Design-Phase Commissioning
Glenn Hansen, P.E., Senior Engineer PECI November 13, 2013
![Page 2: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/2.jpg)
2
Overview • Background • Applicability • Required qualifications • Process • Checklists
![Page 3: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/3.jpg)
3
Background • CCC initiated and helped fund project • SCE funded and supported CASE development • CASE development team: Glenn Hansen, Cindy
Strecker, Matt Tyler, Beth Littlehales, all with PECI • Subcontractor: Karl Stum, Summit Building
Engineering
Intent: “To improve compliance with existing Title 24 Part 6 energy code requirements that leads to designs that are constructible and functional that deliver anticipated energy savings.”
![Page 4: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/4.jpg)
Background - What is Building Commissioning
Commissioning: a quality assurance process that spans the entire design and construction process ….. Includes verifying and documenting that building systems are:
Planned and designed properly
Installed and tested properly
Operated and maintained properly Reference: CALGreen Description - 2010 California Green Buildings Standards Code, Title 24, Part 11.
Design Review
![Page 5: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/5.jpg)
Background - Filling in the Design-Phase Commissioning Gap
ASHRAE Guideline 0
CALGreen 2010 IECC / IGCC LEED 2009
Enhanced Cx
Owner's Project Requirements √ √ √ Cx Plan √ √ √ √ Basis of Design √ √ √ Cx in Construction Documents √ √ √ Construction Checklists √ Design Review √ √ Functional Performance Testing √ √ √ √ Documentation and Training √ √ √ Final Cx Report √ √ √ √ Post Occupancy Cx √ √ √
Was omitted from CALGreen
LEED 2009 Enhanced Cx
![Page 6: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/6.jpg)
6
Background - Traditional Design Review
QC / QA Checks • Design conforms to project requirements • Documents are clear and complete • Documents are free from significant error
![Page 7: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/7.jpg)
7
Background - Benefits of Traditional Design Review
Reduced Cost & Time • Fewer construction problems and corrective action needed
― Lower number of significant change orders ― Less administrative time issuing RFIs and COs
• Minimize delays associated with resolving deficiencies Quality Building
• Has fewer operational problems • Operates as intended • Is easier to maintain • Has lower operating cost
![Page 8: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/8.jpg)
Background - Energy Code Design Review
What’s Checked • Mandatory, Prescriptive or Performance path energy
measures are reflected in design documents • Cxing and Acceptance Testing requirements are reflected
in design documents
Benefits - Energy Savings
• Increase compliance with Title 24 energy requirements • Lower energy using buildings
![Page 9: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/9.jpg)
Background - Drivers for Energy Code Design Review
• U.S.DOE Energy Code Compliance benchmark tied to ARRA funding (90% compliance by 2017)
• Cost effective opportunity • Adoption of carbon policies and drive to net zero
buildings
![Page 10: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/10.jpg)
Background - Stakeholder Input MEP Designers • General support for the design review • Currently doing some form of internal plans check • Concern with added complexity to an already complex compliance
process
Commissioning Providers • Design review is part of successful commissioning • Concern with qualifications of the Design Reviewer
![Page 11: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/11.jpg)
Background - Stakeholder Input
Owners • Mixed experience with commissioning • Value is varied based on who is the commissioning
authority (CA) (process, tech. skill, communication) • Concern of added coordination time and cost
Code Officials • No additional review or compliance checks • Single point of sign off by Design Reviewer
![Page 12: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/12.jpg)
Background - Guiding Principals
• Effective – not overly burdensome • Practical – targets items with most impact • Effort and cost scalable to project size • Integrated with AT and CALGreen Cx • Enforceable • Incrementally improved in future code cycles • Drive market adoption and result in more
effective delivery over time.
![Page 13: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/13.jpg)
Background - CASE Savings Estimate OL Office
Large OS Office-Small RE Restau-
rant RL Retail SC School
CZ Elec Gas Elec Gas Elec Gas Elec Gas Elec Gas
3 4.6% 9.4% 4.8% 4.1% 1.6% 1.0% 2.2% 10.5% 2.5% 6.4%
6 4.4% 9.6% 4.6% 3.3% 1.9% 0.6% 2.5% 9.6% 2.8% 5.4%
10 4.4% 9.5% 5.1% 3.8% 1.8% 0.7% 2.6% 10.1% 3.4% 5.6%
12 4.3% 9.2% 5.2% 3.5% 1.6% 1.1% 2.4% 8.9% 3.3% 6.2%
16 3.8% 8.7% 5.4% 2.7% 1.5% 1.5% 2.3% 6.9% 2.8% 5.4%
Ave. 4.3% 9.3% 5.0% 3.5% 1.7% 1.0% 2.4% 9.2% 3.0% 5.8%
Percent savings of total building energy use
CASE Report Link: http://www.energy.ca.gov/title24/2013standards/prerulemaking/documents/2011-04-18_workshop/review/2013_CASE_Design_Phase_Cx_3.31.2011.pdf
![Page 14: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/14.jpg)
14
Applicability - Design Review for All Buildings
• Design Review in all nonresidential buildings • Mandatory for projects permitted after 1/1/14 • Applies equally for prescriptive or performance
compliance paths
Section 120.8(d) of the 2013 Building Energy Efficiency Standards Section 12.4 of the 2013 Nonresidential Compliance Manual
![Page 15: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/15.jpg)
15
Applicability - Commissioning Added to Title 24 part 6
Requirements: • Owner’s Project Requirements (OPR) • Basis of Design (BOD) • Design-Phase Review • Commissioning measures shown in construction documents • Commissioning Plan • Functional Performance Testing • Documentation and Training • Commissioning Report
Design-Phase Review required for all buildings, while commissioning is required for buildings >10,000sq.ft.
