Harlan High School
Facilities Construction
NNOORRTTHHSSIIDDEE IINNDDEEPPEENNDDEENNTT SSCCHHOOOOLL DDIISSTTRRIICCTT
Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS
Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
Jim Berg DIRECTOR OF FACILITIES CONSTRUCTION
December 2016
2014 BOND PROJECTS
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL)
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – Jim Berg Contractor – Joeris General Contractor GMP - $110,800,000.00 Construction Period – October 2014 – May 2017 Construction Status: 87% Complete Project Scope – New 2800 Student High School
Site grading, utilities and landscaping in progress. Interior CMU walls, drywall framing, electrical, plumbing, and HVAC installation in progress. Window installation, interior painting, exterior brick veneer and roofing in progress. Concrete drives and parking areas in progress. Punch in progress. Athletic field sodding in progress.
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Aerial (Nov. 22, 2016)
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Front Entrance
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (December 2016)
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (December 2016)
HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (December 2016)
KALLISON ELEMENTARY SCHOOL (KALLISON RANCH #2 ELEMENTARY)
Architect – Garza Bomberger Project Architect – Roy Lewis NISD Project Manager – Marilyn Sevedge Contractor – Guido Construction Construction Amount - $24,640,000.00 Construction Period – March 7, 2016 – May 26, 2017 Construction Status: 40% Complete Project Scope – New 800 Student Elementary School
Structural steel erection and masonry ongoing. Floor slabs are 80% complete. Brick, MEP ductwork and roofing are starting. Pedestrian bridge installed.
KALLISON ELEMENTARY SCHOOL Aerial (November 2016)
KALLISON ELEMENTARY SCHOOL Aerial (November 2016)
KALLISON ELEMENTARY SCHOOL Front Entrance
KALLISON ELEMENTARY SCHOOL (December 6, 2016)
KALLISON ELEMENTARY SCHOOL (December 6, 2016)
KALLISON ELEMENTARY SCHOOL (December 6, 2016)
ADDITIONS AND RENOVATIONS
PROJECTS IN PROGRESS
ALLEN ES CLASSROOM - ADDITION/ADA/WINDOW UPGRADES
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Chris Parker Contractor – Suburban Construction Co. Construction Amount - $4,075,000.00 Construction Period – March 2016 – December 2016 Construction Status: 90% Complete Project Scope – Classroom Addition/ADA/Window Upgrades
Addition structural concrete complete. Masonry in progress. Structural steel/decking complete. MEP, paint and ceramic tile in progress.
ALLEN ES CLASSROOM - (Rendering of Site and Floor Plans)
ALLEN ES CLASSROOM - (Rendering of Floor Plan, Elevation and Perspectives)
ALLEN ES CLASSROOM - ADDITION/ADA/WINDOW UPGRADES (December 1, 2016)
ALLEN ES CLASSROOM - ADDITION/ADA/WINDOW UPGRADES (December 1, 2016)
GLENOAKS ELEMENTARY - Administration Upgrades/Security Lobby
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – McGoldrick Construction Co. Construction Amount - $3,750,000.00 Construction Period – June 2016 – March 2017 Construction Status: 30% Complete Project Scope – New Administration Building
Forming for Floor Slab.
GLENOAKS ELEMENTARY (Rendering of Front Elevation)
GLENOAKS ELEMENTARY Administration Upgrades (November 15, 2016)
GLENOAKS ELEMENTARY Administration Upgrades (November 22, 2016)
GLENOAKS ELEMENTARY Administration Upgrades (December 1, 2016)
2014 BOND PROJECTS
IN
BID/DESIGN PHASE
SUMMER 2016
HOLMES HS FINE ARTS UPGRADE
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Jim Berg Contractor – Bartlett Cocke Construction Budget - $27,900,000.00 Tentative Construction Period – June 2017 – December 2018 Project Scope – Fine Arts Building Replacement
Schematic design approved by Board on September 27, 2016. Site and Demolition Construction Documents in progress.
NORTHSIDE ACTIVITY CENTER RENOVATIONS
Architect – Richard Sanchez Architects, Inc. Project Architect – Richard Sanchez NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - $4,000,000.00 Tentative Construction Period – January 2017 – January 2018 Project Scope – Addition
Construction Documents issued for proposals.
PAUL TAYLOR FIELD HOUSE RENOVATIONS
Architect – Garza Bomberger Architects Project Architect – Roy Lewis NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - $4,600,000.00 Tentative Construction Period – February 2017 – August 2017 Project Scope – ADA Interior/Exterior Renovations
Construction Documents issued for proposals.
