 2011 Achievement of 14th Nov Nov.2011 Remarks
1 Segment 1A Drainage pipe installation
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
4 Segment-2 PVD Driving PVD Driving in progress
Sand Blanket filling Sand Blanket filling in progress
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
7 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress
8 Wasa Relocation Newly installed line is functioning
Old line dismantling
9 Laboratory / Field Test
10 Interlocking Block ILB production ILB production in progress
11 Dismantling work Mosque dismantling Mosque dismantling work in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
5
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,15th Nov, 2011
Segment 13
Road Work
-
8/13/2019 Daily Program Nov-2011
6/19
S.l. No. Description Work Program of 16th Nov. 2011 Achievement of 15th Nov Nov.2011 Remarks
1 Segment 1A Drainage pipe installation
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
Rebar fabrication & shuttering
5 Segment-2 PVD Driving PVD Driving in progress
Sand Blanket filling Sand Blanket filling in progress
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
7 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
8 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress
Wasa Relocation Newly installed line is functioning
Old line dismantling Old line dismantling in progress
Laboratory / Field TestField density test at segment-2 (300mm sand
blanket)
Interlocking Block ILB production ILB production in progress
11 Dismantling work Mosque dismantling Mosque dismantling work in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
10
6
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,16th Nov, 2011
Open deep drain4
Segment 13
Road Work
9
-
8/13/2019 Daily Program Nov-2011
7/19
S.l. No. Description Work Program of 17th Nov. 2011 Achievement of 16th Nov Nov.2011 Remarks
Drainage pipe installation Drainage pipe installation in progress
Sub-base work Sub-base work in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
Rebar fabrication & shuttering Rebar fabrication & shuttering in progress
PVD Driving PVD Driving in progress
200mm sand filling
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
7 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
8 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress
Wasa Relocation Newly installed line is functioning
Old line removing Old line removing in progress
Laboratory / Field TestField density test at segment-2 (300mm sand
blanket)
Interlocking Block ILB production ILB production in progress
11 Dismantling work Mosque dismantling Mosque dismantling work in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
10
6
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,17th Nov, 2011
Open deep drain4
Segment 13
Segment-2
Segment 1A1
9
5
Road Work
-
8/13/2019 Daily Program Nov-2011
8/19
S.l. No. Description Work Program of 18th Nov. 2011 Achievement of 17th Nov Nov.2011 Remarks
CC casting of Drainage pipe installation Excavation work
Sub-base work Sub-base work in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
Bracing fixing
PVD Driving PVD Driving in progress
200mm sand filling 200mm sand filling in progress
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
7 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
8 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress
Newly installed line is functioning
Old line removing Old line removing in progress
10 Laboratory / Field TestField density test at segment-2 (300mm sand
blanket)300mm sand blanket filling executed
11 Interlocking Block ILB production ILB production in progress
12 Dismantling work Mosque dismantling Mosque dismantling work in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
9
5
Road Work
Wasa Relocation
6
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,18th Nov, 2011
Open deep drain4
Segment 13
Segment-2
Segment 1A1
-
8/13/2019 Daily Program Nov-2011
9/19
S.l. No. Description Work Program of 19th Nov. 2011 Achievement of 18th Nov Nov.2011 Remarks
CC casting of Drainage pipe installation Excavation work
Sub-base materials laying Excavation executed
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
Bracing fixing Bracing fixing in progress
PVD Driving PVD Driving in progress
200mm sand filling 200mm sand filling in progress
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
7 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
8 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress
Newly installed line is functioning
Old line removing Old line removing in progress
10 Laboratory / Field Test
11 Interlocking Block ILB production ILB production in progress
12 Dismantling work Mosque dismantling Mosque dismantling work in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,19th Nov, 2011
Open deep drain4
Segment 13
Segment-2
Segment 1A1
9
5
Road Work
Wasa Relocation
6
-
8/13/2019 Daily Program Nov-2011
10/19
S.l. No. Description Work Program of 20th Nov. 2011 Achievement of 19th Nov Nov.2011 Remarks
Drainage pipe installation Drainage pipe installation in progress
Sub-base materials laying Sub-base materials laying in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
Bracing fixing Bracing fixing in progress
PVD Driving PVD Driving in progress
200mm sand filling 200mm sand filling in progress
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
7 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
8 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress
Newly installed line is functioning
Old line removing Old line removing in progress
10 Laboratory / Field Test
11 Interlocking Block ILB production ILB production in progress
