Download - Department of Science Technology (DST)
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 1 of 101
RequestforProposal
forSelectionofServiceProvider
ForDesigning,Development/Customization,Implementation,Training,HandHoldingandOperation&Maintenance
SupportFor
IntegratedWorkflowandDocumentManagementSystem(IWDMS2.0)
forDepartmentofScience&Technology(DST)
(GovernmentofGujarat)
(Tenderno:SW19042018159)
BidProcessingfees:Rs.17,700/‐
GujaratInformaticsLtd
Blockno.1,8thfloor,UdhyogBhavan,Sector‐11,Gandhinagar‐382017,Gujarat
PhNo.23259237,23259240Fax:23238925.Website:http://gil.gujarat.gov.in
DemonstrationoftheExistingIWDMS:27thApril,2018at1100hrsLastdateofsubmissionofpre‐bidqueries:30thApril,2018upto1200hrsDateofpre‐bidmeeting:3rdMay,2018at1200hrsLastdateforsubmissionofOnlineBids:24thMay,2018upto1500hrsDateofopeningofbids:24thMay,2018at1600hrs
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 2 of 101
Proprietary&ConfidentialNopartofthisdocumentcanbereproducedinanyformorbyanymeans,disclosedordistributed toanypersonwithout theprior consentof theDepartmentof ScienceandTechnology(DST),excepttotheextentrequiredforsubmittingbidandnomore.Theinformationcontainedinthisdocumentisonlydisclosedforthepurposeofenablingyou to submit a proposal to the Department of Science and Technology (DST) inaccordancewiththerequirementsofthisdocument.Thisdocumentshouldnotthereforebeusedforanyotherpurposeunderanycircumstances.Thisdocumentcontainsproprietaryinformationfurnishedforevaluationpurposesonly;except with the written permission of the department, such information may not bepublished,disclosed,orusedforanyotherpurpose.Youacknowledgeandagreethatthisdocument and all portions thereof, including, but not limited to, any copyright, tradesecretandother intellectualpropertyrightsrelating thereto,areandatall timesshallremainthesolepropertyofthedepartmentandthattitleandfullownershiprightsintheinformationcontainedhereinandallportionsthereofarereservedtoandatalltimesshallremainwiththedepartment.Youagreetotakeutmostcareinprotectingtheproprietaryandconfidentialnatureoftheinformationcontainedherewith.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 3 of 101
Abbreviations
DST:DepartmentofScienceandTechnology DPR:DetailedProjectReport GIL:GujaratInformaticsLimited GoG:GovernmentofGujarat GPR:GovernmentProcessRe‐engineering GoI:GovernmentofIndia G2B:GovernmenttoBusiness G2C:GovernmenttoCitizens G2G:GovernmenttoGovernment GSWAN:GujaratStateWideAreaNetwork HRMS:HumanResourceManagementSystem ICT:Information&CommunicationTechnology IFMS:IntegratedFinancialManagementSystem IT:InformationTechnology ITB:InstructiontoBidders IWDMS2.0:IntegratedWorkflowandDocumentManagementSystemVer2.0 MMP:MissionModeProject QCBS:Quality&CostBasedSelection RFP:RequestforProposal RTI:RighttoInformation SDC:StateDataCentre SP:ServiceProvider COTS:CommerciallyOff‐The‐Shelf
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 4 of 101
TableofContents1. SECTION–I:INVITATIONTORFP..................................................................................................................6 1.1. RFPNotice..................................................................................................................................................................6 1.2. ImportantInformation.........................................................................................................................................7 2. SECTION2:INSTRUCTIONSTOBIDDERS...................................................................................................8 2.1. Definitions..................................................................................................................................................................8 2.2. SOURCESOFFUNDS..............................................................................................................................................9 2.3. Introduction..............................................................................................................................................................9 2.4. QualificationCriteria.............................................................................................................................................9 2.5. DocumentsComprisingBidProposal.........................................................................................................12 2.6. EligibleGoodsandServices.............................................................................................................................12 2.7. CostofBidding......................................................................................................................................................13 2.8. ContentofBiddingDocument........................................................................................................................13 2.9. DemonstrationofExistingIWDMS..............................................................................................................13 2.10. Pre‐BidConference.............................................................................................................................................13 2.11. AmendmenttoRFP.............................................................................................................................................13 2.12. LanguageofBid....................................................................................................................................................14 2.13. DocumentsComprisingtheBid.....................................................................................................................14 2.14. BidSecurity/EarnestMoneyDeposit(EMD)........................................................................................14 2.15. BidForm..................................................................................................................................................................15 2.16. BidPrices.................................................................................................................................................................15 2.17. Validityofproposal.............................................................................................................................................16 2.18. PreparationofProposal....................................................................................................................................16 2.19. Submissionofproposal.....................................................................................................................................17 2.20. OpeningofBidsbyDST/GIL...........................................................................................................................17 2.21. ClarificationofBids.............................................................................................................................................17 2.22. PreliminaryExamination.................................................................................................................................17 2.23. Methodology&CriteriaforTechnical,Commercialandfinalevaluation...................................18 2.24. AwardofContract...............................................................................................................................................21 2.25. DST/GIL’sRighttoAcceptAnyBidandtorejectanyorAllBids...................................................21 2.26. NotificationofAwards.......................................................................................................................................21 2.27. SigningofContract..............................................................................................................................................21 2.28. PerformanceBankGuarantee........................................................................................................................21 2.29. Confidentiality.......................................................................................................................................................22 2.30. Disqualification.....................................................................................................................................................22 2.31. BindingClause.......................................................................................................................................................22 3. SECTION–IIISCOPEOFWORK....................................................................................................................23 3.1. Background............................................................................................................................................................23 3.2. ScopeofWork.......................................................................................................................................................24 3.3. GeographicalScope(Offices/LocationtobecoveredfortheProject):‐.....................................26 3.4. TechnicalEnvisagedArchitecture................................................................................................................27 3.5. ScopeofWork.......................................................................................................................................................27 3.6. IntegrationScope.................................................................................................................................................49 3.7. Operation&MaintenanceSupport..............................................................................................................50 3.8. DevelopmentandO&MTeam......................................................................................................................54 3.9. DatabaseMigration&Management............................................................................................................55 3.10. LanguageoftheProduct...................................................................................................................................56 3.11. EnvisagedProjectPhases:...............................................................................................................................56 3.12. Detailsoftheactivities......................................................................................................................................58 4. SECTIONIV:SPECIFICATIONS.......................................................................................................................61 4.1. AcceptanceCriteria.............................................................................................................................................61 4.2. PerformanceCriteria..........................................................................................................................................62 4.3. AvailabilityCriteria.............................................................................................................................................62 4.4. SecurityCriteria...................................................................................................................................................62 4.5. Manageability........................................................................................................................................................62 4.6. Standards&Protocols.......................................................................................................................................63 4.7. DevelopmentCriteria.........................................................................................................................................63 4.8. Customization/DevelopmentofApplication...........................................................................................63 4.9. DevelopmentControl.........................................................................................................................................63 4.10. ProjectManagement&ProjectPlan............................................................................................................63 4.11. StatusReports.......................................................................................................................................................64 4.12. VersionControl&BugFixing.........................................................................................................................64
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 5 of 101
4.13. HostingCriteria....................................................................................................................................................64 4.14. Availability..............................................................................................................................................................64 4.15. Accessibility...........................................................................................................................................................64 4.16. Security....................................................................................................................................................................64 4.17. Backup&Recovery.............................................................................................................................................65 4.18. Uptime&Performance......................................................................................................................................65 4.19. AccessControlandUserAuthentication:..................................................................................................65 4.20. Thetools/softwarelicensesavailablewithGujaratStateDataCentreonsharedbasisandComputepoweravailableunderG‐CloudatDataCentreshallbegiventothebidderaftersigningNDAwithDST/GIL. 65 5. SECTIONV:TimelineandPAYMENTTERMS..........................................................................................67 5.1. ProposedtimelinesforImplementationandpaymentterms.........................................................67 5.2. PaymentProcedure............................................................................................................................................68 6. SECTIONVI:SERVICELEVELAGREEMENT&PENALTYCLAUSE.................................................69 6.1. Definitions...............................................................................................................................................................69 6.2. CategoriesofSLAs...............................................................................................................................................69 7. SECTIONVII:ROLES&RESPONSIBILITIESOFSTAKEHOLDERS..................................................74 7.1. DepartmentofScienceandTechnology(DST)andGAD..................................................................74 7.2. SI/Bidder:................................................................................................................................................................74 8. SECTIONVIII:GENERALTERMS&CONDITIONS.................................................................................76 8.1. Application..............................................................................................................................................................76 8.2. Relationshipbetweenparties........................................................................................................................76 8.3. Subcontracts.........................................................................................................................................................76 8.4. StandardsofPerformance...............................................................................................................................76 8.5. DeliveryandDocuments..................................................................................................................................76 8.6. SPPersonnel..........................................................................................................................................................76 8.7. ApplicableLaw......................................................................................................................................................77 8.8. UseofContractDocumentsandInformation..........................................................................................77 8.9. GoverningLanguage...........................................................................................................................................77 8.10. IntellectualPropertyRights............................................................................................................................77 8.11. Inspection/Testing..............................................................................................................................................78 8.12. ChangeRequestOrders.....................................................................................................................................80 8.13. Suspension..............................................................................................................................................................80 8.14. Termination...........................................................................................................................................................80 8.15. TerminationforDefault....................................................................................................................................81 8.16. Fraud&Corruption............................................................................................................................................81 8.17. ForceMajeure........................................................................................................................................................82 8.18. PaymentsincaseofForceMajeure.............................................................................................................82 8.19. TerminationforInsolvency.............................................................................................................................82 8.20. ResolutionofDisputes.......................................................................................................................................82 8.21. Arbitration..............................................................................................................................................................83 8.22. ContractPeriod.....................................................................................................................................................83 8.23. ExitManagementProcedure..........................................................................................................................83 8.24. AgreementAmendments..................................................................................................................................84 8.25. LimitationofLiability........................................................................................................................................84 8.26. Severability:...........................................................................................................................................................84 8.27. MaintenanceserviceincludingWarrantySupport:..............................................................................85 8.28. TaxesandDuties..................................................................................................................................................85 8.29. LegalJurisdiction.................................................................................................................................................85 8.30. Notice........................................................................................................................................................................85 9. SECTIONIX:FormsofQualificationandTechnicalBid......................................................................86 9.1. FORMI:BidProposalForm.............................................................................................................................86 9.2. FORMII:ParticularsoftheBidder’sOrganization................................................................................87 9.3. Form:III–FormatforFinancialCapability..............................................................................................87 9.4. FormIV–FormatforRelevantExperience..............................................................................................88 9.5. FORMV:ProjectTeam.......................................................................................................................................88 9.6. FORMVI:SelfDeclaration................................................................................................................................89 9.7. FORMVII:OriginalEquipmentManufacturer(OEM)/DeveloperAuthorizationFormincaseofCOTSProductandforOSandDatabaseSupport.......................................................................................................................90 9.8. FormVIII–EarnestMoneyDeposit/BidSecurityintheformofBankGuaranteeFormat92 9.9. FORMIX‐PerformanceBankGuarantee..................................................................................................93 9.10. FormX–FormatofAffidavit..........................................................................................................................95 10. SectionX:FinancialBid.....................................................................................................................................98
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 6 of 101
1. SECTION–I:INVITATIONTORFP1.1. RFPNoticeThisdocumentisforaRequestforProposalfor“SelectionofServiceProviderforDesigning,Development/Customization,Implementation,Training,HandHoldingandOperation&MaintenanceSupportfor8yearsforIntegratedWorkflowandDocumentManagementSystem”forDepartmentofScienceandTechnology(DST),GovernmentofGujarat.DepartmentofScienceandTechnologyintendstoautomateday‐to‐dayfunctionsatalllevelsof the administrative hierarchy of all Departments, HoDs, Boards, Corporations and otherGovernment offices of Government of Gujarat and to have a solution with integratedcomponents like Correspondence Management, File Movement, Document ManagementSystem, Workflow Automation, Document Archival & Record Management, MeetingManagement, Messaging, Appointment scheduler, Alert Management System, Visitor PassManagement System (Vidhansabha), Sachivalaya Entry Pass Management System etc. forGovernmentofGujarat.The bidder shall be responsible for “Design, Customization/Development, Implementation,Training, Hand Holding and Operation & Maintenance Support for 8 years for IntegratedWorkflow and Document Management System 2.0”. The bidder shall be responsible forprovidingalltypesofservicesandupdatesasmentionedinthisdocuments&ScopeofWork,asapartofthisproject.Thebidder,whointendstoparticipateinthisbid,isrequiredtofollowthebelowmentionedstages: Pre‐BidConference Technical&FinancialBidSubmission OpeningofTechnicalBid EvaluationofTechnicalbid Presentation&ProofofConcept(PoC)/SolutionDemoonproposedSolution,Approach&
Methodology OpeningofFinancialbidsofallqualifiedbiddersBiddermayeitherquoteforbespokeDevelopmentorCOTSSolution.Incomplete/conditionalbidswillbetreatedasnon‐responsiveandwillberejected.EligiblebiddersmaydownloadtheRFPdocumentfromthewebsitehttp://gil.gujarat.gov.in&https://gil.nprocure.com.Thebidsmustbesubmittedonlinethroughhttps://gil.nprocure.com.ThebidprocessingfeeandEMDandaffidavitisrequiredtosubmitphysicallyatGILoffice.DSTreservestherighttorejectanyoralltheproposalsinwholeorpartwithoutassigninganyreasons.ThisRFPdocumentisnottransferable.Minimumabsolutetechnicalscoretoqualifyforcommercialevaluationis50%.Financialbidsofonlythosebidderswhoqualifyonthebasisofevaluationoftechnicalbidswillbeopened.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 7 of 101
1.2. ImportantInformationSr.No.
Information Details
1. RFPNo.anddateofPublishingNo19042018159Date:19.04.2018
2. Lastdateforsubmissionofwrittenqueriesforclarificationsto:[email protected]
30thApril,2018upto1200hrs
3. DemonstrationoftheExistingIWDMS 27thApril,2018at1100hrs
4. PrebidConference
3rd May,2018at1200hrsConferenceRoom,BlockNo1,8thFloor,UdhyogBhavan,Gandhinagar‐382010
5. Dateandtimeforsubmissionofthebids 24th May,2018upto1500hrs
6. DateandtimeforopeningofBids 24thMay,2018at1600hrs
7. PlaceforOpeningofBids
ConferenceRoom,GujaratInformaticsLtd.BlockNo.1,8thFloor,UdyogBhavan,Gandhinagar
8. Place, Date and Time for TechnicalPresentation
ThePlace,DateandTimeforTechnicalPresentation will be informed to theeligiblebidderslateron.
9. Addressforcommunication
Director(e‐Governance),GujaratInformaticsLtd.BlockNo.1,8thFloor,UdyogBhavan,GandhinagarPhone:91‐79‐23259239,59240Fax:91‐79‐[email protected]
10. Place, Date and Time for Opening ofFinancial/CommercialBids
Place, Date and Time for Opening ofFinancial / Commercial Bids will becommunicated to the technicallyqualifiedbidderslateron.
11. Bidvalidity 180 days from the Financial BidOpening
The bidder shall submit the DD of Rs. 17,700/‐ towards bid processing charges andDD/BankGuaranteeofRs.75,00,000/‐towardsEMD/BidSecurityinsealedcover.Thesealed cover should super scribe as “Bid processing fees andEMD forRFP for SelectionofService Provider for Design, Customization/Development, Implementation, Training, HandHolding and Operation & Maintenance Support for 8 years for Integrated Workflow andDocumentManagementSystemforDepartmentofScienceandTechnology(DST)”.The bid processing feesmust be in the form of DemandDraft in in the name of “GujaratInformaticsLtd.”payableatAhmedabad/Gandhinagar.EMD/BidSecuritymustbeintheformof Demand Draft/Bank Guarantee in the name of “Gujarat Informatics Ltd.” payable atAhmedabad/Gandhinagar.IncaseofEMDintheformofBG,itshouldbevalidfor9monthsfromthedateofbidsubmission.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 8 of 101
2. SECTION2:INSTRUCTIONSTOBIDDERS2.1. Definitions2.1.1. “ApplicableLaw”meansthelawsandanyotherinstrumentshavingforceoflaw
inIndiafromtimetotime.2.1.2. “Proposal/bid” means proposal submitted by bidders in response to the RFP
issuedbyDepartmentofScienceandTechnologyforselectionofServiceProvider.2.1.3. “CompetentAuthority”meanstheDepartmentofScienceandTechnology.2.1.4. “Committee” means committee formed by the Department of Science and
Technology(DST) inconsultationwithGADfor thepurposesofprocessingandevaluationofthisbid
2.1.5. “ContractValue”meansthepricepayabletotheselectedfirm/companyundertheContractforthecompleteandproperperformanceofitscontractualobligations.
2.1.6. “Service Provider” means any private or public entity, which will provide theservicestoDepartmentofScienceandTechnologyunderthecontract.
2.1.7. “Contract” means the Contract signed by the parties along with the entiredocumentationasspecifiedintheRFP
2.1.8. “Day” means Working day. A period of 24 hours running from midnight tomidnightandthecalendardayapplicabletoIndia
2.1.9. “Effective date”means the date fromwhich the contract comes into force andeffect.
2.1.10. “Government”meansStateGovernmentofGujarat.2.1.11. “DST”meansDepartmentofScienceandTechnology,Gujarat.2.1.12. “IWDMS 2.0” means IntegratedWorkflow and Document Management System
needstobedevelopedbyselectedServiceProvider2.1.13. “Product” means a final solution after Development of IWDMS 2.0 as per
requirementoftheDST.2.1.14. “Rules” means the applicable rules under different statutes, Acts, Rules,
Government Resolutions, Circulars in relation to personal management ofemployeesinGujaratGovernment.
2.1.15. .“Personnel” means professional and support staff provided by the SP andassignedtoperformservicestoexecuteanassignmentandanypartthereof.
2.1.16. “Intellectual Property Rights” means any and all copyright, moral rights,trademark,patentandotherintellectualandproprietaryrights,titleandinterest,world‐wide,whethervested,contingentorfuture,includingwithoutlimitationalleconomicrightsandallexclusiverightstoreproduce,fix,adapt,modify,translate,create, derivativeworks form,manufacture, introduce into circulation,publish,distribute,sell,license,sublicense,transfer,rent,lease,transmitorprovideaccesselectronically,broadcast,display,enterintocomputermemoryorotherwiseuseanyportionorcopyinwholeorinpart,inanyform,directlyorindirectly,ortoauthorizeorassignotherstodoso.
2.1.17. “Services”meanstheworktobeperformedbytheSPpursuanttotheselectionbyDSTandtothecontracttobesignedbythepartiesinpursuanceofanyspecificassignmentawardedtothembyDST.
2.1.18. Go live means Successful execution of entire solution in secretariat after FATsubjecttosatisfactionofDSTandGAD.
2.1.19. AfterGo‐Livebidderhastoprovidethehandholdingandhelpdesksupportforthe
developedfunctionalitiesanddeploymanpowerasperinstructionofDepartmentof Science and Technology, General Administration Department and other
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 9 of 101
associateddepartments.Thehandholdingandhelpdesksupportratewillbeaspertheratequotedbybidderinthefinancialbid.
2.2. SOURCESOFFUNDSDepartmentofScienceandTechnologyisinvitingServiceProviderfor“Design,Customization/Development,Implementation,Training,HandHoldingandOperation&MaintenanceSupportfor8yearsforIntegratedWorkflowandDocumentManagementSystem”forGovernmentofGujaratEmployeesacrossthestate.TheWorkOrderwillbeplacedtotheselectedServiceProviderbyDepartmentofScienceandTechnologydirectlyandthepaymentfortheservicesmentionedinthe said work order will be made directly by Department of Science andTechnology from their own sources of funds as per the financial terms andconditionsmentionedinthisdocument.
2.3. Introduction2.3.1. Department of Science and Technology is one of the key departments of State
GovernmenttopromoteandimplementITande‐Governanceinthestate.Anelectronicworkplaceandautomatedprocessesaretodayessentialforefficientandtransparentgovernance.Itreducesprocessdelays,helpstoaccessandutilizeinformationquicklyandexpeditework.DepartmentofScienceandTechnologyintends to automate day‐to‐day functions at all levels of the administrativehierarchyofallDepartments,HoDs,Boards,CorporationsandotherGovernmentofficesofGovernmentofGujarat.Department of Science and Technology and its HoDs started the process ofautomationtheadministrativeprocessofSecretariatintheyear2006‐07.Underthis process a system named “IWDMS (Integrated Workflow and DocumentManagementSystem)”The department now wishes to sunset the existing IWDMS application anddevelopsawholenewapplicationwithenhancedfeaturesrequestedinthisRFP.The new system shall be called “IWDMS 2.0” and shall completely replace theexistingsystem.
2.4. QualificationCriteriaThe bidders meeting the following qualification criteria will be short listed andconsideredfortechnicalevaluation.Sr.No. EligibilityCriteria Attachments
1. The bidder would be an IT companyregistered/ incorporated under Indiancompany ACT andmust have 5 years ofexistenceinIndia.
ValidcopyoftheCertificate
2. ThebiddermusthaveturnoverofatleastRs.500Croresforanyoneofthelastthreefinancial years or cumulative Rs 1500crore for last three financial years
AuditedandCertifiedBalanceSheet& Profit/Loss Account of last 3Financial Years/CA certificatementioningturnover
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 10 of 101
Sr.No. EligibilityCriteria Attachments(completed financial year periodcompletedon31stDecember,2017).
3. The bidder should have experience incustomization/development andimplementation, support services of atleast 2 eOffice/workflow and documentmanagement system solution in Indiawhich include workflow and DMS instate/central government or PSU or anyboard or corporation set up bygovernmenthavingeachofvalueatleast5crores.Projectsshouldbefunctionalatmultiplelocation.
Work Order / Project ContractDocument / Agreement /Satisfactory Completion Certificate/ FAT Sign off Certificate by theclientwithdetailsofprojectvalue,sitesandno.ofusers/LetterSignedby Authorized Signatory orCompany Secretarywith details ofprojectvalue,sitesandno.ofusers"which projects are under Non‐Disclosure / ConfidentialityAgreementandcannotbeshared.
4. The Bidder should be a Total SolutionProvider(TSP)havingavalidCMMilevel3orabovecertification.
ValidcopyoftheCertificates
5. ThebiddershouldhaveanexperienceofworkingasTSPorDeveloperforbuildingan IT system catering tominimum1000users or resources any time in last fiveyears.
Work Order / Project ContractDocument / Agreement /Satisfactory Completion Certificatebytheclientwithdetailsofprojectvalue,sitesandno.ofusers/LetterSigned byAuthorized Signatory orCompany Secretarywith details ofprojectvalue,sitesandno.ofusers"which projects are under Non‐Disclosure / ConfidentialityAgreementandcannotbeshared.
6. The bidder should have at least 500technically trained employees on itspayroll as on last date of submission ofbids.
Authorization certificate from HRmanager
7. TheBiddershouldnotbeundertheeffectof blacklisting by anyMinistry/Department of Government ofIndia or by any State Governmentdepartment/agency in India or byGovernment of Gujarat or any of theGovernmentPSUsatthetimeofbidding.
Self‐Declaration Form must besubmitted
8. Bidder should not have violated /infringed on any Indian or foreigntrademark, patent, registered design orotherintellectualpropertyrightsanytimeanywhereinIndia.
Affidavit regarding non‐violation /infringement of any Indian orforeign trademark, patent,registered design or otherintellectualpropertyrightsmustbesubmitted by the bidder as perAttachedformat.
9. The bidder should have an office inGujarat, preferably, at Ahmedabad or
Copyofanytwoofthefollowings:PropertyTaxBill/ElectricityBill/
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 11 of 101
Sr.No. EligibilityCriteria AttachmentsGandhinagar OR Bidder should provideundertaking to open the samewithin45daysfromtheawardofWorkOrder.
TelephoneBill/VAT/CST/GST/Registration/Leaseagreement.
10. The bidder must give undertaking dulysigned&sealedbyAuthorizedSignatorythatifthiscontractisawardedtohim,hewill employ all the resources with thenecessary capabilities catering todifferent phases of projectimplementation,asdefinedinthescopeofwork.Resourcesneed tobeDeployed atdirected by Department of Science andTechnology offices/ places specified byDST.
RelevantundertakingTSP
Notes:
1. Noconsortiumwillbeallowed.2. COTSmeanscommerciallyOff‐The‐Shelf:Thesoftwareapplicationshouldbe
readilydeployablewithorwithoutconfigurationtosuitthecustomer’sspecificprocess requirements and does not involve developing the application fromscratch.COTSsoftwareshallbeimplementableordeployableandmaintainablebyanyothercompetentagencyother than themanufactureroragencywhichhasdeveloped the COTS software. Proposed COTS software solution shall also beavailable with complete transparency including operation manuals, helpdocuments,APIsandcustomizationsourcecode.TheOEMoftheCOTSproductshouldhave50ormoreregisteredpartnertoselltheirproductcommercially.
3. Technicallytrainedmeans“whoisatleastatechnologygraduateandshouldhaveknowledgetodevelop/supportsuchtypeofITsolution”
4. The bidder must give undertaking on its letter head duly signed & sealed byAuthorizedSignatorythatifthiscontractisawardedtohim,hewillemployalltheresourceswiththenecessarycapabilitiescateringtodifferentphasesofprojectimplementation,asdefinedinthescopeofwork.ResourcesneedtobeDeployedasdirectedbyDepartmentofScienceandTechnologyoffices/placesspecifiedbyDST.
5. IncasethebidderisofferingCOTSProduct:a. TheBidderwillhaveto furnishacceptanceonproviding futureversions
and applicable upgrades and ensure the compatibility with existingapplicationanddatabasewithoutanyadditionalcostwheneverrequiredonitsletterhead.Thebiddershallalsoberequiredtoprovideassuranceletter that with each upgrade or feature enhancement, any integrationrequirementsshallalwaysbeservedseamlesslybytheproduct.
b. Initially, thebidderhastogivetheperuserCOTslicensecost for25000userlicenses.
c. ThebiddermustgetandpresentanundertakingdulysignedbyauthorizedsignatoryoftheCOTSOEMtoconveyOEM’sacceptancetothefollowingarrangement“TheCOTSOEMprovider agrees to provide the additional user licenseswithfollowingconditions:
Additional licenses shall beprovided at a discount to the quotedpriceinthisbidsubjecttofollowingdiscountschedule:
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 12 of 101
Additional License quantity from 25001 – 50000 Licenses: 60%Discountonthefinalizedrateperuser.
AdditionalLicenseQuantityfrom50001andaboveLicenses:80%Discountonthefinalizedrateperuser.
Besides the cost of COTS licenses, if there are other items in the biddocumentwhichalsoattractcostsbasedonquantityofuserlicensesthenallsuchlicensesshallattractdiscountsasmentionedaboveintheirlumpsumonetimecostorintheirannuallicensingcosts.TheTSPshallgivethisundertakinginrespectofsuchquantitieswhicharechargeablebyhim.ThediscountshallbecomputedagainstthepricequotedintheFinancialBidofthis RFP. Further the quantity indicated above includes such licensesboughtbyotherGovernmentorganizations, insideGujarat.Thediscountshall applyon incrementalquantityandnoton thecumulativequantity.SuchundertakingwillhavetobetakenfromtheOEMandtobesubmittedbytheTSPalongwiththeBid.
d. ThebidderwillhavetosubmitanauthorizationfromitsOEMfortheproductquoted in the bid. Mentioning back‐to‐back warranty and supportagreement/arrangementforservicesoftheofferedproductandsupportfortheentireprojectperiod.(FormVII)
2.5. DocumentsComprisingBidProposalTheresponsesubmittedbythebiddershallcomprisethefollowingdocuments:2.5.1. Qualification&TechnicalProposal
2.5.1.1. SealedcoverofBidProcessingFeeandEarnestMoneyDeposit/BidSecurity
2.5.1.2. BidProposalform2.5.1.3. GeneralInformation2.5.1.4. FinancialCapabilitywithsupportingdocuments2.5.1.5. RelevantExperiencewithsupportingdocuments2.5.1.6. Self‐Declaration2.5.1.7. AllrelevantCertification2.5.1.8. AllundertakingssubmittedbytheAuthorizedSignatoryshallbeona
StampPaperofvaluenotlessthanRs.1002.5.1.9. Proposaldocumentcontainingabriefabouttheorganization,its
expertiseanddocumentaryevidences.2.5.2. FinancialProposal
2.6. EligibleGoodsandServices2.6.1. Softwareapplicationdevelopmentanddeploymentwithorwithoutconfiguration
to suit the customer’s specific process requirements. Software shall beimplementableordeployableandmaintainablebyanyothercompetentagency.Software solution shall alsobe availablewith complete transparency includingoperationmanuals,helpdocumentsandsourcecode.
2.6.2. Forpurposeofthisclause,"origin"meanstheplacewherethegoodsarefromorfromwhichtheancillaryservicesaresupplied.Goodsareproducedwhen,throughmanufacturing,processing, codewritingandcompiling,orsubstantialormajorassembling of components, a commercially recognized product results that issubstantiallydifferentinbasiccharacteristicsorinpurposeorinpurposeorutilityfromitscomponents.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 13 of 101
2.7. CostofBiddingTheBiddershallbearallthecostsassociatedwiththepreparationandsubmissionof its bid, andDST/GILwill inno casebe responsibleor liable for these costs,regardlessofconductoroutcomeofbiddingprocess.
2.8. ContentofBiddingDocumentTheBidderisexpectedtoexamineallinstructions,forms,termsandspecificationsin the bidding documents. Failure to furnish all information required by thebiddingdocumentsinformatorsubmissionofabidnotsubstantiallyresponsivetothebidingdocumentsineveryrespectwillbeattheBidder'sriskandmayresultinrejectionofitsbid.
2.9. DemonstrationofExistingIWDMS
DST/GILwillmakearrangementonbriefpresentationofexistingIWDMSSystemon thedate specified section1. Thepurposeof thismeeting is that thebidderunderstands the existing system and give the suggestions on the RFP withinstipulated time limit. After receiving the suggestions, DST/GILmay accept thesuitablesuggestions.
2.10. Pre‐BidConference
AprospectiveBidder requiringanyclarificationof thebiddingdocumentsmayseek clarificationsof his/herqueries submittedonorbefore3days ofpre‐bidconference.DST/GILwilldiscussthequeriesreceivedfromtheinterestedbiddersinthepre‐bidmeetingandrespondtheclarificationsbyuploadingonthewebsite.Nofurtherclarificationwhatsoeverwillbeentertainedafterthepre‐bidmeetingdate.Theinterestedbiddershouldsendthequeriesasperthefollowingformat:
Bidder’sRequestForClarification
NameofOrganizationsubmittingrequest
Name&positionofpersonsubmittingrequest:
Addressoforganizationincludingphone,fax,emailpointsofcontact
Sr.No.
