DEPARTMENT OF PUBLIC WORKSDEPARTMENT OF PUBLIC WORKS
PPRESENTATION TO PORTFOLIO COMMITTEERESENTATION TO PORTFOLIO COMMITTEEON PUBLIC WORKSON PUBLIC WORKS
07 SEPTEMBER 201007 SEPTEMBER 2010
2
TABLE OF CONTENTSTABLE OF CONTENTS
• Strategic Context• Implementation of the Strategic Plan in relation to the
Budget of the Department• Under-spending on Provision of Land & Buildings;• EPWP Incentive grants update;• Re Kgabisa Tshwane and the Inner City
Regeneration Programme;• Legislative Plan;• Profile of Vacancies;• Progress report on the Asset Register; and• Implementation of GIAMA.
3
Strategic Context
• MTSF
• Sector outcomes
• DPW’s strategic priorities
• Performance Agreement of Minister with the President
• Risk Management
Implementation of the Strategic Plan in relation to the Budget of the Department
5
PROGRESS/ ACHIEVEMENTS PER PROGRAMME/ SUB-PROGRAMME
• Programme 1: Finance & SCM
Key deliverable Target Progress/Achievements
Implemented action plan for GAAP compliance on PMTE
70% Business case and terms of reference for the system developed
Improved revenue & debtors management on the PMTE
50% reduction
80% collection
Debtors book has increased
Collection has decreased
Improved internal controls 90% implementation (7 policies)
Four policies developed (debtors management, movable asset management, entertainment, revenue and suspense account)
Improved management of movable assets
90% compliance Asset count is progressing as planned. Appointment of Sekela Consulting is underway. The project will be rolled out to the remaining regional offices
Payment of invoices 80% A significant improvement on the management of invoices noted.
6
PROGRESS/ ACHIEVEMENTS PER PROGRAMME/ SUB-PROGRAMME
• Programme 1: Finance & SCM
Key deliverable Target Progress/Achievements
Improved supply chain management
80% compliance
10% SLA achieved
PROQUOTE – monthly meeting to address regional challenges after system implementation. TRAINED OFFICIALS – 2 Bid Admin officials attended PFMA course. Processed application (accredited) 406
7
PROGRESS/ ACHIEVEMENTS PER PROGRAMME/ SUB-PROGRAMME
Business unit Key deliverable Progress/Achievements
Information Services Enabling IT systems to support core operational areas (IE works)
The integration of IE works is at 85% completion, the process is progressing as planned
Human Resource Management
Human Resource Management Plan
Reduced vacancy rate
The structure is been reviewed and updated
453 critical posts were identified and approved, the process of filling these positions is underway
Gender Implementation of the disability strategy
Against the target of 2%, total number of Persons with Disability is 56 = 1.15% against the total staff complement of 5039
International Relations Transfer critical skills courtesy of international bilaterals and agreements
12 draft MoUs on infrastructure development currently under discussion and consideration by counterparts
• Programme 1: Corporate Services
8
Key deliverable Target Progress/Achievements
Accurate and complete information on immovable asset register
90% populated
97 705 properties
The asset register is 80% of target complete.
78 164 properties
National vesting plan 55%
19 660 land parcels
The plan has been completed and circulated for implementation – 52 contract workers will resume duty mid September 2010
Approved amnesty call strategy 100% completed strategy The strategy is 85% complete
Condition assessments Uniform template finalized, circulated to regions and provinces for inputs
Service level agreements with client departments
Signed SLA for all client departments
SLAs submitted to 41 client departments, Human Rights Council & SARS has signed the SLA’s. The process to have client departments signing off will be fastracked
Implemented AIM programs (Energy and water efficiency, accessibility and rehabilitation)
Accessibility – 64 buildings
Rehabilitation – 64 buildings
193 buildings identified for the accessibility program, while 67 are been rehabilitated
• Programme 2: Immovable Asset Investment Management
PROGRESS/ ACHIEVEMENTS PER PROGRAMME/ SUB-PROGRAMME (cont…)
9
Key deliverables Target Progress/Achievements
User Asset Management templates 1-12 90% UAMP templates completed and submitted to 40 clients
Implementation of GIAMA
Well managed immovable assets in line with property portfolio strategies
70% 33% of portfolio strategies developed
Effective CAMPS 70% 22% of CAMPS completed
Developed strategies to increase revenue on superfluous but not redundant state assets
10% 0.25% of revenue increased
Disposal program Foreign properties – 20
Properties for commercial purposes - 30
13 Foreign properties approved for disposal, while 14 are disposed for commercial purposes.
• Programme 2: Immovable Asset Investment Management
PROGRESS/ ACHIEVEMENTS PER PROGRAMME/ SUB-PROGRAMME (cont….)
