Page 1: DAQ Status for cosmic-ray test in RAL

DAQ Status for cosmic-ray test in RAL

Hideyuki Sakamoto

MICE Phone meeting

12th July 2007

Contents• Status• Setup for cosmic-ray test bench • Schedule

Page 2: DAQ Status for cosmic-ray test in RAL

Scheme for DAQ

• DATE (Data Acquisition and Test Environment) framework.

• Need to build modified readout program for MICE in DATE.– Other part (e.g. data format, eventBuilding) will use default one.

– Readout program is prepared for each modules.• VLSB module made by FNAL

• TDC/ADC module made by CAEN

• Sub-framework (readout+initializing) is under preparing by James.

Page 3: DAQ Status for cosmic-ray test in RAL

Status

• New RHB is coming today, taking data with test charge injection/cosmic-ray.– Threshold: 100,120,160,200,240– Bias ON & Heater ON– Try heater current to be low by heating cryostat with OXFORD temperature controller.

• Started working on DATE from last week.– Yesterday, once success to starting readout program in DATE.

…fail at 2nd try…– Should be finished in next week at RAL.

• Readout code is under implementing.– Sub-framework is almost done?– Command lists are replaced from AFEII to AFEIIt.

– Can be tested at stand alone.– Linux driver for SBS(bit3) dataBLIZZARD to test in Imperial.– In next week, test will also be done in RAL.. (using CAEN)

Page 4: DAQ Status for cosmic-ray test in RAL

Threshold 100It seems LHB RHB compared with previous version for Excel sheet.

Page 5: DAQ Status for cosmic-ray test in RAL

Threshold 120Increase noise

Page 6: DAQ Status for cosmic-ray test in RAL

Threshold 160Increase noise

Page 7: DAQ Status for cosmic-ray test in RAL

Threshold 200Decrease noise

Page 8: DAQ Status for cosmic-ray test in RAL

Threshold 240Decrease/Same? noise

Page 9: DAQ Status for cosmic-ray test in RAL

Bias ON - threshold 160 - w/o charge injection

test_pulse_033_old-excel_thre160_heater_on_bias_on

OLD version (afeIIt_vlsb_daq_810.c.xls) Previous RHB

Page 10: DAQ Status for cosmic-ray test in RAL

Bias ON - threshold 200 - w/o charge injection

test_pulse_032_old-excel_thre200_heater_on_bias_on

OLD version (afeIIt_vlsb_daq_810.c.xls) Previous RHB

Page 11: DAQ Status for cosmic-ray test in RAL

Bias ON - threshold 240 - w/o charge injection

test_pulse_031_old-excel_thre240_heater_on_bias_on

OLD version (afeIIt_vlsb_daq_810.c.xls) Previous RHB

Page 12: DAQ Status for cosmic-ray test in RAL

Comment for today’s result

• Noise rate seems to be reproduced as previous RHB.

• Noise rate seems to be reversed at threshold 160 by eye.– This may not true.

• For treatment of heater current, it is better to compare with the same RHB, so taking data with default setting with this new RHB.

Page 13: DAQ Status for cosmic-ray test in RAL

Possible reason for RHB noise

• Remember that we do not see ANY noise with test charge injection data.

• Let’s check this fact by taking data as changing triggering rate.– This will be done by LED pulse injection.

– If we take data with high rate, we cannot not see any noise as LED data.

– It not, there is problem at the setting of self trigger mode.

• Our goal is to identify/remove the noise.– If heater current is the reason, then we should see any changeable results

from it.

– We should check it by taking data with the default setting as previous.

Page 14: DAQ Status for cosmic-ray test in RAL

Run parameters

Run#, #/events,

File name

Configuration

Specify PCs for DAQ

Run options Staring data taking

Start/Stop/Abort

This is copy from ALICE web-page.

Page 15: DAQ Status for cosmic-ray test in RAL

Slow progress for DATE

Last week Yesterday Goal in RAL?

Yesterday, reach to goal, but 2nd try was failed….=> finish in next week at RAL!

Page 16: DAQ Status for cosmic-ray test in RAL

VLSB data format for new firmware (ver. “ce”)

Old Version “cc” New Version “ce”

Header First 4/5 lines (variable) 7 dummy lines (fix?)

+ Trigger location (line#8&9)

+ Discriminator hit map (line#10-17)

Body Channel address/ADC(128) Channel address/ADC(128)

Footer 2/3 lines 0 line?

TOTAL 135 145

12345678910

11

12

13

14

15

16

17

18

19

20

23

21

24

25

26

27

28

29

30

31

32

22

32-bit VLSB data

ADC ADCCounter Status bit

10 lines are added for debug information. “ce” is soon available.

-- Need to check header length to kwame --

Page 17: DAQ Status for cosmic-ray test in RAL

Check numbers for cosmic-ray test

• 2 VME crates– Slow control will be separated from DAQ crate.

• 8 AFEIIt boards– To readout 5 stations, we need 3200 channels in total.

• 8 VLSB modules– 1 VLSB is needed to readout 1 AFE board

• 1 ADC & TDC module– Used for readout defining counter

To readout 5 stations….

Page 18: DAQ Status for cosmic-ray test in RAL

Upside Define counter

Downside Define counter

Low energy filter block

Light shield box embedded 5 stations

2channles for TDC/ADC

2channles for TDC/ADC

3200(640 x5) channels for VLSB

Patch panel

Requires 4 for TDC/ADC & 3200 for VLSB

How many channels are used?

Page 19: DAQ Status for cosmic-ray test in RAL

#1 #2#3

#4#5

8 AFEIIt boards = 8 VLSB modules

How about VLSB modules?This cabling is virtual.

Page 20: DAQ Status for cosmic-ray test in RAL

Setup for test bench (R12)

V27

18

MIL

155

3

V27

18

V12

70

V17

24

VL

SB

VL

SB

VL

SB

VL

SB

VL

SB

VL

SB

VL

SB

VL

SB

V97

7

DAQ(LDC/GDC)

Slow control/Monitoring

Optical cable

Optical cable

VME crate

VME crate

Page 21: DAQ Status for cosmic-ray test in RAL

Schedule

• This week (~13th)– Checking signals for newly RHB today!

– Testing code for VLSB module in Imeprial.• Waiting for driver for SBS(Bit3) dataBLIZZARD.

– Implement readout code for new firmware (ce).

• Next week (16th ~ 20th)– Set up test bench at R12 in RAL with JSG/Mike/Nicholls/Craig/etc.

• Clone system for Geneva University

– Testing code for CAEN modules(V977, V1270, V1724) in RAL.

– To test VLSB modules in RAL, need more modules! Please send to RAL!• Imperial’s VLSB will be in use for QA.

• The week after next (23rd ~ 27th)– DAQ workshop (23,24,25)

– Finish to setup DAQ system (mainly to debug readout program, I think)

Page 22: DAQ Status for cosmic-ray test in RAL

R12Here coming 2 cryostats & 1 compressor & 1 transformer & 8 AFE boards & 5 stations & 25 inter/external waveguides & 1 patch panel & 2 VME crates & 2 NIM crates & VME/NIM modules & 2 DAQ PCs & other stuff…