2014 BOND PROJECTS
IN
BID/DESIGN PHASE
SUMMER 2017
GROSENBACHER AREA ELEMENTARY (Prototype of Boldt ES and Cole ES)
Architect – Noonan Rittiman Project Architect – John Rittiman NISD Project Manager – Tom Curiel Contractor – TBD Construction Budget - $24,000,000 Tentative Construction Period – March 2017 – May 2018 Project Scope – New 800 Student Elementary School (Prototype of Boldt ES and Coles ES)
95% Construction Documents review scheduled for December 7, 2016.
2017 SECURITY LOBBIES at (9) ELEMENTARY SCHOOLS
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $1,260,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – New Security Lobby for (9) Elementary Schools:
Adams Hill ES, Allen ES, Beard ES, Braun Station ES, Forester ES, Hoffmann ES, Knowlton ES, Timberwilde ES, and Villarreal ES
Construction Documents issued for proposals.
BOONE ELEMENTARY - Administration Upgrades, Bus/Student Canopy & Security Lobby
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Jim Berg Contractor – TBD Construction Budget - $4,040,000.00 Tentative Construction Period – June 2017 – May 2018 Project Scope – Administration Upgrades, Bus/Student Walkway Canopy
Modifications Schematic Design approved by Board on October 25, 2016. Construction Documents in progress.
COLONIES NORTH ELEMENTARY Window Upgrades / ADA Work
Architect – Huckabee Architects Project Architect – Jeff Rodriquez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $2,000,000.00 Tentative Construction Period – June 2017 – October 2017 Project Scope – Window Upgrades and ADA Work Construction Documents in Progress.
GLASS ELEMENTARY Window Upgrades / ADA Work
Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $1,500,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Window Upgrades and ADA Work Schematic Design meeting scheduled for December 15, 2016.
GLENOAKS ELEMENTARY - Window Upgrades / ADA Work
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $1,100,000.00 Tentative Construction Period – June 2017 – December 2017 Project Scope – Window Upgrades and ADA Work
Schematic Design Phase pending Board Approval.
GLENN ELEMENTARY School Building Replacements / Security Lobby
Architect – LPA Project Architect – Mark Oppelt NISD Project Manager – Jim Berg Contractor – TBD Construction Budget - $4,800,000.00 Tentative Construction Period – June 2017 – August 2018 Project Scope – Replacement of Buildings
Schematic Design scheduled for Building Committee review October 25, 2016. Construction Documents in progress.
KNOWLTON ELEMENTARY Cafeteria / Kitchen Renovations / Library Addition
Architect – Pfluger Project Architect – Carr Hornbuckle NISD Project Manager – Jim Berg Contractor – TBD Construction Budget – $2,200,000.00 Tentative Construction Period – June 2017 – November 2017 Project Scope – Renovations and Additions
Schematic Design approved by Board on October 25, 2016. Construction Documents in progress.
TIMBERWILDE ELEMENTARY Cafeteria/Kitchen Renovations/Library Addition
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $2,200,000.00 Tentative Construction Period – June 2017 – November 2017 Project Scope – Renovations and Additions
Schematic Design approved by Board on October 25, 2016. Construction Documents in progress.
MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovations
Architect – Garza Bomberger Architects Project Architect – Roy Lewis NISD Project Manager – Tom Curiel Contractor – TBD Construction Budget – $4,400,000.00 Tentative Construction Period – June 2017 – March 2018 Project Scope – Renovations and Additions
Schematic Design in progress.
2017 DOOR HARDWARE Glass ES, Westwood Terrace ES and Holmes HS
Architect – Chesney Morales Project Architect – Richard Morales NISD Project Manager – Jim Berg Contractor – TBD Construction Budget – $117,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Door Hardware
Construction Documents in progress.
2017 FLOORING REPLACEMENTS Elrod, Glenn, Glenoaks, & Michael Elementary
Architect – CWS Architect Project Architect – Robert Watts NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $230,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Flooring
Construction Documents in progress.
2017 FLOORING REPLACEMENTS Carson ES, Neff MS, & Warren HS
Architect – Huckabee Architects Project Architect – Jeff Rodriguez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $325,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Flooring
Construction Documents in progress.
NEFF MS COMPETITION GYM FLOORING AND BLEACHERS
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Chris Parker Contractor – TBD Construction Budget – $ TBD Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Flooring and Bleachers
Construction Documents in progress.