BiddingDocumentReference(Clause/page)
ContentofRFPrequiringclarification
PointsofClarificationrequired
1 2 3 4
2.11. AmendmenttoRFP2.11.1. Atanytimeprior to thedeadline forsubmissionofbids,DST/GILmay, forany
reason,whetheronitsowninitiativeorinresponsetoaclarificationrequestbyaprospectivebidder,modifythebiddingdocuments.
2.11.2. Allprospectivebidderswhohavereceivedthebiddingdocumentswillbenotifiedof the amendment through website and such amendments will be binding onthem.
2.11.3. In order to allow prospective bidders reasonable time to consider theamendmentswhilepreparingtheirbids,DST/GILatitsdiscretion,mayextendthedeadlineforthesubmissionofbids.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 14 of 101
2.12. LanguageofBid
Thebidpreparedby theBidder, aswell as all correspondence anddocumentsrelating to the bid exchanged by the Bidder and DST/GIL shall be in Englishlanguageonly.
2.13. DocumentsComprisingtheBid2.13.1. ThebidpreparedbytheBiddershallcompriseofthefollowingdocuments:
2.13.1.1. EMD&BidProcessingFees2.13.2. Qualification documents, Technical Bids and Financial Bidsmust be submitted
online through thee‐tenderingwebsiteofhttp://gil.nprocure.comusingdigitalsignature.2.13.2.1. The bid documents and addendums (if any) together shall be
consideredasfinalandself‐containedbiddocumentsnotwithstandinganypreviouscorrespondenceordocumentissuedbyGIL/DST.
2.13.2.2. The bid processing fee of Rs. 17,700/‐ (Rupees FifteenThousandsOnly)informofDDandEMDofRs.75,00,000/‐(RupeesSeventy Five Lacs Only) in form of DD/Bank Guarantee are to besubmitted physical in the form favoring ofGujarat InformaticsLtd,Gandhinagar insealedcoverclearlymentioningthat“BidProcessingFeeandEMDofRFP for “Selectionof ServiceProvider forDesigning,Development/Customization,Implementation,Training,HandHoldingand Operation & Maintenance Support for 8 years for IntegratedWorkflowandDocumentManagementSystem”atGILon theaddressmentionedinSection‐1.
2.14. BidSecurity/EarnestMoneyDeposit(EMD)2.14.1. TheBiddershallfurnish,aspartoftheBid,aBidsecurityfortheamountofRs.
75,00,000/‐(RupeesSeventyFiveLacsonly)whichshallbesubmitted in theformofDemandDraftORintheformofanunconditionalBankGuarantee(whichshould be valid for 9 months from the last date of bid submission) of anyNationalizedBank including the public sector bank or Private SectorBanks orCommercial BanksorCo‐OperativeBanks andRuralBanks (operating in IndiahavingbranchatAhmedabad/Gandhinagar)G.R.no.EMD/10/2016/328/DMOdated01.05.2017issuedbyFinanceDepartmentorfurtherinstructionissuedbyFinancedepartmenttimetotime,inthenameof“GujaratInformaticsLtd”payableatGandhinagar(asperprescribedformat)andmustbesubmittedalongwiththecoveringletter.Theun‐pricedbidwillbeopenedsubjecttotheconfirmationofvalidBidsecurity.
2.14.2. UnsuccessfulBidder'sBidsecuritywillberefundedwithinthirty(30)daysfromtheawardofworktothesuccessfulbidder.
2.14.3. ThesuccessfulBidder'sBidsecuritywillbedischargedupontheBiddersigningthecontract/Agreement,andfurnishingthePerformanceBankGuarantee.
2.14.4. TheBidsecuritymaybeforfeitedatthediscretionofTENDERER/GIL,onaccountofoneormoreofthefollowingreasonsif:
a.TheBidderwithdrawstheirBidduringtheperiodofBidvalidity.b.BidderdoesnotrespondtorequestsforclarificationoftheirBid.c.Bidderfailstoco‐operateintheBidevaluationprocess,d.Bidderisfoundtobeinvolvedinfraudulentandcorruptpracticesande.IncaseofasuccessfulBidder,thesaidBidderfails:
i.TosigntheAgreementintime
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 15 of 101
ii.TofurnishPerformanceBankGuaranteeiii.isfoundtobeinvolvedinfraudulentandcorruptpractices
2.15. BidForm2.15.1. TheBiddershallcompletetheTechnicalBidandFinancialBidfurnishedwiththis
documentgivingdetailsaspertheformatmentionedinthee‐Tenderingwebsitehttps://gil.nprocure.com. The bidder shall also complete the bid formas persectionVandsubmititwiththefinancialBidonhttps://gil.nprocure.com.
2.16. BidPrices2.16.1. TheBiddershallindicatethepricesintheformatmentionedinthee‐Tendering
websitehttps://gil.nprocure.com.2.16.2. Followingpointsneedtobeconsideredwhileindicatingprices:
2.16.2.1. Thepricesquotedshouldalsoinclude,inlandtransportation,insuranceandotherlocalcostsincidentaltodeliveryofthegoodsandservicestotheirfinaldestinationwithinthestateofGujaratincaseofprimarysiteandwithinIndiaincaseofDRsiteasindicatedbyGIL/DST
2.16.2.2. Theratesofanyapplicable Indianduties& taxes likeGSTandothertaxeswhichwillbepayablebytheClientonthegoods/services(ifany)ifthiscontractisawarded,shouldbequotedseparately,
2.16.3. TheBidder'sseparationofthepricecomponentswillbesolelyforthepurposeoffacilitatingthecomparisonofbidsbyDST/GILandwillnotinanywaylimittheClient'srighttocontractonanyofthetermsoffered.
2.16.4. Sharingofresponsibility(betweenDSTandthebidder)ofprocurementofvarioustypesofsoftwareshallbeasunder:2.16.4.1. Thepricesquotedshallbeinclusiveoflicensesoftwarerequired
for actual running of applications developed (i.e. OperatingSystem, databases, any COTS product and any other softwarerequiredtillthetenureofcontract).
2.16.4.2. The Bidder has to provide the required software solution atcentrallevelandDepartmentwillprovidetherequiredsoftwareinfrastructureatuserlevelforrunningofproductslikeOperatingSystem,systemsoftware,etc.
2.16.4.3. Thebidderwillprovide IWDMS2.0 environment at the centralsideforDatabasemanagement.
2.16.4.4. The price quoted shall be inclusive of “Designing,Development/Customization,Implementation,Training,HandHoldingandOperation&Maintenance, Support for IntegratedWorkflowandDocumentManagementSystem”fortheperiodofcontract.Thisshallalso include the cost of integration with applicable modules ofintegrated solutions like IFMS, SAATHI, SWAGAT, Digital Gujarat, e‐Vidhan(proposed),SevaSetu,PragatiSetu,GovernmentEmail&anyotherupcomingand/orupgradedPortaland/orapplicationsofGovt.ofGujaratduringthetenureofthecontract.
2.16.4.5. Bidderisexpectedtofilltherates/amountforallitemsinFinancialBidformat.BiddersquotingincrediblyloworunrealistichighcostofitemswithaviewtosubvertingthetenderprocessshallberejectedstraightawaybyDST.GILandEMDofsuchBidder(s)willbeforfeited.However,incase,thebidderchoosestoquotezero,nilamountorblank,itwillbehisriskandthesameshallinnowayrestrictthescopeofthework.Anyrate quote field kept blankwould imply that bidder is quoting zeropricesforthatitem.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 16 of 101
2.16.4.6. Thebidderagrees to thatDepartmentofScienceandTechnologyshallhavetheunrestrictedrighttodeployoruseIWDMS2.0applicationsoftware and thedocumentation related thereto, in anyGujarat stategovernment department, at no additional cost to client. StateGovernmentmaychoosetocarryoutthedevelopment/customizationofthesoftware,aftertheexpiryofthepostimplementationsupport,byanywaytheywant.
2.16.4.7. BidCurrencyPricesshallbequotedinIndianrupeesonly.
2.17. Validityofproposal2.17.1. Proposalsshallremainvalidforaperiodof180days(onehundredeightydays)
afterthedateoffinancialbidopeningprescribedintheRFP.Aproposalvalidforshorter period may be rejected as non‐responsive. DST/GIL may solicit thebidders’consenttoanextensionofproposalvalidity(butwithoutthemodificationinproposals).
2.17.2. Inexceptionalcircumstances,GILmaysolicittheBidder'sconsenttoanextensionoftheperiodofvalidity.Therequestandtheresponsestheretoshallbemadeinwriting.TheBidsecurityperiodprovidedshallalsobesuitablyextended.ABiddermayrefusetherequestwithoutforfeitingitsbidsecurity.ABiddergrantingtherequestwillnotbepermittedtomodifyitsbid.
2.17.3. Bidevaluationwillbebasedonthebidpricesandtechnicalbidwithouttakingintoconsiderationtheabovecorrections
2.18. PreparationofProposal2.18.1. TheproposalandallassociatedcorrespondenceshallbewritteninEnglishand
shall conform to prescribed formats. Any interlineations, erasures or overwritingsshallnotbevalid.
2.18.2. Theproposalshallbetypedorwritteninindelibleink(ifrequired)andshallbeinitialedonallpagesbyauthorizedrepresentativeofthebiddertobindthebiddertothecontract.TheauthorizationshallbeindicatedbyBoardResolution/PowerofAttorneyandshallaccompanytheproposal
2.18.3. In addition to the identification, the covering letter (Form1) shall indicate thenameandaddressofthebiddertoenabletheproposaltobereturnedinthecaseitisdeclaredlatepursuant,andformatchingpurposes.
2.18.4. The information submitted must be definitive and specific. Vague terms,incomplete information, counteroffers,and 'uncalled for' correspondenceshallnotbeentertained.
2.18.5. Alteration / Rewording / Deletion / Correction of any part in the TenderDocumentarenotpermitted.Iffoundinanybidproposal,bidmaybeliabletoberejectedwithoutpriorintimationtothebidder.
2.18.6. Bidderisrequiredtosubmitthecompleteproposalalongwithrequiredformsetc.,on https://gil.nprocure.com. The proposal shall be exactly according to thepresentedformatsgivenonthehttps://gil.nprocure.com.Thetechnicalresponseshouldbeconcise.Anyresponsenotasperthespecifiedformatmaybeliabletoberejected.Nomarketingliteraturepertainingtothebiddershouldbeenclosedalongwiththeproposal.Ifenclosed,itmaybetreatedasdisqualification.
2.18.7. Committee would ask the Bidder(s) for detailed presentations /Demo of thesolution.AllsuchpresentationsandPoC/Demoshallbeatthecostofbidder.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 17 of 101
2.18.8. The bidder is expected to examine carefully all instructions, forms, terms andspecificationsintheTenderdocument.FailuretofurnishallinformationrequiredintheTenderDocumentorsubmissionofaproposalnotsubstantiallyresponsiveto theTenderDocument in every respectwill be at thebidder’s risk and shallresultinrejectionoftheproposal.
2.19. Submissionofproposal2.19.1. SubmissionofBids:
a) TheBiddershallsubmittheTechnicalBidandaFinancialBidaspertheformatmentioned in thee‐Tenderingwebsitehttps://gil.nprocure.com.ThebiddershallalsocompletethebidformasperFormIandsubmititwiththefinancialbidonhttps://gil.nprocure.com.
b) Telex,cable,e‐mailedorfacsimilebidswillberejected.2.19.2. PricesshallbequotedinIndianRupeesOnly. 2.20. OpeningofBidsbyDST/GIL2.20.1. DST/GIL will open all bids (only Technical stage at the first instance), in the
presenceofallBiddersortheirrepresentativeswhochoosetoattend,andatthefollowingaddress:
GujaratInformaticsLtd,Blockno.1/8,Sector‐11,UdyogBhavan,Gandhinagar‐382010
2.20.2. The bidder's representative who is present shall sign an attendance registerevidencingtheirattendance.IntheeventofthespecifieddateofBidopeningbeingdeclaredholidayforDST/GILoffice,theBidshallbeopenedattheappointedtimeandlocationonthenextworkingday.
2.20.3. Thebidder'snames,bidmodificationsorwithdrawal,bidprices,discounts,andthepresenceortheabsenceofrequisitebidsecurityandsuchotherdetails,asGIL,at its discretion, may consider appropriate, will be announced at the time ofopening.NoBidshallberejectedattheopening,exceptforlatebids,whichshallbereturnedunopenedtothebidders.
2.20.4. Bidsandmodificationsentthatarenotopenedandreadoutatbidopeningshallnotbeconsideredforfurtherevaluation,irrespectiveofthecircumstances.
2.20.5. TheFinancialBidsofonlythosebidderswhoqualifyonthebasisofevaluationoftechnical bid will be opened in the presence of the qualified bidders of theirrepresentativesatpre‐specifiedtimeanddatewhichwillbecommunicatedtothequalifiedbidderswellinadvance.
2.21. ClarificationofBids
During evaluation of bids, GIL may, at its discretion, ask the Bidder for aclarificationofitsbid.GILmayalsoaskforrateanalysisofanyorallitemsandifratesarefoundtobeunreasonablyloworhigh,thebidshallbetreatedasnon‐responsiveandhenceliabletoberejected.Therequestforaclarificationandtheresponseshallbeinwritingandnochangeinpricesorsubstanceofthebidshallbesought,offeredorpermitted.
2.22. PreliminaryExamination2.22.1. DST/GILwillexaminethebidstodeterminewhethertheyarecomplete,whether
anycomputationalerrorshavebeenmade,whethersuretieshavebeenfurnished,
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 18 of 101
whether the documents have been properly signed, and whether the bids aregenerallyinorder.
2.22.2. Priortothedetailedevaluation,GILwilldeterminethesubstantialresponsivenessof each bid to the bidding documents. For purposes of these clauses, asubstantiallyresponsivebidisone,whichconfirmstoallthetermsandconditionsof the bidding documents without material deviation. Deviations from orobjections or reservations to critical provisions such as those concerningperformancesecurity,Warranty,Applicable lawandTaxesanddutieswillhavedeemed to be material deviations. DST/GIL determination of a bid'sresponsivenessistobebasedonthecontentsofthebiditselfwithoutrecoursetoextrinsicevidence.
2.22.3. IfaBidisnotsubstantiallyresponsive,itwillberejectedbyDST/GILandmaynotsubsequently be made responsive by the Bidder by correction of the non‐conformity.
2.22.4. Conditionalbidsareliabletoberejected.2.23. Methodology&CriteriaforTechnical,Commercialandfinalevaluation2.23.1. DSTwill formaCommitteewhichwillevaluate theproposalssubmittedbythe
biddersforadetailedscrutiny.Duringevaluationofproposals,DST/GIL,may,atitsdiscretion,askthebiddersforclarificationoftheirTechnicalProposals.
2.23.2. The bidders are expected to provide all the required supporting documents&compliancesasmentionedinthisRFP.
2.23.3. During the technical evaluation, DST/GILmay seek the clarification inwritingfromthebidder,ifrequired.Ifbidderfailstosubmittherequiredclarificationsindue time, the technical evaluation will be done based on the informationsubmittedinthetechnicalbid.Thepricebidwillbeopenedofthebidderswhosetechnicalbidsarefullycompliedandwhohavescored60%oftechnicalevaluationout of 100.At anypoint of time, ifDST/GIL feels that thebidder is hiding anyinformationwhichwillaffecttheprojectcostinshortorlongrun,DST/GILmayrejecthisbidwithoutassigninganyreasonorexplanation.
2.23.4. Priceshallbeloadedappropriatelyforthemissingcomponent/quantity/taxetc.Price quoted in the financial bid will be final. Bidder is required to fulfill allobligationsasrequiredinthebidasperthepricesquotedinthefinancialbid,forthe proposed scope of work and bill of material, applicable taxes or missingcomponent(s),ifanyforwhichthedescriptionisthereintechnicalresponsebutpriceisnotprovidedinthefinancialsheet.Pricewillbeappropriatelyloadedforthemissingtaxcomponents/missingcomponentsthatintheunderstandingoftheevaluatorsisfoundtobemissingfromtheproposedbillofmaterialexceptincasewherethereisawrittenjustificationprovidedinthetechnicalbidresponse.Basisofloadingshallbethehighestcostquotedbythebidders.
2.23.5. ProofofConcept(tobeshownatthetimeof
Presentation)
• DocumentCapture&DocumentManagementSystem• FileLifeCycleManagement• LetterManagement&Tracking• WorkflowAutomation• RecordManagement• DocumentEditingfeatures
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 19 of 101
2.23.6. Thefollowingcriteriashallbeusedtoevaluatethetechnicalbids.
Sr.No.
Particulars PointsSystem Max.Marks
TechnicalCapabilitiesPOC/DemooftheProposedSolution
1. TechnicalEvaluationcumDemonstration ofproposed/offeredsolution.
Efficient & User Friendly Graphical UserInterface
10 80
EaseofCustomization 10Methods of Report generation includingmethodofexportingthesame
05
Modularapproachmakingitconvenienttoaddmodules later and feature integration likeDigitalSignature,Bio‐metrics,BarCode,SmartCard,etc.
05
DocumentCapture&DocumentManagementSystem
05
File Life Cycle Management and workflowautomation
10
LetterManagement&Tracking 05RecordManagement 05ArchivalManagement 05DocumentEditingFeatures 05MobileApplicationandinterfacewithTablet 05Committeeandmeetingmanagement 05Userfriendlinessandacceptance 05
Presentation2. Presentatio
n onImplementation Plan,Capabilities& ApproachandArchitecturalCapabilities
AdoptionofOpenSourcetechnologies 10
20
Implementation Strategy (Approach &Methodology), Data management andmigration strategy, Scalability of Software,Risk andmitigation Plan, Training & Plan tomanagemultiplestakeholders
5
Development and deployment architectureTools/Technologies used for design anddevelopment etc.), security, conformance toindustries standard, database, BusinessIntelligence (Modularity, Scalability,Suitability of Tools&Technologies proposedincludingcapacitytohandlelargevolumesofdocuments as envisaged by IWDMS 2.0),Approach to develop the API based system,Managing the API eco system, Approach forinterfacingwithothersystems
5
TechnicalMarks(TM) 100MinimumQualifyingScores 60
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 20 of 101
Note:Bidderhas toscoreminimum60marksoutof100marksof technicalbidevaluationtoqualifyinthetechnicalbids.2.23.7TechnicalBidEvaluation:Thetechnicalscoreofabidder‘Tb’willbeassignedtothebidder&itwillbeawardedbased on the Technical Evaluation Criteria as specified above. DST’s decision in thisregardshallbefinal&bindingandnofurtherdiscussionwillbeheldwiththebidderswhosebidsaretechnicallydisqualified/rejected.Bidderswithtechnicalscoreof60%oftechnicalevaluationoutof100willqualifyfortheevaluationofthecommercialbids.The total technical scoresachievedby thebidders shallbesharedwith thebidders&underanycircumstancesthebreakupofthetechnicalscoreshallnotbesharedwiththebidders.Tb: AbsoluteTechnicalScoreTmax: MaximumTechnicalScoreTn: NormalizedtechnicalscoreofthebidderunderConsiderationNormalizedtechnicalscore(Tn)=Tb/Tmax*100
FinancialBidevaluation:The financial bids of only those bidders,who have scored at least 60%marks in thetechnicalevaluationprocess,willbeopened.TheFinancialBidswillbeopened, inthepresenceofBidders’representativeswhochoosetoattendtheFinancialBidopeningondateandtimetobecommunicatedtoallthetechnicallyqualifiedBidders.TheBidder’srepresentativeswhoarepresentshallsignaregisterevidencingtheirattendance.Thenameofbidder&bidpriceswillbeannouncedatthemeeting.Thefinancialscoreofabidder‘Fb’willbeassignedtothebidder.‘Fb’willbethetotalfinancialquotemadebythebidder(excludingtheOptionalServicesquotessoughtinthefinancialbid)Fn=normalizedfinancialscoreforthebidderunderconsiderationFb=commercialquoteforthebidderunderconsiderationFmin=commercialquoteofthelowestevaluatedfinancialproposalThe lowest evaluated Financial Proposal (Fmin)will be given themaximum financialscore(Fn)of100points.Thefinancialscores(Fn)oftheotherFinancialProposalswillbecalculatedaspertheformulafordeterminingthefinancialscoresgivenbelow:NormalizedFinancialScore(Fn)=100xFmin/FbFinalEvaluationofBidProposalswillberankedaccordingtotheircombinedtechnical(Tb)andfinancial(Fn)scoresusingtheweights(T=0.30theweightgiventotheTechnicalProposal;P=0.70theweightgiventotheFinancialProposal;T+P=1).ThefinalevaluationwillbebasedonFinalScorewhichshallbecalculatedasshownbelow:FinalScore(S)=TnxT+FnxPThebidderachievingthehighestcombinedtechnicalandfinancialscorewillbeinvitedfornegotiationsforawardingthecontract. Incaseofatiewheretwoormorebiddersachieve the samehighest combined technical and financial score, the bidderwith thehighernormalizedtechnicalscorewillbeinvitedfirstfornegotiationsforawardingthecontract.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 21 of 101
2.24. AwardofContractOnacceptanceofProposalforawardingthecontract,DST/GILwillnotifythesuccessfulbiddersinwritingthattheirproposalhasbeenacceptedandContractAgreementwillbesigned.AftersigningoftheContractAgreement,novariationsinormodificationsoftheterms of the Contract shall bemade except bywritten amendment signed by all theparties.2.25. DST/GIL’sRighttoAcceptAnyBidandtorejectanyorAllBidsDST/GILreservestherighttoacceptorrejectanybid,andtocancelthebiddingprocessandrejectallbidsatanytimepriortoawardofContract,withouttherebyincurringanyliabilitytotheaffectedbidderorbiddersoranyobligationtoinformtheaffectedBidderorbiddersofthegroundsforDST/GILaction.
2.26. NotificationofAwards2.26.1. Prior to theexpirationof theperiodof thebidvalidity,DST/GILwillnotify the
successfulbiddersinwriting,tobeconfirmedinwritingbyregisteredletter,thathisbidhasbeenaccepted.
2.26.2. ThenotificationofawardwillconstitutetheformationoftheContact.2.26.3. Upon the successful Bidder's furnishing of performance security DST/GIL will
promptlynotifyeachunsuccessfulBidder.
2.27. SigningofContract2.27.1. AtthesametimeasconcernedDST/GILnotifiesthesuccessfulBidderthatitsbid
hasbeenaccepted,DSTwillsendthebiddertheContractForm,incorporatingalltheagreementsbetweentwoparties.
2.27.2. Within15daysofreceiptoftheContractForm,thesuccessfulbiddershallsignanddatethecontractandreturnittoDSTandsendcopytoGIL.
2.28. PerformanceBankGuarantee2.28.1. ThesuccessfulBidderhastofurnishasecuritydepositsoastoguaranteehis/her
(Bidder)performanceofthecontract2.28.2. ThePerformanceBankGuarantee(PBG)hastobesubmittedwithinfifteen(15)
workingdaysofreceiptofaward.ThePBGshallcomprisetwoparts;10%ofthevalue of Development Cost of Price Bid valid for 2 years which would bedischargedandreturnedafterGo‐Live+180daysandsecondpartas10%ofthevalueofO&MPeriodofFinancialBid(O&Mcomponent)validupto180daysbeyondtheexpiryofcontract.
2.28.3. ThePBGshallbedenominatedinIndianRupeesandshallbeintheformofaBankGuarantee issuedbyanyNationalizedBank including thepublic sectorbankorPrivate Sector Banks or Commercial Banks or Co‐Operative Banks and RuralBanks(operatinginIndiahavingbranchatAhmedabad/Gandhinagar)aspertheG.R. no. EMD/10/2016/328/DMO dated 01.05.2017 issued by FinanceDepartment or further instruction issuedbyFinanceDepartment time to time.(ThedraftofPerformanceBankGuaranteeisattachedherewith).
2.28.4. The proceeds of the Performance Bank Guarantee shall be payable to theDepartmentascompensationforanylossarisingfromthebidder(s)’sfailuretocompleteitsobligationsunderthecontract.
2.28.5. The Performance Bank Guarantee will be discharged by the Department andreturnedtothebidder(s)oncompletionofthebidder’sperformanceobligationsunderthecontract.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 22 of 101
2.28.6. Intheeventofanycontractamendment,thebiddershall,within21daysofreceiptofsuchamendment,furnishtheamendmenttothePerformanceBankGuarantee,renderingthesamevalidforthedurationofthecontract,asamendedforfurtherperiod.
2.28.7. NointerestshallbepayableonthePBGamount.DSTmayinvoketheabovebankguarantee for any kind of recoveries, in case; the recoveries from the bidderexceedtheamountpayabletothebidder.
2.29. ConfidentialityInformationrelatingtotheexamination,clarificationandcomparisonoftheproposalsshallnotbedisclosedtoanybidderoranyotherpersonsnotofficiallyconcernedwithsuch process until the selection process is over. The undue use by any bidder ofconfidential informationrelated to theprocessmay result in rejectionof itsproposal.ExceptwiththepriorwrittenconsentofDST,noparty,shall,atanytimecommunicatetoanypersonorentityanyconfidentialinformationacquiredinthecourseoftheContract.2.30. DisqualificationDSTmayatitssolediscretionandatanytimeduringtheevaluationprocess,disqualifyanybidder,ifthebidderhas:2.30.1. SubmittedtheProposaldocumentsaftertheresponsedeadline.2.30.2. Made misleading or false representations in the forms, statements and
attachmentssubmittedinproofoftheeligibilityrequirements.2.30.3. Submittedaproposalthat isnotaccompaniedbyrequireddocumentationor is
non‐responsive.2.30.4. Failedtoprovideclarificationsrelatedthereto,whensought.2.30.5. DeclaredineligiblebytheGovernmentofGujarat,oranyofthedepartmentsinthe
Gujarat State Government, for corrupt and fraudulent practices or has beenblacklistedatthetimeofsubmittingthebid.
2.30.6. Submittedaproposalwithpriceadjustment/variationprovision.2.31. BindingClause
AlldecisionstakenbyDSTregardingtheprocessingofthistenderandawardofcontractshallbefinalandbindingonallpartiesconcerned.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 23 of 101
3. SECTION–IIISCOPEOFWORK3.1. BackgroundAnelectronicworkplaceandautomatedprocessesaretodayessentialforefficientandtransparentgovernance.Itreducesprocessdelays,helpstoaccessandutilizeinformationquicklyandexpeditework.Thesystemwillautomateday‐to‐dayfunctionsatalllevelsoftheadministrativehierarchy.ItcombinesBusinessProcessManagementandDocumentManagement Solutions todeliver a unifiedplatform forGovernment toCitizen (G2C),GovernmenttoBusiness(G2B)andGovernmenttoGovernment(G2G)processes.IWDMS 2.0 is aimed at significantly improving the operational efficiency of StateGovernmentDepartmentsthroughimprovementintheworkflowmechanisms.IWDMS 2.0, as an e‐Governance initiative, would be crucial in shaping GovernmentProcess Re‐engineering (GPR), which eventually enhances the quality of servicesdeliveredtothecitizens.Any Government office is a hub of a variety of communicationswhich require To‐beprocessing and thereafter communicating in some form. Inputs and outputs of allgovernmentactivityneedtobeinvariablycommunicatedwithinandoutsidetheoffice.Theefficiencyofanofficeissignificantlydeterminedbytheefficiencyofitssystemsofcommunicationandinternalprocessing.Governmentofficesaremostamenabletoworkflowautomationsincealloperationsaregoverned by high levels of process definition and the presence of high stakeholdercommitmenttofollowsetrules.ObjectivesTheneed forefficiency ingovernmentprocessesandservicedeliverymechanism is along‐felt one. The IWDMS2.0 is being designed to serve as themeans to achieve thefollowingobjectives:
Toimproveefficiency,consistencyandeffectivenessofgovernmentresponses Toreduceturnaroundtimeandtomeetthedemandsofthecitizens’charter To provide for effective resource management to improve the quality of
administration Toenhancetransparencyandaccountability TopreparebilingualIWDMSmanual
ServicesOfferedThemost critical pre‐requisite for the success of IWDMS2.0would be an exercise tosimplify the government processes and procedures, which includes,streamliningdecisionmaking,leveljumping,standardizationandautomationofrepetitiveprocesses,eliminating unproductive / non‐value‐add work and reducing paperwork.ExpectedOutcomes
Workflow automation including Standardization & automation of repetitiveprocesses/workflows
KnowledgeManagement,includingcreationofinstitutionalmemories RecordManagement
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 24 of 101
EfficientCommunicationsManagemento Registration&routingofcommunicationsdigitally(throughemail,e‐file,
SMS,MobileApp) QualityAssurance ProductivityManagement
o Dashboardviewo PerformanceManago Filetracking
User‐friendliness Accountability,includingaudittrails Cost‐effectiveness Responsivenesstocitizens,i.e.totracktheirrepresentation/letters Integration
o Horizontal‐withinthesameoffice&withotherdepartments,withotherportalsandoutlooke‐maillikeIFMS,HRMSetc.
o Vertical‐withsuperior&subordinateoffices RTIcompliance Transparency
o Decisionsaccessibletogovernmentofficialsatdifferentlevelso Stakeholderscanknowstatusoftheircases
Impact
Provide government functionaries with knowledge, information andcommunicationtoolstoperformtheirdailyoperationsandsupportinthevariousstagesofthecomplex,knowledge‐intensivetaskswhichtheyperform
Establish a system of efficient document & e‐file management to facilitateinformationretrieval,
Provideefficient support forhandlingof incomingcorrespondence/mailsandmanagementofmeetings
Earlier office procedure, BPR, Streamlined processes, accessibility to allconcerned
Introduceanewaspectofoperationalperformancemeasurement
3.2. ScopeofWorkThesuccessfulbidderwouldberesponsibleforsubmissionoftechnicalandfinancialbidsin detailed RFP and the bidder who’s selected in RFP will be responsible fordesigning/customizing,developing,implementing,trainingandO&Mofthesolutionforaperiodofeightyears.Thescopeofworkforthispurposecouldbebroadlydividedasfollows:‐
ComponentwiseScopeofWork
Sr.No.
Component ScopeofWork
1. Application Design, customization/development, test, deploy andmaintainApplicationforproposedsystem.
2. CentralApplication
EstablishmentofaCentralApplicationDevelopment(O&M)Team for Government of Gujarat to provide additionalcustomization/development of new modules, feature
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 25 of 101
Development(O&M)Team
enhancements,defectfixing,etc.atnoextracostduringtheperiod of contract. No Change request will be entertainedduringO&Mperiod.Anydevelopment/changeduringtheO& M will be developed through continuous developmentteammentionedinthisRFP.At the end of the contract period, in case of open sourcesoftware,thesourcecodeshouldbesuccessfullyhandedovertodepartment/its selectedagencyand in caseofCOTS thecustomized part of coding shall be handed over to thedepartment/its selected agency along with all applicablefeature upgrades/product enhancements of the deployedsolution ensuring the deployed solution is up to themarkbearingthelatestversionincaseofbespokedevelopmentaswellasCOTS.