10
Key deliverables Target Progress/Achievements
Effective release of land for reform purposes
55 properties 34 properties disposed
Effective release of land for housing and agricultural purposes
1 000 hectares of Land parcels
1067.47 hectares of land disposed for human settlement purposes
• Programme 2: Immovable Asset Investment Management
PROGRESS/ ACHIEVEMENTS PER PROGRAMME/ SUB-PROGRAMME (cont…)
11
• Programme 2: Inner-City Regeneration
Key deliverables Progress/Achievements
Revitalization and development of rural towns to serve as centres for rural economies
Focus will be on Tshwane (Salvokop) as there is no budget allocation to extend the programme
Maximize utilization of state properties within major cities
Spatial research is been conducted for Matatiele and Mthatha with the view of developing Government Precincts
Construction of capital projects 19 client capital projects and 37 DPW capital projects are underway, including 3 BCOCC Capital Projects that are under construction stage – (rolled over projects)
Construction of maintenance projects 28 planned maintenance projects are underway
PROGRESS/ ACHIEVEMENTS PER PROGRAMME/ SUB-PROGRAMME (cont….)
12
• Programme 2: Special Projects
Key deliverables Progress/AchievementsBuilt and upgrade 2010 stadia The projects were 100% completed
and handed over
GOLELA (Swaziland) 90% complete
Vioolsdrift ( Namibia) 100% complete
SKILPADHEK (Botswana) 85% complete
LEBOMBO (Mozambique) 100% complete
PROGRESS/ ACHIEVEMENTS PER PROGRAMME/ SUB-PROGRAMME (cont…)
13
• Programme 2: Regional Operations
Key deliverable Target Progress/Achievements
Total number of capital projects = 3447
80% completion of capital projects
Client Capital = 1472
DPW Capital = 552
Planned maintenance = 1423
117 projects (status 6A:Practical completion-278 projects (Status 7-Final delivery)-33 projects (status 8)
Procured leased accommodation
3028
Property and facilities management and maintenance projects
cleaning services (557), day-to-day maintenance (± 4950) , municipal services (state) (7480) and municipal services (leased) (1743)
PROGRESS/ ACHIEVEMENTS PER PROGRAMME/ SUB-PROGRAMME
14
• Programme 4: Construction & Property Policy
Key deliverables Progress/Achievements
Contribution to the review of the Ministerial handbook
The review of Chapter 4 is currently underway
Review and development of DPW White Paper
ToRs has been developed
Construction and Property Charter implementation
The Construction Charter Constitution amended as per DPW requirements. The process of launching the Charter Council is underway. Property Charter Council continued with engagements with DTI on Section 9 application.
