First Floor Columns& Second Floor Slab
Prepared by
Elton Gallimore
![Page 2: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/2.jpg)
Scope of Works
• Area of construction: 86.4m x 46.8m grid= 4043.52 m2.
• To construct 39 First Floor reinforced steel concrete columns at 60 x 30 cm to a height of 2.10m.
• To construct a Second Floor Slab to an area of 4043.52 m2 thickness of 250mm. Height from first floor slab 2.45m
![Page 3: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/3.jpg)
Area of Construction (zones)
15.6m
7.2m
![Page 4: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/4.jpg)
Area of construction (sections)
46.8m
86.4m
![Page 5: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/5.jpg)
Section Breakdown
![Page 6: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/6.jpg)
Safety Platform AssemblyAccess to workableAreas will be viaTemporary stairsWhich be movedAccording to Construction schedule
Week one Week two
Week Week
![Page 7: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/7.jpg)
Zone 1 Column formwork• Sections 1-9 Column
formwork arrangement with re bar
• 3 gangs (2 men per gang), 1 gang per column
• 1 column + rebar 30mins• 12 columns = 2hrs.
Zone 2 Column formwork• Sections 10-18 Column
formwork arrangement with re bar
• 4 gangs (2 men per gang), 1 gang per column
• 1 column + rebar 30mins• 9 columns = 1.5hrs.
200kg of 10mm steel rebar per m3 of concrete (Peri requirements)
![Page 8: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/8.jpg)
Zone 3 Column formwork• Sections 19-27 Column
formwork arrangement with re bar
• 4 gangs (2 men per gang), 1 gang per column
• 1 column + rebar 30mins• 9 columns = 1.5hrs.
Zone 4 Column formwork• Sections 30-34 Column
formwork arrangement with re bar
• 4 gangs (2 men per gang), 1 gang per column
• 1 column + rebar 30mins• 9 columns = 1.5hrs.
200kg of 10mm steel rebar per m3 of concrete (Peri requirements)
![Page 9: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/9.jpg)
Column formwork detail
Positioned to monolithic kickers from ground floor columns
Firs
t fl
oor
Gro
und
floor
![Page 10: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/10.jpg)
Column formwork Sequence
![Page 11: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/11.jpg)
Column formwork assembly zone 1
Retaining wall
![Page 12: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/12.jpg)
Column formwork assembly zone 1
![Page 13: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/13.jpg)
Column formwork assembly zone 1
![Page 14: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/14.jpg)
Zone 1 Ready for pour / first floor slab construction still in progress
![Page 15: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/15.jpg)
Zone 1 & 2 Concrete pour complete
![Page 16: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/16.jpg)
Assembly of Peri LIWA lightweight panel
Zone 1
• 4 sections of wall formwork to be
assembled
• 1 gang (2 men) per wall section
• 15 mins per m2
• 111.72 m2 approx. 1hr 45mins.
Zone 2
• 3 sections of wall formwork to be
assembled
• 1 gang (2 men) per wall section
• 15 mins per m2
• 35.28 m2 approx. 45 mins.
Zone 3
• 3 sections of wall formwork to be
assembled
• 1 gang (2 men) per wall section
• 15 mins per m2
• 35.28 m2 approx. 45 mins.
Zone 4
• sections of wall formwork to be
assembled
• 1 gang (2 men) per wall section
• 111.72 m2 approx. 1hr 45mins.
![Page 17: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/17.jpg)
LIWA lightweight panel concrete pour
Zone 1
• 4 sections of wall to be poured;
• 2 sections of 15.6 x 0.30m @ 2.45m
height
• 2 sections of 7.2 x 0.30 @ 2.45m height
• Amount of concrete required 33.5 m3
Zone 2
• 3 sections of 7.2 x 0.30m @ 2.45 height
• Amount of concrete required 31.8 m3
Zone 3
• 3 sections of 7.2 x 0.30m
@ 2.45 height
• Amount of concrete
required 31.8 m3
Zone 4
• 4 sections of wall to be
poured;
• 2 sections of 15.6 x 0.30 @
2.45m height
• 2 sections of 7.2 x 0.30 @
2.45m height
• Amount of concrete
required 33.5 m3
![Page 18: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/18.jpg)
2.45m
First floor slab
• 90 panels of Skydeck per section
• Panels @ 1.50 x 0.75
• 810 panels for each zone
• 1.125m2 per section
150 kg of steel rebar for every m3 of concrete (Peri requirements)
Skydeck slab formwork assembly
![Page 19: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/19.jpg)
Beams and slab rebar
Beams integrated into slab formwork
Beam layout for each zoneSection of slab rebar
![Page 20: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/20.jpg)
Framing and shear wall assembly
![Page 21: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/21.jpg)
Skydeck slab formwork assembly
![Page 22: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/22.jpg)
Zone 1 Skydeck slab panels & beam formwork assembled, ready for concrete pour
![Page 23: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/23.jpg)
Zone 2 slab concrete pour complete
![Page 24: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/24.jpg)
Zone’s 3 & 4 column formwork assembly and pour, Zone 3 wall assembly and pour
![Page 25: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/25.jpg)
Repositioning of plant machinery
![Page 26: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/26.jpg)
Zone 4 shear wall assembly and pour/ Zone 3 Slab concrete pour complete
![Page 27: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/27.jpg)
Zone 4 slab concrete pour complete
![Page 28: First Floor Columns and Second Floor Slab Construction Final Cut](https://reader035.vdocument.in/reader035/viewer/2022081504/55cf9dfb550346d033b024bb/html5/thumbnails/28.jpg)
Handover