MEP– Designing, Quantity Survey, Tendering, Estimation, Operation (Project
Execution), Subcontracts and Invoicing to Client & Subcontractor.
(Electrical (LV &HV), HVAC, Plumbing, Firefighting & Low Current System)
PERMANENT ADDRESS OVERSEAS ADDRESS
DEENADAYALAN. N DEENADAYALAN.N
No.15 Poonganagar Nagar No.36, 36 B Street,
Chennai, Tamil Nadu, Near Airport ,Rashidiya
India. Dubai, United Arab Emirates.
Mobile No: 00971527858822
Email-id: [email protected]
Career:
Objective: Hardworking nature with responsible, dedicative, straight forward and truthful for the right way. As involved
in all Technical and Commercial activities till Handover for Electrical, HVAC, Firefighting, Plumbing and Low
Current System. Looking for the Top management position to manage all activities as to lead the organization in
successful way for the welfare of employer and employee team.
Experience Summary:
(Heavy Construction -High Raised Buildings & Oil-Gas)
Skills: (MEP or Electro Mechanical in Designing, Quantity Surveyor, Tendering, Estimation, Contracts, Cost
Control, Procurement, Construction, Subcontracts & Business Development)
Total MEP Work Experience: 16.4 Years (India experience – 7 Years and Gulf Countries – 9 Years).
a. Operations (Projects Execution) : 7 Years ( India & abroad)
b. Tendering, Estimation & its related (Designing, Quantity Surveyor, Contracts, Cost Control &
Procurement, Operation Coordination) : 9.4 Years (India & Abroad)
Page 2 of 11
Type of Projects:
Heavy Construction & High Raised Buildings : Residential, Commercial, Software Tech Park, Hotel, shopping mall,
Hospital, Interior Fitout, Retails Stores(Different brands – NEW YORKER, ZARA ,ALDO etc. up to 63 outlets &
Restaurant.
Oil & Gas: Lead the Tendering activities for Etihad Rail, Infrastructure and Administration ,Processing Buildings in
areas for Static, Rotor, Electrical,HVAC,Fire Fighting,Plumbing,NDT,Field Joint Coating for Pipeline & Plants) for the
Client ADCO, ADNOC, KNPC, KOC, SONTRACH,ZCINA & Etihad Rail .
Employer: Worked with Consultant, Contracting Company, Real estate & Construction & EPC (Oil & Gas
Sector).
Designations lead as Site Engineer, Project Engineer, Project Manager, Business Development Engineer,
Quantity Surveyor, Estimation and Contracts Engineer, Senior MEP Estimation Engineer
1. Roles & Responsibilities (As of 16 years)
Abilities & Capabilities – Involved in Designing, Tendering, Estimation, Quantity survey, Project execution, Cost
control, Procurement, Contracts & subcontracts for technical & commercial for the successful completion of the project.
Designing & Quantity Survey - MEP: Design verification of Electrical, Mechanical, Quantities take off, BOQ from
drawings, issuing variation orders, Specification application & Preparation of RFQ with required documents as per
supporting documents
Tendering, Estimation & Contracts: Leading the team, Bidding activities of Government projects & internal projects,
Coordination with Procurement &Operations statements, estimate & negotiations, subcontractor finalization, contract
preparation to Client & Subcontractors, verifications & pre approval of procurement ,operation & financial activities,
Invoices preparations to Clients ,Prepare & verifications of Subcontractor activities, Cost Control, cash flow & reports
preparations & submission.
Contracts : Review of Contractual letters from Client & Subcontractors, drafting of contact, delays, scope of work
confirmation, agreed terms between both parties, Variation claims, Review assist of project team of variation claims,
liquidation damages, Penalty delays, Liaise with finance & legal department as per company policies and procedure.
Coordination with other relevant team.
Procurement: Floating to the vendors, follow-up, comparisons, technically & commercially evaluation, maintaining the
track records, negotiations, recommending the supplier with technical & commercial compliance to the management,
support for technical submittal.
Execution(Operations)-Heavy Construction (MEP) : Execution of Electrical -(Low Voltage, Medium voltage, High
Voltage,),Low Current-(Telephone, Data, CCTV,Fire Alarm, Public Address system, Access Control System) &
Mechanical (HVAC-Chiller,AHU,ducting,Air outlets), Fire Fighting-(Piping Pumps & Sprinklers),
Pluming(Draingae,Watersupply & Rainwater) as per executing project requirements, planning, materials requisition,
deliverables, approvals, man power & subcontractors equipment’s, shop drawings, as built drawings, Billing,
certifications, snag list, Testing & Commission, hand over.