PROGRESS/ ACHIEVEMENTS PER PROGRAMME/ SUB-PROGRAMME
FINANCIAL PERFORMANCEFINANCIAL PERFORMANCE
UNDER-SPENDING ON PROVISION OF LAND & BUILDINGS
16
Financial Performance per ProgrammeFinancial Performance per Programme
Programme Adjusted budget allocation 2009/10
R’000
Expenditure as at 31 March 2010
R’000
% Exp
Prog 1
Administration 774 228 773 431 100%
Prog 2
Provision of Land and Buildings 4 390 594 4 170 356 95%
Prog 3
National Public Works Programme 837 177 697 223 83%
Prog 4
Auxiliary and Associated Services 47 131 46 207 98%
Total 6 049 130 *5 687 217 94%
*Amounts reported here differ from those reported to National Treasury as the Departments’ accounts were still open when reporting to National Treasury. The amounts reported here takes the Audit journals into account
17
Expenditure Report 2009/10- Programme TwoExpenditure Report 2009/10- Programme Two
Subprogrammes Final Appropriation
Expenditure Exp
%
Infrastructure 1 462 325 1 253 581 86%
Property Management 2 200 264 2 194 225 100%
Asset Management 139 594 138 835 100%
Augmentation of PMTE 588 411 588 411 100%
Total 4 390 594 4 175 052 95%
18
Expenditure Report 2009/10- Programme ThreeExpenditure Report 2009/10- Programme Three
Economic classification Final Appropriation
Expenditure Exp
%
Compensation of employees 72 716 60 670 83%
Goods and services 121 817 118 055 97%
Transfers and subsidies 641 091 513 184 80%
Capital assets 1 553 1 553 100%
Total 837 177 693 462 83%
19
Breakdown of Capital Budget - InfrastructureBreakdown of Capital Budget - Infrastructure
Item
Allocation
R’000
Adjustment/Roll-over
R’000
Final Allocation
R’000
Expenditure
R’000
% Exp
Departmental 58 260 6 187 64 447 58 178 90%
Accessibility for disabled people 20 000 20 000 14 614 73%
Dolomite Risk Management 25 376 25 376 21 168 83%
Land Ports of Entry 668 284 17 101 685 385 643 306 94%
Prestige 415 569 34 113 449 682 390 342 87%
RKTP / ICR 33 150 54 285 87 435 80 117 92%
Macro Re-organisation of the State 130 000 130 000 45 859 35%
TOTAL 1 220 639 241 686 1 462 325 1 253 584 86%
20
Reasons for under spending on the infrastructure Reasons for under spending on the infrastructure budgetbudget
• Departmental– Delay in payment as part of DPW’s contribution to the
replacement of the research base on Marion Island
• Accessibility for people with disabilities– Non responsiveness of the bidders delayed the appointment
of service providers– Cancellation of SAPS facilities as part of the programme due
to devolution process– Change in the initial scope of works– Funds were spent against 126 of the 137 allocated projects
21
Reasons for under spending on the infrastructure Reasons for under spending on the infrastructure budgetbudget
• Dolomite Risk Management– Delay in procurement of specialist consultants and
contractors required to implement programme successfully
• Land Ports of Entry– Skilpadhek: The project was delayed due to negotiations for
the acquisition of a portion of a property in the middle of Border Post footprint. This is a National Key Point and the property had to be acquired
– Lebombo: The One Stop Border Post project initially planned for Lebombo had to be restructured into phases due to financial constraints. Legal implications relating to operations and construction required on foreign territory further hampered the execution of the project
22
Reasons for under spending on the infrastructure Reasons for under spending on the infrastructure budgetbudget
• Prestige– Under-expenditure due to delays experienced in the
acquisition of Prestige house. This was caused by:• Suitability and availability of houses( challenge)• Price negotiation process (challenge)
• Inner City Regeneration – Delay in obtaining approval for additional work at the
Government Garage (accommodation for Government Printer)
– Delay in the procurement process to appoint consultants for the joint DPW and Tshwane Inner City Precinct Plan
• Procurement process has been finalised and the consultants consortium will be appointed shortly
23
Reasons for under spending on the infrastructure Reasons for under spending on the infrastructure budgetbudget
• Macro Re-organisation of the State– Funding to the amount of R 150 million was made available– R 130 million of this amount was allocated to the provision of
accommodation while the balance of R 20 million was allocated to the procurement of furniture for houses and offices
– The amount allocated was to be used for residential and office accommodation
– Accommodation to be acquired or leased depending on the need of the Client and the availability of accommodation
24
Infrastructure Expenditure
-
500,000
1,000,000
1,500,000
2,000,000
2007/08 2008/09 2009/10
Budget
Expenditure
57%
87%
86%
25
Funding of the IDTFunding of the IDT
• A request amounting to R800m over the MTEF period was included in the Department’s Policy Options submitted to National Treasury
• This amount is made up of R200m, R300m & R300m for the 2011/12, 2012/13 and 2013/14 financial years respectively
• The Department presented to MTEC on 26 August 2010 where this was once again emphasized as one of the Department’s priorities in terms of request for additional funding
• The Department now has to await the final MTEC outcome.
26
EPWP INCENTIVE GRANTS EPWP INCENTIVE GRANTS UPDATEUPDATE
27
Introduction
• The EPWP incentive has now been introduced to all sectors of the EPWP from the 10/11 financial year.
• The Infrastructure sector incentive is applicable to Provincial Departments and Municipalities.
• The Environmental sector incentive is applicable to National Departments through their appropriations from National Treasury.