3.
CentralHelpdesk
a) Establishment of a Centralized Helpdesk at DST toprovidetechnical,trainingandInformationalsupporttoalltheusers(Internalusers)throughemail/phone.b) ManagementofHelpdeskOperationsbydeploymentofHelpdeskoperatorsduringtheperiodofcontract.
4.
Training a)SensitizationofDepartmentalstaffontheproject,trainingonuseofapplication.
5. DataMigration
SPhastomigratedatafromtheexistingIWDMS.Costfordatamigrationfromexistingapplicationshouldbeincludedinthepricebid.
1. During the 8 years of O & M period any migrationactivities required to carry out due to change inInfrastructure,Software,etc.shouldbedonebybidderatnoextracost.
2. Thebidderhastomigrateall thecurrentdataoutofwhich only last one‐year data to be kept in the newsystem. Other data are to be kept in the archivalsystem. As and when required by the respectivedepartment, the bidder shall have to support toretrievethesamebydeputingonededicatedperson.Thelastyeardatais:0.15TBTotaldatabasesizeis:1.76TB
ApplicationThebidderisrequiredtomeetalltherequirementsofRFPincludingtheactivitieslisted,timelines and deliverables mentioned in RFP, functional, performance, service levelrelated and any other requirements stated in RFP. Bidder should have to submit theproposedBillofMaterialforIWDMS2.0withdetailsrequiredminimumnumberofCores,Memory,etc.asapartoftechnicalbids.Bidderisalsorequiredtodeliverworkflowenginecomprisingofformbuilder,processdesigner and rule engine for cateringneedsof differentdepartment table/MIS reportgenerator and govt. offices. The form builder and process designer will be used foreveryday data capturing needs of Government organization. GovernmentDepartment/Organizationcanbuildformsandprocessaspertheirrequirementbyitsown.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 26 of 101
MentionedbelowislistofactivitiestobeperformedbytheServiceProviderofthescopeofwork.Ineachphase,theserviceprovidershalltakeformalapprovaloftheDepartmentfor deliverables (including documentation); only then should the selected ServiceProvidercommencewiththenextphase.
RequirementStudyandAnalysisofRequirementsThe selected Service Provider would be required to study all the functionalities andfunctioningoftheDepartmentinamannerthatwillenabletheselectedServiceProvidertomeetalltherequirementsofthisRFP.Postthedetailedstudy,theselectedServiceProviderwillberequiredtosuggesttotheDepartmentmorefunctionalitiesinadditiontotheonesmentionedinthisRFPthatmaybe included in RFP to meet the business requirements of the Department. Anyfunctionalitywhichhasbeenmissedduringrequirementanalysishastobeincludedorshallbeenhancedasandwhenrequired. SolutionDesignBasedontherequirementsstudycompleted,thedesignoftheSolutionwouldbedonebytheselectedServiceProvider.Anindicativelistofdocumentationtobepreparedaspartofcontract:• AsIsandTo‐be• Detailed Business Requirement Document (BRD), User Requirement Specification,
System Requirement Specifications (SRS), System Design document (SDD), UserManual detailing processes, various applicable Acts and business rules based onfunctionalandQuality‐of‐Servicerequirements.
• DetailedDesign document detailing Technical architecture (application,workflow,network,andsecurity)
• Database architecture, including clustering/mirroring, backup strategies, definingdatastructure,data dictionary as per standards laid‐down by Government ofIndia/GovernmentofGujarat(Incasesuchstandardsarenotdefined,thesamewouldbeapprovedbyGoG)
DataArchitecture,interfacearchitectureandintegrationarchitecture.Appropriateloadbalancing and clustering techniques should be adopted by the Selected ServiceProviderintheSolutiondesignformeetingtherequirementsoftheRFPTheselectedServiceProviderisrequiredtokeepallsuchdocumentationuptodatetoreflectthelatestenhancements/modificationsmadetotheapplication. ApplicationDevelopment ApplicationTesting ImplementationandSupport eMailGatewayandSMSGateway(DepartmentwillprovideEmail,SMSgateway) DigitalCertificatesbothDSC/eSign InterfaceswithExternalSystems AadhaarenableeSignauthentication3.3. Geographical Scope (Offices/Location to be covered for the Project): ‐ TheprojectwillbeimplementedcentrallyinitiallyinGujaratStateDataCenter(&any
otherenvisioned future locationbyGoG)androlledout inallDepartmentsand itsHoDs,Boards,Corporation,PSUandanyGovt.officeacrossthestate.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 27 of 101
Inphase‐1,Secretariat (Rajbhavan, GAD, Assembly & departments including HoD offices)willbecovered.
In Phase 2, All state government offices and all panchayat offices in district andtalukaswillbecovered
InPhase3,OtherBoards,Corporations,andotherapplicablegovernmententitieswillbecovered.
Approximateusersare25,000users.However,theno.ofusersmayincreaseandthe
systemshouldbescalableenoughtoprovideseamlessoperationsaccordingly.
3.4. TechnicalEnvisagedArchitecture
3.5. ScopeofWork
Government of Gujarat has envisaged the requirement of a new version (2.0) ofIntegratedWorkflowandDocumentManagementSystem(IWDMS)asacentralizedwebcummobilebasedapplicationwhichcanbeaccessedbydepartmentalofficialsofvariousdepartments/ agencies of Government of Gujarat across the State either on securedintranetandinternetusingseveraldeviceslikeLaptop,PCandMobileTablets/iPad.Govt.ofGujaratintendtoimplementState‐of‐the‐arttechnologysolutionsthatwouldsupportallthecurrentandfutureautomationneedsoftheStateGovt.departmentsandagenciesinordertooptimizetheinternalefficiencyofthedepartment,asfollows:1 Thesolutionshouldbeaccessiblebydepartmentalofficialsofvariousdepartments/
agenciesofGovernmentofGujaratacross theStateeitheronsecured intranetandinternet using several devices like Laptop, PC and Tablets/iPad. Managementfunctionalities and report functionalities and features requested by individualdepartmentsfortheirapplicationsshouldbeavailableonmobileplatformaswell.
2 ProvidecentralizedapplicationforofficeautomationbuiltusingEnterpriseContentManagement and Business Process Management for covering File Movement and
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 28 of 101
Tracking,LettermovementandTrackingandCommitteeandMeetingManagementincludingvariousoperationalreports,etc.(theunlimitedlicensespertainingtotherequiredmodules)
3 Procure the necessary system software for the implementation of the solutionincluding Operating System, Database and all other applicable third partycomponents.
4 Procurement/Supply, installation, integration, implementationandmaintenanceofnecessaryapplicationsoftwareinDataCentre.
5 DeploymentofCentralApplicationDevelopmentTeamtoconfigure/customizeanddevelopotherprocesses/workflowsandmodulesforGovt.ofGujarat
6 TrainingandHandholdingservicesshallincludeplanningandorganizingtrainingsatvarioususerlevelsinthestate,providingfieldlevelsupporttotheusers,etc.
7 Implement and maintain (including all applicable feature Updates andUpgrades/EnhancementsoftheapplicationsoftwarepostGoLivetillendofcontractterm
8 Setting up of helpdesk operations for assisting the internal and external users inresolutionoffunctional,technicalandadministrativeissuesfortheperiodof8Years.
9 CentralApplicationDevelopmentTeamtodevelopNewModulesfortheapplicationsoftwareasandwhenrequired.
10 Planning&monitoringthedatamigrationactivityoftheexistingdata.11 DevelopmentofbilingualIWDMS2.0manualforuserstobeapprovedbyGADandto
be upgradedwith each update/upgrade aswell as any developments introducedthroughContinuousApplicationDevelopmentTeam.
TomeetandprovidetheactivitiesmentionedunderScopeofWork,thebiddershallberequiredtocomplywiththefollowingrequirements:1 Undertakerequirement/GAPAnalysis,customization/developmentandinstallation
ofnewcustomized/developedintegratedproductasperthetransactionalneedsoftheStateofGujaratforaminimumsupportofconcurrent(transacting)userbaseof10,000.Thisinstallationshallbeupwardscalableforincreaseinvalueofconcurrentuser base gradually. Concurrency of users heremeansnot just the userswho areloggedintothesystematapointoftimebutthosewhoareactuallytransactingwiththeserversatthatspecificinstantoftime.
2 Suggesting necessary business process re‐engineering of theDepartmental/Governmentprocesses toenableadoptionof thesolutionproposed.MustdocumentthisandsubmitacopytoGIL,DST,andGADalso.Also,updateusermanualaccordingly.
3 SupplyofInstallationManual,AdministrationManualandUserReference/TrainingManualinEnglishandGujaratilanguage
4 Defineoveralltrainingrequirementsandpreparationofthetrainingplan5 HavingbacktobacksupportarrangementswithOEMtoprovidetechnicalsupportto
theCOTSproduct,incaseofbidderisofferingCOTSProduct.TheOEMmustsubmitanaffidavitforsupportingtheCOTSproductfortheentiredurationofthecontract.
ModulesforDevelopment
3.5.1. GeneralCompliance1 The proposed solution should be platform independent and should support all
Operatingsystemsforwithorwithoutvirtualization.2 Supportopen,scalable,Multi–tenancyandMulti‐tierarchitecturewitheachtierfully
independentwithsupportforclustering.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 29 of 101
3 TheworkflowmanagementsystemshallsupportInbuiltGraphicalworkflowdesignerformodelingcomplexBusinessProcessesusingdraganddropfacilities.
4 ShouldhaveaRuleEnginefordesigningcomplexrulesandconditionsforworkflowroutingWorkflowshouldbeflexibleasbelow;
Backwardandforwardwithinhierarchy HorizontalandverticalLeveljumping
5 Shouldsupportvariousflexibleomni‐directionalroutingmechanismslikesequentialrouting,parallelrouting,rulebasedrouting,ad‐hocrouting.
6 Compliancetoworkflowstandards:BusinessProcessModelandNotation(BPMN),BusinessProcessExecutionLanguage(BPEL)andWorkflowManagementCoalition(WFMC).
7 ThesystemshallsupportdedicatedDocument/Imageserverforbettermanagementof documents, Proper naming conventions, quick retrieval of document, and storeonly metadata information in database. Drop downmenu of subjects, forms, MISreports,hierarchypostdesignation.
8 Inter‐operability ‐ The systems must seamlessly integrate with any or all of theexisting legacyandCoreapplicationsandshall support interfacewithotheropen‐standardsystems.
9 The system shall support multiple databases for reducing database engine leveldependency.
10 DMS,Workflow/BPM,Letter/FileManagementandScanningcomponentshouldbefrom a single OEM or should be design and develop/customized with integratedapproach under Bespoke development in order to have the homogeneous andintegratedsolution.
11 The status tracking, appointment scheduler, Committee of Secretaries, e‐Cabinet,VisitorPassManagementSystemetc.CustomizedappointmentScheduler forCMO,meeting/ program follow up of meeting/program held by Hon’ble CM and otherfacilitiesasdecidedbyindividualDepartments.
12 andreportviewingfacilityshallbeavailableonMobileAppalso.MobileAppshallhave facilities bi lingualUI andUnicode Compliant. Bidderhas to provide the 3‐4themeoptionfromwhichdepartmentwillselecttheUIforapplication.
13 NotingandDraftPreparations in IWDMScanbedoneusingDigitalWritingPad tohandlethefileinthesamewayofhandlingthephysicalfile.Seniorofficialswillbeabletoputnotinginafileusingdigitalwritingpad.
14 User shall be able to configure Homepage such as Dashboards, Quick links, KeyPerformanceIndicators,etc.Thesystemshouldhavefunctionalityallowingtheusertopersonalizethelookandfeel,usabilityandfeaturesaspertheirwish.
15 Through personalization, the users can configure the attributes of applicationsspecifictotheirneeds.
16 ThesystemshallhavefeatureofTagCloudwhichwilldisplaythemostwidelyusedapplicationnamesinhomepageforeaseofaccess.
17 Thesystemshouldhavefeatureslikeevernotei.e.tosharenotes,totakeandattachpicturestoanote,attachvoicememosandaudiotoanote,attachfilestoanynote,toscantextinaphotousingOpticalCharacterRecognitiontechnology,tosetremindersforvarioustasks,goals,andprojects,tocreatecheckboxesthatserveasvirtualto‐dos,tosyncautomaticallybetweenalldevices.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 30 of 101
18 Thebiddershallprovideunlimiteduserandunlimitedinstance.Sothat,eachofficemaycreatelocalinstancebasedontheirrequirementandintegratewithbaseproductthroughAPIorAPIManagementTool.i.e.IWDMS2.0
19 ThesystemshallbecompatiblewithDigitalSignatureCertificateandAadharenablede‐Sign.
20 Thesystemshallallowuserstodefineentry‐levelsettingslikeincreaseofpriorityorsendinganemailtriggeronthebasisofpre‐definedconditionsorsettingupparticularvariableorproperty,etc.
21 Theworkflowmanagement system shall support the definition of roles and allowmany‐to‐manyrelationshipsbetweenusersandrolestobedefined.
22 Support for creating ad hoc tasks at runtime and assigning to users. Support forcreatingtemporaryadhocuserstooonneedbasishowever,oncetheactiveperiodlapses,thisadhocusershouldbemaintainedinthesystemininactivemoderatherthanpermanentlydeletingsothattheactivitylogcanbetracedatanypointoftimeinthefutureonneedbasis.
3.5.2. IntegratedDocumentCapturing(Scanning)Module1 Shouldprovideanintegratedindividual&bulkscanningenginewithcapability for
centralized and decentralized Scanning & Document Capturing. The scanning anddocumentmanagementsolution.
2 Thescanningsolutionshouldhavethecapability tocapturethedocumentthroughmobiledevices.
3 Should have a well‐defined capture module for support of document processing,validation,indexbuilding,andimageenhancements.
4 Should be able to support the capture of digital records of at least the followingformats:
a. Emailsandattachments.b. OCRdocuments.c. Images‐.tiff,jpeg,gif,PDFetc.
5 Theproposedsolution shouldprovide forautomatic correctionofparameters likeimproper format/ compression, skew, wrong orientation, error in automaticcropping, punch hole marks, etc. during scanning. The scanning solution shouldprovide support for automatic document quality analysis so that any bad qualitydocumentdoesn’tgetuploadedtotherepository.Thereshouldbean independentsoftwarequalitycheckserviceavailableaspartofoverallscanningsolutionwhichcanbeusedtoauditscanneddocumentsforresolution,format/compression,orientationetc.
6 Support all the special image enhancement functionality offered by the scannerthroughthedriverinterface.
7 SolutionshallsupportBulkImportofimageandelectronicdocuments.8 Should have capability of automatic segregation of documents/records based on
Barcode,Blankpage,FixedpageandautoFormrecognition.9 ShouldhavethecapabilityofscanningonmultipleplatformslikeWindows,Linux,etc.10 Provide Image processing libraries that support image enhancements such as
changing contrast, zoom in/out, cleaning, etc. and other imaging features likecompressionandextraction,etc.
11 ThesoftwaresolutionshouldincludetheRubberbandfeaturefortheextractionofthedatausingOCR technology so thatuser canmarka zoneon image at runtimeduringscanningstage&maptheextracteddatawiththeindexingfield.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 31 of 101
12 Themobilecaptureshouldsupportimagecompression,B/Wconversionfromcolorimages, G4 compression for B&W, JPEG for color and gray scale, multiple pagedocument capture, auto cropping, auto orientation, perspective correction, noiseremovalandgeocapture.
3.5.3. Electronic File System (e‐File) & Correspondence/Letter Management
System13 IWDMS2.0completelyautomatesfile&correspondencemanagementfromcreation
toarchivaloffilesandcorrespondence.Alldecisionscanbecapturedinthefileitselfand remain intact throughout the lifetime of the file. Effective transformation topaperless office environment by providing functionalities like electroniccorrespondence/filecreation,management,movementandperformanceof relatedtasks likediaryentry, indexing,noting, cross referencing, search/retrieval,DigitalSignatureIntegration,etc.
14 File&LetterManagement system shouldbuildusing robustEnterpriseDocumentManagement and Business Process Management as a platform or equivalentfunctionality under bespoke development and should comply with the Manual ofOfficeProcedure(MOP),publishedbytheGeneralAdministrativeDepartment(GAD),GovernmentofGujarat(GoG).
15 InbuiltInboxforreceivingofCorrespondence/Letter.16 Maintenanceofe‐Registers–personal,division&departmentwise.17 Providesprovisionforinterdivisionalsharingoffiles,papers,etc.18 SMS, E‐mail based notifications on workflow movement of file/letter across the
definedroute.19 Thesystemshallhavearepositoryorpredefinedfolder/areawhereallnewLetters
arereceivedafterscanning.Thesystemshouldbesecureandshouldbe tested forOpenWebApplicationSecurityProject(OWASP).
20 Thesystemshouldbecapable&configurableenoughforcompleteFile&LetterLifeCycleManagement.
21 Thesystemshallhaveafacilitytosavethefileinthedesiredfolderinthesystem.22 Thesystemshallhaveafacilitytocreatebothmain,linkedaswellaspartfile.23 FilecreationshalcontainorcreateatleastFileNumber,LetterNo.,andFileSubject
asaninputwhenacommandisgiven.24 ThesystemshallalsogenerateaBarcodenumberonsuccessfulcreationofafile.This
barcodecanbepastedonaphysicalfilefortracking,incasephysicalfileisalsoused.Barcodeno.andfileno.slipshallbegeneratedfromsystem.
25 Thesystemshallhavefacilitytoprintbarcodenumberoffileatanypointoftime.26 Thesystemshallhavefacilitytocreatecustomizablenotes.27 Solution should have the Green Note sheet. Therefore, the system shall support
collationofall relateddocuments intoavirtual file.The systemshall replicate thePresentfilehandlinginthesamemannerasfollowed,i.e.,ElectronicfilesshallgivethesamelookandfeelofPhysicalfilewithdocuments/lettersontheright‐handsideand green note sheet on the left hand side. TheMIS report should have featuresgraphicalrepresentationofstatisticsofno.offiles,inprocess,pendingetc.
28 ThesystemshallhavefacilitytoadddocumentsintheFileascorrespondenceside.EachfileshouldhaveNotingsideandcorrespondencesidewithpagesnumber.pageno.withsubjectofpageindextobeautomaticallygeneratedinthebeginningofthefile.Noteshouldbeonleftsideofuserandcorrespondencesideonrightsideofuser.
29 Systemshouldhave the facility tomaintainversionhistoryofnotes,documents&letters.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 32 of 101
30 The systemshall support collationof all relateddocuments into a virtual file.ThesystemshallreplicatethePresentfilehandlinginthesamemannerasfollowedi.e.ElectronicfilesshallgivethesamelookandfeelofPhysicalfilewithdocumentsontheright‐handsideandgreennotesheetonthelefthandside.
31 ThesystemshallhaveanIn‐builtWebbasedTextEditorwithbasic functionalitiessuchasbold,alignment,font,fontsize,color,highlighting,etc.
32 Thesystemshallprovidefacilitytoviewallcorrespondencetheright‐handside(RHS)ofthefolderwithnote‐sheetonlefthandside.
33 The system shall provide facility to users to e‐Sign their notes, which shall beautomaticallystampedwithusername,dateandtime.
34 ThesystemshallprovidefacilitytosecurenotesinFileView.35 Thesystemshallprovidefacilitytomaintainversionhistoryofnotes,documents&
letters.36 Thesystemshouldbecapableenoughtomanagefiledifferentiation,foraninstance,
differentiation between Administrative general files (Subject Files) andAdministrativespecificfiles(SpecialFiles).
37 Thesystemshallhaveafacilitytocreate/openanewelectronicsubjectfile.38 SubjectFilecreationshalltakeatleastFileNumberandFileSubjectasinputs.39 ThesystemshallhavefacilitytoaddmultipledocumentsintheFileinasinglego.40 ThesystemshouldhaveafacilitytosearchafileonFilenumberand/orfilesubject.41 Thesystemshouldhaveaprovisiontodefinesearchingattributes foreachtypeof
specialfile.42 Thesystemshouldhaveanindextableofallcreatedfiles.43 Thesystemshouldsupportcreationofanytypesofspecialfilessuchasemployeefiles,
propertyreturnfileetc.44 The system should have a separate searching interface for each type of file. i.e
differentsubtypesoffiles.45 Thesystemshallprovidefacilitytouserstolinkthenotestoanydocument,fileand
previousnotes,sothatcorrespondingobjectscanbedirectlyopenedfromthenoteview.
46 Thesystemshallprovidefacilitytouserstoappendnotesinthesameparagraph.47 ThesystemshallprovidesecurityonnotessothatNoting/commentsoncewritten,
signed and forwarded shall not be amendable by any user including originator,however,ifanewnotehasnotbeenwritten,theusershallbeabletomodifythelatestnote,whichheiswritingprovidedthatthenotehasnotmovedforwardtonextlevelintheheirarchy.
48 Thesystemshallprovidefacilitytotakeprintoutofthenoting/correspondencesideforfilinginpaperfolderasrecord.
49 ThesystemshallprovideafacilitytoaddnewdocumentsinthefilebycallingnativeapplicationsfromMS–OfficeSuite,OpenOfficeSuite,etc.fromthesameinterface.
50 Thesystemshallprovidefacilitytoopenmultipledocumentssimultaneously.51 Thesystemshallhaveafacilitytocreateapaperprofileofadocumentinthefile,in
casedocumentisnotavailableinelectronicform.52 Usingworkflow featureof a system,user shall be able to route the file.Workflow
shouldbeflexible,bothforward,backward&levelJumping.53 Thesystemshallprovidearole‐basedconfigurablefeaturetorecallaFilefromother
user.54 Thesystemshallprovideaninterfacetosearchthestatusofafileinaworkflow.55 ThesystemshallprovideafacilitytotrackadepartmentwhereaFileispending.56 Thesystemshallsupportthecasefilemanagement.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 33 of 101
57 Fileviewshallprovidefacilitytoviewalldocumentsinsidefile,Noting/commenting,editfileproperties.
58 The system shall have facility tomark a file as complete/closed and thereby un‐editableexceptwithspecialapprovals.
59 Thesystemshallhaveafacilitytoaddoruploadadocumentorletterinelectronicformatfromlocalcomputer/networkdrive/scanner/externalstoragedrive.
60 ThesystemshallprovideafacilitytoviewLetteronRHSandindexingfieldsonLHS.61 ThesystemshallhaveafacilitytoaddaNotewithaLetter.UsingtheTablets/iPad
andmobiles,usersshouldbeabletoaccesstheFilesandLetter.62 Note View & Letter View should be simultaneous, i.e., Note should be on LHS &
correspondingLetter(s)shouldbeonRHS.63 The system shall have a facility to save the Letter in an existing file and tag it to
multiplenotes.64 ThesystemshallhaveafacilitytoroutetheLetterusingworkflowfeatureofasystem
inaflexiblemannerforward,backwardandleveljumping.65 Thesystemshallsupportad‐hocroutingofadocument.66 The system shall have a facility to prepare response and attach with the Letter
workflow.67 The systemshallprovidean interface to track& search the statusof aLetter in a
workflow.68 Thesystemshallhaveafacilitytosendthereminders.69 Thesystemshallhaveafacilitytogeneratevariouscustomizablereportsw.r.t.Letter
workflow such as pending with users, pending since, elapsed time, initiated by,completedbyetc.
70 The system shall have a facility to track a department/organizational unit whereletterispending.
71 Thesystemshallprovideanadvancedsearchinterfacefortracing&searchingaletterbasedontitle,dates,subject,pendingwith,completedby,pendingsince,etc.alongwithaconfigurationprovisionforthesesearchparametersinthesystem.
72 Thesystemshallhaveafeaturetorecallaletterfromotheruser.73 ThesystemshouldhavefacilitytoputthecompletedLetterinaneworanexisting
file.
3.5.4. WorkflowManagement1 Theworkflowmanagementshouldhavefollowingin‐builtfunctionalities
OrganizationManagement RoleManagement RolebasedAccess StructuredWorkflow UnstructuredWorkflow EachDepartmentforitsdifferentapplicationsshouldbeabletocustomizethe
workflowifitsowishes.2 The system shall facilitate re‐engineering of processes and act as a platform for
building specific application and have aworkflowmanagement engine to supportdifferenttypesofdocumentroutingmechanismincluding:
Sequential routing: ‐ Tasks are to be performed one after the other in asequence.
Parallelrouting:‐Taskscanbeperformedinparallelbysplittingthetasksamongmultipleusersandthenmergingassinglecompositeworkitem.Thesystem shall support conditionalmerging ofmultipleparallel activities, i.e.,
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 34 of 101
responsefrommandatoryparallelworkstagesbeforeitcanbeforwardedtonextstage.
Rule‐basedrouting:‐Oneoranothertaskistobeperformed,dependingonpredefinedrules.(Systemshallhavein‐builtconfigurationprovisiontodefineroutingrules).
Customrouting:‐Taskscanberoutedontheflybasedonrequirementsorpriorities.
Ad‐hocrouting:‐Changingtheroutingsequencebyauthorizedpersonnel. Compliancetoworkflowstandards,viz.,BPMN,BPELandWFMC. Supportforregisteringandconfiguringthirdpartyapplicationsinportletlike
view.i.e.usercanseemostfrequentusedfunctiononscreen.Usershallbeabletocustomizetheirdashboardaccordingtotheirrequirementalso.
3 Thesystemshouldprovideprocessdesigningfeaturesasfollows: The system shall allow users to define entry‐level settings like increase of
priority(urgent,immediate,veryurgent,routine)orsendinganemailtriggeron the basis of pre‐defined conditions or setting up particular variable orproperty,etc.
Theworkflowmanagementsystemshallsupport thedefinitionofrolesandallowmany‐to‐manyrelationshipsbetweenusersandrolestobedefinedbydropdownmenuofadministrativehierarchy.Supportforcreatingadhoctasksatruntimeandassigningtousers.
In‐builtFormDesigner Thesystemshallprovideinbuiltfacilitytodesigncustomizedformsthatcan
beattachedatoneormorestagesofworkflow. TheFormdesigner interfaceshallsupport facilitytodefinevarioustypesof
text boxes, Combo boxes, radio buttons, drop downs, etc. (Just likecorresponding features of table designing, indexing signs etc inMS‐ Office,Safarietc)
The system shall provide facility to define variables in the process or inexternaldatabasetables,whichcanbelinkedtofieldsdefinedintheformforefficientdataentry.
Thesystemshallprovidefacilitytodefinezonesatformsandimages,sothatrelevantpartoftheimageishighlightedforImageassisteddataentry.
Thesystemshallsupportfieldlevelcalculationsatformlevel. Facilitytousescriptsfordefiningfieldlevelvalidations.
In‐builtExceptions
ThesystemshouldhaveRuleEnginefordefiningrules. Facilitytoraisetriggersonthebasisofexceptions. Facilitytoraiseautomaticexceptionsonthebasisofpre‐definedconditions. Thesystemshalltrackalltheexceptionsraisedinthecourseofprocessand
shallmaintainhistoryofthatwithusername,date,timeandcomments. The system shall clearly differentiate process instances with and without
exception.Triggers
Thesystemshallprovide facility todefine custom triggers likeEmails,newfiles in inbox, Word template or launching executable, etc. on predefinedconditions.
Sentstatus,pendingstatus,reportsformonitoringdeadlinesetc.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 35 of 101
Thesystemshallprovidefacilitytodefinecustomtemplatesforthetriggerswithstaticanddynamicdata.
The system shall provide facility to generate event based triggers forautomaticallysendingmails/fax,generatingresponses,invokingdataformfordataentry,communicatingfromexternalsystems.
Theworkflowmanagementsystemshallhaveemailnotificationtouserwhentheuser isnot loggedonto theworkflowmanagementsystem.Uponreceiving theemail,theusershallbeabletoclickontheURLintheemailtoautomaticallylaunchtheWorkflowmanagementsystemandpresenttheuserwiththetasktoacton.
3.5.5. DocumentView1 TheSystemshallsupportintegratedin‐builtviewerforviewingImagedocuments.2 Evenformulti‐pagedocument.Thedownloadandviewshouldbepagebypage.The
mobileappshouldsupportaccessingdocuments3 Thesystemshall facilitate zoom‐in/zoom‐out, zoompercentageandZoomLens to
zoominonapartofimageandotherimageoperationslikeInvert,rotate,etc.4 Supportarchival&viewofPDF/Aformatdocuments(openISOstandardforlongterm
archivalofdocuments).5 Documentviewshallhavetheprovisiontodrawaline,insertarrows,etc.overimage
document.6 The system should support viewing and renderingof PDF/Adocuments in inbuilt
viewer.7 Documentviewshallhavetheprovisiontohideorhighlightcertaintextbydrawing
lineandshapes.8 TheSystemshallsupportforviewingdocumentsinnativeapplication.9 Thesystemshallprovide facilityofputtingtext,graphicandimageannotationson
scanneddocumentpages.4 Themobileapplicationshouldhavesupportforretrievalandarchivingofdocuments.
3.5.6. Annotations1 TheImageappletshallsupportcomprehensiveannotationfeatureslikehighlighting,
markingtext,underliningputtingstickynotesondocuments,andsupportfortextandimagestamps,etc.
2 Thesystemshallsupportautomaticstampingofannotationswithusername,dateandtimeofputtingannotations.
3 Thesystemshallprovidefacilityforsecuringannotationsforselectiveusers.4 Thesystemshallstoreannotationsasseparatefileandatnotime,theoriginalimage
shallbechanged.Thesystemshallprovidefacilityoftakingprintoutswithorwithoutannotations
3.5.7. Indexing1 TheSystemshall automatically index folders, filesanddocumentsonuser‐defined
indexeslikedepartment,ministry,filenumber,year,pageno.onCorrespondencesideandnotingside,subject.
2 Thesystemshall facilitateeditingofautomaticindexingusingOCRfunctionalityorfromotherapplications.
3 TheSystemshallsupportAutomaticfulltextindexingforTextsearch.
3.5.8. Search&Retrieval1 The system shall provide extensive search facility to retrieve documents or
Folders/Files.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 36 of 101
2 Thesystemshallsupportlocalsavingofsearchqueriesandsearchresults.3 Thesystemshallsupportsearchfordocumentsorfoldersondocumentorfolderor
archivesonprofile informationsuchasname,created,modifiedoraccessedtimes,keywords,owner,etc.