12 Dismantling work Mosque dismantling Mosque dismantling work in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
9
5
Road Work
Wasa Relocation
6
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,20th Nov, 2011
Open deep drain4
Segment 13
Segment-2
Segment 1A1
-
8/13/2019 Daily Program Nov-2011
11/19
S.l. No. Description Work Program of 21th Nov. 2011 Achievement of 20th Nov Nov.2011 Remarks
Drainage pipe installation Drainage pipe installation in progress
Sub-base materials laying Sub-base materials laying in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
Concrete Pouring CH 820-840 (2nd lif t) Rebar fabrication & Shuttering executed
PVD Driving PVD Driving in progress
200mm sand filling 200mm sand filling in progress
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
7 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
8 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress
Newly installed line is functioning
Old line removing Old line removing in progress
10 Laboratory / Field Test
11 Interlocking Block ILB production ILB production in progress
12 Dismantling work Mosque dismantling Mosque dismantling work in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,21th Nov, 2011
Open deep drain4
Segment 13
Segment-2
Segment 1A1
9
5
Road Work
Wasa Relocation
6
-
8/13/2019 Daily Program Nov-2011
12/19
S.l. No. Description Work Program of 22th Nov. 2011 Achievement of 21th Nov Nov.2011 Remarks
Drainage pipe instal lation (CC casting) Drainage pipe instal lation in progress
Sub-base materials laying Sub-base materials laying in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
PVD Driving PVD Driving in progress
4 Open Deep Drain Earth Excavation,Soling,CC(CH 865-885)
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
7 Electric Substation Concrete Pouring of Column Concrete Pouring of Column in progress
Newly installed line is functioning
Old line removing Old line removing in progress
9 Laboratory / Field Test
10 Interlocking Block ILB production ILB production in progress
11 Dismantling work Mosque dismantling Mosque dismantling work in progress
12 Released Material removing MS Rod deposit to CPA store-1 MS Rod deposit to CPA store-1in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Wasa Relocation
5
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,22th Nov, 2011
Segment 1A1
Segment 13
8
Road Work
-
8/13/2019 Daily Program Nov-2011
13/19
S.l.No.
Description Work Program of 23th Nov. 2011 Achievement of 22th Nov Nov.2011 Remarks
Drainage pipe installation (CC casting) Drainage pipe instal lation in progress
Sub-base materials laying Sub-base materials laying in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
PVD Driving PVD Driving in progress
4 Open Deep Drain CC(CH 865-885) Earth excavation executed
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
Concrete Pouring of Column Concrete Pouring of Column in progress
Shuttering of slab Shuttering of slab in progress
Newly installed line is functioning
Old line removing Old line removing in progress
9 Laboratory / Field Test
10 Interlocking Block ILB production ILB production in progress
11 Dismantling work Mosque dismantling Mosque dismantling work in progress
12 Released Material removing MS Rod deposit to CPA store-1 MS Rod deposit to CPA store-1in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
3
8
Road Work
Wasa Relocation
5
Electric Substation7
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,23th Nov, 2011
Segment 1A1
Segment 1
-
8/13/2019 Daily Program Nov-2011
14/19
S.l.No.
Description Work Program of 24th Nov. 2011 Achievement of 23th Nov Nov.2011 Remarks
Drainage pipe installation Drainage pipe installation in progress
Sub-base materials laying Sub-base materials laying in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
CC(CH 865-885) Earth excavation executed
3rd lift wall casting (CH 840-865)
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
Concrete Pouring of Column Concrete Pouring of Column in progress
Shuttering of slab Shuttering of slab in progress
Newly installed line is functioning
Old line removing Old line removing in progress
9 Laboratory / Field Test
10 Interlocking Block ILB production ILB production in progress
11 Dismantling work Mosque dismantling Mosque dismantling work in progress
12 Released Material removing MS Rod deposit to CPA store-1 MS Rod deposit to CPA store-1in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Open Deep Drain4
Wasa Relocation
5
Electric Substation7
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,24th Nov, 2011
Segment 1A1
Segment 13
8
Road Work
-
8/13/2019 Daily Program Nov-2011
15/19
S.l.No.
Description Work Program of 26th Nov. 2011 Achievement of 25th Nov Nov.2011 Remarks
Drainage pipe installation Drainage pipe installation in progress
Sub-base materials laying Sub-base materials laying in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
CC(CH 865-885) Earth excavation executed
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
6 Rail Relocation Sub base preparation (CH 400-580) Sub base preparation (CH 400-580) in progress
Concrete Pouring of Column Concrete Pouring of Column in progress
Shuttering of slab Shuttering of slab in progress
Newly installed line is functioning
Old line removing Old line removing in progress
9 Laboratory / Field Test
10 Interlocking Block ILB production ILB production in progress
11 Dismantling work Mosque dismantling Mosque dismantling work in progress
12 Released Material removing
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,26th Nov, 2011
Segment 1A1
Segment 13
8
Road Work
Open Deep Drain4
Wasa Relocation
5
Electric Substation7
-
8/13/2019 Daily Program Nov-2011
16/19
S.l.No.