• The Non-state sector grant is paid to Non-Government Organisations ( NGOs) and Non-Profit Organisations through the Independent Development Trust ( IDT) which was appointed as the intermediary.
• The Social sector grant is paid as a schedule 5 grant to Provincial DSD and DoE
28
- Develop and review of policy framework for incentive
- Determine targets, thresholds and incentive allocations
- Provide technical support- Verify and report data for incentive payments- Audit public bodies – compliance to incentive
requirements
Role of eligible Public bodiesRole of DPW
29
- Prepare EPWP project plans i.r.o. targets
- Register and implement EPWP projects
- Update project information monthly
- Maintain project documentation and records for audit purposes
Role of Public bodies
30
Role of Provincial Treasury
- Disburse incentive to Provincial Departments
- Monitor incentive spending and compliance to the
Division of Revenue Act (DORA)
31
Role of National Treasury
- Monitor compliance of DPW and Public Bodies to DORA i.t.o. the incentive
- Monitor spending by DPW and Public Bodies on the incentive
- Support DPW in the development of the incentive policy framework
32
Province Incentive allocation for the 09-10 financial year
(R’000)
Incentive payment for 3rd quarter 09-10
( R’000)
Cumulative Incentive payment after 3rd quarter 09-10
(R’000)
Percentage of the 09/10 incentive allocation paid (%)
Eastern Cape ‘29,992 15,381 17,457 58%
Free State 23,008 0 0 0%
Gauteng 500 0 0 0%
KwaZulu-Natal 84,180 35,100 84,854 101%
Limpopo 500 0 0 0%
Mpumalanga 5,047 0 0 0%
Northern Cape 500 0 0 0%
North West 7,192 0 0 0%
Western Cape 500 3,152 14,269 2,854%
Total 151,419 53,633 116,581 77%
Performance on the EPWP incentive grant by Provinces after 3rd Quarter 09/10 financial year ( paid in 4th quarter 09/10)
33
Province Incentive allocation for the 09-10 financial year
(R’000)
Incentive payment for 3rd quarter 09-10
(R’000)
Cumulative Incentive payment after 3rd quarter 09-10
(R’000)
Percentage of the 09/10 incentive allocation paid (%)
Eastern Cape 53,559 3,905 7,818 15%
Free State 9,073 1,047 1,956 22%
Gauteng 34,881 51,038 59,875 172%
KwaZulu-Natal 39,974 15,038 26,102 65%
Limpopo 18,328 2,626 6,140 34%
Mpumalanga 13,454 1,468 2,453 18%
Northern Cape 15,496 960 5,769 37%
North West 9,694 1,493 2,787 29%
Western Cape 7,289 708 1,271 17%
Total 201,748 78,644 114,170 57%
Performance on the EPWP incentive grant by municipalities after 3rd Quarter 09/10 financial year ( Paid in the 4th quarter of the 09/10 financial year).
34
Performance on the EPWP infrastructure incentive by Provinces after the 1st Quarter of the 10/11
financial year reporting
Province Infrastructure Incentive allocation for the 10/11 National financial year (R’000)
1st Quarter incentive payment for the 10-11 financial year
(R’000)
Total incentive disbursed
In the 10/11 financial year (R’000)
Percentage of the 10/11 incentive disbursed (%)
Eastern Cape 60,354 5,640 19,011 3%
Free State 13,767 817 817 6%
Gauteng 38,821 0 2,498 6%
Kwa-Zulu Natal 169,470 28,896 59,300 35%
Limpopo 2,903 0 2,617 90%
Mpumalanga 18,074 0 0 0%
Northern Cape 1,167 0 0 0%
North West 2,897 0 0 0%
Western Cape 23,218 0 1,700 7%
Total 330,671 35,352 85,943 26%
35
Performance on the EPWP infrastructure incentive by Municipalities after 1st quarter 10-11
reporting
Province Infrastructure Incentive allocation for the 10/11 National financial year (R’000)
1st Quarter incentive payment for the 10-11 financial year
(R’000)
Total incentive disbursed
In the 10/11 financial year (R’000)
Percentage of the 10/11 incentive disbursed
Eastern Cape 97,806 6,844 16,182 17%
Free State 34,400 1,402 1,539 4%
Gauteng 165,048 69,984 110,476 67%
Kwa-Zulu Natal 123,613 18,056 42,526 34%
Limpopo 55,355 4,955 16,195 29%
Mpumalanga 37,288 568 602 2%
Northern Cape 50,399 1,889 1,931 4%
North West 36,049 1,887 9,400 26%
Western Cape 26,038 823 1,408 5%
Total 622,996 106,119 200,259 32%
Inner-City Regeneration ProgrammeInner-City Regeneration Programme
37
Inner-City Regeneration ProgrammeInner-City Regeneration Programme(Overview)(Overview)
• As per cabinet memorandum of 2005, objective is to improve the physical work environments of the headquarters of National Government departments in the Inner City of Tshwane.