3.5.9. Security&UserManagement1 The Documentmanagement system shall support definition of Users, Groups and
Rolesrelationinthesystem.2 Thesystemshallsupportsecureloginidandpasswordsforeachuserandpasswords
shallbestoredinencryptedformatindatabase.3 Thesystemshallhaveafacilitytodefinepasswordpolicywithextensivepassword
validationslikepasswordsmustbeofminimum8characters,shallbealphanumeric,locking of user‐id after a specified number of un‐successful attempts, passwordexpiry,passwordhistorysothatpasswordsarenotsameaspreviouspasswordsetc.
4 UsercanadditionallyresetpasswordbyOTPonmobile.5 Thesystemshallsupportrole‐basedaccesspermissionmanagementatvariouslevels
likeFolders,documentsandobjectlevel.6 The system shall support multiple levels of access rights (Delete/ Edit/ View/
Print/WriteCopyorDownload)andexternalapplicationbasedrights.7 ThesystemshallsupportsystemprivilegeslikeCreate/DeleteUsers,Defineindexes,
BruteForce,etc.8 ThesystemshallprovideLDAPsupportforintegratingwithdirectoryservices.9 The system shall have support Single Sign On facility. The single sign on facility
availableinSATHI(HRMS)shallbeused.10 ThesystemshallsupportExtensiveAudit‐trailsatdocument,Folderandforhighest
levelsforeachactiondonebyparticularuserwithusername,dateandtime.11 TheSystemshallsupportintegrationwithdatabase‐basedauthentication.12 ThesystemshallsupportintegrationwitheSignandPKI(publickeyinfrastructure)
forenhancedsecurity.13 TheworkflowmanagementsystemshallsupportSSL,HTTPSandsessiontimeouts.
3.5.10. SystemAdministration1 Thesystemshallsupportweb‐basedsystemadministrationmoduleforthecomplete
managementofsystem.2 TheAdminmoduleshallsupportUsers/Groups/RoledefinitionandgrantingAccess
Rightstothemandsetpasswordexpirypolicies.3 The Admin module shall provide easy to use configuration interface for Index
structuredefinitionthatcanbeusedbydifferentusers.4 TheAdminmoduleshallprovideinterfaceforpurgingoldaudittrailanddoselective
logging,i.e.,selectthesystemorapplicationfeaturesfor,whichtheaudittrailshavetobegenerated.
5 TheAdminmoduleshallprovidefacilitytotakecompleteandincrementalbackupsandshallbeabletointegratewiththirdpartybackupsolutions.
3.5.11. AuditTrails1 ThesystemshallsupportExtensiveAudit‐trails;atuser,Folder,CoS(Committeeof
Secretaries)andCabinetlevels.2 The system shall provide facility to generateAudit trails on separate actions, and
betweenspecificdate/times.3 TheSystemshallhaveaudittrailtomaintainhistoryofallactivitiesperformedonthe
system.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 37 of 101
4 Thesystemshallgiveflexibilitytoadministratortodoselectiveloggingi.e.suspendandresumeaudittrailgenerationforspecificsystemanduseractivities.
5 Theapplicationshalllogalltheactionsdonebyindividualuserswithusername,dateand time and the administrator shall be able to generate detailed audit logs andhistoryoftheprocessinstance.
3.5.12. RemindersandAlarmsThe system should have the capability to set automatic reminders and alarms toconcernedusers.
3.5.13. ProcessMonitoringandReporting1 Systemshallprovideafacilitytoconfigurerole‐baseddashboardforindividuals,for
e.g., dashboard for Secretary, dashboard for Director/Commissioner/HoD/Officersassignedtomonitor.
2 Usershouldbeabletoconfiguredashboardwithoutanycoding.3 Theworkflowmanagementsystemshallbeabletokeeptrackoftheworkitemstatus,
thedate/timethe jobsarestartedandended,thecreationandarchivaldateofthedocuments.
4 Theworkflowmanagementsystemshallprovidegraphicalandtabulartoolstoviewprogressofeachindividualprocess.(Reports)
5 Thesystemshallsupportextensiveconfigurablereportingfacilityatdocument,folderand user level. Please specify all inbuilt reports available in the system in theproposedsolution.
6 Report Creation should be configurable and there shouldn’t be any limit on thenumberofreportsthatcanbecreated.
7 Usershallbeabletodrilldowninareportforspecificinformationanalysis.8 Theworkflowmanagement system shall support the generation of statistical and
managementreportslike: Numberofpendingfiles,lyingatindividualuserlevel Timetakentocompleteeachtask ProcessHistoryReport UserPerformanceReport AverageProcessTimeReport ParticipantReport ParticipantProcessingTimeReport ProcessDefinitionSummaryReport ExceptionDetailsReport ExpiredWork‐itemReport DiversionReport,etc
9 The workflow management system shall support the generation of performancecomparisonreports.
10 Theworkflowmanagementsystemshallsupportusersdrilldownfromahigherlevelviewofbusinessprocessestolowerleveldetails.
11 TheworkflowmanagementsystemshallsupportconfigurablestatisticalreportslikeTotalturnaroundtimeanddelayreportforcompleteprocessorspecificworkstages.
12 The workflow management system shall support definition of new customizedreportsbasedonexposeddatapointsfromexternalapplications.
13 Theworkflowmanagementsystemshallalsoprovidedashboardinterfaceforonlinereportingofvariousprocesses.Theinterfaceshallgiveaflexibilitytotogglebetweengraphicalandtabularviewandtiledifferentwindowsinthesameinterface.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 38 of 101
14 The system should include administration module to configure the user, groups,queuerelatedtoaprocess.Thesystemshouldallowusertosettheirdisplaysettingsaccordingtotheindividualpreferencesandcompanypolicies.Userscancustomizetheirthemes,resizecomponents,andconfiguresingle/multi‐columnviews.Itshouldhavenavigationcontainer todisplay the listofall component instancesassociatedwiththeviewofauser.
15 Systemwillpublishoridentifythe2ChampionUsersonthebasisofusageofIWDMSeverymonth.
3.5.14. Committee and Meeting Management including cabinet, CoS, CMO,DepartmentandothermeetingsofVariousgroupsandCommittees.
1 Thesystemshouldhavethecapabilitytoconstitutethecommitteewithitsmembersandconvenerdetails.
2 Thesystemshouldhavethecapabilitytodefinetheroleofeachcommitteemember.3 Thesystemshouldhave thecapability tocapturevariousdetailsof thecommittee
suchastermofreference,tenure,committeemembers,etc.4 Thesystemshouldhave thecapability todefine thecommitteemembers fromthe
internaldepartmentsaswellasexternalusersalongwithrequireddetails.5 Thesystemshouldhavetheconfigurationcapabilitytodefinethemessagetemplate
forsendingthenotificationtorespectivecommitteemembers.Also,itshouldhavethecapability to create and saving the templates for different type of notificationmessages.
6 Thesystemshouldhavethecapabilitytodefinetheapprovalprocessforcommitteeconstituted.
7 The system shouldprovideUser Inboxwhere committeemembers/approvers canviewthependingrequestforapproval.
8 Thesystemshouldhavethecapabilitytoattachtherequireddocumentswithvariouscommitteesconstituted.
9 Thesystemshouldhave the capability to circulate theOfficeMemorandawith therespectivecommitteemembers’/stakeholdershavingdetailsaboutthecommittee.
10 ThesystemshouldhavethecapabilitytodefinethemeetingdetailssuchasAgenda,date,time,venue,priority,etc.alongwiththerequireddocuments.
11 The system should have the configuration capability to link the members withmeetingfromthelistofpre‐approvedcommittees.
12 Thesystemshouldhavetheconfigurationcapabilitytodefinetheapprovalworkflowformeetingscheduled.
13 ThesystemshouldhavetheconfigurationcapabilitytodefinetheMeetingInvitationtemplatesforsendingthenotificationstoallthecommitteemembers.
14 The system should provide the calendar view having details about the meetingscheduleonweekly/monthlybasis.
15 The system should provide the capability to submit the response about theiravailability for the meeting scheduled. Also, system should have the capabilitywhereinconvenercandefinethedeadlineofsubmittingtheresponseofmember’savailability.
16 ThesystemshouldhavethecapabilitytocapturetheMinutesofMeeting.17 Thesystemshouldprovidetheconfigurationcapabilitytodesigningthetemplatefor
circulatingtheMinutesofMeeting(MoM).18 ThesystemshouldprovidethecapabilitytosendtheMoMnotificationthroughemail.19 Thesystemshouldhave thecapability toassign theaction items to the respective
committeemembers.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 39 of 101
20 Thesystemshouldprovidethecapabilitytodefinethedeadlinesofsubmittingtheresponsefordefinedactionitems.Also,thesystemshouldbecapableenoughtotrackthe action items assigned to the respective committee members based on thedeadlinesbeenset.
3.5.15. AppointmentScheduler• AutomatedScheduling
o Systemshouldhavefacilitytosubmittheappointmentrequesttoofficialsbyinternaluserandgeneralpublic.
o SystemShouldhavefacilitytoconfirm,RejectorpostponetheappointmentRequest
o SystemshouldhavefacilitytosuggestthetentativetimefortheappointmentSystemshouldhavefacilitytocreate,edit,deletetheappointmento Alerttoofficials/requesterondifferenteventoftheappointmento RealtimeupdateonMobileappo SystemShouldhavefacilitytosendtheAppointmentReminders
• CalendarManagemento System should have facility to show the confirm appointment, pendingrequestforappointment.o Systemshouldhavefacilitytoautogeneratethefreetime/Notbookedtimeslot.
• GroupSchedulingo SystemshouldhavefacilityfortheSchedulingtheGroupappointment.
• Multi‐Locationo Shouldaccessibleonwebbasedandmobile/tablet/i‐Pado Shouldbeaccessiblefromanytime,anywhere.
3.5.16. DashboardandMISreportsfacilitytobeprovided.
3.5.17. KnowledgeRepositoryTheKnowledgeRepositorywillenablethedepartmenttostoreandmanagealltypeofdocuments,includingHTML,imagedocumentsandmultimedia.KeyfeaturesrequiredintheKnowledgeRepositoryare:1 OnlinerepositoryofGovernmentofGujarat‐circulars,notifications,policies,schemes
andguidelinesarrangedinachronological,thematicfashionforeasyaccess.2 Provisiontopostonlinerequestsforpolicyclarification/interpretation,newpolicy
creation/amendment.3 Onlinerepositoryofclarifications/interpretationcasesrespondedinthepast.3.5.18. ArchivalofElectronicDocuments1. Thesystemshouldbecapableenoughtostorebillionsofdocumentsinrepository.2. TheSystemshallsupportcategorizationofdocumentsinfolders‐subfoldersjustlike
windowsexplorerinterface.Thereshouldnotbeanylimitonthenumberoffolderandlevelsofsubfolder.
3. The System shall provide facility to link cross‐related documents like ApplicationformandFieldreport,Grievanceandreplysent,etc.
4. Thesystemshallprovidesearchfacilitytointhesameinterface,sothatusersareabletosearchthedocumentstobelinked.
5. Thesystemshallsupportversioningofdocumentswithfacilitytowriteversion‐wisecomments.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 40 of 101
6. ThesystemshallallowLockingofdocumentsforeditingandimportingitbackintothesystemthroughcheck‐in/Check‐outfeatures.
7. Repositoryshouldbeformatagnostic.8. Systemshouldsupportconfigurationofverificationprocessesfordifferentbusiness
types.Itshouldbeabletohandlemulti‐userenvironmentforprocessingfilesrelatedtodifferentdepartmentandsubjects.Whileprocessingafile,allthecontentslikedataand images for each transaction should be displayed to processing users andprocessingusersshouldbeallowedtoaccept,rejectorsendthefilesforreview.
3.5.19. Integration&WebServices1. ShouldbebasedonopenstandardsandhaveAPIsupportfordataimport&export.2. The System shall provide support to invocation of external programs to perform
activitiesofaprocesslikelegacyapplicationscreenfordataentry.3. TheSystemshallsupportintegrationbasedonstandardssuchasXML.4. TheSystemshall supportmessage‐basedcollaborationbasedonprotocolssuchas
HTTP,FTPandSMTP.5. TheSystemshallsupportintegrationwithSMSGateway.6. TheSystemshallsupportintegrationwithEmailServers.7. TheSystemshallprovidefullyfunctionalAPIsforIntegration.8. TheSystemshallsupportWebbasedinterfaces.9. SystemshallsupporttheAPIintegrationwithDMSandNASStoragewhichmaybe
procuredbyGovernmentforstoringhistoricaldata.3.5.20. Architecture&Scalability1. Solutionshouldhavebeenbuiltusingopen‐sourceserversidetechnologies.2. Solutionshouldbemulti‐tenancy,multi‐tier,web‐basedsolution(havingweb‐based
front‐end for users and as well as for system administrative functions) havingcentralizeddatabase,webandapplicationserverwithsupportforclustering.
3. Thesystemshouldstoreonlyindexinformationindatabasewhiledocuments,images&otherobjectsshouldbestoredinseparatefileservers.
4. SolutionshouldbecomplianttoODMA,WebDAV,CMIS,etc.5. Formatagnosticrepositorytostorecontentinmultiplefileformats.3.5.21. OfficeNoteCreation&ApprovalThisapplicationshouldfacilitatethefollowingfeatures:1. Createnewofficenotedocumentandsavingitasdraftforfurtherapproval2. Capabilityforroutingtheofficenoteforapprovaltodifferentofficials3. CapabilityforOnlineediting4. Supportforwriting&editingofficenoteinEnglish&Gujarati.5. Capabilityofrevisionhistorytracking6. Capabilityforcurrentstatusmonitoring&tracking7. Capabilityforprintingofficenotewithorwithouttracksheet8. ShouldbebasedonWorkflowandDocumentManagementSystem.
3.5.22. GOIIssue1. InitiateGOIissue2. UpdatetheGOIissues3. EdittheGOIissue4. ReplyonGOIissue3.5.23. RecordManagement
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 41 of 101
1. Solutionshouldmanagelifecycleofboth,physicalandelectronicdocumentsthroughrecordretention,storage,retrievalanddestructionpolicies.
2. Solutionshouldsupportmanagingandtrackingofphysicallocationofdocumentsifrequired.
3. Solutionshouldprovidetheconfigurablecapabilityofrecordclassificationaspertherecordkeepingstructure(FilePlan)ofdepartment.
4. Solutionshouldhaveafacilitytodefinedispositionschedule/policiesforrecord.5. Solutionshouldprovidethecapabilityforonlyauthorizedindividualstoview,create,
edit,anddeletedispositionschedulecomponentsofrecordcategories.Thecompletescheduleswouldbeaspertheorganizationalpolicies.
6. Solution should have a provision to move & track a record among users withinoffice/acrosslocations.
7. Whenrecordismovedoutofthefacility,systemshouldhaveacapabilitytocapturethetransport/courierdetail.
8. As a part of reporting mechanism of the solution, the solution must provideconfigurable and customizable reports on the Records in the selected file plancomponent such as number of records present, number of record folder, Recordcreationdate,Reportonactivitiesoftheselecteduser,ReportontheRequest/Returnactivities,Reportonoverdueitems,Reportonitemsborrowed,Reportsonrecords,whoseretentionperiodaregettingoverinspecifiedtimeandsoforth.
9. Solutionshouldprovidetheconfigurablecapabilityofrecordclassificationaspertherecordkeepingstructure(FilePlan)ofdepartment/organizationalunit.
10. Thesolutionshouldbecertified for compliancewithprovenRecordsManagementStandards such as theDoD 5015.2‐STD (U.S. Department of Defense Standard) orVERS(VictorianElectronicRecordsStrategy).
3.5.24. CircularManagementThe circulars module is used for management of circulars issued by the head ofdepartmentsforvariousgovernmentoffices.Inaddition,onecancreateanewcircular,editanexistingoneordelete/archivecirculars.
3.5.25. e‐Cabinetandfewotherimportantmeetingandsubjects.1. AppointmentofMinisters,MinistersofStates,DeputyMinistersandParliamentary
Secretaries.2. Allotment of Subjects to Ministers, Ministers of State, Deputy Ministers and
ParliamentarySecretaries.3. ConveningofCabinet/CouncilofMinistersmeeting.4. TheGujaratMinisters’ Salaries andAllowancesAct andAmendments thereunder.
SalariesandallowancesofMinistersandParliamentarySecretariesandotherrelatingWork.
5. Rules/Order of Traveling and Daily allowances of Ministers/ ParliamentarySecretaries.
6. Rules for Minister’s Medical treatment. Medical treatment bills of Ministers andParliamentarySecretaries.
7. GujaratMinister’s(MedicalAttendanceandTreatment)Rules.8. Governor’sAddress.6. Governor’sConference.9. ConveningofSecretariesmeeting.(CommitteeofSecretariesMeeting)10. MatterrelatingtoWesternZonalCouncil.11. MLAs’standingconsultativecommitteeconstitutedunderchairmanshipofHon’ble
ChiefMinister.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 42 of 101
12. Reservation of Committee Rooms/Auditorium/Conference room & its relatingmatters.
13. PaymentofSurchargeofTelephonebillandMobilehandsetbillforMinisters/StateMinisters/DeputyMinistersandParliamentarySecretaries.
14. IssueofFax‐WirelessMessageofProgammeofoutofStatetourofMinisters/StateMinisters/DeputyMinisters.
15. Air traveling ticket booking and cancellation of Chief Minister, Ministers/StateMinisters/ Deputy Ministers and Parliamentary Secretariesand officers and othergovt.functionaries.
16. Matters relating to purchasing of books/magazines for Chief Minister, Ministers/StateMinisters/DeputyMinistersandParliamentarySecretaries.
17. AllmattersrelatingtosumptuaryallowanceplacesunderdisposalofChiefMinister.18. DisposalofAuditparasraisedwithrespecttothealltypeofBillsofEx‐Ministers.19. Mattersrelatingto(H.O.R.)HighofficialreservationforMinisters.20. IssueofformsforRailwaytravelH.O.R.&ExchangeOrderformsforAirTravel.21. Legislativeworkrelatingmattersmentionedabove.22. MattersmentionedaboverelatingtoGovernor&hisadvisorduringPresident’sRule.23. Activities tobedonebyG.A.D. relating to council ofMinisters over and above the
mattersmentionedabove.24. PaymentofSumptuaryBillreceivedfromHon’bleChiefMinister’sOffice.25. ActivitieswithrespecttopersonalmattersofEx‐ChiefMinistersasbeingundertaken
towithrespecttomembersofcouncilofMinisters. 3.5.26. CMOAppointmentSchedulerandTracker
CMOreceivesvariousprogrammes/eventsrequestsondailybasis.Theseprogrammes/eventsmaybebroadlycategorizedinfollowingcategories:1. Meeting2. Inauguration3. CulturalFunction4. PublicRally5. RoadShow,etc.
Suchprogramme/eventrequestsreceivedinformof1. Letter2. Email3. InvitationinPerson4. SMS5. RecommendationfromMinister/respectivedepartments6. PhoneCall
Further,basedontheobjective,thesemayalsobetaggedas1. Political2. AdministrativeThesystemshouldhavefacilitiestocapture/Key‐in1. Demographicdetails of theprogramme/event such as,Date, location, invitee
(institute/organizations/Individuals,numberofattendees,approx.crowd),2. Stage arrangement (Seating Arrangement) for future reference (with
photograph)
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 43 of 101
3. Feedback of the said programme/event with necessary comments/remarks(InitiallybytheCMOofficials.Infuture,maybegiventootherofficials)
4. MoM(Officialsshouldbeabletocapturedigitalnoteduringthemeetingheldby/withHon’bleCMwithhelpofTab/iPad/Android)andotherdocumentsasmaybeapplicablefortherespectiveprogramme/eventforfurtherfollow‐up.
Forclosemonitoring&tracking,CMOdesirestohaveastateoftheartInformationSystemequippedwithvarioustypeofreports,suchas,butnotlimitedto,
1. Requests for appointment Approved / Rejected for a duration bySpecificindividual/group
2. DistrictwiseNumberofprogrammes/eventsingivenduration(e.g.,from01st–31stJan,2018)
a. NumberofAdministrative/Politicalprogrammes/events(withrespectivedocumentslikeMoMforfollow‐up)
3. District wise Type of programmes in given duration (Political /Administrative)
4. FeedbackAnalysis5. AnyotherreportasmayberequiredbyCMOfromtimetotime.6. Thisisjustanindicativelist.Ithastobecustomisedinmobileappas
perCMO’srequirement.
3.5.27. LAQManagement5. CapabilitytocapturetheQuestionsfromAssembly/Parliament/Auditagencies
and allow the personnel to assign selected query to the respective officerssimultaneouslyforresponse.
6. Capability to alert the department officials through email, dashboard alerts,automated SMS messages with reminders on deadlines for query responsebeforetheduetime.
7. Capabilityforgeneratingconsolidatedresponselettercompilingtheresponsesfromeachofficerinpre‐definedformat
8. Capabilitytorecord/update/closethestatusofLAQ.9. CapabilitytoreopenaLAQwhichwasinappropriatelyaddressedandclosed10. ShouldbebasedonWorkflowandDocumentManagementSystem.
3.5.28. MP/MLAReferences1. CapabilitytoInitiatetheMP/MLAreference2. ProcessingofMP/MLAreferences3. ReplyonMP/MLAReference
3.5.29. EntryPassManagement1. RequestingforVisitorpasstoNewSachivalayabymobileapp,SMS,etc,2. Approving/rejectingofrequest.3. Onlineverificationofvisitor
3.5.30. AppointmentScheduler1. Appointmentmanagementofofficials/Ministers2. Managetheschedule/appointments3. PA/PStomaintainthescheduleofseniorofficers4. Helpstoreplacetheexistingphysicalscheduler
3.5.31. AuditParas
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 44 of 101
1. InitiationofAuditParawiththeabilitytoenterdetailsanduploaddocuments.2. DraftingReplyofAuditPara3. WorkflowbasedreviewandapprovalofAuditParareply
3.5.32. Legal/Case Management module would deal with tracking and
managementofcourtcaseswhicharerelatedtothedepartment.KeyfeaturesrequiredintheLegal/CaseManagementsystemare:1. CapabilitytoCreateaCourtCasefilewhichwillincludevariouscasedetailssuchas
Caseno, CaseType,Date of Filing, Casedetails, CourtOrderdetails,Hearing date,Orderdateetc.
2. CapabilitytoaddvariousdocumentsintheCourtCasefilerelatedtothecase.3. CapabilitytoTrackcourtdates,hearingdatesetc.(MIS)4. Capabilitytoprovidealertsfortheupcominghearings.5. CapabilitytoCross‐referencealldatesforonecase,oneclient,oneattorney,agroup,
ortheentireoffice.6. CapabilitytogeneratetheCaseDiaryhavingcompletedetailsandhistoryofthecases.7. Capabilitytoprovideamechanismforanalysisofworkflow,casestatus,andtypesof
casesopenedanadclosed8. Capabilitytomaintainanaudittrailofentriesandchanges.9. Capabilitytocapturenotesheetwiththecourtcasefiles.10. Realtimereportonlab‐wisependingcasedetails11. Onlinerepositoryoflegalcasesforfasterretrieval.12. ShouldbebasedonWorkflowandDocumentManagementSystem.13. Shouldbeinastatetofullyintegratewiththeexistingcourtmanagementsystemof
GoG.
3.5.33. RTIManagementIt is a process pertaining to providing information to people.A lot of times the sameinformationissoughtbydifferentpeople.Insuchcasestheautomatedprocessfollowstheentireinformationsharinglife‐cycleinacostandtimeeffectivemanner.Throughouttheprocess information is collectedandsharedwithin theorganization ina seamlessmannerandmaintainedinaknowledgerepositoryforfuturereference.
3.5.34. AssetManagement,CondemnationandDeadStockManagement1. InawardingtheassetsofDepartment/Office2. Managingtheasset,thedistributions3. Keepingtherecordofpaymenthistory4. GenerationtheBarcoded/QRcodeddeadstockno.sticker5. Linkagewithworkorder/purchaseorderassetno.andregistercondemnationorder,
deadstockregister.3.5.35. AwardManagement:ManagingtheawardreceivedbytheStateGovernment
3.5.36. ProjectandContractManagement1. ItshouldbefullycustomizablefordifferentdepartmentlikeR&B,Watersupply,GIL
DSTandvariousotherDepartments.Belowarefewindicativeexpectations;2. TheSystemtohavevariousstagesofapprovalsforalltheproposedprojects.These
approvals will pertain to project selection, budget approvals, vendor selectionincluding technical and financial evaluation, SLA andmaintenancemilestones andapproval for project closure. It should be linked with IFMS, nprocure and other
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 45 of 101
paymentgateway. Itshouldprovideforonlinesubmissionofinvoiceandpaymentrequestbyvendor.
3. The System should be flexible to define approval stages and criteria for differentprojecttypes
4. Facilitytocreatenewproject/reviewexistingprojectwithcriticalinformation’slikeactivity/tasklistswithtargetdatesandfinancialresourcerequired
5. Ability to track and analyze Project Schedule, Costs, Materials, Equipment andServices
6. Abilitytorecord,manageandreportDataforallProject‐relatedTransactions7. Facility to record periodic Progress Information from Weekly / Monthly Project
Reports(MIS)8. Facilitytoidentifyprojectmilestonesandtargets9. Abilitytodefinesub‐projectswithinaproject10. Abilitytoanalyzeindividualprojectsbycomparingprojectplansagainstprogressand
produceexceptionreports(MIS)11. Provision to select multiple projects based on selection criteria and display
any/specifiedstoreddetails12. Reporting facility through which users can define and develop reports related to
singleormultipleprojects13. WorkBreakdownStructures(WBS)tostructureprojectshierarchicaland/orusing
networktechniques.Milestonesanddocumentstomarkprojecteventsappropriately.14. Costs actually incurred are posted directly to project (and its linkage with
measurementbookandSoRandCost)15. Systemprovides various standard reports for real‐time reporting of financial and
logisticprojectdata16. Abilitytocapture,computeandreportreal‐timeactuals(e.g.costs,effort,schedule
statusimage)17. Abilitytoaggregatecost,effort,andscheduledataacrossprojects18. Abilitytocalculateperformanceratiosmanuallyorautomaticallyatspecifiedpoints
intimeoratprojectmilestones19. Abilitytoprovidedashboardviewofstatusofallprojectswithabilitytodrilldown.20. Ability to compute/display estimates of remaining work (hours to completion,
percentofwokcompleted,end‐dateforecasting,etc.)21. Abilitytoprovidecomparisonofactualvs.plannedprogresswithvarianceanalysis,
alerts,andrule‐basednotification.22. Abilitytoprovideprojectreporting/forecastingaccordingtogovernmentcontracting
requirements(e.g.,earnedvalueanalysis).23. Abilitytouseprojectstatusandprojectforecaststoupdatefinancialbudgetforecasts.24. FacilitytorecordvariousCostDataforaproject(suchasbudgetamount,expenditure
todate,costtocompletion,costestimateofchanges,etc.)25. Facilitytorecordprojectallocations,advancedpaymentandbankdetails26. Facilitytomarkprojectsforarchivingonceallthecostshavebeenpaidandproject
completedFollowingarethedepartmentalfunctionalitieswhichwereusedinexistingIWDMSwhichmay be developed in IWDMS 2.0 as per departments latest& upcomingrequirementwhichneedstobecollectedafterworkorderisgiven.Sr.No DepartmentName ApplicationList1 Development
CommissionerateDDODiary1:No.ofvisitsatVillageandTalukaVillageInspection
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 46 of 101
Sr.No DepartmentName ApplicationListReceiptVerification:RevenueReceiptVerification:PanchayatTaxPendingPensionCasesAppeals
2 DevelopmentCommissionerate
DDODiary2:AuditParas:AccountantGeneralAuditParas:LocalFundParasForDistrictPanchayatAuditParas:PhysicalVerificationAuditParas:DcOfficeInspectionParasGovernmentDues:LandRevenue
3 DevelopmentCommissionerate
DDODiary3:GovernmentDues:EducationCessGovernmentDues:OthersTax&FeesCollection(forGP):LightTaxTax&FeesCollection(forGP):HouseTaxTax&FeesCollection(forGP):SafaiTaxTax&FeesCollection(forGP):OthersTax
4 DevelopmentCommissionerate
DDODiary4:SardarAwasYojana:PlotAllotmentSardarAwasYojana:CurrentYearProgress(2005‐06)SardarAwasYojana:SpilloverWorksof2004‐05SardarAwasYojana:SpilloverWorksof2003‐04SardarAwasYojana:SpilloverWorksof2002‐03
5 DevelopmentCommissionerate
DDODiary5:PanchayatGhar‐cum‐TCSQtrsschemeEncroachment,DetailsofCitizenchartersCasesforemployementtoDependentCadrecasesforinterdistricttransfer
6 DevelopmentCommissionerate
DDODiary6:Detailsofimportantcases/papers(vigilancecommission)Detailsofimportantcases/papers(KhatriSamiti)Detailsofimportantcases/papers(JansamparkRefofCM)Detailsofimportantcases/papers(HonourableMinisterReference)Detailsofimportantcases/papers(MP/MLAReference)InquiryTDO
7 DevelopmentCommissionerate
DDODiary7:DetailsofPreliminaryinquiriesclassIandII(otherthanTDO)DetailsofPreliminaryinquiriesclassIIIandIVCourtCasesGramSabha(forthecurrentfinancialyear)CentralAssistanceaccordingto12thfinancecommissionStatementshowingthedetailsofL.F.AuditRecovery
8 DevelopmentCommissionerate
DDODiary8:NoofVacantPostsofClass‐IandIIofficersinPanchayatSuspensionofPresident/Vice‐PresidentofTalukaPanchayatUnderSection73
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 47 of 101
Sr.No DepartmentName ApplicationListRemovalofPresident/Vice‐President/MemberofTalukaPanchayatUnderSection71RemovalofSarpanchUpsarpanchMemberofVillagePanchayatUnderSection57SuspensionofSarpanchUpsarpanchMemberofVillagePanchayatUnderSection59
9 EducationDepartment
ClassStatisticsDetail
11 EducationDepartment
MonitoringofNirmalGujaratDriveinSecondaryandHigherSecondarySchools
12 EducationDepartment
NOC‐ ReasonOfAvailability
13 EducationDepartment
NOC‐ StandardandSubjectApplication
14 EducationDepartment
NOC‐ Standard WiseWorkLoadDetailsApplication
15 EducationDepartment
NOC‐ StudentandClassDetails
16 EducationDepartment
NOC‐ TeacherDetailsApplication
17 EducationDepartment
NOC‐ TeacherWorkload Details
18 EducationDepartment
NOC‐ WorkloadEntryAApplication
19 EducationDepartment
NOC‐ WorkloadEntryCApplication
21 EducationDepartment
SchoolStatisticsDetail
22 EducationDepartment
StudentStatisticsDetail
23 EducationDepartment
TeacherStatisticsDetails
24 Energy&PetrochemicalsDepartment
ApplicationforAnalysisoftheElectricitySupplyStatusintheState
25 Energy&PetrochemicalsDepartment
ApplicationforMonitoringoftheEnergySupplyStatusintheState
26 Energy&PetrochemicalsDepartment
GeneratingvariousGraphicalReportsforMonitoringoftheElectricitySupplyStatusintheState
27 HomeDepartment ActionsuggestedbyGVConEnquiryReports(Department/Board/Corporationwise)
28 HomeDepartment ActiontakenbyDepartment/Board/CorporationunderIPCandPCActforrecommendationgivenbyGVC
29 HomeDepartment Actiontakenbydepartments/Board/CorporationsonrecommendationsofGVC
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 48 of 101
Sr.No DepartmentName ApplicationList30 HomeDepartment ActiontakenbyGVConComplainsReceived
(Department/Board/Corporationwise)31 HomeDepartment Actiontaken/SuggestedbyGVConReferencecases
received(Department/Board/Corporationwise)32 HomeDepartment CasesReceivedforofficersandgovernmentservants
duringmonthoftheirRetirement(Department/Board/Corporationwise)
33 HomeDepartment ComparativestatementofComplainsreceivedinlastfiveyears
34 HomeDepartment DetailsofAccusedOficer/StaffReccommendedbyGVC
35 HomeDepartment DetailsofActionandFinalOutcomeofcases36 HomeDepartment DetailsofactiontakenonActionrecommendedbyGVC
(Department/Board/Corporationwise)
37 HomeDepartment Detailsofdelayofretirementcases38 HomeDepartment EnquiryofComplains40 HomeDepartment EstablishmentofGPSOfficers‐ PostingInformation41 HomeDepartment EstablishmentofGPSOfficers‐ SuspensionDetails45 HomeDepartment EstablishmentofIPSOfficers‐ CourtCaseDetail46 HomeDepartment EstablishmentofIPSOfficers‐ DeputationDetails48 HomeDepartment EstablishmentofIPSOfficers‐ IPSTransfer52 HomeDepartment EstablishmentofIPSOfficers‐ PersonalInformation53 HomeDepartment EstablishmentofIPSOfficers‐ PostingDetails54 HomeDepartment EstablishmentofIPSOfficers‐ SuspensionDetails55 HomeDepartment EstablishmentofIPSOfficers‐ TrainingDetails56 HomeDepartment PendingPreliminaryEnquiryCases(Department/
Board/Corporationwise)
57 HomeDepartment PunishmentorderedbyDepartment/Board/CorporationwiseagainstrecommendationmadebyGVC
58 HomeDepartment RecommendationbyGVCunderIPCActandPCAct(Department/Board/Corporationwise)
59 HomeDepartment RecommendationbyGVCforCriminalProcedureunderIPCandPCAct(Department/Board/Corporationwise)
60 HomeDepartment RecommendationsbyGVC61 HomeDepartment ReferenceCases62 HomeDepartment ReferencecasespendingwithGVCforfurtherDetails
(Department/Board/Corporationwise)
63 HomeDepartment Reportshowing2ndstageConsultancyDetail(Department/Board/Corporationwise)
64 HomeDepartment TrackingofNHRCCases‐ Complaints65 HomeDepartment TrackingofNHRCCases‐ CustodialDeath66 HomeDepartment VC‐ AccusedDetails67 HomeDepartment VC‐ ApplicantDetails
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 49 of 101
Sr.No DepartmentName ApplicationList68 HomeDepartment VC‐ ComplainApplicationReceivedandActionstaken
duringtheCurrentYear
69 HomeDepartment VC‐ RecommendationdetailsbyVigilanceCommissioner/Secretary/ChiefEngineer/US
70 HomeDepartment VC‐ ReportReceived/Trackingdetails71 HomeDepartment VCComplainerReport72 HomeDepartment VCReport73 HomeDepartment VigilanceCommission‐ Detailsof
Corresponence/Decision74 Narmada,Water
Resources,WaterSupply&KalpasarDepartment
Fortnightlyprogressreportforirrigation
75 Narmada,WaterResources,WaterSupply&KalpasarDepartment
MonitoringprogressofLandAcquistion,RehabilitationandResettlementoftheproject
76 Narmada,WaterResources,WaterSupply&KalpasarDepartment
WorkingrelatedtoAppealsregrdinglandacquistionCourtCases(Hon.Highcourt/supremeCoourt)
77 RevenueDepartment MonitoringofStaterainfall78 Science&Technology
DepartmentGSWANConnection
79 Science&TechnologyDepartment
SICNTelephoneFacility
80 Science&TechnologyDepartment
VideoConferencingRequest
3.6. IntegrationScopeIntegrationwithCommonServicePortal IntegrationoftheCommonServicePortalforCitizenCentricServices CitizencanapplythroughCommonServicePortalandthecorrespondencecanbe
convertedinfileforfurtherapproval CitizencantackthestatusIntegrationwithHRMS. PersonalInformationsystemofHRMS PrivilegeoftheuserwillbebasedonHRMSIntegrationwithSWAGAT IntegrationwithSWAGATtosubmitthegrievancesforCitizen. AssigningtheGrievancestoDepartment/HoDandotheroffices. ProcessingoftheGrievances.