Maintenance: Maintenance of Electrical works at staff quarters, Offices, Club, Hospital, Marriage Hall, Maintaining of
street light, Transformer, Earth pits, Panel.
Page 3 of 11
Business Development: Company profile preparation & update, registration in Govt. & Private sectors, Meeting with
consultants & Developers, Tenders purchase & submission with necessary supporting documents, Invoices submission &
follow-up, Business assessment with work progress, market analysis-Suppliers, Competitors & recruitments & Operation
Supports.
.Employer and Work Experience Details :-
2.
S.No Employer Location Work Duration Project Type Designation
1
M\s.STEEL MAN
Electro Mechanical
LLC
Dubai
,UAE April-2016 – Till date
Residential, retail shops,
Commercial, shopping malls,
Industrial Projects, Hospital,
Fitout projects.
MEP –
(Estimation ,
Tendering
Manager &
Operation)
2 FROSTERS Dubai,
UAE
July-2015 – March
2016
Dubai Design District – D3 Interior works for New Office
– 10 Floors- Low Voltage,
cable trunking,cable tray,
floor boxes, Cabling,HVAC
Works, Fire Fighting, fire
alarm, access control &
Chilled Water Piping,
accessories.
Project
Manager- MEP
3
DODSAL
ENGINEERIN &
CONSTRUCTION
PTE LTD.
(Dec-2012 – June 2015)
Dubai,
UAE
Dubai,UAE
Dec-2012 – June 2015
EMMAR (Villa Project)
Eexecution- Building, Luxury
Residential Project –Chillers,
Electrical, Plumbing,
Landscaping & Irrigation
Etihad Rail, Administration
(Project Value-9 Million
AED to 600 Million AED)
.
Senior MEP
Engineer –
Estimation,
Procurement
(Static,Rotor,Pip
e line,
Electrical,HVAC
,Plumbing,Fire
Fighting &
Subcontracts)
EPC-Oil and Gas (Pipeline
and Plant),MEP-Residential
and Administration Buildings
(Project Value- 1.3 Billion
AED to 3.3 BillionAED
4
Fawaz Al Hokair Real
Estate
(Jan-2007- Nov-2012)
Riyadh,
Saudi
Arabia
Jan 2007 – May 2011
Shopping Mall, Hotel,
College, Residential Project,
Hospitall (Project Value: 25
million AED to 350 Million
AED)
Estimation &
Contracts
Engineer-MEP
(Pre award &
Post award
projects
4.1 June -2011- May.
2012
High Raised Buildings (210
Million AED to 350 Million
AED).
Projects
Operations
4.2
Vijaya Energy Plus ,Pvt
Ltd (May 2004 -
December 2006)
Bangalore,
India
May 2004 -December
2006
Residential Project -400
flats(AKME Apartment), 12
floors – 2 buildings (Techno
park),Spring Field (12 floors)
Project Manager
Page 4 of 11
S.No Employer Location Work Duration Project Type Designation
5. Sobha Developers Ltd. Bangalore,
India
June 2003 - April
2004
Accommodation Building for
Infosys Staff.
Electrical
Engineer-Project
6.
MV Power Consultant
and Engineers Pvt
Ltd(Consultancy &
Contracting)
Chennai,
India
June - 2000 to May-
2003
Consultancy for Hall Mark
foundations, & Supervision,
Execution of Hotels, Hospital
accommodation’s project.
Assistant
Electrical
Engineer
(Estimation &
Operation’s),
Business
Development,
7
Pentasoft Technologies
Ltd ( IBM Certified
Software Professional)
Feb 2001 to Feb 2002
(One Years)- Part time
Proficiency in MS Excel,
Timberline estimation software &
Knowledge in C, C++, Autocadd,
Web designing, handling
assembling of computers.
Faculty &
Software programmer.
Education:
S.no Course Duration Graduation Percentage
of Marks School / University
1. 1996-2000
B.E (Bachelor of Engineering)
( ELECTRICAL &
ELECTRONICS)
Ist Class Annamalai University,
India
2. 1994-1996 Higher Secondary 83 S.V.M. Matriculation
Higher. Sec. School
3. 1993-1994 Matriculation 75 S.V.M. Matriculation ù.