• Inner City regeneration of Tshwane & metropolitan Cities is the core responsibilities of Municipalities & DPW’s role in contributing to this is to upgrade its buildings in line with the spatial development planning framework (SDF).
38
Inner City Regeneration Programme (Over Inner City Regeneration Programme (Over view cont’d)view cont’d)
• Memorandum of Understanding for the RKTP signed in November 2005 between the DPW and the CTMM, as well as the involvement of the Gauteng Province
• MOU for the RKTP signed in February 2006 between the DPW and National Treasury
• Participate in other Cities using the same principle, i.e. Upgrading of State buildings for use by National Government department’s in line with SDF of respective local authority
39
• Improve office accommodation to an acceptable norm;
• Jointly develop solutions with departments
• Improve urban environment, including urban security, public spaces, and accessibility
• Attract private sector investment
• Contribute to Inner City renewal and rejuvenation
• Develop the image of Tshwane as an important capital city in Africa
• Contribute to BEE
OBJECTIVES of RKTPOBJECTIVES of RKTP
40
LEGISLATIVE PLAN FOR DPWLEGISLATIVE PLAN FOR DPW
41
Agrément South Africa (ASA)Agrément South Africa (ASA)
1. Agrément SA was established through a delegated authority by the then Minister of Public Works in 1969;
2. The Department has began a process of reviewing the governance of ASA as well as its performance and effectiveness;
3. After approval by the Public Works Minister, the Business Case will be submitted to the Joint Committee of the Ministries of Public Service and Administration and Finance (the JEC) for establishment of Agrément as a Schedule 3 entity;
4. The draft Bill will then be submitted to Parliament
42
Expropriation BillExpropriation Bill The Expropriation Bill [B16-2008], was withdrawn from
Parliament in September 2008 • The Department is currently finalising a discussion
document on the review of the Expropriation Act• This will be distributed for comments to identified
government role-players and state-owned enterprises• Comments received will be considered on the discussion
document and Bill be drafted• Normal legislation consultation process will be followed
including submission of the Bill to NEDLAC • The certified draft Bill will thereafter be submitted to
Parliament
43
PROFILE OF THE VACANCIESPROFILE OF THE VACANCIES
44
Vacancy Profile : April – August 2010Vacancy Profile : April – August 2010
Establishment (Total) 6283
Filled 4986
Vacant 960 Core
1297
337 Support
Vacancy % 20,64%
45
Vacant Core Positions Per Salary Level
Salary level Number of vacant positions
15 1
14 4
13 24
11 157
9 127
8 68
7 AND BELOW 579
TOTAL VACANT CORE POSITIONS 960
46
Filled Vacant Posts per Regions-August 2010
REGION FILLED VACANT TOTAL VACANCY %
Bloemfontein 315 92 407 22.60
Cape Town 854 163 1017 16.03
Durban 611 52 663 7.84
Head Office 819 320 1139 28.09
Johannesburg 407 107 514 20.82
Kimberley 177 61 238 25.63
Mafikeng 211 88 299 29.43
Mthatha 140 59 199 29.65
Nelspruit 203 71 274 25.91
Polokwane 289 75 364 20.60
Grand Total 4986 1297 6283 20.64
47
Possible Reasons For The High Vacancy RatePossible Reasons For The High Vacancy Rate
• Staff attrition (e.g. resignations and retirement)
• Shortage of scarce skills & funds
• Changes in the strategic focus
• Ongoing organisational development.