ReplyonGrievances. Linkinggrievancestoapplicablecorrespondingfile,ifany.
IntegrationwitheCourt IntegrationwitheVidhan
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 50 of 101
Integration with any other existing/upcoming/futuristic departmentalportal/applicationsofGovt.ofGujaratduringthetenureofthecontract.
IntegrationwithIFMSandn‐Procurement IntegrationwithSevaSetu&PragatiSetu3.7. Operation&MaintenanceSupporto The SP has to provide the operation & maintenance for the period of 8 years
Resolutionoferrors/bugs(ifany),softwareupdates,patches,changesinthesoftwarethatmaybenecessaryduetolegal/statutory/GR/AnyACTetc.changes.
o Ongoingtechnicalsupportforapplicationo FineTuningupdates/patchesreportingo Fixinglogical/run‐timeerrorsintheapplicationso Development,TestingandImplementationforBug‐Fixeso Generatereportsonchangesmadeinapplicationso Generatereportsonchangegiventosupportteamo Systemadministrationanddatabasemanagementsupporto Developmentofnewapplicationreleaseo Deploymentofnewapplicationonproductionserverso SynchronizetheapplicationreleaseinallapplicationserversofDST,andFarDRo Maintainingchecklistforthestatusofdeploymentonallserverso Monitoring&ReportingServer/SystemperformanceBiddershallsetupcentralizedhelpdeskatDST(Gandhinagar)tologcomplaintsoftheusers and issue the log ticket number and communicate the correctivemeasure. Theservicemanagement/supportrequestmodule/toolshallbeprovidedbytheSP.SPshallprovide Customer support interface with online, telephone and on‐site support, andotherdeliverablesasdescribedbelow.ThespaceforhelpdeskfacilitywouldbeprovidedbyGovt.ofGujarat.Thescopeofservicestobeofferedbybidderisdetailedbelow: Providewarranty/on‐sitemaintenanceproduct,softwarethatshallbesuppliedand
installedunderthisprocurementthroughouttheperiodofcontractasperSLAandalsoprovidewarrantyexecution/onsitemaintenanceoftheDatabaseS/W.
Undertake Performance Tuning and ensuring optimum performance of theequipmentsupplied.
ThesupportcoverageshallbeaspertheservicewindowmentionedintheSection–“ServiceLevel”.
Providemanpowerforoperations,maintenanceandonsitewarrantysupportofalltheexistingandsupplieditems.
Bidder is required to propose the required compute power, storage and otherrequirementtohosttheIWDMS2.0applicationatPrimarySiteandDRSiteSeparately.The payment for DR Site will be applicable only once DR Site will be ready andoperational. The necessary compute infrastructure will be provided by Govt. ofGujarat.
Recently,Govt.ofGujarathasdone theprocess forSelectionofAgency forSupply,Installation, Commissioning and Support of CloudEnabled Infrastructure atGSDC,Gandhinagar on behalf of Department of Science & Technology, Government ofGujarat.TheinfrastructureandenvironmentdetailsisavailableinSection4ofthisRFP.TheIWDMS2.0willbehostedonthiscloudinfrastructure.Forstorage,EMCVMA200Kstoragewillbeprovided.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 51 of 101
Aspartoftechnicalbid,thedetailBoMrequirestobeproposedasbelow:
ForSizingPurposeonly:*Concurrentusers(Transactingusersduringthesamesession):10,000a. Documentviewer:500mssecondb. Filelinkopen:1secondc. Accepting,processingand renderingoutputof amultiplevariableMIS&DSS
system–4variabletask:3secondsd. 100MSlatencyaspartofnetwork.Bandwidth:1Mbps
o Departmentwillprovidethevirtualization/cloudenvironment.Bidderhastoprovideproposedbillofmaterialinthefollowingformatinthetechnicalbid.
BillofMaterialforHardwareSr.No. *Description vCPU RAM HDD
SpaceQuantity Remarks,
ifany
*Description:requiredDBservers,appsevers,reportingserversoranyotherserver(for production, testing development etc), equipment required for running theapplicationatDCandDR1physicalcore=2vCPU
a. BillofMaterialforSoftwareSr.No. *Product
DescriptionUnitof
MeasurementLicensesquantityforDC
LicensesquantityforDR
Remarks,ifany
*Description:RequiredallthereadymadesoftwareincludingOSandDatabase,App,Web,BIetc.forDCandDR
Concurrentusersmean“thoseuserstransactingduringthesamesession.”
InStateDataCentreandDRSitetherequiredcomputeinfrastructureandstoragewillbeprovided. However, bidder has required to quote, supply, install and maintain therequiredOS,Databaseandothers/wlicensesprovidedbybidder.Consideringthe8yearsof growth ifmore compute infrastructureandstoragewillbe required than itwill beprovidedbyDepartment.However,theincremental licensesoftheOSandDatabaseisrequiredtobesuppliedandmaintainedwithrequiredATS/AMCbybidderduring8yearsofO&Mperiodaspartofthisbid.ThebidderhastoenvisageincrementallicensesandAMC/ATScostandthequoteforthesameinfinancialbid.TheDRshallbe25%ofDCintermsofresourcecapacity(sizing).Itshallbeactive‐passiveandpassiveactivesetup.SPshouldproposeasolutionwheretheRecoveryPointObject(RPO)shouldnotbemorethan5minutesandRecoveryTimeObjective(RTO)shouldnotbe more than 120 minutes. The DC and DR Site should work as Active‐passive and
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 52 of 101
passive‐active.Thedatalossshouldnotbemorethan5minutes.TheDRlocationmaybein Delhi or Hyderabad or some other place. The DR environment will also be cloudenvironment.TechnicalDetails: Applicationtype:Threetiermobile&webbasedapplication TechnologyPlatform:‐OpenStandards(Opensource/Commercialproduct) BackendTechnology:‐OpenStandards(Opensource/Commercialproduct) DatabaseTechnology:‐Opensource/Commercialproduct ServerOSSupport:Windows,Linux&Environment PresentationLayer:Thefrontendremainsthefrontfaceofanyapplication;henceit
mustbedesignedconsideringtheutmostpreferencetotheenduserandstakeholdersusingthedifferentfunctionalitiesoftheapplication.Thus,theproposedsolutionisexpectedtomakeuseoflatestframeworks/technologiestodesignthefrontfaceoftheapplication.
BusinessorServicesLayer:WhilethePresentationLayerwilltakecareofthefront‐endfunctionalitiesandUI,thebusinesslogiclayerwillcontainthebusinesslogicandrulesgoverningtheapplication.ItisimportanttonoteherethatakeydesignprincipleforGujaratIWDMS2.0applicationistoensurethatthearchitectureismodular,whichinturnwouldrequirethatallmajorbusinesslogicbeessentiallymaintainedintheBusinessLogicLayer,andnotinanyotherlayers.
Akeyconsiderationwhileimplementingthebusinesslogicwillbethattheseshouldadaptabletofrequentchangesinthebusinessprocessgiventhedynamicnatureofthe regulations governing entities and associated stakeholders’ bodies. Hence, thedevelopment should be done in a way that changes may be implemented in theshortest possible time, and with minimal changes to the application code. TheWorkflows should be enterprise and flexible enough to allow upward flow anddownwardflowofprocessesandinclusionofnewactorswhichcanbedonethroughchangesinconfiguration.Allthesefactors‐dynamismofbusinessrequirements,needformulti‐agentandcomplexworkflows,highfrequencyofbusinessprocessesgettingexecuted, involvement of multiple stakeholders in a business process/ workflow,would require a Business Process Management in the overall architecture of thesolution.
BusinessRule Enginemay be leveraged to create parameterized and configurablebusiness rules, eliminating need to do code level changes for every change.Irrespective, any logic developed for this application should adhere to the designprinciples,andshouldideallybeanaggregationoflooselycoupledservices.
It should support easy workflow configuration, its maintenance, and need basedmodification,additionalterationofthestepsandsupportprocessmodellingbasedonBPMN2notationstandard.
The proposed solution should provide business rule engine and a managementplatform.Usersshallbeabletomodifythebusinessrulesonlinewithoutanyneedofdeployment.
Systemshouldhavecomplexdatamanagementcapabilities. Integration Layer: Integration development must be able to support a business
environmentwhichrequiresfastresponsetimes.So,theIntegrationLayershouldbedevelopedonaprovenIntegrationBus/APIPlatform.
ItshouldSupportisprovidedforbuilt‐inanduser‐definedpatternstechnology. DocumentManagementSystem:InagovernmentapplicationlikeIWDMS2.0,itmust
dealwithlotsofdocuments&contentsacrossvarioussectionoftheoverallIWDMS
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 53 of 101
2.0application.Henceitisnotjusttheholdingthecontentatoneplace,butitisalsohoweffectivelythecompletemanagementofenterprisecontentfromitscaptureanddisposition. Thus, delivering contextual information to business stakeholders forimproved collaboration, smarter decision making and enhanced customersatisfactionisofprimeimportance.
Theapplicationshouldbeabletohostonx86platform.TherequiredcomputepowerandstoragewillbeprovidedinSDCbyDepartment.
Theapplicationshouldbecompatiblewithanyopenstandardtechnology.ThebidderhastoquoteandsupplyanyOSanddatabaseonopenstandardtechnologywith8years of AMC/ATS support. The bidder has to envisage incremental licenses andAMC/ATScostandthequoteforthesameinfinancialbid.
Incaseofbidderisofferingopensourceproducts,thesupportfromaproductvendorshouldberequiredandbidderhastogivecomplianceonthesame.
Bidder should provide a mobile app which must provide all the requisitefunctionalitiesfromwebinterfacefunctionalitieswhicharefeasibletodeliverfrommobileappinallthe3versionsofmobileOS,viz.,Android,iOS&Windows.
ThemobileappshouldbecompatiblewithlatestOSand2earlierversionsofOSandall future versions on each platform i.e. Android, Window and iOs. Example: ifcurrentlyAndroidversion8isrunning.Themobileappshouldbecompatiblewithandroid6,7and8andallfutureversions."
N. nos. of reports which is generated by system should be available onMobile/Tablet/i‐Padalso.Thesystemshouldworkon100%onlinemode.
Theapplicationshouldrunonallmajorbrowsers like InternetExplorer,MicrosoftEdge,GoogleCrome,MozillaFirefox,Safari,Operaandmobilebrowseranditshouldbecompatiblewithlatestand2earlierversionofbrowserandallfutureversions.
Shouldhavefollowingfeatures:o Supportfordistributeddatabasesandstorageo Supportfordatabasereplicationo Supportforwebenabledapplicationso Supportfordatawarehousingo Networksupportforawiderangeofprotocolso Portabilityofdatathroughimport/exportprocedureso Should support all features of partitioning to improve performance and
simplifymanagementofverylargedatabaseenvironmentso ShouldbeabletosupportBackupforhotbackupandrecoveryatenterprise
levelandeliminateanyriskofdataloss. The application developer/software provider should ensure that the proposed
application architecture & offered solution including software or any other toolshouldbelatestandshouldnotbeendofsupport/endofsalesduringthe8yearsofO& M period. Bidder has to provide the latest version of application, latest majorupgrade/alternate productwith all relevant customizationwithout any additionalcosttoGoG.Theundertakinghastogiveforthesamebybidder.
Theproposedsolutionshouldbeonopenstandardandcompatible/inter‐operablewithothertechnologysothat,thereshouldnotbeanyproprietarylockinsituationduringthe8yearsofO&Mperiod.
Aftercompletionof8yearsandatthetimeofhandover‐takeover,SPhastoprovidetheapplicationwithlatesttechnologyversion,updateandupgrades.
Every6months,Bidderhastosubmitthedocumentationincludingsourcecode,codestructureandarchitecture.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 54 of 101
3.8. DevelopmentandO&MTeam
3.8.1. BiddershallproposethedevelopmentTeamforprojectasfollow(thecostofthesamehastomentioninpart1offinancialbid:
Bidder shall proposedevelopment teamwith efficient resource todevelop/customizeIWDMS2.0inprescribedtimeline.Thedeveloperteamresourceswillbebasedonsiteatlocation/premisestobeprovidedbyGovernmentofGujarat.onsite3.8.2. Bidder shallpropose theOperationandMaintenance team forprojectas
follow(costofthesamehastomentioninfinancialbidpart5and6):Aftertherollout,theserviceprovidershallkeepvarioustypesofresourceteamatsiteindicatedinthisRFPortheplaceearmarkedfordevelopmentinpara3.7.1duringtheentiredurationofO&Masfollow:a. ContinuousDevelopmentandO&MTeam1ProjectManager+5Developer
Team).1. One Project Manager (PM) with (ICT Graduate(BE/B.Tech(CE/IT/EC)/MCA/Msc.IT + MBA/PG in management/PMP withminimum10yearsofexperienceanddomainknowledge).PMwillheadofthetechnicalteamandco‐ordinatethedevelopers,centralO&Mteam,supportandhandholdingteamandGovernmentdepartmentsandvariousoffices.2.Fora.Continuousdevelopmentprocessofapplication,ateamof5developerswithminimum5yearsofexperienceindevelopmentofsimilarapplicationorinsame solution (in case of COTS solution), headed by Project Manager withminimum10yearsofexperiencewillbeprovided.
b. To support the technical support for hardware/software, mobile app, webinterface including applying patching, OS updation, antivirus updation, DBManagement, take new requirement, a Central Site O & M Team of SystemAdministrator,System/BusinessAnalyst,DBA,SecurityExpert,MobilityExpert,BIExpertetc.withBE(CE/IT/EC)/B.Tech(CE/IT/EC)/MCA/M.Tech in IThavingminimum4ormoreyearssofexperienceintheirrespectivefield.
c. Hand‐holdingSupportTeam
1. The bidder has to deploy at least 3 resources having at least 2 year ofexperienceofITCallCentreonsiteduringprojectperiodforbetterexecutionandmonitoring of the project. The resources should be well trained about thisproject,clientproblemresolutionandguidance.Thehelpdeskserviceshouldbeavailablefrom9:00a.mto7:00p.mhrsandasandwhenanycritical issuearises,oncall/onsitesupportneedtobeavailableanytime.The call logs details need to bemaintain in an online system. Periodic clienthelpdesk agent calls should be recorded to monitor the quality of grievanceredressal(10Callspermonthperhelpagent.Thisvaluecanchangesolelyatthediscretionofgovernmentwithoutanyclauseorcondition)2. To provide the hand‐holding support, the SP has to depute 35 technicalresourcesinitiallyfor25000users.Aftereveryincreaseof500users,theSPhastodeployadditionaloneresource.Thepaymentofadditionalresourceshallbemadeaspertheman‐monthratefinalizedTheseresourceswillbehelpinghandtothatlocationandthatsubordinateoffices.Theywillresolvetheissuesofusersandalsoprovidethetrainingonanynew/existingfunctionality.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 55 of 101
The manpower for O & M support of the application should be at leastBE/B.Tech/MCA graduate and having 2 years of experience inhandholding/Operation & Maintenance support of IT software/application.Theyshouldbewelltrained.
IntheOperationandMaintenancePeriod,thebidderisexpectedtocarryoutchangethatisrequiredduetochangeinfunctionalitiesorneed,Act,Rule,GRetc.duringthe8yearsofOperationandMaintenanceperiodwiththehelpofabovementionedteam.NoadditionalpaymentwillbemadeduringO&Mperiod.
Theentireteamhastodeployat100%onclientsitebyserviceprovider.Bidderhas to deploy same type of resources inO&M phasewho haveworked indevelopmentphase.Departmentof ScienceandTechnology,Govt. ofGujaratmayincreaseordecrease theno.ofresourcesrequired forhandholdingontimeto timeduring the8yearsofO&Mperiod. Thepaymentwillbemadeasonactualno.ofresourcesdeployedbythebidder.
Incaseofabsenceofthemanpower,bidderhastoprovidethealternatearrangement
tocarryouttheactivities. Incasetheresourcehasresigned,thenthebidderhastoinformatleast2weekprior
tosuchresignation. BeforeassigninganyreplacementmemberoftheKeyPersonneltotheprovisionof
theServices,SPshallprovide:o aresume,curriculumvitaeandanyotherinformationaboutthecandidatethat
isreasonablyrequested;ando anopportunitytointerviewthecandidate.
Thebidderhastoensureatleast4weeksofoverlapperiodinsuchreplacements3.9. DatabaseMigration&ManagementSPshallberesponsibleformanagementofthedatabaseduringthecontractperiod.Whilerollingouttheproject,itisenvisagedthatyettobeclosedfilesofExistingIWDMSwillbemigratedinIWDMS2.0.TheSPwillberesponsibleforcapturingthatdata.CurrentlythesizeofthedatabaseofexistingIWDMSis1.75+TB.TheselectedServiceProviderisrequiredtomigratealltheexistingdataavailablewithDepartmentinthedigitizedformatoftheexistingapplicationifrequired,initscurrentdatabasetothenewsystemtobehostedatStateDataCentrefreeofcost.ThecurrentIWDMS2.0datashouldbeloadinitiallyinDatawarehouse.Thesizeofthedatabaseasmentionedabove.YettobeclosedfilesshallbemigratedinnewsystemandotherdatashallbekeptinArchivalandwillbefetchedasandwhenrequired.Thedatashouldberetainedlifetime.ThedataarchivalpolicyshallbeasperGADofficeprocedureandclassification.Duringthe8yearsofO&MperiodanymigrationactivitiesrequiredtobecarriedoutduetochangeinInfrastructure,Software,etc.shouldbedonebybidderatnoextracost.Thiswillnotbeconsideredasanychangerequest, as thiswillbecontinuousdevelopmentprocess.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 56 of 101
Aspart of datamigration from the existing application, the selected Service Providerwouldperformthefollowingactivities:1) PreparetheDatacleaningandmigrationplanandsubmittoDepartmentforapproval.2) Ensureminimumbusinessdowntimeatthetimeofdatacleaningandmigration.3) OntheDepartment’sapproval,preparetherequisitemigrationarchitectureandthen
cleanandmovethedatatothenewtargetenvironment.4) Ensuretheaccuracyandcompletenessofthemigrateddata.Departmentreservesthe
right to verify the accuracy and completeness of themigrated data on its own orthroughitsnominatedagencies.
5) Ensuremigrationofalldataforpilotlocationiscompletedbythetimeofpartrolloutandfortheentirestateiscompletedbythetimeofstate‐widerollout.
3.10. LanguageoftheProduct
o TheproductmodulestobedevelopedbytheSPmustbesupportGujaratiandEnglishlanguages.
o Theapplicationuserinterfacewillhavetoprogramintwodifferentinterfaceformats–1.EnglishLanguageand2.GujaratiLanguage.
o For the Gujarati typing Unicode standard (shruti font) shall be used. ThenumberofsystemshouldautomaticallygeneratefromEnglishtoGujarati.
3.11. EnvisagedProjectPhases:Stage0:DiscoveryPhase The entire solutions team will be given 1 month long crash course in
understanding Government Administrative Processes that go in officeadministration. Such training will take place at Ahmedabad/Gandhinagar.OnlyinfrastructureforthetrainingwillbegivenbyGoG.Theexpenditureandfacility of accommodation, travelling, food, etc. will be exclusivelyborne/managedbythebidder.
StageI:DesignPhase Documentation of the existing processes of Workflow Automation
Management&deliveryacrossallemployees. DocumentexistingprocessesLevelsofGovernmentProcesses. Propose process Levels, based upon benchmarking / opportunities for
improvementofprocesses. IdentificationofBusinessProcessReengineeringrequirementtoachievethe
proposedservicelevels,includinglegalchangesrequiredinprocesses. Documentation of To‐Be Process maps in line with the BPR proposed of
processes. DesigntheUserRequirementsSpecification. CapacityBuilding/TrainingPlan/PreparationofIWDMSManualsalongwith
BPR. SPshallensurethatIWDMS2.0musthavecompletecapabilitytointegratein
fullasandwhenrequiredwithanyofthemodulesofHRMS,IFMS,n‐procureoranyotherdepartmentalapplications.ThisstatementisequallyvalidforanyoftheassociatedGoGapplications.
PrepareSystemRequirementSpecification(SRS)forapplicationdevelopment DesigntheChangeManagementPlan DesignandseekapprovaloftheimplementationStrategyfromGADandDST
priortothecommencementoftheimplementationplan
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 57 of 101
Design&documentationofHardwaresizingandotherrequirements,networkarchitecture&otherinfrastructuralrequirements,basedonapplicationstobedevelopedandsubmitBillofMaterialtotheDSTwhichwillbeprocuredbyDSTseparately.
StageII:ImplementationPhase TheSelectedbiddershallrecommendallnecessaryITinfrastructurerequired
for this project including hardware, systems software having operatingsystem, database server, application/web server and related networkinginfrastructure and third party applications. Procurement of requisitehardwarecomponentsshallbedonebyDST.
Softwaredevelopment/customization,integration,testing&deployment.o Software components required for successfully running the solution
shouldbe latest& shouldbePerpetual innature.Open source softwareshouldbewithenterprisesupport.
o ApplicationSoftwareasperrequiredspecifications. Projectmonitoring and progress reporting to the GAD and DST onweekly
basis. Bidderhastoprovidethetest&developmentaswellasUATdatabase and
afterdecidingGoLive,theexistingsoftwarewillbeswitchedovertoIWDMS2.0.
Entiresolution’sstate‐widerolloutwillbestartedwithintimelimitmentionedaspercontractandthencompletedinayears’timeframeonceitisstarted.TheSPwillworkwithGADandDSTtodevelopprojectimplementationscheduleimmediately after the awardofworkorder andwill complete the schedulewithinamonth’stime.
DevelopmentofUATproceduresandtestcases.o Commissioning&AcceptanceTestingshall involvethecompletionofthe
supplyandinstallationoftherequiredsoftwareandhostingthecompleteapplication inGujaratStateDataCentre forcarryingout liveOperationsandgettingtheacceptanceofthesamefromGovt.ofGujarat.
o Acceptance testing shall be carried out for all the sites before thecommencementofLiveOperationsinthecentralizedlocation/departmentmutuallydecidedbetweentheGovt.ofGujaratandthebidder.
ProvidedatabasesoftwareoranyothersoftwareneedstoruntheIWDMS2.0Application.
BugfixingandincorporatefeedbackfromUsers. EndUserTrainingandgivingacopyofGADapprovedIWDMS‐2BPRmanual
toeveryuser. Rollout/ImplementationofApplicationofat‐leastonelocationmentionedin
thegeographicalscope. InterfacewithfrontenddeliverycentersforapplicationGo‐Live Application Testing through EQDC and Security audit of the application
throughCERT‐Inempaneledagency.StageIII:PostImplementation–WarrantyandSupport SP will be responsible for providing support, in terms of product support,
duringcontractperiodfromthedateofGo‐Liveoftheapplicationsoftware.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 58 of 101
3.12. Detailsoftheactivities3.12.1. Documentation
The SP shall prepare all necessary documentation for the project, andprovidethemtotheGADandDSTforreview,approval,record,reference,etc.asmentionedinthisRFP.ThefollowingisthelistofdeliverablesintheformofdocumentstobesubmittedbytheSPinthecourseofprojectimplementation.
As‐IsprocessReportforalltheprocessesofservices. BusinessProcessRe‐engineeringreportforthealltheservicesofDST. To‐BeprocessmapbasedontheBPRreport. Business Requirement Documentation (BRD) stating all key business
processesandtheirrelevantintegration. UserRequirementSpecificationdocumentsforalltheselectedprocesses. System Requirement Specification (SRS) document containing detailed
requirementcaptureandanalysisincludingfunctionalrequirement,dataflow,workflow based on the BPR report, interface specifications, applicationsecurityrequirements.
HighLevelSoftwareDesigndocumentincludingSoftwareArchitecturedesign,LogicalandPhysicalDatabaseDesignetc.
SoftwareDesignDocument TestPlansandTestcases(includingUnitTestPlan,System/IntegrationTest
Plan) UserAcceptanceTestPlan,SecurityTestPlan,Load&PerformanceTestPlan. IntegrationPlanwithotherapplications IntegrationTestcases&resultsforapplicationsdeveloped CompleteSourceCodeofCustomization. Inspection and testing procedures manual including QA Policy as per
EQDC/Cert‐In Certified Company Test Plans and Test cases (Stress/Loadtesting, functional testing, Performance testing, Security testing, ,Configurationtesting,,)
DetailsstudyreportfortherequirementofcentralsideITInfrastructurebasedontheapplicationdeveloped.
SecurityLevelDesignDocument&implementationofSecuritypolicy ConfigurationandAccessManagementPolicy IWDMS‐2ManualinEnglish&GujaratilanguagesdullyapprovedbyGAD SystemsAdministrationManuals UsermanualsinEnglish&Gujaratilanguages InstallationManuals BPRPartwithroles,responsibilities.Timelineforimplementation,usageofe‐
Sign,Securitypolicy,Compulsiondate. PeriodicStatusandReviewReports(MIS) EscalationMechanism ExitManagementPlan FAQforconcernedstakeholders ChatbotFacilityforuserstobecreated. Documentationincludingcodestructureandarchitectureoneverysixmonths. Complete phase wise project plan, giving out micro‐level activities with
milestones&deadlines.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 59 of 101
User & Administrative manuals, dully approved by GAD for applicationsoftware: The bidder shall be responsible for providing the same to thedepartmentintwocopies,bothhard&softcopy.