Sec. School
4. MBA- project Management(Under pursuing) Alagappa University
5. Additional Qualification
IBM -Certified E-Business software Professional Pentasoft Technologies
Ltd,
AWARDS, HONORS AND ACCOMPLISHMENTS
Held the post of Director for Institute of Engineers (IOE) in Final year B.E. (IOE is an association of
Electrical & Electronics Department students of Engineering Institutes all over India. Role of
Director is to organize Technical Symposiums, Seminars and Competition,)
NCC “B” Grade with rating “A” (80%) ,Acted as Convener in college National level Technical
symposium
. Sound Communication skills. 2. Effective Leadership skills. 3. Good Interpersonal skills. 4. Great
Motivator. 5. Ability to inspire creativity among team members.
Page 5 of 11
Personal Skills & Qualities:
Personal Information:
Father Name : N.kuppa Naidu
Mother Name : Gunapushnam
Date of Birth :20-06-1978
Sex : Male
Marital Status : Married
Citizen :Indian
E - Mail ID : deena_elect_soft @yahoo.com
Passport No : J-3535608; Validity Till: 2020.
Area of Interest : Design, Implementation, Testing, Inspection, Transmission, R&D.
Hobbies :Reading Books, Listening music, learning day today activities
Language Known
Read & Write : English & Tamil.
Speak : Hindi, Malayalam, Telugu, Kannada.
Place : Yours Sincerely,
Date :
(DEENADAYALAN .N)
Page 6 of 11
Summary (Role and Responsibilities) :-
A. MEP - Estimation ,Tendering, Operations , M\s.STEELMAN Electro Mechanical LLC –Dubai, United
Arab Emirates
MEP Manager-Estimation and Tendering & Operations.
Pre Award :
Lead the Estimation Team & Coordination Monitoring the Operation ( Execution & Cost)
Review and study the technical and commercial related for tender received, analysis for bid to proceed, assign the
responsibilities to estimation team and quantity surveyors, procurement , prepare the BOQ, activities monitor for enquiry
floated to suppliers and subcontractors, Sort out the difficulties to reach the solution, Raise the queries to client,
Evaluate and compare the received quotation by technically and commercially as per specification, given tender terms
and condition, planning schedule., meetings for clarifications and negotiation with suppliers and subcontractors, Man
hour calculation , Prepare and review the cost BOQ with design ,specification, procurement and construction, Indirect &
direct cost, graduations, tools, fixed cost , elated. Internal discussion with procurement & Construction for competitive
cost.
Post Award :
1. Provide the tender drawings, basis, scope, planning and method of project, materials, manpower requirement, cost to
achieve, duration, mobilization and documentation.
2. Organize the project requirement for mobilization, manpower, tools, by coordinate with HR, Finance and procurement.
3. Monitor the progress activities, cost, and sort out the arising difficulties & Coordination with operations.
4. Additional work, variations, raises the variation claims, project extension for changes in variations.
A. Projects Manager - MEP , M\s.Frosters –Dubai, United Arab Emirates
Projects Manager – MEP
Execution of Project with related to MEP works Planning of activities as per the scope of work ,Reevaluate the contract
and analyses the budget cost for to set the target cost, Procurement activities, Negotation,man power requirements,
mobilization, cash flow,Organise the indirect and direct manpower , Handling the engineers and safety officers,
Meetings with Engineers and client, Preparation and Coordination of preparation shop drawings, materials submittals
and approvals, cost monitoring, Material request, Cost , negotiation and approvals, Finalizing the subcontractor with
explaining the scope of work, review the technical and commercial activities as per the project requirement and target
cost.
B .Senior MEP Engineer & Operations –Estimation & Procurement at M\s.Dodsal Engineering &
Construction –Dubai, United Arab Emirates
MEP Manager(Operations) – Execution of residential project includes with following activities as follows –
Coordination with consultant , study and review of drawings, BOQ & technical specifications, shop drawings, materials
takeoff, inputs to planning for to prepare the manpower histogram, Engineering, procurement & Construction activities.
mobilization, temporary facilities, shop drawings, material submittals, supervision of engineer, subcontractor, suppliers
for material deliverables and issuing of materials for execution, progress meeting, reports preparation and submission,
coordinate with procurement for discussion and finalization the materials and compliance.