48
Current Interventions To MitigateCurrent Interventions To Mitigate
• Recruit graduates and young professionals
• Advertisement of Scarce Skills on a higher notch
• Corporate Social Investments – Bursaries, Outreach Programmes/Social Mobilization Campaigns, etc. (members of Portfolio Committee can also assist)
• Retention Strategy – e.g. Counter offers
• Assessment to abolish and/or refocus certain posts
49
Status ReportStatus Report
• 360 posts advertised since April 2010
• 101 appointments made (96 permanent/ 5 contract)
• HCI Initiatives
50
IMMOVABLE ASSET REGISTERIMMOVABLE ASSET REGISTER
51
Audit qualifications: 2009/10Audit qualifications: 2009/10
• No record of physical condition of assets
• Incomplete information on the register
• FNB Stadium not on the register
52
Action Plan and ProgressAction Plan and Progress
Activities Progress
Condition Assessment of assets.
•Asset Register Management has finalized the draft template on condition assessment which has been circulated to internal DPW units and regions for comments• Formal engagements with all Provincial Public Works departments will continue to ensure uniformity between the two spheres of government •Funding for 2010/11 MTEF will be requested from National Treasury to conduct condition assessments
53
Action Plan and ProgressAction Plan and Progress
Activities Progress
Some of the required fields in line with the National Treasury guide. Not all the cells in a column have been completed
•Asset/Property Management Information System has various modules which contains the information fields as indicated on the national treasury guide, for example Asset Register, Debtors, Municipal rates & services charges, Day to day maintenance and Leasing modules. Auditor- General refers to the fields on the Debtors and Lease modules. The information provided to the Auditor-General was on the Asset Register Module as requested. An analysis conducted on completion of fields on land parcels by Auditor-General reflects improvements on erf/farm number 99%, user departments 99%, extent/hectares 94%, title deeds 91%, portions 100%, registered owner 98% and responsible department 66%
54
Action Plan and ProgressAction Plan and Progress
Activities Progress
The FNB stadium is not reflected on the asset register
The FNB stadium is reflected on the asset register as property code 145852 on the land parcels
55
PROGRESS REPORT ON THE PROGRESS REPORT ON THE IMPLEMENTATION OF GIAMAIMPLEMENTATION OF GIAMA
56
Progress made towards implementation
In April 2009, the President signed a proclamation to bring GIAMA into operation as follows:
National departments 30 April 2009
Provincial departments 01 April 2010
National and Provincial stakeholders finalized key policies and guidelines to be put in place for the strategic management of immovable assets. These policies and guidelines are the –
a) compilation of a user asset management plan (U-AMP) as well as the custodian asset management plan (C-AMP);
b) compilation and maintenance of immovable asset registers;
57
Progress made towards implementation (Cont…)
c) the updating of the vesting guidelines to be applicable to both national and provincial departments;
d) the alignment of asset & property management policies such as the state official residential accommodation policy;
Compilation of Asset Management Plans (Provinces)
a) all provinces have started developing the user asset management plans for submission to relevant treasury for funding purposes in terms of section 6 of the Act.
58
Progress made towards implementation (Cont…)
Compilation of Asset Management Plans (National)
a) DPW has finalized all UAMP templates for FY’s 2011-2012, supported by High Level Options Analysis for 27 National Departments and 6 Entities.
b) DPW is also providing commitment information to 3 Departments that have opted to appoint private service providers to assist in the compilation of their UAMP’s;
c) DPW is interacting with the newly created, split and merged departments regarding the acquisition of new or split of immovable assets per client portfolio;
d) Newly created departments may require exemption
59
Progress made towards implementation (Cont…)
Compilation of Immovable Asset Registers
a) The guideline for the compilation of immovable asset registers has been completed with inputs from provinces;
b) The “ideal end state” information fields have been incorporated into the GIAMA Asset Register (GAR) module of the iE-Works system;
c) DPW has developed a proposal for a valuation model to assist custodians in determining the book value of state-owned immovable assets. The model consists of three (3) valuation methodologies that could be utilised depending on the nature of properties and the availability of comparative information;
60
Progress made towards implementation (Cont…)
Confirmation of ownership “vesting” of state-owned properties
a) National Vesting Master Plan incorporating national and provincial land has been developed and requires custodians to finalise the vesting of state land by latest 2014;
b) Although the bulk of applications are still with the Provincial State Land Disposal Committees (PSLDC) for finalisation, a significant progress has been made;
c) It is important to note that the delay in the finalisation of the vesting programme does not preclude departments from populating their asset registers and preparing U-AMPs and C-AMPs;
61