Delivery Ring AIP
Jerry AnnalaDec 12, 2012
![Page 2: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/2.jpg)
µScope
Beam line aperture improvements Beam line power supply upgrades Delivery Ring injection Delivery Ring abort system Collider equipment removal Delivery Ring power supply
upgrades Infrastructure Instrumentation upgrades
![Page 3: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/3.jpg)
µBeam line aperture
MI-52 Lam. / V701 C-magnets
V714 C-magnets
Tev. F0 Lambertsons F-17 C-
Magnets HV100 dipoles
HV102 dipoles
Larger trims
Large aperture quads
Jim Morgan
![Page 4: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/4.jpg)
µBeam line apertures
![Page 5: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/5.jpg)
µInjection Septum
54 mm
upstream
upstream
downstream
downstream
Jim Morgan
Circulating beam
Injected beam
40 pi-mm-mr
Modified version(wider pole gap) ofBooster BSE
Technical DivisionT. J. GardnerSasha MakarovGueorgui Velev
![Page 6: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/6.jpg)
µInjection Septum
![Page 7: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/7.jpg)
µ
Booster Extraction Septa
![Page 8: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/8.jpg)
µInjection Large Quad
LQx
8Qx
Upstream
Downstream
Circulating
40 pi-mm-mrad
Jim Morgan and Steve Werkema
![Page 9: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/9.jpg)
µInjection kicker aperture
40 pi-mm-mrad
Jim Morgan
![Page 10: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/10.jpg)
µ
Magnet
Injection and AbortKicker
Flourinert skid
Power Supply
![Page 11: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/11.jpg)
µ
the Delivery Ring
Brian Drendel
![Page 12: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/12.jpg)
µAbort System
![Page 13: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/13.jpg)
µCollider equipment removal
![Page 14: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/14.jpg)
µ
Functional Requirements
Provide adequate aperture for 8 GeV primary proton beam to the new M3 beam line (through P1, P2, and M1 line)– Un-normalized transverse emittance – 2 p-mm-
mrad– Dp/p < .23%
Provide an injection system capable of accepting beam specified above at an average rate of 12 Hz with a burst rate of 100 Hz
Provide an abort system capable of removing beam within 10 msec of a detected fault condition
Provide an un-normalized ring admittance of 40 p-mm-mrad and a Dp/p of .23%
![Page 15: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/15.jpg)
µ
Functional Requirements
Provide the electrical infrastructure improvements necessary in the existing antiproton source buildings to support the operation of g-2 and Mu2.
Provide needed upgrades to power supply systems that use obsolete components or have insufficient regulation capabilities.
Provide instrumentation suitable for use for g-2 and Mu2e operation– SEMS with reliable high gain amplifiers– BLMs that can be used with high intensity proton
beams– BPMs that function with 2.5 MHz beam structure
with expected repetition rates– Toroids general maintenance needed for reliability
![Page 16: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/16.jpg)
µProject Plan
Baseline CostsWBS Name Base
cost with escalation
Contingency
Indirect costs
Total
1 Delivery Ring AIP $4,977,411
$2,107,643 $2,481,736
$9,566,789
1.01 Project management $99,969 $55,569 $85,262 $240,800
1.02.01 Transport general $56,258 $33,144 $54,222 $143,624
1.02.02 Beam line modifications $511,913 $228,167 $248,645 $988,725
1.02.03 Beam line instrumentation
$308,438 $177,048 $201,835 $687,321
1.02.04 Beam line infrastructure $70,340 $38,431 $46,000 $154,770
1.03.01 Ring general $92,659 $54,589 $89,304 $236,552
1.03.02 Ring injection $1,317,107
$533,451 $461,064 $2,311,622