Tendering : Cost Evaluation (Verifying technically and commercial) – Study and review the scope of work, raise the
queries for clarifications, review the MR which is received from engineering, Conduct regular meetings with engineering,
procurement and other departments, Coordination with procurement for float the enquiries, evaluate the vendor offers as
per feed , design and coordinate with engineering for technical compliance, prepare the cost comparison sheets, selection
of vendors with full compliance, Negotiation, estimate the cost for temporary facilities, home office, Site office, Direct,
Indirect Man power, equipments,Coordinate with finance,HR,procurement to collect the relevant inputs, presentation
preparation, review of techno commercial documents as per feed requirement.
Procurement: Float the enquiries, coordinate with engineering, and reply the vendor queries, meeting with suppliers for
technical and commercial clarifications & scope of work, comparison, include the in-house cost.
C .Project Engineer &Tendering Estimation and Contracts Engineer – (Electro-Mechanical) at (M\s.Fawaz
Alhokair Real Estate, Kingdom of Saudi Arabia
Page 7 of 11
Tendering, Estimation & Contracts Engineer : As a Part of Commercial Department activities involved such as
Quantity Survey, Contracts, Estimation, Tendering, Cost Control for internal and external projects such as Shopping
malls, Hyper market, Hospital, Hotels,University,Residential,Villa & Retail Outlets for the following activities as follows
Estimation: Design review, Quantities take off, Preparing Bill of quantities from design drawings, Getting quotations by
arranging relevant packages with BOQ, specifications to procurement, floating enquiry to subcontractors, evaluation,
comparison , estimate the cost and submission to Management for review and add the Overheads and profit.
Tendering: Study and design review, verify the bill quantities, and raise the queries for clarifications, Coordination with
other departments, floating enquiry with relevant details for procurement, Evaluations of offers, analyses and prepare the
cost BOQ, preparation of techno commercial submission with related.
Post Award (Operations) : Variation claims and justification to Client as approved Shop drawings, Comparison, analysis,
Evaluation, Negotiation, Finalizing the subcontractor, Comparison, negotiation to meet minimum cost within our
Estimated Price & Target Cost, Contracts Preparing & Project Coordination, verification invoices to Client, Verified the
subcontractor invoices as per scope, contract and forward the invoices to finance for processing.
Project Engineer – Execution – Low Voltage, Medium voltage, Low Current system, HVAC, Fire Fighting & Plumbing
includes Drawing Review, Coordination with design department for to prepare Shop drawing, Load calculations,
Coordinate with departments such as Design, Planning, Commercial department, procurement, fire Fighting department
for to receive the inputs for execution, Variation Claims, material submittals, material requisitions, material approvals
and Inspection, .Meetings with Site engineers, Supervisors, Subcontractors and Client & Project Manager. Progress
Reports submission, Invoices preparation to Client, Certifications. Issuing variation orders. Testing, Commissioning &
hand over.
D. Project Manager , Project Engineer-Electrical – Bangalore, India
Project Manager :
1. Study and review of scope of work, drawings, Contracts, technical specifications and budget cost.
2. Preparation of Execution methodology, manpower requirement’s (indirect, direct & administration staff), equipment’s, tools &
materials requiring for mobilization &execution.
3. Providing inputs to planning for preparing the Engineering schedules, Procurement approvals, Procurement deliverables schedule,
Construction schedule and manpower histogram.
4. Coordinating with HRD for recruiting the indirect & direct manpower for the concern position. Ensure that site administrator have
employee information’s and implementation of companies HR policies and procedures.
5. Arranging, approvals and work permit from the concerned external authorities for mobilization and start with Temporary site
facilities & Storage facilities for client and contractor.
6. Ensured that the site well equipped with safety and awareness with safety measures.
7. Get the required inputs from all departments, Keep aware and track overs and maintain a records certified record for the project
requirements incorporate the safety methodology from safety officers. Technical discussion with engineers for to prepare the shop
drawings and materials submittals from the procurement. Submission and discussion for clarifications with related approvals for
shop drawings and materials submittals from the Client. Variations with related to change in Scope and design, technical
specifications. Highlighted and discussion with client for time extension for the variations items.