![Page 16: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/16.jpg)
16
Applicability - Integration with Acceptance Testing
![Page 17: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/17.jpg)
17
Design Reviewer Qualifications - Minimum Requirements
Typically - Licensed Professional Engineer
HVAC Systems
Size Qualified reviewer
Simple <10,000 sq.ft.
Engineer-of-record (self-review), OR Contractor (if engineer-of-record not required)
Simple 10-50,000 sq.ft.
Qualified in-house engineer with no project involvement, OR third party engineer
Simple >50,000 sq.ft. Third party design engineer
Complex Any size Third party design engineer
![Page 18: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/18.jpg)
18
Definitions - Simple vs. Complex HVAC
Simple HVAC Systems: • Unitary or packaged equipment that serve one zone • Two-pipe heating only systems serving one or more
zones Complex Mechanical Systems: • Fan systems serving multiple zones (VAV) • Built-up air handler systems • Hydronic or steam heating systems • Hydronic cooling systems
![Page 19: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/19.jpg)
Process
Design
Programming Schematic Design
Design Development
Construction Documents
Permit Application
Plan Check
Acceptance Testing
Commissioning & Acceptance
Testing
Certificate of Occupancy
Design Review Kickoff
Meeting
Design Review
Completed Checklists
Permitting Construction
Performance Path Compliance Forms
Building ≤ 10,000 ft2
Building >10,000 ft2
![Page 20: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/20.jpg)
Early Design Influence - Early involvement generates greatest impact
![Page 21: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/21.jpg)
21
Design Review Kickoff Meeting • Occurs during early design • In-person meeting
• Project owner • Design team
• Mechanical • Electrical • Architect
• Commissioning coordinator • Design reviewer
![Page 22: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/22.jpg)
22
Design Review Kickoff Meeting Topics • Project coordination • Project schedule • Project scope • OPR & BOD • Design elements and assumptions • HVAC system selection • Code compliance path • Introduction of design review checklists and highlight
appropriate sections • Recommend best practice energy efficiency
measures
![Page 23: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/23.jpg)
23
Design Review Kickoff Checklist NRCC-CXR-01-E (1 page)
• xxx Checklists issued
General Info
Reviewer quals
Attendees
Topics discussed
Reference Documents
![Page 24: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/24.jpg)
24
Design Review • Occurs around 90% CD completion (typically pre permit set) • Timing and documents (plans and specs) are
discussed at Design Review Kick-off Meeting
![Page 25: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/25.jpg)
25
Design Review Checklists - Certificate of Compliance • Doesn’t encompass all T24 energy code measures • Selected based on experience of team members or
published reports of commonly excluded or non functional measures
• Includes best practice energy measures • Current format relies on use of “Notes” section • Will be updated as future energy measures are
added to Title 24 Part 6 • Future performance path compliance simulation
software may automatically generate checklists for the exceptional code measures
![Page 26: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/26.jpg)
26
Design Review Checklists - NRCC-CXR-02-E: General (7 pages)
• Envelope • Lighting • Daylight Area • Daylight Controls • Outdoor Lighting Controls
& Equipment • Service Hot Water • HVAC Design • HVAC Zoning • Controls • DCV • Economizers • Duct Design • Acceptance &
Commissioning
![Page 27: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/27.jpg)
27
Design Review Checklists -NRCC-CXR-03-E: Simple HVAC (1 page) • Fan System • Controls
![Page 28: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/28.jpg)
28
Design Review Checklists - NRCC-CXR-04-E:Complex HVAC (5 pages)
• Fan Systems • Supply Air reset • Heat Rejection
Equipment • Chillers & Boilers • Hydronic Systems –
Pumping • Hydronic Heat Pump
![Page 29: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/29.jpg)
29
Checklist - Reviewer & Designer Interaction
Design Reviewer: • Yes, Complies • Does Not Comply • Consider Better Practice
Designer Response: • Complies • Will Include in Next Draft • Not Included – State Reason
![Page 30: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/30.jpg)
30
Design Review Completion - NRCC–CXR-05-E: Final Sign-off (1 page)
• Owner / Owners Representative
• Designer(s) • Design Reviewer
![Page 31: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/31.jpg)
31
Summary of Checklists
01: Design Review
02: General (non-HVAC)
03: Simple HVAC
04: Complex HVAC
05: Final Sign-off
Design Review Kickoff Meeting
Design Review
![Page 32: Design-Phase Commissioning Meeting Presentation dated … · 2013. 11. 13. · Design-Phase Commissioning Meeting Presentation dated November 13, 2013 Author: Glenn Hansen Created](https://reader034.vdocument.in/reader034/viewer/2022051906/5ff8d904ab883e1f017b2c5f/html5/thumbnails/32.jpg)
32
CCC Outreach & Training Resources
• FAQ • Online training presentations • Reference Guide