Description Work Program of 27th Nov. 2011 Achievement of 26th Nov Nov.2011 Remarks
Drainage pipe installation Drainage pipe installation in progress
Sub-base materials laying Sub-base materials laying in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
Rebar binding of Base (CH 865-885) CC executed
Sub base work (CH 240-340) Sub base work (CH 240-340) in progress
Improved sub grade work (180-240) Improved sub grade work (180-240) in progress
6 Rail Relocation Sub base preparation (CH 550-620) Sub base preparation (CH 550-620) in progress
Concrete Pouring of Column Concrete Pouring of Column in progress
Shuttering of slab Shuttering of slab in progress
Newly installed line is functioning
Old line removing Old line removing in progress
9 Laboratory / Field Test
10 Interlocking Block ILB production ILB production in progress
11 Dismantling work Mosque dismantling Mosque dismantling work in progress
12 Released Material removing
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Open Deep Drain4
Wasa Relocation
5
Electric Substation7
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,27th Nov, 2011
Segment 1A1
Segment 13
8
Road Work
-
8/13/2019 Daily Program Nov-2011
17/19
S.l.No.
Description Work Program of 28th Nov. 2011 Achievement of 27th Nov Nov.2011 Remarks
Drainage pipe installation Drainage pipe installation in progress
Sub-base materials laying Sub-base materials laying in progress
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
Base Casting (CH 865-885) Rebar binding & Shuttering executed
5 Rail Relocation Sub base preparation (CH 550-620) Sub base preparation (CH 550-620) in progress
Concrete Pouring of Column Concrete Pouring of Column in progress
Shuttering of slab Shuttering of slab in progress
7 Wasa Relocation Newly installed line is functioning
8 Laboratory / Field Test
9 Interlocking Block ILB production ILB production in progress
10 Dismantling work Mosque dismantling Mosque dismantling work in progress
11 Released Material removing
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
3
Open Deep Drain4
Electric Substation6
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,28th Nov, 2011
Segment 1A1
Segment 1
-
8/13/2019 Daily Program Nov-2011
18/19
S.l.No.
Description Work Program of 29th Nov. 2011 Achievement of 28th Nov Nov.2011 Remarks
Drainage pipe installation Drainage pipe installation in progress
Sub-base materials laying Sub-base materials laying in progress
Water Supply pipe Installation work
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
W all casting/1st lift (CH 865-885) Concrete pouring of Base finished
5 Rail Relocation Sub base preparation (CH 550-620) Sub base preparation (CH 550-620) in progress
Electric Sub station Shuttering of slab Shuttering of slab in progress
7 Wasa Relocation Newly installed line is functioning
8 Laboratory / Field Test
9 Interlocking Block ILB production ILB production in progress
10 Dismantling work Mosque dismantling Mosque dismantling work in progress
11 Released Material removing
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Segment 1A1
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,29th Nov, 2011
Segment 13
Open Deep Drain4
-
8/13/2019 Daily Program Nov-2011
19/19
S.l.
No. Description Work Program of 30th Nov. 2011 Achievement of 29th Nov Nov.2011 Remarks
Drainage pipe installation Drainage pipe installation in progress
Sub-base materials laying Sub-base materials laying in progress
Water Supply pipe Instal lation work Water Supply pipe Instal lation work in progress
Layout of HT Cable Trench
2 Segment 2A Settlement Record Settlement Record in progress
Sand bagging for preloading work Sand bagging for preloading work in progress
Surcharge material placement Surcharge material placement in progress
Wall casting/1st lift (CH 865-885) Concrete pouring of Base finished
5 Rail Relocation Sub base preparation (CH 550-620) Sub base preparation (CH 550-620) in progress
6 Electric Sub station Shuttering of slab Shuttering of slab in progress
7 Wasa Relocation Newly installed line is functioning
8 Laboratory / Field Test
9 Interlocking Block ILB production ILB production in progress
10 Dismantling work Mosque dismantling Mosque dismantling work in progress
11 Released Material removing
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
4
Segment 1A1
NCT BACK-UP PROJECT, CHITTAGONG
Work Program,30th Nov, 2011
Segment 13
Open Deep Drain