8. Monitor and Coordination with procurement for comparison, discussion, selection, deliverables and finalization of items by
coordination with technical, commercial and contractual terms within target cost within scheduled time. Coordinating and
organizing the inspection with client for approvals. Pre requirement materials will be raised as Material requisitions will be
verified as per BOQ, certified will be send to procurement. Collect and monitor the progress reports and discussed for the disputes
area and get the required clearance. Evaluate and identify the productivity of assigned responsibilities. . Highlighted issues
resolved by discussed from the concern
9. Certification of progress invoices from the client and aware of the received payments. Certification of supplier’s deliverables at the
site, subcontractor’s progress quantities & work quality.
10. Assist in collection of payments with clear all disputes if any.
11. Snag list and Handover with required documents and as built drawings.
Project Engineer :
1. Raised technical query for any conflict information within the project technical document,
2. Prepared comparison report between tender documents and IFC documents in terms of materials quantities, specification and
scope of work to commercial department to claim any variations in project objectives.
3. Prepared value engineering if required by authorized authorities
4. Assisted project manager in advising on construction methodologies in coordination with other disciplines/contopi8iohghractors/
subcontractors prior to construction
5. Assisted Project Manager in supervising the construction in terms of proper method, material reservation and optimum output of
labor.
6. Engaged with planning department to define project activities within the scope of work
Page 8 of 11
7. Engaged with procurement and planning departments for defining the materials required to execute the project and provide the
technical support required to select the proper materials
8. Reviewed the technical submittal of materials and ensure its compliance with project specifications
9. Supervision & preparation of full detailed shop drawings required to execute the project
10. Obtaining of drawings and materials approvals
11. Full and extensive instruction to his team.
12. Executed the works according to the latest approved revision of drawings and /or instruction of authorized authorities.
13. Follow up of progress planning and arranging all its requirements
14. Monitoring of Subcontractor’s performance.
15. Ensure that any variations and instructions received from the client are incorporated into the latest construction issue drawings and
auctioned by the construction team
16. Ensure that the quantity surveyor is aware of any such changes (reference above)
17. Ensure pass all instructions issued to him by the authorized representatives to his manager to handle contractually prior to
commencement. However, in some cases he should act immediately and then report.
18. Analyzing and resolving field problems.
19. Reporting to management.
20. Materials take off from contract drawings
21. Materials requisition
22. Knowledge of local authority rules and regulations.
23. Responsible for all dialogue, administration with all statutory bodies.
24. Maintain an awareness of all potential risks to the company’s day to day objectives and progress of the works, this applies to
commercial risks due to delays, non-performing direct labour, sub-contractors etc. and or delays by others (3rd parties), observing
and adhering to company PQP’s and QHSE plans.
25. To ensure the Operations & Maintenance manuals as well as handover documents are in line with contract specification and
requirements
D. Assistant Engineer & Business Development , Chennai, India
Assistant Electrical Engineer
1. Prepare the tender document for Client by Assist in Designing, load calculation, preparation of drawings, quantities take off,
technical specification, prepare the bill of quantities, recommended manufacturers, contract terms and conditions etc.
2. Assist in Tender Cost estimate by floating the enquiries and get the quotations from the suppliers, fabricators &
subcontractors,followup, cost analysis, preparation of comparison sheets, highlight the cost to estimator.
3. Recommended for finalize the subcontractor to Client ,Float the tender document, assist in finalization of Subcontractors by
evaluating the quotations, cost, make of materials, analyze the company ,technical meetings and clarifications, reply for the techno-
commercial queries.
4. After award, assist in attend the inspection of materials, subcontractor work, Supervision of work.
Site Engineer & Project Coordinator:
1. As Per Engineer Instruction executed the work, review of the drawings, materials takeoff, materials requisition and supervision of
Foreman, Electricians & helpers. Surveying and Site execution of Electrical Works.Discussion with Railway Engineers,
Installation of Panels in Five Division- Cable laying, Designing, Drawings finalization and approvals,Handle the entire project,
Attending Meetings with Divisional Engineer, Senior Electrical Engineer, areas, Rates negotiation with Fabricator, workers,
Dealers. Arranging Man power, materials, Getting Approval, Planning, estimating, analysis through bar char Erection, Testing and
commissioning of Panel Board for Substation and Station Buildings at different)
Maintenance Engineer (BHEL) : Maintenance of Electrical works at BHEL staff quarters ,Offices, Club ,Hospital, Marriage Hall ,internal wiring, conduiting,
Boxes, lighting fixtures Maintaining of street light, Transformer, Earth pits, Panel.