2016 GROWTH & IMPROVEMENT
2016 ATHLETIC AREA UPGRADES JAY HS, CLARK HS, JONES MS & ROSS MS
Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Chris Parker Contractor – STI-GC Contract Amount - $1,500,000.00 Construction Period – May 2016 – August 2016 Construction Status: 96% Complete Project Scope – Installation of Athletic Storage Units and Interior
Renovations. Locker and millwork replacement complete. Athletic storage
unit installation complete. Wire mesh partitions installation in progress. Closeout in progress.
CHILD NUTRITION WAREHOUSE Warehouse Renovation
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Henry Acosta Contractor – Workman Commercial Contract Amount - $5,726,500.00 Construction Period – July 2016 – January 2017 Construction Status: 29% Complete Project Scope – Warehouse Renovation
Contract in progress. Renovation funded from Child Nutrition 2016 Growth & Improvement funds and 2010 Bond Savings.
Demo complete, rough-ins in progress. Walk in cooler/freezer floor in progress.
CHILD NUTRITION WAREHOUSE - Warehouse Renovation (Aerial View)
CHILD NUTRITION WAREHOUSE Warehouse Renovation (Nov. 18, 2016)
CHILD NUTRITION WAREHOUSE Warehouse Renovation (Nov. 18, 2016)
CHILD NUTRITION WAREHOUSE Warehouse Renovation (Nov. 18, 2016)
2017 GROWTH & IMPROVEMENT
2017 ATHLETIC AREAS UPGRADES Hobby MS, Pease MS, and Taft HS
Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Chris Parker Contractor – TBD Contract Amount – TBD Construction Period – June 2017 – August 2017 Construction Status: 0% Complete Project Scope – Installation of Athletic Storage Units and Interior
Renovations. Schematic Design in progress.
ROOFING PROJECTS
BOONE ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – Samuel Dean Sheet Metal Inc. Contract Amount – $336,973.00 Construction Period – June – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project Closeout in Progress.
CABLE ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Austech Engineering Contractor – Cram Roofing Contract Amount – $199,550.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repairs & Waterproofing
Project Closeout in Progress.
HOWSMAN ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – Beldon Contract Amount – $692,986.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project Closeout in Progress.
ANSON JONES MIDDLE SCHOOL ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – Cram Roofing Contract Amount – $165,000.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project Closeout in Progress.
LEWIS ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Austech Contractor – Empire Roofing Contract Amount – $190,151.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project Closeout in Progress.
LINTON ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – ATC Contractors, Inc. Contract Amount – $208,500.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project Closeout in Progress.
MARY HULL ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – Cram Roofing Contract Amount – $317,385.00 Construction Period – June 2016 – August 2016 Construction Status: 100% Complete Project Scope – Roof Replacement & Waterproofing
Project Closeout in Progress.
MAY ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – Port Enterprise Contract Amount – $1,678,997.00 Construction Period – June 2016 – October 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project closeout in progress.
TAFT HIGH SCHOOL ROOFING PROJECT
Roofing Consultant – Hollon + Cannon Contractor – Port Enterprise Contract Amount – $1,632,113.00 Construction Period – June 2016 – December 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project closeout in progress.
VILLARREAL ELEMENTARY SCHOOL ROOFING PROJECT
Roofing Consultant – Austech Contractor – Samuel Dean Sheet Metal Inc. Construction Budget – $97,090.00 Construction Period – June 2016 – August 2016 Construction Status: 98% Complete Project Scope – Roof Repair & Waterproofing
Project Closeout in Progress.
2016 HAIL DAMAGE
ROOFING PROJECTS
BEARD ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Hollon & Cannon Contractor – TBD Contract Amount – $566,480.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement & Restoration
Project in Design.
CARNAHAN ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Hollon & Cannon Contractor – TBD Contract Amount – $2,125,200.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement
Project in Design.
CLARK HIGH SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Hollon & Cannon Contractor – TBD Contract Amount – $2,490,800.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement
Project in Design.
SOUTH TRANSPORTATION HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – TBD Contract Amount – $261,920.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement
Project in Design.
STEVENSON MIDDLE SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Raba Kistner Contractor – TBD Contract Amount – $1,904,450.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement & Restoration
Project in Design.
CARLOS COON ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Austech Contractor – TBD Contract Amount – $1,409,870.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement & Restoration
Project in Design.
ELROD ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Austech Contractor – TBD Contract Amount – $784,880.00 Construction Period – June 2017– December 2017 Project Scope – Roof Restoration
Project in Design.
FERNANDEZ ELEMENTARY SCHOOL HAIL DAMAGE ROOFING PROJECT
Roofing Consultant – Austech Contractor – TBD Contract Amount – $1,102,400.00 Construction Period – June 2017– December 2017 Project Scope – Roof Replacement & Restoration
Project in Design.