3.12.2. Training
Introducinganychangeneedstoconsidertheimpactthatchangewillhaveonallstakeholders–bothwithinandoutsidethedepartment.Itisthereforenecessary,for the SI, to formulate a change management strategy that encompasses therequirements of the end user and the employees. The SP should ensure thatchange management starts from the project planning stage and continuesthroughout the life of the project. It is essential to understand that changemanagementisnotaonetimeactivity.It isacontinuousactivitypropagatingtocomplete life of the project and touching all the stakeholders involved in theproject
TheChangeManagementPlansuggeststhekeystrategiesneededtoaddresstheaforementionedchangeimplicationshavinghighestimpact.ThedeveloperteamshallhavetoprepareadraftchangemanagementplanwhichitwillpresenttotheprojectteaminGADandDSTforapproval.AfterincorporatingchangesproposedbytheGADandDST,thedeveloperteamshalloperationalizethechangemanagementplan.Thedeveloperteamshallhavetoprepareadraftchangeplanwhichitwillpresentto the project team inGAD andDST for approval. After incorporating changesproposedbytheGADandDST,thedeveloperteamshalloperationalizethechangemanagementplan.Thebasiccontoursoftheplanhave: Trainingtomastertrainers(FivefromeachdepartmentandCommissionerate
andoffice) TrainingofsoftwaresupportprofessionalsfromGILorDST Trainingteamwhoshouldfurtherprovidecompulsorytrainingtoeachuser
for3daysatregional/DistrictSPIPACentre.TheBidderisresponsibletoprovideaminimumof7daysTrainingtoidentifiedsetofgovernmentofficialsandusergroupsontheusageoftheproposedsolution.Successful Bidder has to provide Training tools and material; space will beprovidedbyGovt.ofGujarat.
NatureoftheTrainingandsupportrequired:1 The selected bidder shall have to provide all requisite resources for imparting
trainingtoaselectedgroupofendusersfromeachofthedepartments/agencies.2 TrainingshallbeconductedatSecretariatoranyappropriategovernmentlocation.
However, it would be ‘Train the Trainer’ concept, where representatives fromdifferentdepartments,divisionsandagencieswouldbetrainedwhointurnwouldtrain individual users in the respective divisions and departments/agencies.However,in‘TraintheTrainer’concept,thereshallbeonetechnicalsubjectmatterexpertfromOEMtoresolveanyon‐the‐flyqueriesofthetraininggroup.
3 TheGovt.ofGujaratshallarrangeallrequisitetraininginfrastructurecomputers,laptops, projectors with screen and internet connectivity during the varioustrainingsbeingconductedatvariouslevels.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 60 of 101
4 Govt.ofGujaratshallberesponsibleforprovidingtrainingspace/computerlabsforfacilitatingtheconductingoftrainings.
5 The selected agency shall provide training material, the language of trainingmaterialshallbeinGujaratiandEnglish.
6 ThetrainingmaterialshallbeinformofusermanualsapprovedbyGAD(inEnglish&Gujarati)hardcopy&Softcopyandinteractivevideotutorialswithvoiceovers.
7 Theselectedagencyshallensurethatall thetrainingdocumentationandvideosarealsoavailableinSoftcopy(usertraining,operationprocedures,visualhelp‐kitetc.)peruser.
3.12.3. HelpdeskServicesThesuccessfulbidderwillprovidehelpdeskservicewhichwillserveasasinglepointofcontactforallIWDMS2.0relatedincidentsandservicerequests.TheservicewillprovideaSinglePointofContact(SPOC)andresolutionofincidents.Thescopeofworkincludes:1 ProvideHelpdeskfacilityduringagreedserviceperiodwindowforreportinguser
departmentincidents/issues/problemswiththeproposedApplicationrelatedissues.
2 Provide necessary channels for reporting issues to the help desk. The incidentreportingchannelscouldbethefollowing:
Onlineincidentreportingfromviaweb‐login‐Phonecall SpecificE‐Mailaccount
3 ImplementaServiceCallLoggingSysteminlinewiththeseveritylevelsaspertheSLAs. Helpdesk shall log user and assign a Ticket number. Severity shall beassignedtoeachcallaspertheSLAs.
4 Trackeachincident/calltoresolution5 Analyzetheincident/callstatisticsandprovidemonthlyreportsincludingbutnot
limitedto: Typeofincidents/callslogged Incidents/callsresolved Incidents/callsopen RootCauseAnalysisforfrequentlyoccurringincidents
6 Getuserfeedbackdaily7 Analyzethecallstatistics/qualityofcall.8 Creation of knowledge base on frequently asked questions to assist users in
resolvingbasicissuesthemselves/chatbotfacility9 Escalatethecalls,totheappropriatelevels,ifnecessaryaspertheescalationmatrix
agreedbetweenthebidderandtheGovt.ofGujarat.TheescalationmatrixshallbedevelopedbythebidderindiscussionwithGovt.ofGujarat.
10 ThebiddershallprovideHelpdeskfacilityduringtheworkinghoursforreportingissues / problems with application related issues. The bidder shall provide aservicedeskfacilityandsetupallnecessarychannelsforreportingissuestohelpdesk.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 61 of 101
4. SECTIONIV:SPECIFICATIONS4.1. AcceptanceCriteriaTheprimarygoalofTestingandAcceptancewouldbetoensurethattheprojectmeetsrequirements, standards, specifications and performance prescribed in the RFPdocument,byensuringthatthefollowingareassociatedwithclear,quantifiablemetricsfor:
accountability: Performance Availability Security Manageability StandardsandProtocols Accessibility UserFriendliness
Theprojectwouldbedesignedtomeetall functional,non‐functionalandmanagementrequirementsasmentionedintheRFPdocument.Foreachoftheprojectrequirements,thereareoperationalrequirements,deliverablesandasetofstandards,whereverapplicableasperthefollowing:
Sr.No. Component Standard1. Business Process
Management/WorkflowEngine
WFMC, BPEL & BPMN 2.0 or higherStandards
2. Document ManagementSystem
ODMA,WebDAV,CMIS
3. RecordManagementSystem DoD5105.02,ISO15489,VERS4. InformationAccess/Transfer
ProtocolsSOAP,HTTP/HTTPS
5. Interoperability WebServices,OpenStandards6. PortalDevelopment W3CSpecifications7. Photograph JPEG(minimumresolution640X480
Pixels8. DigitalSignatureande‐Sign RSA Standards and as decided by
govt.timetotimeandAadhaarenableOTPbasedeSign
9. Documentencryption PKCSspecification10. InformationSecurity ISO27001certifiedSystem11. Operational Integrity &
SecurityManagementISO17799certifiedSystem
12. Operation ISO9001Certified13. ServiceManagement ISO20000specificationsorlatest14. ProjectDocumentation IEEE/ISO Specifications for
documentation15. DataStandards All‐important dataentitiesshouldbe
in line with standards published byDIT. These can be accessed athttp://egovstandards.gov.in.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 62 of 101
16. LocalizationStandards Localization standards, like Fontstandardsarenotified, andavailableat the DIT website. All Applicationsshould complywith these standardstoensurecommonlookandfeel.
17. Application OpenStandard4.2. PerformanceCriteriaPerformancewould be that aspect of service, which would bemeasured in terms ofthroughputand latency.Higher throughputand lower latencyvalueswouldrepresentgood performance of a service. Throughput would represent the number of servicerequestsservedperunittime.Latencywouldbetheround‐triptimebetweensendingarequestandreceivingtheresponse.4.3. AvailabilityCriteriaHighAvailabilitywouldbeakeyrequirement.Theapplicationsmustprovidedepartmentofficials with timely, continuous access to information 24X7. The log files of theapplicationsmustalsobeable toreboundor recover fromanyplannedorunplannedsystemdowntime,ensuringaminimal impactontheoperations.Availabilitywouldbethe quality aspect of whether the service is present or ready for immediate use.Availabilityrepresentstheprobabilitythataserviceisavailable.Largervaluesrepresentthat the service would always be ready to use while smaller values indicateunpredictability of whether the service will be available at a particular time. Alsoassociatedwithavailabilityistime‐to‐repair(TTR).TTRwouldrepresentthetimeittakestorepairaservicethathasfailed.
4.4. SecurityCriteriaSecurity would be the aspect of the service of providing confidentiality and non‐repudiationbyauthenticatingthepartiesinvolved,encryptingmessages,andprovidingaccesscontrol.Theapplicationscanhavedifferentapproachesand levelsofprovidingsecurity,dependingontheservicerequester.Securityrequirementssuchassinglesignon,encryptionofpasswords,logsanddigitalsignatureande‐signetc.isamust.DepartmentofScienceandTechnology’sapplicationsecuritywillbeofutmostpriority.Theformsshouldbeprotectedfromimproperdatainput,bothintheuser'sbrowserandattheremoteserver.Databasesshouldbesecuredviausername/passwordprotectionand potentially sensitive information should be secured using industry‐standardencryptionalgorithms.4.5. ManageabilityManageabilityneedstobeacrucialaspectofDepartmentofScienceandTechnology’sapplication.TheImplementationPartner‐SPhastoensurethatthesolutiondeployedhas adequate monitoring and tracking features for measuring the utilization andavailabilityofresources.Thisincludes:
RemoteMonitoringofStatusandStatisticsofallhigh‐levelcomponents Managementcapabilitytostart/stop/restartservicesandsystems Autodiscoveryofallcomponentsmanageable Autodiscoveryofallothersystemcomponents Abilitytotrackchangesinconfigurationofthesystemcomponentstohelptrack
service Systemdisruptions
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 63 of 101
4.6. Standards&ProtocolsTheprojectshouldbecompletedasper theopenstandardsandprotocolsapplied fordevelopment,hostingandmaintenanceofanautomatedsystem.The softwaredevelopedunder thisContract shall conform to theopenstandardsandwhen no applicable standard is mentioned; to the authoritative open standardappropriatetothecountryoforigin.4.7. DevelopmentCriteria
ThedeliverablecomponentsofthisRFPinclude: Aweb‐based systembywhichGovernmentofficial performday‐to‐day routine
activitieswithregardstoFile/LetterManagement. Customization/Development of comprehensive IWDMS2.0 application through
DevelopmentofCOTS/WebBasedapplicationwhichaccomplishesallthetasksasmentionedinthescopeofworkincludingtheDSSandMISreports
Thedesign,looks,andfeelsoftheUserInterfaceasapprovedbytheGADandDST. Arelationaldatabase(s)tobeusedforapplicationmanagement,sitemaintenance,
calendaringandactivities,andrelateddocuments. Asystemtocontroluseraccessprivileges.Grantedprivilegesarebasedonroles
and responsibilities including site administration and content management,calendar,activities,anddocumentmaintenance.
Monthlyorondemandreports/queriesshowingstatistics. Monthly/Quarterlyreportonproductup‐timehostedattheDataCentre
4.8. Customization/DevelopmentofApplication
The Customization/Development of Application must be done as per globalindustry standard environment. The bidder must justify the choice ofdevelopmentenvironment.Thesoftwaremustbedevelopedandhostedutilizingindustry standard. The bidder must list all tools to be used to develop andmaintainthesoftware,aswellasthehostingplatformhardwareandsoftware.
4.9. DevelopmentControlThebiddermustuseallreasonablecaretoprotect the integrityof theproductduringdevelopment. Use of a version and library control tool is desired. The bidder mustdescribethedevelopmentenvironmenttobeused.4.10. ProjectManagement&ProjectPlanThebiddermustprovideanexperiencedProjectManagertooverseethedevelopmentoftheIWDMS2.0softwareapplicationsandshouldserveasprimarypointofcontactfortheDepartmentofScienceandTechnology.ThebiddermustfollowanestablishedProjectManagementmethodologyconformingtothebestpracticesoftheProjectManagement.Thebiddermustdescribethemethodologytobeused.During the Technical Presentation, the biddermust provide the GAD andDSTwith adetailedProjectPlanforthedevelopmentoftheDSTapplication.ThisProjectPlanmustinclude at minimum the Project Charter, a work breakdown structure showing allproposedmilestonesanddeliverables,andalistingofallprojectissuesandrisks.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 64 of 101
4.11. StatusReportsThebiddermustprovideweeklystatusreportstotheDSTduringthedevelopmenteffort.ThesereportsmustbesubmittedbycloseofbusinessoneachMondayandmustreflectstatus against the Project Plan as of close of business on the previous Friday. AnyfalsificationofthesestatusreportsorfailuretoinformtheDSTofissuesimpactingthedeliverablesortimeframeoftheprojectmayresultincancellationofthecontract.4.12. VersionControl&BugFixingThebiddermustmakeanymodificationsnecessaryforthedurationofthecontracttoensurethatthesystemiscompatiblewithcurrentandsupportedversionsandreleasesoftherelevantoperatingsystemandothersystemsoftware.4.13. HostingCriteriaThebiddermustworkwiththeGADandDSTtoprovideadetailedimplementationplan,includingbutnotlimitedto,orderlyprocessof inventory,versioncontrol,andloadallapplicationmaterials,assignmentofuserrightsandsecurity,andverificationofcorrectfunctionality.ThebiddermustpresentanimplementationplantotheGADandDSTfortheirapprovalbythebeginningofthetestperiod.ItisproposedthattheproductwouldbehostedinStateDataCentre,asperprovisionsprovidedbyDepartmentofScience&Technology,Gujarat;however the finaldecisionregardingtheprimarysiteforhostingwouldrestentirelywiththeDST.TheproductshouldalsobehostedinDRSite,asperprovisionsprovidedbyDepartmentofScience&Technology,Gujarat;howeverthefinaldecisionregardingtheDRSiteforhostingwouldrestentirelywiththeDST.ThebiddershallberesponsibletosetuptheHelpDesk.ThehelpdeskwillbesetupatGandhinagarasDSTmaydecide.Helpdeskwillbeforinternaluser.TheexternaluserswillcallatGoGcallcentreandifanytechnicalqueryitwillbetransfertoHelpDeskofIWDMS2.0.4.14. AvailabilityTheproductmustbeavailableaspertheServicelevelsdefined.Thebiddermuststatehowthatavailabilityistobeprovided,includingallmeasures.Thebiddermustshowtheability to report availability to DST on a quarterly basis, and must indicate howavailabilityistobeverified.4.15. AccessibilityTheDSTapplicationsmustmeettheopenstandardsforsoftwareapplication.Thebiddermusttesttheapplicationswithacommerciallyavailableaccessibilitymonitor,andwithaleadingaccessibilitytool,ifnecessary.4.16. SecurityThebiddermusttakerigorousprovisionstopreventunauthorizedalterationordamagetothesoftwareandallrelatedmodulesanddatabases.Thebiddermustdescribeindetailallmeasurestobetaken,includingtheuseoffirewalls,monitoringforintrusiondetection,etc.Thebiddermustalsospecifythedependencies,ifany,inachievingthedesiredlevelofsecurity.(NOTE:Thisinformationwillbekeptconfidential.)
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 65 of 101
4.17. Backup&RecoveryThebiddermustprovideandsuccessfullytestbackupandrecoverycapabilitiesfortheapplicationsandrelateddatabases.Thebiddermustdescribethisfunctionality,andthefrequencyofbackup.4.18. Uptime&PerformanceThebiddermustprovidesufficientprovisionstoensurethatproduct’sallfunctionality,including data access, file downloads, and online transactions is performed withincommerciallyacceptableresponsetimes.Thebiddermuststatethecapacitythatwillbeavailablefortheapplications,andwhattoolsandtechniqueswillbeusedtocontinuouslymonitorapplicationperformance.4.19. AccessControlandUserAuthentication:The bidder must prepare the access control & User Authentication policy and get itapproved by DST. The bidder shall be responsible to provide access control & UserAuthenticationmanagementduringtheperiodofcontract.4.20. The tools/software licenses availablewith Gujarat State Data Centre on
sharedbasisandComputepoweravailableunderG‐CloudatDataCentreshallbegiventothebidderaftersigningNDAwithDST/GIL.Below reports list is submitted by Cloud ImplementationTeam,DCOwillprovidethefollowingreportsforVMofCloud1) Summary of changes undertaken in the respective Cloud infrastructure
includingmajor changes like configuration changes,patchupdates, etc. andminor changes like log truncation, volume expansion, user creation, userpasswordreset,etc.
2) VirtualizationLayerpatchupdate statusof respective servers including theVirtualMachinesrunningonit
3) ComponentwiseserveraswellasVirtualmachinesavailabilityandresourceutilization
4) ConsolidatedrespectiveSLAreport.5) Summaryofcomponentwiseuptime.6) Logofpreventive/scheduledmaintenanceundertaken7) DetailsofPatch,updatesimplementationstatusofsame8) Detailsofbreak‐fixmaintenanceundertaken9) Consolidatedcomponent‐wiseavailabilityandresourceutilization
Followingfacilitiesshallbeprovidedbyselectedbidder:
Attimeofinstallationofapplication‐ApplicationSecurityAuditisrequiredfromCERT‐INEmpaneledVendor.Afterinstallation,GSDCwillaudit2timesinayearasapartofGSDCpolicy.
PatchManagementwillbedonebySelectedBidderwiththehelpofcurrentDCO SelectedBidderisresponsibletocomplianceallVA/PT/ISO/anyotherauditdone
byGSDC. SelectedBidderhastoadheretoallGSDC&ISOpolicy. RegularpatchmanagementofcomponentsoftheIWDMS2.0,reportingsecurity
incidents and resolutionof the same, proactivelymonitor,manage,maintain&administerallsecurityfeatures.
Update the system as applicable,managing andmonitoring of anti‐virus, anti‐malware,phishingandmalwareformanagedresources.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 66 of 101
Maintainingsecuredomainpolicies,Resolutionofcallsforsecuritynotifications,systemalerts,vulnerabilitiesinsoftwareandalertingIWDMS2.0asappropriate,providingrootcauseanalysisforalldefinedproblemsincludinghackingattempts,maintainingdocumentationofsecuritycomponentdetailsincludingarchitecturediagram,policiesandconfigurations(forapplicationands/wrelated).
Performing periodic review of security configurations for inconsistencies andredundanciesagainstsecuritypolicy,Reviewinglogsdailyofsignificancesuchasabnormal traffic, unauthorized penetration attempts, any sign of potentialvulnerability. Security alerts and responses. Proactivemeasures in the event aproblemisdetected(forapplicationands/wrelated).
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 67 of 101
5. SECTIONV:TimelineandPAYMENTTERMS5.1. ProposedtimelinesforImplementationandpaymentterms
Activity CompletionTimelines(inMonths)
PaymentTerms
Date of Signing ContractSigning T
‐‐‐
Project Initiation & TeamMobilization T1=T+1 20%costofCAPEXamount
quotedinFinancialBidSubmission of SRS, URS andSDD T2=T+3
ApprovalofUI T3=T+6 10% cost of CAPEX amountquotedinFinancialBid
ProcurementofCOTSandOS,Database Licenses and otherreadymade softwarerequired to run theapplication andDevelopment/Customizationof IWDMS2.0, installationoffunctionalitiesandUAT,DataMigration, Training, SecurityAudit andEQDCTesting andGo‐live and Roll out inSecretariatandHoDs
T4=T+12
30%costofCAPEXamountquoted in Financial Bid onDevelopment/CustomizationofIWDMS2.0,installationoffunctionalitiesandUAT,DataMigration,Training,SecurityAuditandEQDCTestingandGo‐live includingdevelopment of tablet andmobileinterface
After3monthsofGo‐liveandbugfixing T5=T+15 30% of of CAPEX amount
quotedinFinancialBidonRolloutinDistrictOfficesandintegrationwithalreadyexistsystem like revenuedepartmentefileregistryetc.
As per mutuallydecidedtimeline
‐‐‐
Implementation inBoard/Corporation/ OtherGovt.Offices
Asandwhenrequiredandmutuallydecidedtimeline
‐‐‐
30% payment will bereleasedondeliveryofpaperlicenses/onlinecertificate.
20%oncustomizationasperrequirement
20% payment will bereleasedonUAT.
30% on completion of 3months of go‐live and bugfixing.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 68 of 101
Activity CompletionTimelines(inMonths)
PaymentTerms
Operations and Maintenanceof IWDMS 2.0 & DataMigration support forcontract period includingTechnical support, ProductUpgrades, Updates, patches,security updates, bug fixesetc. and ContinuousDevelopment/Change in O&M Phase (with technical andfunctional document)without additional cost,helpdesksupport
T7= T4 + 8 Year(Mutually AgreedTimelines betweenrelevant Department,DST and bidder forContinuousDevelopment/ChangeinO&MPhase(withtechnical andfunctional document)without additionalcost)
Quarterly in equalinstallments aftercompletion of each quarterandsubmissionofInvoiceasmentionedinFinancialbid.
ATS&AMCofCOTSfor8YearsandCostofAMC/ATSofOS, Database Licenses andother readymade softwarerequired to run theapplication.
At the beginning ofeachyear
Payment of ATS/AMC will bereleased yearly in advance.(100% payment after thesubmission of confirmationregarding the renewal ofsupport/subscription.)The payment of ATS/AMC willbe payable after Go live of theproject.
Note: T ‐ Date of Award of Contract. 5.2. PaymentProcedure5.2.1. TheDST/GIL shall certify actual implementation. The SP has to ensure proper
hand‐holding&supportofthesystem.5.2.2. SP shall raise the component wise invoice as per the milestones achieved as
mentionedaboveinthepaymentschedule&submittheinvoicetoDST.5.2.3. DSTshallverifytheInvoiceraisedagainstthemilestoneachieved&shallmakethe
payment.5.2.4. TheSI’srequest(s) forpaymentshallbemadetoDSTalongwith the2original
copies of invoice and necessary documents. The invoice should be in EnglishlanguageandGujaratbased.
5.2.5. Payment shall be made in Indian Rupees. While making payment, necessaryincometaxandservicetaxdeductionswillbemade.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 69 of 101
6. SECTIONVI:SERVICELEVELAGREEMENT&PENALTYCLAUSE
Thepurposeof thisServiceLevelAgreement (hereinafterreferredtoasSLA) is toclearlydefinethelevelsofservicewhichshallbeprovidedbytheSPtoDSTforthedurationofthecontractforprovidingIWDMS2.0Applications,Training,MaintenanceandWarrantysupportagainstthestatedscopeofwork.DSTshallregularlyreviewtheperformanceoftheservicesbeingprovidedbytheSPandtheeffectivenessofthisSLA.DepartmentofScienceandTechnology/GILorTPAappointedbyDSTwillcheckthe application availability, severity level and SLA and calculate the penaltyaccordingly.
6.1. Definitions
For purposes of this Service Level Agreement, the definitions and terms asspecifiedinthecontractalongwiththefollowingtermsshallhavethemeaningsassetforthbelow: “Incident” refers to any event / abnormalities in the functioning of DST
specified services thatmay lead to disruption in normal operations of DSTservices.
“Response Time” shall mean the time taken after the incident has beenreported at the concerned reporting center in resolving (diagnosing,troubleshooting and fixing) or escalating to (the second level, getting theconfirmatorydetailsaboutthesameandconveyingthesametotheenduser),theservicesrelatedtroublesduringthefirstlevelescalation.
Theresolutiontime:theresolutiontimeisthetimetakenforresolutionoftheproblemand this includesprovisioningof thework around to immediatelyrecoverthesituation.Theresolutiontimeshallvarybasedontheseverityoftheincidentreported.
6.2. CategoriesofSLAs
This SLA document provides for minimum level of services required as percontractual obligations based on performance indicators and measurementsthereof.TheSPshallensureprovisioningofallrequiredserviceswhilemonitoringtheperformanceofthesametoeffectivelycomplywiththeperformancelevels.TheservicesprovidedbytheSPshallbereviewedbyDSTagainstthisSLA.TheSPshall: Discuss escalated problems, new issues and matters still outstanding for
resolution. Reviewof statistics related to rectificationofoutstanding faultsandagreed
changes. Obtainsuggestionsforchangestoimprovetheservicelevels.The following measurements and targets shall be used to track and reportperformance on a regular basis. The targets shown in the following table areapplicableforthedurationofthecontract.
6.2.1. Implementationrelatedpenaltyofservicelevels6.2.1.1. ImplementationrelatedpenaltyforApplicationsoftware
TheseSLAsshallbestrictly imposedandasoftwareaudit/certificationshallbecarried out at the sole discretion of DST for certifying the performance of theapplicationsagainstthetargetperformancemetricsasoutlinedinthetablebelow:
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 70 of 101
Milestone Target Severity Penalty
Submission of BRD,SRS,URSandSDD
AsperdeliverySchedule
Critical
A Penalty of 0.5% ofcontract value ofrespective milestoneof SoftwareApplication per weekdelay subject tomaximum 5% ofmilestone cost asdefined in paymentterms.Thecostfortheworkwhichisyetnotcompleted won’t bepaid. Penalty isadditional.
Completion ofDevelopment
AsperdeliverySchedule
Critical
UAT
AsperdeliverySchedule
Critical
Training and Go‐Live
AsperdeliverySchedule
Critical
Note:Ifthebidderisnotadheringtotheindividualmilestonesasdefinedinthedeliveryschedule,thecumulativepenaltywillbeleviedforthedelayedweeks,atthesolediscretionofDST.Ifdelayexceedsmaximumdelayweeksattheparticularmilestone, DST may have rights to terminate the contract. In that case thePerformanceBankGuaranteeofthebidderwillbeforfeited.The SLA applicable after the implementation shall be purelymeasured on theavailabilityoftheservices.
6.2.2. OperationalRelatedPenalty
6.2.2.1. ForSoftwareUptimeSl.No
Measurement Target Penalty
1 Application (IWDMS 2.0)AvailabilityDowntime required formaintenance, new initiativesundertaken by TSP or forPerformance enhancementmeasures shall not be consideredwhile calculating productavailability.Allmajormaintenanceshall be carried out in a plannedmanner after announcing it acrosstheplatform.
>=99.7%
INR50,000forevery10hoursofdowntimeatastretchorinpartsonaquarterlybasis.And INR 25,000 for everysubsequenthourofdowntimeatastretchorinpartsfortotaldowntimemorethan10hoursonaquarterlybasis.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 71 of 101
6.2.2.2. OperationandMaintenance
* Response Time: A time in which the support team will contact the users via telephone/email and understand the problem & visit will be made to the user’s desk, if required. * Resolution Time: A time in which the support team will contact the users via telephone/email and understand & resolved the problem. Severity1:Serviceisunavailableorafatalerrorthatmakesthesystemunusableresultinginadirectbusinessimpact.Theproblemhasresultedinthefailureofbusinesscriticalactivities.Immediateactionrequired.Example:IWDMSApplicationSoftwarerelatedproblemsaffectingallormostoftheuserse.g.allusersareunabletolog‐in/createanyfileorinwardanyTappal(Correspondence)Severity 2: Service is adversely affected or an error that results in incorrect outputsleading to amajor function being unusable resulting in indirect business impact butwhoseimpactislocalizedandnotsystem–wide.Immediateactionisneeded.Example:Individualuserunabletousesomeofthefeatures/applicationsofIWDMSe.g.unabletocreateafileforaparticularsubject,unabletouseleaveapplication,etc.Severity3:Serviceisadverselyaffectedresultinginlimitedbusinessimpactoranerrorthatmakesaminorfunctionunusable.Example:Individualuserunabletousesomeoftheadvancedfeatures/applicationsofIWDMSe.g.unabletopullafileorcorrespondence,incorrectdatainthereports,etc.Severity4:Serviceisnotaffected,ChangesandEnhancementtoberesolvedatafuturedate.
SLAMeasure
Severity1
PenaltyRs.
Severity2
FlatPenaltyRs.
Severity3
FlatPenaltyRs.
Severity4
FlatPenaltyRs.
*ResponseTime*
30Min 60Min 2Hours 4Hours
*ResolutionTime
<1Hrs>1&<2HrsAbove2to3Hrsorpartthereof
Nil15,00030,000
<4Hrs>4&<8HrsAbove8Hrs
Nil1000020000
<3Days>3&<6DaysAbove6Days
Nil500010000
<1Days>1&<5DaysAbove5Days
Nil10005000
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 72 of 101
Example:Minorsuggestions,Labelchanges,etc.Severityindicatetheprioritytoresolvetheissue.Severity1meanshighestpriorityandseverity4meansleastpriority.ProcesstomeasuretheSLAandPenalty:Step1: All problems/issues faced by IWDMS 2.0 users need to be communicated toIWDMSSupporthelpdesk/OfficialLetter/E‐Mail.Step2:Uponreceiptofacomplaint,toreproducetheproblemTeamwouldfirstcontacttheuserviatelephone/emailandunderstandtheproblem.Ifrequired,visitwillbemadetotheUser’sDesk.Step3:Uponconfirmationoftheproblem,teamresolvedtheProblemandInformtheUser.IfProblemisnotundersupportteamthansupportteamcontacttodeveloperteamanddeveloperteamwouldresolvetheproblemaspertheSLAmatrixprovidedabove.Step4:Uponresolutionoftheproblem,ifProblemResolvedbydeveloperteamtheywillinformthesupportteamandsupportteamwillinformtheconcerneduser.PenaltyCalculations
Penaltycalculationsshallbecalculatedonaccumulatednon‐complianceforalloftheaboveSLAs.
TotalTimeshallbemeasuredon24*7basis. Anyplanneddowntimeformaintenanceshallbewithpriorwrittenpermission
fromDSTandmustbeintimatedtoallusers.
Anyavailability/uptimerequirementsunderSLAshallbesubjecttostandarddowntime,thetimelostduetoanyofthefollowingreasonsaretakenintoaccountwhilecalculatingtheavailability/uptimerequirement: Timelostduetopowerorenvironmentalfailures; Timetakentorecoverthesystembecauseofpowerorenvironmentalfailures; Time taken for scheduled maintenance/ troubleshooting either for preventive
purposesorimprovementinfunctionorotherpurposes; Timetakenforreconfigurationorotherplanneddowntimesituations; ScheduledshutdownsasrequiredbyDepartment
TheOverallpenaltycapduringthecontractperiodshallbecappedat5%ofquarterlyinvoicevalue.Howeverifsuchvalueof5%isreachedforanyTwoQuartersduringthecontractperiod,thentheDepartmentofScienceandTechnologywillhavetherighttoterminatethecontract.6.2.2.3. Development/ChangeduringO&MPeriod
SLAMeasure Target FlatPenaltyRs.
ResponseTime 1Day ‐
ResolutionTime
UponMutuallyagreedtime NIL
>1Day<7Days 1000Perday>7days 2000perday
6.2.2.4. OperationalRelatedPenaltyforDevelopment/ChangeduringO&MPeriod
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 73 of 101
Once the change isdevelopedand implemented, itwill become thepartof theSoftwareapplicationandtheoperationrelatedpenaltyoftheapplicationsoftwarewillbeapplicableonthat,ifany.
6.2.2.5. OperationalRelatedPenaltyforHandholdingSupportSLAMeasure Target FlatPenaltyRs.
AbsenceofManpowerandnot made alternatearrangement
>1Day 500perday
Not recruited/deployedmanpower
>7daysto<15days 2000perday>15days 3000perday
6.2.2.6. UserInterface(*ResponseTimewillbemeasurefromSDCtoSDCClientPC.)
NetworkBandwidth:1MbpsEvent Maximum
AcceptableResponseTime
Penalty
1.Documentviewer 500 milliseconds
DepartmentofScienceandTechnology/GIL or TPAappointed by DST mayrandomly check theresponse time of theapplication for about 10days/month. If in morethan 10% cases responsetime is measured morethan response timementioned thanpenaltyof1% of quarterly paymentmade to bidder will bededucted and subsequentevery 5% cases of suchincrease, penalty willincrease by 0.5%.Maximumpenalty capwillbeasdefineinRFP.