1.03.03 Ring modifications $504,080 $284,108 $329,627 $1,117,815
1.03.04 Abort system $1,297,376
$588,974 $621,272 $2,507,622
1.03.05 Ring instrumentation $142,511 $75,445 $108,361 $326,317
1.03.06 Ring infrastructure $576,760 $38,717 $236,144 $851,621
![Page 17: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/17.jpg)
µ
Escalation and Contingency
Escalation– M&S = 2.7%/year– SWF = 2.7%/year
Contingency Average = 30%
![Page 18: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/18.jpg)
µFunding Profile
FY13 FY14 FY15 FY16 TotalLabor
SWF base escalated $1,957,762
SWF indirect costs $1,872,654
Subtotal $3,830,416
SWF Contingency $1,105,469
Total $4,935,885
M&S
M&S base escalated $3,019,648
M&S indirect cost $609,080Subtotal $3,628,72
8M&S Contingency $1,002,17
7Total $4,630,90
5Total
SWF+M&S base esc $4,977,410
SWF+M&S Indirects $2,481,734
Subtotal $7,459,144
SWF+M&S contingency $2,107,646
Total $699,676 $1,078,618
$7,142,637
$645,855 $9,566,790
![Page 19: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/19.jpg)
µLabor by Categories
Category FY13 FY14 FY15 FY16 TotalEngineering Physicist .55 1.03 2.18 .36 4.12App Dev & Sys Analyst .15 .15 .15 .45Electrical Engineer .18 .15 1.22 .85 2.4Mechanical Engineer .43 .48 1.88 .01 2.8Electrical Technician .27 .45 3.49 1.17 5.38Mechanical Technician .08 .23 1.99 .13 2.43Electrical Drafter .25 .07 .32Mechanical Drafter .07 .14 .64 .85Geodesist .11 .07 .18Metrologist .05 .01 .06Accelerator Physicist .45 .45Mechanic .09 .09FESS Engineer .07 .07Magnet Engineer .16 .16Magnet Technician .23 .23TOTAL 2.12 2.79 12.49 2.54 19.94
![Page 20: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/20.jpg)
µFY 13 M&S
Prepare magnets for P1, P2, M1 aperture improvement
Procure hardware for kicker controls
WBS Name FY131.02.02.01 Beam line magnets $41,5801.03.02.02.02
Injection Kicker Controls $37,500
1.03.04.03.02
Abort Kicker Controls $37,500
![Page 21: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/21.jpg)
µFY 14 M&S
Riggers for beam line magnet installation
Vacuum parts for beam line magnet installation
WBS Name FY131.02.02.03.02
Beam line magnet installation
$124,800
![Page 22: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/22.jpg)
µFY 15 M&S
WBS Name FY131.02.02.02 Transport line power supplies $286,4551.02.04.03 Transport line infrastructure $27,0611.03.02.01 Ring injection general $697,0001.03.02.02.02 Injection kicker power supply $212,5001.03.02.02.01 Injection kicker magnet $6,0001.03.02.02.02 Injection kicker flourinert system $80,0001.03.04.03.02 Abort kicker power supply $252,5001.03.04.03.01 Abort kicker magnet $6,0001.03.04.03.02 Abort kicker flourinert system $80,0001.03.04.01 Abort system general $300,9001.03.04.02 Abort Dump $103,0001.03.06.03 Ring Infrastructure $396,0001.03.03.02 Ring power supplies $70,0001.03.03.03 Ring mechanical and vacuum $67,0001.03.03.01 Collider equipment removal $53,0001.02.03 Beam line instrumentation $116,9501.03.05 Ring instrumentation $35,000
![Page 23: Delivery Ring AIP](https://reader036.vdocument.in/reader036/viewer/2022062310/56816252550346895dd29a7c/html5/thumbnails/23.jpg)
µMilestones
Milestone Definition BaselineStart Project Directive signed, funding available Month 0Transport aperture improvement complete
All magnet replacements complete from P1 line stub to target vault
Month 18
Complete Infrastructure Improvements
Complete building wiring necessary for new circuits and have floor space available
Month 30
Complete Collider equipment removal
Remove all obsolete ring devices that limit the aperture
Month 30
Complete Injection system
Install kicker, septum, large quad and power supplies
Month 35
Complete Abort system
Install kicker, septum, power supplies, beam line and dump
Month 35
Project Complete Project closed Month 36