Business Development
Preparation & update the Company Profile, Register the Companies in Government Sector & private sector with required documents, meeting
consultant, Builders to get new projects, Analyse the market information and provide inputs to tendering department, Purchase and submission
the Bidding document by submitting the relevant documents, Co-ordinate with Clients, clarification from consultants, negotiations & pretender
meetings & post award meetings,followup the business activities.
Detailed Employer ,Work Period involved in List of Projects (Refer-Part 2)& Nature of work
Page 9 of 11
Annexure-I (Project Details)
S.No Employer Work
Duration Project Location
Project
Type Role & Responsibilities
1 STEELMAN April 2016-
till date
High raised
buildings Dubai
MEP Manager– Tendering and
Estimation & Operations
2 FROSTERS June 2015 –
March 2016
D3-Dubai
Design District
– 10 & 11 (10
Floors),
Dubai,
United
Arab
Emirates
Commercial
office.
Execution of MEP Works such as
Low Voltage, Telephone ,Data
,HVAC ,Fire Fighting & Plumbing
3
DODSAL
ENGINEERING &
CONSTRUCTION
PTE Ltd .Dubai,
UAE
December
2012 to June
2015 (2 year
6 month)
EMAAR Dubai Residential
MEP Manager- Operation \
Execution- Electrical (LV &Low
Current- Telephone, data,
CCTV,Audio Visual System,) HVAC
(Chillers, AHU, Ducting & Air
outlets),Plumbing, Fire Alarm,
Swimming Pools, Landscaping &
Irrigation system.
Etihad Abu Dhabi Railways
Oil & Gas -Pipe Line & Plant –
Bidding activities
Senior MEP Estimation and Contracts
Engineer –Dubai, United Arab Emirates
Cost Evaluation (Verifying
technically and commercial) Study the
Scope of work which is given in Client
document, Verify & review the client
feed document & raise the queries, Float
the enquiry to vendors in behalf of
procurement, evaluate technically &
commercially the received offers with
our feed documents. Prepare and
compare the cost estimate, vendor,
Temporary facilities, Home office &
Site office, Direct, Indirect Man power,
tool and tackles, equipment’s related,
Coordination with finance, HR,
Procurement to collect the relevant
documents, presentation preparation,
Submission of Cost estimate to
Estimation head for review and
approval. After award Detailed
Engineering co-ordination with
procurement, contracts and Projects.
ADCO-NEB-
Rumaitha
&Shanayel
Abu Dhabi Pipe line
&plant
KOC-Feed Pipe
line Kuwait Pipe line
Sonatrach Algeria Compression
& Pipe line
KNPC-
Revamping &
Expansion of
Ahmadi Depot
Kuwait
Plant -Storage
Tank & its
utilities –
Brown field
project
KOC-Lower
Fars Heavy Oil
Project
Kuwait Pipe line &
Plant
Aramco-MGS Saudi Pipeline
project
ADCO-Al
Dabiyah Abudhbai
Pipe line &
Plant
Zanzibar Tanzania Resort
Page 10 of 11
S.No Employer Work
Duration Project Location
Project
Type Role & Responsibilities
4
Fawaz Alhokair
Real Estate Ltd
(Riyadh, Saudi
Arabia)
Private Projects:
1. Mall of Arabia.
2. Mall of Dharan
Extn.
3.AlNoorMall
4.Marriot Courtyard
5.Sheraton Four
Points
6. Hofuf Mall.
7.Makkah Mall
8..Salam Mall
Jan 2007 to
November
2012 (Nearly
6 Years)
Mall of Arabia,
Noor Mall,
Dharan Mall,
Makkah Mall,
Salam
Mall,Hofuf Mall
Madina,
Saudi
Arabia
Shopping Mall
1.Estimation & Contracts
Engineer: Design verification,
Preparing Bill of Quantities from
Drawings, Estimation, Design
verification , Prepare Budget ,Cost
Control ,Receiving quotations and
finalise the subcontractors ,
Procurement Coordination, assisting
with Contracting Manager, issuing
variation orders & Claim variations to
Client, processing the invoices for
Complete Electro-mechanical works
(Electrical - Low voltage, High Voltage,
Low Current system), HVAC-Chilles,
DX units, Ducting, Grills & Diffuser,
Plumbing, Fire Fighting.