2.Filelink 300 millisecond
3. Accepting, processing and renderingoutputofamultiplevariableMIS&DSSsystem–4variabletask
3seconds
BidderhastosubmitthequarterlyreportofSystemUptime,SupportrequestreceivedandresolveredwithrequireddetailsandreportonUserInterfacequarterlyatthetimeofinvoicing.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 74 of 101
7. SECTIONVII:ROLES&RESPONSIBILITIESOFSTAKEHOLDERSItissuggestedthatthisprojectwouldrequirea2tierstructuretobefollowed,withGADandDSTatthetoptierbeingassistedbyvariouscommittees.TheSPwouldbethe2ndtier providing a complete support system for successful execution of this project.HoweverthefinaldecisioninthisregardrestswiththeDSTonlevelofengagementsforSI.7.1. DepartmentofScienceandTechnology(DST)andGAD
Receiveandappraiseproposals/suggestionsfromtheSPandGILforprojectimplementation
ToformProjectManagementGroup(PMG)formonitoringtheimplementationprogramacrosstheState.
Ensure that the SP conducts a detailed BPR exercisewhile developing andimplementingtheautomatedsystem.
AssistinOrganizationalcapacitybuilding. Monitoring implementation, consolidation and approvals of AS‐IS, BPR,
Products,Casestudiesetc. Identifythedepartments/districts/officesandapprovetheprojectreportfor
takinguptheforprojectimplementation. Definetheservices/modulesforPilotprojectimplementationasprescribedin
theselectioncriteria ToenterintonecessaryMoUs/agreementswithSPfordefiningservicelevels
foridentifiedservices,ensuringserviceleveladherence,implementationandsustainabilityofthepilotprojectandsubsequentstatewiderollout.
Workasdriverforpolicy,regulatoryandotherrelevantchanges. ProvidingFinancialSupportaspertheprojectrequirements. AssistinprovidingInfrastructureandothersupporttotheSI Toorganizefordataentryofservicerecordsofalltheemployees
7.2. SI/Bidder:
Provide close tie‐ups with all the stakeholders in the Project at all levels,includingfieldlevel.
Providecommitmentandsupporttobring‐intheprocesschanges. Work closely with the different department officials, field agents, support
agencies etc. to undertake the field work, comprehend the requirements,document the observations and redesign the processes by doing BPR ofgovernmentadministrativeprocesses.
Help build capacity for the staff and executive resources at all levels, byproviding necessary training and undertaking awareness campaigns.DepartmentofScienceandTechnologyandGILwouldalsoworkcloselywiththe Service Provider for developing the software and implementing thetechnicalsolutions.
To provide services, IT resources, and capacity building for creation ofecosystemforhighadaptabilityofbackendcomputerizationande‐Governanceinitiativesasperdepartmentsvision.
Coordinateand facilitate interactionsbetweenthevariousstakeholders likeDepartment of Science and Technology, all government Officials, other
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 75 of 101
instrument bidders and GIL, through its project coordinators and mobileteams.
PreparationofProjectFramework,includingaspectslikescalability,security,manageabilityandintegrationfeatures.
SubmitsuggestionsonBusinessProcessReengineering(BPR). Carryingout the fieldstudy inordertounderstandtherequirementsof the
citizens, existing delivery mechanism, levels of interfaces with theGovernments,theimpedimentsanddifficultiesinaccessingtheservicesandinformation.
Designinganefficientandeffectiveendtoendservicedeliveryprocess. Understandingthecapacitybuildingrequirementsandhelpcreateafacilityfor
developmentofcapacity.
ForadditionalDetailson theRolesandResponsibilityof theSPplease refer toScopeofworksectionIII.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 76 of 101
8. SECTIONVIII:GENERALTERMS&CONDITIONS8.1. Application
ThesegeneralconditionsshallapplytotheextentthatprovisionsinotherpartsoftheContractdonotsupersedethem.ForinterpretationofanyclauseintheRFPorContractAgreement,theinterpretationoftheDSTshallbefinalandbindingontheSI.
8.2. Relationshipbetweenparties
Nothing mentioned herein shall be constructed as relationship of master andservantorofprincipalandagentasbetweenthe‘DST’and‘theSI.TheSPsubjecttothiscontractforselectionhascompletechargeofpersonnelandsub‐SI,ifany,performingtheservicesundertheProjectexecutedbyDSTfromtimetotime.TheSPshallbefullyresponsiblefortheservicesperformedbythemorontheirbehalfhereunder.TheDSTwillallocatework/assignmenttotheSI.
8.3. SubcontractsSPisnotpermittedtoout‐sourceorsharecontractualobligationwithanyotherpartyoftheworkassignedtotheSP.However,incaseofanyexplicitrequirement,DepartmentofScienceandTechnologymaypermitSPtoout‐sourceservicesorpart of services for execution of their contractual obligation. The payment,however,shallbemadetotheSP,whichhasavalidcontractwiththeconcernedDepartmentofScienceandTechnology.
8.4. StandardsofPerformanceTheSPshallgivetheservicesandcarryouttheirobligationsundertheContractwithduediligence,efficiencyandeconomyinaccordancewithgenerallyacceptedprofessional standardsandpractices.TheSP shall alwaysact in respectof anymatterrelatingtothiscontractasfaithfuladvisortoDST.TheSPshallabidebyalltheprovisions/Acts/RulesetcofInformationTechnologyprevalentinthecountryasonthedateoftherequirementsanddesignsubmissions.TheSPshallconformtothestandardslaiddowninRFPintotality.
8.5. DeliveryandDocuments
AsperthetimescheduleagreedbetweenpartiesforspecificprojectsgiventotheSPfromtimetotime,theSPshallsubmitallthedeliverablesonduedateasperthe delivery schedule. No party shall, without the other party’s prior writtenconsent, disclose contract, drawings, specifications, plan, pattern, samples orother documents to anyperson other than an entity employedby the affectedpartyfortheperformanceofthecontract.Incaseoftheterminationofthecontact,all the documents prepared by the SP under this contract shall become theexclusivepropertyofDST.TheSPmayretainacopyofsuchdocuments,butshallnotuseanywhere,withouttakingpermission,inwriting,fromDST.DSTreservesrighttograntordenyanysuchrequest.
8.6. SPPersonnel
TheSPshallemployandprovidesuchqualifiedandexperiencedpersonnelasmayberequiredtoperformtheservicesunderthespecifiedprojectasassignedbyDST.Thisisaspecializeddomainof‘eGovernance’anditisdesirablefromtheSPtodeploy the personnel, who have adequate knowledge and experience in the
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 77 of 101
domainrelatedwiththisproject.ItisdesirablethattheSPshallhiretheservicesofdomainSpecialists,ifrequired,toworkontheProjecteffectively.
8.7. ApplicableLaw
ApplicableLawmeansthelawsandanyotherinstrumentshavingtheforceoflawinIndiaastheymaybeissuedandinforcefromtimetotime.ThecontractsshallbeinterpretedinaccordancewiththelawsoftheUnionofIndiaandthatoftheStateofGujarat
8.8. UseofContractDocumentsandInformation8.8.1. TheSPshallnot,withoutDST’spriorwrittenconsent,disclosetheContract,orany
provision thereof, or any specification, plan, drawing, pattern, sample orinformation furnished by or on behalf of the in connection therewith, to anypersonotherthanapersonemployedbytheSPinperformanceoftheContract.Disclosure toanysuchemployedpersonshallbemade in confidenceandshallextendtoonlyasfarasmaybenecessaryforpurposesofsuchperformance.
8.8.2. TheSPshallnot,withoutDST’spriorwrittenconsent,makeuseofanydocumentorinformationexceptforpurposesofperformingtheContract.
8.8.3. Anydocument,otherthantheContractitself,shallremainthepropertyofDSTandshall be returned (in all copies) toDST on completion of the SI’s performanceundertheContractifsorequiredbytheDST.
8.9. GoverningLanguage
TheContractshallbewritteninEnglishLanguage.EnglishversionoftheContractshall govern its interpretation. All correspondence and other documentspertaining to the contract, which are exchanged between the parties, shall bewritten in the English Language. Allsubmissions/documentations/manuals/codesshallbeinEnglishonlyexcepttheusermanual.
8.10. IntellectualPropertyRights8.10.1. For a bespoke development, the Department shall retain exclusive intellectual
property rights to the software (including source code of customizations/enhancements/amendmentsdone).Theserviceproviderisadvisednottobringanysoftwareasbaselayerforfuturedevelopmentasasolution.FinalsolutionIPRwill be sole andexclusiveproperty of department, expectBI tools,OSandDB.ServiceProviderwillhavenoclaimtoanybaselayeroranyothercomponent.
8.10.2. InbespokedevelopmentaswellasCOTSproducttheDepartmentofScienceandTechnology shall have full rights of sharing source code with Gujarat StateGovernmentDepartments/Boards/Corporations./PSUsorotherGujarat’sStateGovernmentEntity.
8.10.3. IncaseofbiddernotofferingtheCOTS(ERPSolution),thanthebidderhasalsototransfersourcecodesodevelopedfortheIWDMS2.0projecttoGovernmentofGujarat from GO Live onwards The source code, fully documented for itsarchitecture will be exclusive property of the Government of Gujarat and thebidderwillhavenoright touse itanywhereelsewithoutpriorapprovalof theGovernment of Gujarat through the Department of Science and Technology.ConsideringtherightsofgovernmentofGujaratoverthesourcecode,thebidderisspecificallydirectednottouseanyproprietarylayereitherofitsownownership
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 78 of 101
or of ownership of otherswith the source code to deliver the solution for theIWDMSproject.
8.10.4. For COTS Product the full IPR of the customized/developed solution for thisprojectshallrestwiththeDSTexcepttheCOTS,BI,OSandDB.IncrementalIPRwillbecreatedduringtheDevelopmentprocesswhichwillbesincepaidforbyGovt.ofGujarat;hencesuchIPRwillrestinGovernmentofGujarat.
8.10.5. IncaseofCOTSProductthestateGovernmenthasrighttoretaincustomizationlayer and should the agreementwith service provider and to further develop.Therefore,GovernmentofGujaratwillholdIPRofthecustomizedCOTSsolution.The same would be applicable to copyrights. The TSP shall sign any/all thedocumentsinthisregardandwillgetnecessaryundertakingtothiseffectfromtheCOTSOEM.TheGujaratGovernmentfurtherintendsusecustomizedCOTSbacktotheCOTSOEMtoenableittouseinGovernmentorganizationsinotherStatesorin organizations in Government of India. At the time of awarding contract,authorized representative of COTS OEM will have to sign a separate contractagreement to suchanextentwithGovt. ofGujarat.TheTSPhas toget suchanundertakingfromtheOEMatthetimeoffilingthisbidandhandoverthesourcecode, Meta data details etc. to the Department of Science and Technology atdifferent stages of customization and before release of final payment oncompletionoftrainingandrolloutofsoftware.
8.10.6. TheDepartmentofScienceandTechnologyshallhavetheunrestrictedright todeployoruseIWDMS2.0softwareandthedocumentationrelatedthereto,inanyGujaratstategovernmentdepartment,atnocosttoclient.
8.10.7. The SP shall indemnify DST against all third‐party claims of infringement ofcopyright,patent, trademarkor industrialdesignrightsarising fromuseof theGoodsoranypartthereofinIndia.
8.10.8. Whilepassingontherights(license)ofusinganysoftware/softwaretool,theSPshall ensure that such rights are inclusive of the use of that software fordevelopmentinadditiontodeployment.
8.10.9. ThesoftwarelicensessuppliedbySPshallbegenuine,perpetualandfulluse.Itshould provide patches, fixes, security updates directly from the OEM at noadditionalcosttoDSTfortheentireperiodofcontract.AllthelicensesandsupportshouldbeinthenameofDepartmentofScienceandTechnologyfromthedateofprocurement.
8.10.10. Intheeventofanyclaimassertedbyathirdpartyofinfringementofcopyright,patent,trademarkorindustrialdesignrightsarisingfromtheuseoftheGoodsoranypartthereofinIndia,theSPshallactexpeditiouslytoextinguishsuchclaim.IftheSPfailstocomplyandDSTisrequiredtopaycompensationtoathirdpartyresulting from such infringement, the SP shall be responsible for thecompensationincludingallexpenses,courtcostsandlawyerfees.DSTwillgivenotice to theSPofsuchclaim, if it ismade,withoutdelaywhereuponSPshallreimburse.
8.11. Inspection/Testing8.11.1. Application:
a) DST,GADortheirrepresentativeshallhavetherighttoinspectand/ortotestthesoftwareorworkoftheSPtoconfirmtheirconformitytotheContractspecificationsatnoextracosttotheDST.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 79 of 101
b) AsperGovt.OfGujaratcirculardated10thMarch2006,theDSTapplicationsmustbe testedatEQDC,GIDC,Gandhinagarorat the locationspecifiedbyDSTatthecostofSI.TheSPmustincludetestingcostintheirfinancialbid.Thedifferent typesof tests thathas tobeperformedthroughEQDC/othercompetentagencyareasmentionedbelow:Stress/LoadtestingPerformancetestingSecuritytesting
8.11.2. ApplicationSecurityAudit:
In addition to inspection & testing, the SP shall also be responsible to getapplicationsecurityauditedbyCERT‐InEmpanelledapplicationsecurityAuditorsatthecostoftheSPandsubmittheSecurityAuditClearanceCertificateissuedbyCERT‐InEmpanelledSecurityAuditors.a) TheSPmustsubmitthetestresultstoDST.b) Shouldanyinspectedortestedsoftwarefailtoconformtothespecifications,
theDSTmayrejectthesoftwareandtheSPshalleitherreplace/redevelopthe rejected software ormake alterations necessary tomeet specificationrequirementsfreeofcosttoDST.
c) DST’s right to inspect, test and, where necessary, reject the software /deliverableafterthesoftwaredeploymentatProjectSiteshallinnowaybelimitedorwaivedbyreasonofthesoftwarepreviouslybeeninspected,testedandpassedbyDSTforitsrepresentativepriortothesoftwaredeployment.
d) NoclauseintheRFPdocumentreleasestheSPfromanywarrantyorotherobligationsunderthisContract.
e) Theinspectionoftheworkingofthedevelopedsoftwareshallbecarriedoutto check whether the software is in conformity with the requirementsdescribed in the contract.The testswill beperformedafter completionofinstallationandcommissioningofallthesoftwareatthesiteofinstallation.Duringthetestrunofsoftware,nomalfunction,partialorcompletefailureofanymoduleofsoftwareorbugsinthesoftwareisexpectedtooccur.Allthesoftware should be complete and no missing modules/sections will beallowed.TheSPshallmaintainnecessarylogsinrespectoftheresultofthetesttoestablishtotheentiresatisfactionofDST,thesuccessfulcompletionofthetestspecified.Anaverageuptimeefficiencyof99.7%forthedurationoftestperiodshallbeconsideredassatisfactory.OnsuccessfulcompletionofacceptabilitytestandafterDSTissatisfiedwiththeworkingofthesoftwareonthe, theacceptancecertificateofDSTwillbe issued.Thedateonwhichsuch certificate is signed shall be deemed to be the date of successfulcommissioningofthesoftware.
f) BeforetheApplicationmodulesaretakenoverbyDST,theSPshallsupplyIWDMS‐2manualsdullyapprovedbyGAD.Theseshallbeinsuchdetailsaswill enable DST to use the software as stated in the specifications. ThedocumentationshallbeintheEnglish/Hindi/Gujaratilanguageandinsuchformandnumbersasstatedinthecontractdocument.Unlessandotherwiseagreed,thesoftwareshallnotbeconsideredtobecompleteforthepurposeoftakingoveruntilsuchdocumentationissuppliedtoDST.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 80 of 101
8.12. ChangeRequestOrders8.12.1. During thedevelopment andO&Mphase, any change in scopeofwork, or in
designanddevelopmentofDecisionSupport systems (DSS)orofManagementInformation system (MIS) shall not be construed as changeRequestorder andinsteadwillbecomepartofscopeofworkaccompanyingthisbiddocument.
8.12.2. DSTmay,atanytime,bywrittenordergiventotheSPmakechangeswithinthegeneralscopeoftheContractinanyoneormoreofthefollowing:a) Designs, specifications, requirements of which software or service to be
providedundertheContractaretobespecificallydeveloped/renderedforDST;
b) Theplaceofdelivery;and/ortheServicestobeprovidedbytheSI.c) ThebiddershouldberesponsibleforchangesintheIWDMS2.0systemuser
Interface and due to change of legal/statutory/GR/Any ACT etc. changesissuedbygovt.timetotimeduringthecontractperiod.
8.12.3. Oncethechangerequestisdevelopedandimplemented,itwillbecomethepartoftheSoftwareapplicationwithoutanyadditionalcosttoGoG
8.12.4. TrainingofpersonneloftheDSTintermsofhours/subjectswillbewithoutanyadditionalcost.
8.12.5. Any change during the operation and maintenance period should not beconsidered as a change request. However, the bidder has to deploy TeammentionedinthisRFPforanychangesintheapplication.
8.13. SuspensionDSTmay,bywrittennoticetoSI,suspendallpaymentstotheSPhereunderiftheSPfailstoperformanyof itsobligationsunder this contract including the carryingoutof theservices,providedthatsuchnoticeofsuspension.8.13.1. Shallspecifythenatureoffailure.8.13.2. ShallrequesttheSPforremedyofsuchfailurewithinaperiodnotexceedingthirty
(30)daysafterreceiptbytheSPofsuchnoticeoffailure.
8.14. TerminationUndertheContract,DSTmay,bywrittennoticeterminatetheSPinthefollowingways:8.14.1. TerminationbyDefaultforfailingtoperformobligationsundertheContractofif
thequalityisnotuptothespecificationorintheeventofnon‐adherencetotimeschedule.
8.14.2. TerminationforConvenience:DSTbywrittennoticesenttotheSI,mayterminatetheContract, inwholeorinpart,atanytimeforitsconvenience. ThenoticeofterminationshallspecifythattheterminationisforDST’sconvenience,theextenttowhichperformanceof theSPunder theContract is terminated,andthedateuponwhichsuchterminationbecomeseffective.
8.14.3. Thesoftwarethat iscompleteandreadyforrendering/deploymentwithin30daysaftertheSI’sreceiptofnoticeofterminationshallbeacceptedbyDSTattheContracttermsandprices.Fortheremainingservices,DST/GILmayelect:a) To have any portion completed and delivered at the Contract terms and
prices;and/orb) Tocancel theremainderandpay to theSPanagreedamount forpartially
completedsoftwareandforsoftwarepreviouslyprocuredbytheSI.8.14.4. TerminationforInsolvency:DST/GILmayatanytimeterminatetheContractby
givingwrittennoticetotheSI,iftheSPbecomesbankruptorotherwiseinsolvent.Inthisevent,terminationwillbewithoutcompensationtotheSI,providedthat
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 81 of 101
suchterminationwillnotprejudiceoraffectanyrightofactionorremedywhichhasaccruedorwillaccruethereaftertoDST/GIL.
8.14.5. InallthethreecasesterminationshallbeexecutedbygivingwrittennoticetotheSI.Uponterminationofthecontract,paymentshallbemadetotheSPfor:a) Servicessatisfactorilyperformedandreimbursableexpenditurespriortothe
effectivedateofterminationb) Anyexpenditureactuallyandreasonablyincurredpriortotheeffectivedate
oftermination8.14.6. No consequential damages shall be payable to the SP in the event of such
termination.8.14.7. Department of Science and Technology will pay the Service Provider for the
Services /Deliverables / Goodsprovided by service provider and acceptedbyDepartmentofScienceandTechnologytilleffectivedateoftermination.
8.15. TerminationforDefault8.15.1. ThePurchasermay,withoutprejudicetoanyotherremedyforbreachofcontract,
bywrittennoticeofdefaultsenttotheBidder,terminatetheContractinwholeorpart:
8.15.2. ifthebidderfailstodeliveranyoralloftheproductasperthedeliveryscheduleincluding installation, Final acceptance test& commissioningmentioned in thebid,orwithinanyextensionthereofgrantedbythePurchaseror
8.15.3. iftheBidderfailstoperformanyotherobligation(s)undertheContract/Purchaseorder.
8.15.4. If the Bidder, in the judgment of the Purchaser has engaged in corrupt orfraudulentpracticesincompetingfororinexecutingtheContract.
8.16. Fraud&Corruption
DST requires that SP selected through this RFP must observe the higheststandards of ethics during the performance and execution of such contract. Inpursuanceofthispolicy,DST:
8.16.1. Defines,forthepurposesofthisprovision,thetermssetforthasfollows:a) “Corrupt practice” means the offering, giving, receiving or soliciting of
anything of value to influence the action of DST or any personnel ofDepartmentincontractexecutions.
b) "Fraudulentpractice"meansamis‐presentationoffacts,inordertoinfluenceaprocurementprocessor the executionof a contract, toDST, and includescollusive practice among bidders (prior to or after Proposal submission)designed to establishProposalprices at artificially highornon‐competitivelevelsandtodepriveDSTofthebenefitsoffreeandopencompetition.
c) “Unfair trade practices” means supply of services different from what isorderedon,orchange intheScopeofWorkwhichwasgivenby theDSTinSection3.
d) “Coercive Practices” means harming or threatening to harm, directly orindirectly, persons or their property to influence their participation in theexecutionofcontract.
8.16.2. Willrejectaproposalforaward,ifitdeterminesthatthebidderrecommendedforaward by DST to having been engaged in corrupt, fraudulent or, unfair tradepracticesandcoercivepractices.
8.16.3. WilldeclareaSPineligible,eitherindefinitelyorforastatedperiodoftime,forawarding the contract, if it at any time determines that the SPhas engaged in
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 82 of 101
corrupt,fraudulentandunfairtradepracticeincompetingfor,orinexecutingthecontract.
8.17. ForceMajeure8.17.1. Notwithstanding anything contained in the RFP, the SP shall not be liable for
liquidateddamagesorterminationfordefault,ifandtotheextentthat,it’sdelayinperformanceorotherfailurestoperformitsobligationsundertheagreementistheresultofaneventofForceMajeure.
8.17.2. Forpurposesofthisclause“ForceMajeure”meansaneventbeyondthecontroloftheSPandnotinvolvingtheSI’sfaultornegligenceandwhichwasnotforeseeable.Sucheventsmayincludewarsorrevolutions,fires,floods,epidemics,quarantinerestrictions and freight embargos. The decision of the DST regarding ForceMajeureshallbefinalandbindingontheSI.
8.17.3. If a ForceMajeure situation arises, the SP shall promptly notify to the DST inwriting,ofsuchconditionsandthecausethereof.UnlessotherwisedirectedbytheDST in writing, the SP shall continue to perform its obligations under theagreementasfarasreasonablypractical,andshallseekallreasonablealternativemeansforperformancenotpreventedbytheForceMajeureevent.
8.18. PaymentsincaseofForceMajeure
During theperiod of their inability of services as a result of an event of ForceMajeure, theSPshallbeentitledtocontinuetobepaidunder thetermsof thiscontracteffectivefromresumptionofservicespostForceMajeure,aswellastobereimbursed for costs additional costs reasonably and necessarily incurred bythem during such period purposes for the purpose of the services and inreactivatingtheserviceaftertheendofsuchperiod.
8.19. TerminationforInsolvency8.19.1. TheDepartmentmayatanytimeterminatethecontractbygivingwrittennotice
tothebidder(s),ifthebidder(s)becomesbankruptorotherwiseinsolvent.Inthisevent,terminationwillbewithoutcompensationtothebidder(s),providedthatsuchterminationwillnotprejudiceoraffectanyrightofactionorremedywhichhasaccruedorwillaccruethereaftertotheDepartment.
8.20. ResolutionofDisputes
Ifanydisputearisesbetweenparties,thentherewouldbetwowaysforresolutionofthedisputeundertheContract.
8.20.1. AmicableSettlementPerformance of the contract is governed by the terms the conditions of thecontract,howeverattimesdisputemayariseaboutanyinterpretationofanytermor condition of contract including the Schedule of Requirement, the clauses ofpayments etc. In such a situation disputes arising between parties are out ofcontract,eitherpartyofthecontractmaysendawrittennoticeofdisputetotheotherparty.Thepartyreceivingthenoticeofdisputewillconsiderthenoticeandrespondtoitinwritingwithin30daysafterreceipt.Ifthatpartyfailstorespondwithin30days,orthedisputecannotbeamicablysettledwithin60daysfollowingthe response of that party, then clause8.18 shall become applicable. Amicablesettlement clause shall be only applicable in case of dispute is arising out ofcontract.Thesaidclauseshallnotbeapplicableinthecaseofcyber‐crimesand
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 83 of 101
any other type of security breach relating to PHI carried out by either bidderorganizationitselforitsemployees.
8.20.2. ResolutionofDisputesInthecasedisputearisingbetweenthepartiesinthecontract,whichhasnotbeensettledamicably,anypartycanrefer thedispute forArbitrationunder(Indian)ArbitrationandConciliationAct,1996.SuchdisputesshallbereferredtoArbitralTribunal as prescribed by Ministry of Law, Government of India. The IndianArbitration and Conciliation Act, 1996 and any statutory modification orreenactmentthereof,shallapplytothesearbitrationproceedings.ArbitrationproceedingswillbeheldinIndiaatGandhinagarandthelanguageofthe arbitration proceeding and that of all documents and communicationsbetweenthepartiesshallbeinEnglish.Thedecisionofthemajorityofarbitratorsshallbefinalandbindinguponboththeparties.Allarbitrationawardsshallbeinwritingandshallstatethereasonsfortheaward.Theexpensesofthearbitrationasdeterminedbythearbitratorsshallbesharedequallybetweenthetwoparties.However,theexpensesincurredbyeachpartyinconnectionwiththepreparation,presentation shall beborneby theparty itself. Arbitration clause shall be onlyapplicableincaseofdisputeisarisingoutofcontract.Thesaidclauseshallnotbeapplicable in the case of cyber‐crimes and any other type ofconfidentiality/security breach relating to PHI carried out by either bidderorganization itself or its employees. Both the parties agree the jurisdiction ofAdjudicating Authority, Gujarat state and Cyber Appellate Tribunal, NewDelhiunderInformationTechnologyAct,2000(includinganyamendmentstherein)incaseofanycontraventions,securityandconfidentialitybreaches.
8.21. Arbitration8.21.1. ArbitrationproceedingswillbeheldinIndiaatGandhinagarandthelanguageof
the arbitration proceeding and that of all documents and communicationsbetweenthepartiesshallbeinEnglish.
8.21.2. Thedecisionofthemajorityofarbitratorsshallbefinalandbindinguponboththeparties.
8.21.3. Allarbitrationawardsshallbeinwritingandshallstatethereasonsfortheaward.8.21.4. Theexpensesofthearbitrationasdeterminedbythearbitratorsshallbeshared
equallybetweenthetwoparties.However,theexpensesincurredbyeachpartyinconnectionwiththepreparation,presentationshallbebornebythepartyitself.
8.22. ContractPeriodThecontractperiodwillbeGo‐Liveduration+8yearsO&MaftertheGo‐LiveofApplication.However theDepartmentwill take the reviewon all the activitiescarriedout,performancereportssubmittedbybidderafterthecompletionof3Years and 5 years. The SP agrees that in any case SP shall not terminate thecontract.However,thedepartmentreservesarighttoterminatethecontractbysending a notice to the bidder in the events of non‐performance, securityviolationsandnon‐compliance.
8.23. ExitManagementProcedure8.23.1. ThisSchedulesetsouttheprovisions,whichwillapplyonexpiryortermination
oftheContractPeriodand/orearlierterminationoftheSPand/ortheSLAforanyreasonswhatsoever.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 84 of 101
8.23.2. In the case of termination of the Project implementation and/or SLA due toillegality,thepartiesshallagreeatthattimewhether,andifsoduringwhatperiod,theprovisionsofthisScheduleshallapply.
8.23.3. ThepartiesshallensurethattheirrespectiveassociatedentitiescarryouttheirrespectiveobligationssetoutinthisExitManagementSchedule.
8.23.4. TheExitManagementPeriodstarts,incaseofexpiryofContract,6monthsbeforetheContractcomestoanendorincaseofearlierterminationofContract,onthedate of service of termination orders to the Service Provider. The ExitManagement Period ends on the date agreed upon by the Department or sixmonthsafterthebeginningoftheExitManagementPeriod,whicheverisearlier.
8.23.5. DuringtheExitManagementPeriod,theServiceProvidershalluseitsbesteffortsto deliver the Services. Payments during the ExitManagement Period shall bemadeinaccordancewiththeTermsofPaymentSchedule.
8.23.6. TheselectedServiceProviderwillberequiredtoprovidenecessaryhandholdingand transition support to the Department’s staff or its nominated agency orreplacementServiceProvider.Thehandholdingsupportwill includebutnotbelimitedto,conductingdetailedwalkthroughanddemonstrationsforhandingoverall relevant documentation, addressing the queries/clarifications of the newagencywith respect to theworking /performance levels of the infrastructure,conductingtrainingsessionsetc.
8.23.7. The Service Provider shall permit the Department and/or any replacementService Provider to have reasonable access to its employees and facilities asreasonablyrequiredbytheDepartmenttounderstandthemethodsofdeliveryofthe Services employed by the Service Provider and to assist appropriateknowledgetransfer.
8.24. AgreementAmendmentsNovariationinormodificationofthetermsoftheagreementshallbemadeexceptbywrittenamendmentsignedbyboththeparties.However,Departmentshall,asthe situationwarrants, in consultation and agreementwith bidder shall makemajoradditionstothescopeandagreeforsuitablepayments.
8.25. LimitationofLiabilityThe entire liability of the bidder shall be limited toMaximum (Limitationofliability)=Paymentmadetothebidderandexplicitlyexcludealldirect,indirectand consequential losses impact, etc. to the Department except as may bedeterminedbycourtsoflawundertheapplicablelawandawardedafterfollowingthedueprocessoflaw.
8.26. Severability:Ifanyterm,clauseorprovisionoftheagreementshallbejudgedtobeinvalidforanyreasonwhatsoeversuchinvalidityshallnotaffectthevalidityoroperationofanyotherterm,clauseorprovisionoftheagreementandsuchinvalidtermclauseorprovisionshallbedeemedtohavebeendeletedfromtheagreementandiftheinvalidportion is such that theremaindercannotbesustainedwithout it,bothpartiesshallenterintodiscussionstofindasuitablereplacementtotheclausethatshallbelegallyvalid.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 85 of 101
8.27. MaintenanceserviceincludingWarrantySupport:FreemaintenanceservicesincludingWarrantysupportshallbeprovidedbytheBidderduringthecontractperiodof8yearswithoutalteringtheterms.
