Discussion pointsTBM meeting23/09/2015
Updates
• Global 3D assembly updated, no severe problems/clashes• T1 RF network dimensions updated• WPS arms machined• Mock-ups under machining, brazing starts next week
Adjustable DBQ support
• Supports for T0 ready• The rotation of the magnets has some implications
(adjusting knobs on the inside)• Some modifications might be required – investigation
needed• Design for T1 tricky to implement due to Epucret
design
Adjustable V-supports
• Finalised design and drawings
• Adequate for proof of concept, still a bit rough
• Fixed supports already on Epucret
Stay with fixed supports (both V and DBQ) and organise a side project, perhaps on second Epucret girder with dummy loads?
BPM deletion drift tube• Clash 15mm
• Bellow compression 7mm
• Drift tube play in magnet 5mm
• If decided to be replaced, needs to be done before magnet assembly
5mm
Vacuum
• ‘Baseline’ design almost ready
• Vacuum forces are significant
• Shall we proceed with baseline design or launch a design project for force cancelation?
• 2 quick proposals
MBQ support
• Only piece missing before floor drilling
• Concrete block needs to be replaced
• Shall we assume the base plate as reference and produce steel support block?
U-clamps
• For MB:• In principle CLEX design can be used• Compatibility check pending
• For DB:• Same design as T0.1• Probably not compatible with adjustable
V-supports
• Redesign needed?
Mysterious additional support in CLEX
DAQ
# Description1 SAS 1 water in temperature2 SAS 1 component temperature3 SAS 1 water out temperature4 SAS 2 water in temperature5 SAS 2 component temperature6 SAS 2 water out temperature7 SAS 3 water in temperature8 SAS 3 component temperature9 SAS 3 water out temperature
10 SAS 4 water in temperature11 SAS 4 component temperature12 SAS 4 water out temperature13 PETS 1 in14 PETS 1 out / 2 in15 PETS 2 out16 DBQ 1 in17 DBQ 1 component18 DBQ 1 out/ 2 in19 DBQ 2 component20 DBQ 2 out21 Ambient 122 Ambient 223 Spare 124 Spare 225 Spare 326 Spare 427 Spare 528 Spare 629 Spare 730 Spare 831 Spare 932 Spare 10
• According to test plan, 22 temperature sensors are foreseen for each TBM
• Current architecture (NI cDAQ) allows 32 sensors per box
• Remaining signals (flow meters, control valves, heaters) will be connected to 4th electronics box
• Total of 4 boxes, connected via USB to central PC
• Room for expansion• Optional upgrade to cRIO system with
embedded CPU for increased robustness
TBM 1 TBM 2 TBM 3
Cooling rack
PC
32x Temp sensors
32x Temp sensors
32x Temp sensors
Flow meterControl Valve
Heater
Usb x4
Next tasks
• Critical path:• WPS arms assembly• T1 MB cradles machining• Girders fiducialisation• Floor drilling• Girders installation
• In parallel:• Cooling rack assembly – already started• PETS T0.2 fiducialisation