Hypermarket –
Geant & Hyper
Panda - Wafa
Tower, Salman
Compound
Marriot Court
yard ,Grand
Hyatt, Aloft
Hotel, Sheraton
Four points
Jeddah,,
Madinah,
Hofuf,
Makkah,
Riyadh,
Sheikh
family
Riyadh,
Jeddah,
Saudi
Arabia
Residential
Hotel (52
floors,22
floors)
Saudi
Government
Projects:
Najran Hospital
((790 Beds), &
Khurais
Hospital (250
Beds)
145,000 Sq.m
Saudi
Arabia Hospital
Technical, Commercial, Project
managing activities, Subcontract
handling activities of Electrical (LV and
HV), Low Current systems HVAC,
Plumbing and other activities.
Faculty of
Dental, Faculty
of
administration
science.
Najran,Sau
di Arabia University
Private Projects
High Raised
building
Saudi
Arabia
Residential \
Hotel
\Shopping
Mall
3
Vijaya Energy Plus
Pvt Ltd (Bangalore
,India)
May 2004 -
Dec 2006
(2 Yrs.7
month)
Sigma Softech
park (12 Floors,
2 Buildings) –
(Value-13
million USD)
Bangalore,
India
Commercial
Building \
Interior work \
Software
Technology
Park. (12
floors – 2
Buildings)
Project Manager
AKME Project
Ltd
(9 Blocks,
8Floors)
Bangalore,
India
Residential \
Apartments(40
0 flats)
Project Engineer
Spring Fields (3
Blocks,12
Floors)
Bangalore,
India
Residential \
Apartments Project Engineer
4
SOBHA
Developers Pvt Ltd
., (Bangalore,
India)
June 2003 -
April 2004 (
11 Months)
Infosys Project Mysore,
India
Software
Project
Electrical Engineer- ( Execution of
Electrical works for Staff
Accommodation)
5
MV Power
Consultant
Engineers & Ltd
June 2002 to
May 2003
(1Yrs.0
Month)
Mount Abu
Palace
Chennai,
India Hotel
Site Engineer – Execution of Electrical
works, Preparing shop drawings,
Quantity Surveying.
BHEL(Bharat
Heavy Electrical
Ltd)
Tamil
Nadu, India Industry
Maintenance Engineer- Maintenance
of Electrical works at staff quarters
,Offices, Club ,Hospital, Marriage Hall ,
,Maintaining of street light ,
Transformer ,Earth pits, Panel
Page 11 of 11
S.No Employer Work
Duration Project Location
Project
Type Role & Responsibilities
Southern
Railways
(Chennai)
Chennai
India
Railways
Projects
Project Co-ordinator- Discussion with
Railway Engineers, Installation of
Panels in Five Division- Cable laying,
Designing, Drawing, Erection, Testing
and commissioning of Panel Board for
Substation and Station Buildings at
different areas.(Handle the entire
project, Attending Meetings with
Divisional Engineer, Senior Electrical
Engineer, Rates negotiation with
Fabricator, workers, Dealers. Arranging
Man power, materials, Getting
Approval, through bar chart
5.1
June 2000 to
May 2002
(2 Yrs.)
Assistant Electrical Engineer
(Estimation)
Assist in Designing, Tendering,
Estimation, Verifying the Bill of
quantities. Float the enquiries and
follow up with vendors, arranging the
quotations
Meeting suppliers, fabricators to get the
quotation
cost analysis, preparation of cost sheets
Reports submission to MD, Invoices
processing. Material submittal and
approval.
Supervision, inspection, verifying
material submittals.
Business Development :
Company profile preparation &
update, registration in Govt. &
Private sectors, Meeting with
consultants & Developers, Tenders
purchase & submission with
necessary supporting documents,
Invoices submission & follow-up,
Business assessment with work
progress, market analysis-Suppliers,
Competitors & recruitments & Site
supports.
6
Penta Soft
Technologies Pvt
Ltd, (Chennai,
India)- IBM ( E-
Business Certified
Software
Professional)
June 2000 to
July 2001
(Part Time)
MS-office,Java,ASP, C, C++, MS
Primavera , AutoCAD, Faculty,
Software Programmer, System
Administrator , Knowledge in
Assembling, Installation of computer
and rectifying Trouble shooting of
computers, printers.
Place : Dubai
Yours Sincerely,
Date : (DEENADAYALAN .N)