8.28. TaxesandDuties
Priceshallbeinclusiveofallfreight,forwarding,transitinsuranceandinstallationcharges.PricesshallbeinclusiveofExciseDuties,ifany.Thepricesshallstrictlybe submitted in the given format.Quotedprices shall bewithoutGST. The taxcomponents as applicable shall be mentioned separately in the respectivecolumns.SuccessfulBidderwillhavetosupply/provideserviceswithanInvoicefromaplacelocatedwithinStateofGujarat.OfferedpriceshouldbeexclusiveofallapplicabletaxessuchasGST.ThebillingshouldbedoneinGujaratonly.
8.29. LegalJurisdiction
All legaldisputesbetween thepartiesshallbesubject to the jurisdictionof thecourtssituatedinGandhinagar/AhmedabadofGujaratonly.
8.30. Notice
Anynotice,requestorconsentrequiredorpermittedtobegivenormadepursuanttothiscontractshallbeinwriting.Anysuchnoticerequestorconsentshallbedeemedtohavebeengivenormadewhendeliveredinpersontoanauthorizedrepresentativeofthepartytowhomthecommunicationisaddressed,orwhensent to such party at the address mentioned in the project specific ContractAgreement.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 86 of 101
9. SECTIONIX:FormsofQualificationandTechnicalBid9.1. FORMI:BidProposalFormReference:Date:TenderNo.:GIL/ToSir/MadamHavingexaminedtheBiddingDocumentsincludingAddendaNos.________________(insertnumbers,ifany),thereceiptofwhichisherebydulyacknowledged,we,theundersigned,offer to render “Design, Customization/Development, Implementation, Training,HandHoldingandOperation&MaintenanceSupport for8years for IntegratedWorkflow andDocumentManagement System forDepartment of Science andTechnology(DST)inconformitywiththesaidbiddingdocumentsforthesameasperthetechnicalandfinancialbidandsuchothersumsasmaybeascertainedinaccordancewiththeFinancialBidsubmittedonlineandmadepartofthisbid.We undertake, if our bid is accepted, to render the services in accordance with thedeliveryschedulewhichwillbespecifiedinthecontractdocumentthatwewillsigniftheworkordergiventous.Ifourbidisaccepted,wewillobtaintheguaranteeofabankinasumequivalenttofixedamountbasedontheestimationofthetotalprojectcostforthedueperformanceoftheContract,intheformprescribedbyDepartmentofScienceandTechnology.Weagreetoabidebythisbidforaperiodof180(Onehundredandeightyonly)daysafterthedatefixedforbidopeningasmentionedundertheInstructiontoBiddersanditshallremainbindinguponusandmaybeacceptedatanytimebeforetheexpirationofthatperiod.Until a formal contract ispreparedandexecuted, thisbid, togetherwithyourwrittenacceptance thereof and your notification of award shall constitute a bindingContractbetweenus.Commissionsorgratuities,ifany,paidortobepaidbyustoagentsrelatingtothisBid,andtocontractexecutionifweareawardedthecontract,arelistedbelow:Amount:_____________________Rupees:___________________________________Name:__________________________________________________________________Address:_______________________________________________________________________________________________________________________________________PurposeofCommissionorgratuity:_______________________________________________________________________________________________________________(ifnone,state“none”)Weunderstandthatyouarenotboundtoacceptthelowestoranybidyoumayreceive.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 87 of 101
Datedthis_______________dayof________________20____Signature (inthecapacityof)DulyauthorizedtosignBidforandonbehalfof_______________________9.2. FORMII:ParticularsoftheBidder’sOrganizationS.No. Particulars DetailsBasicinformationofOrganization1. Name offirm2. Addressofthecorporate headquarterswith
Name,Address,telephoneno.,contactperson,mobileno.,emailID
3. Dateofincorporation4. PAN/TAN/ServiceTaxDetails5. Listofcurrentdirectors6. Otherkeymanagement persons7. Keycontactperson/s for this projectalong
withdesignationandcontactdetails(Mobileno.,emailIDetc)
Note: Above details are mandatory, Bidder may use additional sheets for abovesubmissions.(AuthorizedSignatory)Name:________________________Designation&Authority:__________Place:_________________________Date:__________________________Stamp:________________________CompanyName:________________BusinessAddress:_______________Note:‐Kindlyattachnecessarysupportingdocuments9.3. Form:III–FormatforFinancialCapability
FinancialInformation
FY1 FY2 FY3
TotalTurnover(inINRCrores)
Turnover from IT relatedservices(inINRCrores)
Turnover from SoftwareConsultancy, developmentand implementation (in INRCrores)Profitaftertax (inINRCrores)
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 88 of 101
FinancialInformation
FY1 FY2 FY3
Networth (inINRCrores)
Otherrelevant information
Note:Pleaseattachrelevantsectionsofthedocumentaryproofs 9.4. FormIV–FormatforRelevantExperienceAssignmentname: Approx. value of the contract:
Country:LocationwithinCountry:
Duration of assignment(months):
NameofClient: Total No of staff‐monthsoftheassignment:
Address: Approx.valueof theservicesprovidedunder thecontract(inCurrentINR):
StartDate(Month/Year):CompletionDate(Month/Year):
Number of Man‐MonthsofProfessionalStaffProvidedbyAssociatedConsultants:
ProjectCompletionCertificates: Licensing/UserBase/GeographicalSpread:
AcceptancefromConcernedOfficers: Name of senior professionalstaffofyourfirmProjectManager:
NarrativeDescriptionofProject:
DescriptionofActualServicesProvidedbySI/Vendor:
Note:Pleaseattachrelevantdocumentaryproofs
9.5. FORMV:ProjectTeamTheentireteamoftheprojectproposedbybiddershouldbe100%onsite.Using the formatbelow,pleaseprovide the summary informationon theprofiles youproposetoincludeforevaluationandtherolestheyareexpectedtoplayintheproject:
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 89 of 101
Sl.No. ProposedRole
NumberofResources
AreaofExpertise
KeyResponsibilities
CVforProfessionalStaffProposedPleaseprovidedetailedprofessionalprofiles of the staff proposed for evaluation.Theprofileforasinglestaffmembermustnotexceedtwopages.
Sr.No. Description Details1 Name2 Designation3 Roleproposedfor4 Current responsibilities in the responding
firm5 Totalyearsofrelevantexperience6 Yearsofexperiencewiththerespondingfirm7 Educationalqualifications:
DegreeAcademicinstitutiongraduatedfromYearofgraduationSpecialization(ifany)
8 Professionalcertifications(ifany)9 Professional Experience details (project‐
wise):ProjectnameClientKeyprojectfeaturesinbriefLocationoftheprojectDesignationRoleResponsibilitiesandactivitiesDurationoftheproject
9.6. FORMVI:SelfDeclarationThe‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐,‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐Sir/Madam,HavingexaminedtheBiddingDocumentsincludingBidNo.:‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐thereceipt of which is hereby duly acknowledged, we, the undersigned, offer to provideservicesfor‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 90 of 101
We undertake, if our bid is accepted, to provide_____________________________________________________, in accordance with the terms andconditionsinthetenderdocument.Ifourbidisacceptedwewillobtaintheguaranteeofabankforasumequivalentto10%oftheContractvalue,intheformprescribedbythepurchaser.Weagreetoabidebythisbidforaperiodof180daysafterthedatefixedforopeningofPriceBidsectionundertheInstructiontoBiddersandshallremainbindinguponusandmaybeacceptedatanytimebeforetheexpiryofthatperiod.Until a formal contract ispreparedandexecuted, thisbid, togetherwithyourwrittenacceptance thereof and your notification of award shall constitute a bindingContractbetweenus.Weunderstandthatincompetingfor(andiftheawardismadetous,inexecutingtheabovecontract),wewillstrictlyobservethelawsagainstfraudandcorruptioninforceinGujaratnamelyPreventionofCorruptionAct1988.Weunderstandthatyouarenotboundtoacceptthelowestoranybidyoumayreceive.Wehavenotbeenunderadeclarationofineligibilityforcorruptandfraudulentpractices,and/orblack‐listedordebarredbyanyoftheGovt.DepartmentoritsPSUinthepast3years, ending on 31stMarch, 2017 in Gujarat.We have not imposed any condition inconflictwiththetenderconditionifitisfounditshouldbetreatedaswithdrawn.Wehavenotbeenconvictedforanycriminalcases(s)byanyoftheGovt.DepartmentoritsPSUinGujaratregardinganysupplyandcontractswithourfirm/company.We have not breached/violated any contractual conditions so far to any of the Govt.DepartmentoritsPSU.Incaseanyoftheabovestatementsmadebyusarefoundtobefalseorincorrect,youhaverighttorejectourbidatanystageincludingforfeitureofourEMDand/orPBGand/orcanceltheawardofcontractDatedthis_________dayof____________20__Signature:______________________________(intheCapacityof):______________________Dulyauthorizedtosignbidforandonbehalfof9.7. FORM VII: Original Equipment Manufacturer (OEM)/Developer
Authorization Form in case of COTS Product and for OS and DatabaseSupport
No.__________________dated___________________
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 91 of 101
ToRef:TenderNo.________________Subject:_______________________________________________________________________________DearSir,We,________________________.,withaddress__________________________________________________________________________________________________________________________,doherebyconfirmthatwewillbeoffering__________________________________________________aspartofoursolutionfortheabovementionedRFP.We hereby confirm that the offered Product in the referenced RFP will be providedunconditionallywithabacktoback24x7x365warrantyandsupportincludingsubscriptioncoveringupgrades,updates,patchupdates,bugfixes,FaultReporting,TroubleTicketing,callresolution etc. available for the period of eight years for the entire scope of the projectthroughM/s___________________(SI/Bidder)fromthedateofGo‐LiveandalsotillGo‐live.Ifwe go for bespokedevelopment or COTS product theDST shall have full rights ofsharing source code with Gujarat State GovernmentDepartments/Boards/Corporations./PSUsorotherGujarat’sStateGovernmentEntity.IfwegoforCOTSproduct,weagreetoprovidethelicensesasfollow:ThelicensecostofCOTSProductaskedinfinancialbidserialno.2isfor25,000users.Theunitpriceofthesamewillbecalculatedaccordinglyasunder:
UnitRate=QuotedRatefor25000users/25000 ThesimilarmethodforcalculationofunitrateforATS/AMCfor8yearswillbe
applicable. Forlicensesupto25000nos.:bidderhastoprovidetheunitquotedratei.e.Unit
Rate=QuotedRatefor25,000users/25000 Forpurchaseofadditionallicensesquantityfrom25001to50000,bidderhasto
provide60%discountonunitquotedpriceonincrementalquantity Forpurchaseofadditionallicensesquantityfrom50,001andabovebidderhas
toprovide80%discountonunitquotedpriceonincrementalquantity ThesamewillbeapplicabletoAMC/ATSfor8yearsalso.
WeagreetothefactthatfullIPRofthecustomized/developedsolutionforthisprojectshallrestwiththeDSTexcepttheCOTS,BI,OSandDB.IncrementalIPRwillbecreatedduringtheDevelopmentprocesswhichwillbesincepaidforbyGovt.ofGujarat;hencesuchIPRwillrestinGovernmentofGujarat.WeagreetothefactthatStateGovernmenthasrighttoretaincustomizationlayerandshould the agreement with service provider and to further develop. Therefore,GovernmentofGujaratwillholdIPRofthecustomizedCOTSsolution.Thesamewouldbeapplicabletocopyrights.TheTSPshallsignany/allthedocumentsinthisregardandwillgetnecessaryundertakingtothiseffectfromtheCOTSOEM.TheGujaratGovernmentfurtherintendsusecustomizedCOTSbacktotheCOTSOEMtoenableittouseinGovernmentorganizations in other States or in organizations in Government of India. At the time ofawarding contract, authorized representative of COTS OEM will have to sign a separate
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 92 of 101
contract agreement to such an extent with Govt. of Gujarat. The TSP has to get such anundertakingfromtheOEMatthetimeoffilingthisbidandhandoverthesourcecode,Metadatadetailsetc. to theDSTatdifferentstagesofcustomizationandbeforereleaseof finalpaymentoncompletionoftrainingandrolloutofsoftware.WeabidethatDepartmentofScienceandTechnologyshallhavetheunrestrictedrighttodeployoruseIWDMS2.0applicationsoftwareandthedocumentationrelatedthereto,inanyGujaratstategovernmentdepartment,atnocosttoclient.Yoursfaithfully,(Name)(Nameofmanufacturers)Note:ThisletterofauthorityshouldbeontheRs.100stamppapershouldbesignedbyapersoncompetentandhavingthepowerofattorneytobindtheOEMofCOTSaswellasBidder.TheBidderinitsbidshouldincludeit.9.8. Form VIII – Earnest Money Deposit/Bid Security in the form of Bank
GuaranteeFormatRef: BankGuaranteeNo. Date:To,Director(e‐governance)GujaratInformaticsLimited8thFloor,Block‐1,UdyogBhavan,Sector‐11,Gandhinagar‐382017Gujarat,IndiaWhereas ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (here in after called "theBidder")hassubmitteditsbiddated‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐inresponsetotheTenderno:XXXXforTender No: ‐ _______________ RFP for “Design, Customization/Development,Implementation, Training, HandHolding andOperation&Maintenance Support for 8yearsforIntegratedWorkflowandDocumentManagementSystem”,KNOWALLMENbythesepresentsthatWE‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐havingourregisteredofficeat‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (hereinafter called "the Bank") are bound unto the ______________,GujaratInformaticsLimitedinthesumof‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐forwhichpaymentwellandtrulytobemadetoGujaratInformaticsLimited,theBankbindsitself,itssuccessorsandassignsbythesepresents.SealedwiththeCommonSealofthesaidBankthis‐‐‐‐‐‐‐‐‐‐‐‐‐‐dayof‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐2018.THECONDITIONSofthisobligationare:TheE.M.D.maybeforfeited: IfaBidderwithdrawsitsbidduringtheperiodofbidvalidityDoesnotacceptthecorrectionoferrorsmadeinthetenderdocument;IncaseofasuccessfulBidder,iftheBidderfails: 1) TosigntheContractasmentionedabovewithinthetimelimitstipulatedbypurchaser
or
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 93 of 101
2) Tofurnishperformancebankguaranteeasmentionedaboveor 3) Ifthebidderisfoundtobeinvolvedinfraudulentpractices.4) Ifthebidderfailstosubmitthecopyofpurchaseorder&acceptancethereof.WeundertaketopaytotheGIL/Purchaseruptotheaboveamountuponreceiptofitsfirst written demand, without GIL/ Purchaser having to substantiate its demand,providedthatinitsdemandGIL/Purchaserwillspecifythattheamountclaimedbyitisduetoitowingtotheoccurrenceofanyoftheabovementionedconditions,specifyingtheoccurredconditionorconditions.Thisguaranteewillremainvalidupto9monthsfromthelastdateofbidsubmission.TheBank undertakes not to revoke this guarantee during its currency without previousconsent of the OWNER/PURCHASER and further agrees that the guarantee hereincontainedshallcontinuetobeenforceabletilltheOWNER/PURCHASERdischargesthisguaranteeTheBankshallnotbereleasedofitsobligationsunderthesepresentsbyanyexercisebytheOWNER/PURCHAERofitsliabilitywithreferencetothemattersaforesaidoranyofthem or by reason or any other acts of omission or commission on the part of theOWNER/PURCHASERoranyotherindulgenceshownbytheOWNER/PURCHASERorbyanyothermatterorthings.TheBankalsoagreethattheOWNER/PUCHASERatitsoptionshallbeentitledtoenforcethis Guarantee against the Bank as a Principal Debtor, in the first instance withoutproceedingagainsttheSELLERandnotwithstandinganysecurityorotherguaranteethattheOWNER/PURCHASERmayhaveinrelationtotheSELLER’sliabilities.Datedat_______________onthis_________dayof___________20__.____________________Signedanddeliveredby_____________________For&onBehalfofNameoftheBank&Branch&ItsofficialAddress ApprovedBank:Any Nationalized Bank including the public sector bank or PrivateSectorBanksorCommercialBanksorCo‐OperativeBanksandRuralBanks(operatinginIndia having branch at Ahmedabad/ Gandhinagar) as per the G.R. no.EMD/10/2016/328/DMOdated 01.05.2017 issued by FinanceDepartment or furtherinstructionissuedbyFinanceDepartmenttimetotime.9.9. FORMIX‐PerformanceBankGuarantee(TobestampedinaccordancewithStampAct)Ref: BankGuaranteeNo. Date:To
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 94 of 101
Name&AddressofthePurchaser/Indenter________________________________________________________DearSir,InconsiderationofName&AddressofthePurchaser/Indenter,GovernmentofGujarat,Gandhinagar(hereinafterreferredtoastheOWNER/PURCHASERwhichexpressionshallunlessrepugnanttothecontextormeaningthereofincludesuccessors,administratorsand assigns) having awarded to M/s.……………………………………………………………………………………………………………… havingPrincipalOfficeat……………………………………………………………………(hereinafterreferredtoas the “SELLER” which expression shall unless repugnant to the context or meaningthereof includetheirrespectivesuccessors,administrators,executorsandassigns)thesupplyof____________________byissueofPurchaseOrderNo……………….Dated…………issuedbyGujaratInformaticsLtd.,GandhinagarforandonbehalfoftheOWNER/PURCHASERandthesamehavingbeenacceptedbytheSELLERresultingintoCONTRACTforsuppliesofmaterials/equipmentsasmentionedinthesaidpurchaseorderandtheSELLERhavingagreed to provide a Contract Performance and Warranty Guarantee for faithfulperformance of the aforementioned contract and warranty quality to theOWNER/PURCHASER, __________________________________having HeadOffice at (hereinafterreferred to as the ‘Bank’ which expressly shall, unless repugnant to the context ormeaning thereof includesuccessors,administrators,executorsandassigns)doherebyguaranteetoundertaketopaythesumofRs._______________(Rupees________________________)to the OWNER/PURCHASER on demand at any time up to________________ without areferencetotheSELLER. AnysuchdemandmadebytheOWNER/PURCHASERontheBankshallbeconclusiveandbindingnotwithstandinganydifferencebetweenTribunals,Arbitratororanyotherauthority.TheBankundertakesnottorevokethisguaranteeduringitscurrencywithoutpreviousconsent of the OWNER/PURCHASER and further agrees that the guarantee hereincontainedshallcontinuetobeenforceabletilltheOWNER/PURCHASERdischargesthisguarantee. OWNER/PURCHASERshallhavethefullest libertywithoutaffectinginanywaytheliabilityoftheBankunderthisguaranteefromtimetotimetoextendthetimefor performance by the SELLER of the aforementioned CONTRACT. The OWNER/PURCHASERshallhavethefullestliberty,withoutaffectingthisguarantee,topostponefromtimetotimetheexerciseofanypowersvestedinthemorofanyrightwhichtheymighthaveagainsttheSELLER,andtoexercisethesameatanytimeinanymanner,andeither to enforce to forebear to enforce any covenants contained or implied, in theaforementionedCONTRACTbetweentheOWNER/PURCHASERandtheSELLERoranyothercourseoforremedyorsecurityavailabletotheOWNER/PURCHASER.TheBankshallnotbereleasedofitsobligationsunderthesepresentsbyanyexercisebytheOWNER/PURCHAERofitsliabilitywithreferencetothemattersaforesaidoranyofthem or by reason or any other acts of omission or commission on the part of theOWNER/PURCHASERoranyotherindulgenceshownbytheOWNER/PURCHASERorbyanyothermatterorthings.TheBankalsoagreethattheOWNER/PUCHASERatitsoptionshallbeentitledtoenforcethis Guarantee against the Bank as a Principal Debtor, in the first instance without
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 95 of 101
proceedingagainsttheSELLERandnotwithstandinganysecurityorotherguaranteethattheOWNER/PURCHASERmayhaveinrelationtotheSELLER’sliabilities.NotwithstandinganythingcontainedhereinaboveourliabilityunderthisGuaranteeisrestricted to Rs. _________________ (Rupees _________________________) and it shall remain inforceuptoandincluding________________andshallbeextendedfromtimetotimeforsuchperiodasmaybedesiredbytheSELLERonwhosebehalfthisguaranteehasbeengiven.Datedat_______________onthis_________dayof___________20_______________________Signedanddeliveredby_____________________For&onBehalfofNameoftheBank&Branch&ItsofficialAddress 9.10. FormX–FormatofAffidavit(TobesubmittedINORIGINALonNon‐JudicialStampPaperofRs100/‐dulyattested
byFirstClassMagistrate/Notarypublic)I/We,___________________________,age______yearsresidingat_______________________incapacityof _________________________________________ M/s. ___________________________________ herebysolemnlyaffirmthat1) AllGeneralInstructions,GeneralTermsandConditions,aswellasSpecialTerms&
ConditionslaiddownonallthepagesoftheTenderForm,havebeenreadcarefullyandunderstoodproperlybymewhicharecompletelyacceptabletomeandIagreetoabidebythesame.
2) I/WehavesubmittedfollowingCertificates/DocumentsforT.E.asrequiredasper
GeneralTerms&ConditionsaswellasSpecialTerms&Conditionsofthetender
Sr.No. NameoftheDocument1 2
3) All theCertificates/Permissions/Documents/Permits/Affidavitsarevalidand
currentasondateandhavenotbeenwithdrawn/cancelledbytheissuingauthority.
4) Itisclearlyanddistinctlyunderstoodbymethatthetenderisliabletoberejectedifonscrutinyatanytime,anyoftherequiredCertificates/Permissions/Documents/
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 96 of 101
Permits/Affidavits is/arefoundtobe invalid/wrong/incorrect/misleading/fabricated/expiredorhavinganydefect.
5) I/WefurtherundertaketoproduceondemandtheoriginalCertificate/Permission/ Documents / Permits for verification at any stage during the processing of thetenderaswellasatanytimeaskedtoproduce.
6) I / We also understand that failure to produce the documents in "PrescribedProforma"(whereverapplicable)aswellasfailuretogiverequisiteinformationintheprescribedProformamayresultintorejectionofthetender.
7) My/Ourfirmhasnotbeenbanned/debarred/blacklistedatleastforthreeyears(excluding the current financial year) by any Government Department / StateGovernment/Governmentof India/Board/Corporation/GovernmentFinancialInstitutionincontexttopurchaseprocedurethroughtender.
8) I / We confirm that I / We have meticulously filled in, checked and verified theencloseddocuments/certificates/permissions/permits/affidavits/informationetc.fromeveryaspectandthesameareenclosedinorder(i.e.inchronology)inwhichthey are supposed to be enclosed. Page numbers are given on each submitteddocument.Importantinformationineachdocumentis"highlighted"withthehelpof"markerpen"asrequired.
9) Theabovecertificates/documentsareenclosedseparatelyandnotontheProformaprintedfromtenderdocument.
10) I/WesayandsubmitthatthePermanentAccountNumber(PAN)givenbytheIncomeTax Department is____________________,which is issued on the nameof___________________________[KindlymentionhereeithernameoftheProprietor(incaseofProprietorFirm)ornameofthetenderingfirn;1,whicheverisapplicable].
11) I /Weunderstand thatgivingwrong informationonoathamounts to forgeryandperjury,andI/Weam/areawareoftheconsequencesthereof,Incaseanyinformationprovidedbyusarefoundtobefalseorincorrect,youhaverighttorejectourbidatanystageincludingforfeitureofourEMD/PBG/canceltheawardofcontract.Inthisevent,thisofficereservestherighttotakelegalactiononme/us.
12) I/Wehavephysicallysigned&stampedalltheabovedocumentsalongwithcopyoftenderdocuments(pageno.‐‐‐‐to‐‐).
13) I/Weherebyconfirmthatallourquoteditemsmeetorexceedtherequirementandareabsolutelycomplimentwithspecificationmentionedinthebiddocument.
14) My/OurCompanyhasnotfiledanyWritPetition,CourtmatterandthereisnocourtmatterfiledbyStateGovernmentanditsBoardCorporation,ispendingagainstourcompany.
15) I/Weherebycommitthatwehavepaidalloutstandingamountsofdues/taxes/cess/charges/feeswithinterestandpenalty.
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 97 of 101
16) In case of breach of any tender terms and conditions or deviation from bidspecificationotherthanalreadyspecifiedasmentionedabove,thedecisionofTenderCommitteefordisqualificationwillbeacceptedbyus.
Whateverstatedaboveistrueandcorrecttothebestofmyknowledgeandbelief.Date: Stamp&SignoftheTendererPlace: (SignatureandsealoftheNotary)
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 98 of 101
10. SectionX:FinancialBidBiddershouldquotefirmratesfortheentireScopeofWorkandTechnicalRequirementsmentionedintheSectionIIIofTenderDocument:Intherateschedule,wherevertheunitpriceisnotasked,thebidderwillhavetoquotethelump‐sumpriceofindicateditem.Theperunitpriceforeachitemwillbecomputedbydividingtotalbidpriceforeachitembythenumberofunits/quantities.FinancialBidFormat:Table1:CAPEX
Sr.No.
DescriptionTotalAmount(Rs.)
Taxes
1.
One time cost of IWDMS 2.0 including design,customization/development, implementation,Migration of existing database & testing as per thescopeofworkdefinedinthisRFP–Part1
2.
OnetimecostofrequiredCOTSlicenses,OS,Databaselicenses and other readymade software required forrunning of application for 25000 users (*except DRlicenses)‐Part2
GrandTotal (Rs.) – (A) Table2:OPEX
Sr.No.
DescriptionTotalAmount(Rs.)
Taxes
1.
Cost of Operations and Maintenance of IWDMS 2.0including continuous development team, help desksupport, hand‐holding support and central site O&Mteam for Technical support for Software Upgrades,Updates,patches,securityupdates,bugfixesetc.‐Part3
2.
Cost of AMC/ATS ofOS, Database licenses, COTS andother readymade software required for running ofapplication for the period of 8 years (*except DRlicenses)‐Part4
3. CostofTraining
GrandTotal(Rs.) (B) GrandTotal (Rs.) (C=A+B)
Note:
1. The cost of the above parts should be matched with the breakup of each component mentioned in Part.
2. Taxes are extra as applicable 3. *ThelicensesforDRwillbecounted25%ofthequantityandpricequotedforDC.
As andwhenDRmade operational by Government of Gujarat, theDR licensesmaximumupto25%maybeseparatelyorderedandsuccessfulbidderisrequired
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 99 of 101
todeliverandinstallthesame.ThepaymentfortheDRshallbemadebasedontheactual licensesorderedand installedmaximumup to25%.Other than licensespaymentnoadditionalpaymentshallbemadetobidderforO&MofDRSite.TheresponsibilityofimplementationofDRsiteasandwhenrequiredshallbeofTSP.
4. ThelicensecostofCOTSProductaskedinfinancialbidserialno.2isfor25,000users.Theunitpriceofthesamewillbecalculatedaccordinglyasunder:UnitRate=QuotedRatefor25000users/25000
ThesimilarmethodforcalculationofunitrateforATS/AMCfor8yearswillbeapplicable.
Forlicensesupto25000nos.:bidderhastoprovidetheunitquotedratei.e.UnitRate=QuotedRatefor25,000users/25000
Forpurchaseofadditionallicensesquantityfrom25001to50000,bidderhastoprovide60%discountonunitquotedpriceonincrementalquantity
Forpurchaseofadditionallicensesquantityfrom50,001andabovebidderhastoprovide80%discountonunitquotedpriceonincrementalquantity
ThesamewillbeapplicabletoAMC/ATSfor8yearsalso.
TheTechnicalbidshallhaveaweightedat30%intheoverallevaluationofthebidandtheCommercialbidshallhaveaweightedat70%intheoverallevaluation.FormulaforNormalizationofTechnicalbidforeachbidderTn=(Tb/Tmax)x100WhereTbisthebidder’s technical score and Tmax is the Highest technical score. Formula forNormalizationofFinancialbid foreachbidderFn=(Fmin/Fb)x100WhereFb is thebidder’sfinancialbidvalueandFministheLowestbidvalue.Individualbidder’sTnandFnwillbeaddedtoreachthefinalvalue.Further30%ofTnand70%Fnwillbetaken.Thewinnerwillbethehighestof(Tnx30/100+Fnx70/100).L1bidderwillbecalledforfurthernegotiationsifrequired.
Part1:One‐timecostofIWDMS2.0includingdesign,customization/development,implementation,Migrationofexistingdatabase&testingasperthescopeofworkdefinedinthisRFP
Sr.no.
ItemDescriptionOriginal
TotalManmontheffort
RateperMan‐month Total
amount(Rs.)
A B C D E=C*D1 Conceptualization,As‐Is,BPRand
To‐be
2 BRD,URS,SRS 3 Customization/ Development &
Coding
4 Testing,UAT 5 Training 6 MigrationofExistingdatabase
TotalAmount(Rs.) Part2:OnetimecostofrequiredCOTs licenses,OS,Database licensesandotherreadymadesoftwarerequiredforrunningofapplicationfor25000users
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 100 of 101
Part3:CostofOperationsandMaintenanceof IWDMS2.0 including continuousdevelopmentteam,helpdesksupport,hand‐holdingsupportandcentralsiteO&Mteam for Technical support for Software Upgrades, Updates, patches, securityupdates,bugfixesetc.
Sr.no.
Particular
No.of
Resource
Year1
Year2
Year3
Year4
Year5
Year6
Year7
Year8
PermonthRate
Y1
PermonthRate
Y2
PermonthRate
Y3
PermonthRate
Y4
PermonthRate
Y5
PermonthRate
Y6
PermonthRate
Y7
PermonthRate
Y8
Total
A B C D E F G H I J K L M N O P Q R S
1. ProjectManager
1
2. Continuous
developmentteam
5
3. Helpdesk
support
3
4. Hand‐holdingsupport
35
Sr. no. Particular No. of Licenses
Unit Cost
Total Cost
A B C D E=C*D
COTSlicenses 1.
2.
3.
Operatingsystem ..
..
Databaselicenses
Otherreadymadesoftwarerequiredforrunningofapplication
Total
Request for Proposal Department of Science and Technology
Government of Gujarat Confidential 101 of 101
5. SystemAdministrator
1
6. System/BusinessAnalyst
1
7. DBA 1 8. Security
Expert1
9. MobilityExpert
1
10. BIExpert 1 Total
Part 4: Cost of AMC/ATS of OS,Database licenses, COTS and other readymadesoftwarerequiredforrunningofapplicationfortheperiodof8years
Sr.no.
Particular
No.ofUnit
Year1
Year2
Year3
Year4
Year5
Year6
Year7
Year8
PerunitRate
Y1
PerunitRate
Y2
PerunitRate
Y3
PerunitRate
Y4
PerunitRate
Y5
PerunitRate
Y6
PerunitRate
Y7
PerunitRate
Y8
Total
A B C D E F G H I J K L M N O P Q R S
1. 2. 3. 4. 5. 6. 7. 8. 9. 10.
Total