Flood Diversion Authority October Report
Presented by
Program Management Consultant (PMC) Team
1
October 10, 2013
Outline
Schedule Update
– OHB Levee
– In-Town Levees
Supplemental EA Changes
September 2013 Highlights
– Technical
– Other
October Priorities 2
OHB Levee Project Plan
3
OHB Levee Schedule Oct 2013
WP-43A Land
Start: Oct 2013
End: May 2014
Begin acquisition of agricultural land
WP-43C Land
Start: Oct 2013
End: Apr 2016
Begin residential and business acquisition and relocation
4
Borrow area for levees
OHB Levee Schedule Mar 2014
WP-43B Land
Start: Mar 2014
End: Apr 2015
Begin acquisition of
remaining
agricultural land
5
Borrow area for levees
OHB Levee Schedule Summer 2014
WP-43A Land:
Complete
WP-43B Land:
Continues
WP-43C Land:
Continues
WP-43A
Construction:
Summer 2014
6
Borrow areas for levees
Oxbow Development Begins
OHB Levee Schedule Summer 2015
WP-43A
Construction:
Complete
WP-43B
Construction:
Summer 2015
WP-43D - Pump Station
Construction:
Summer 2015
WP-43B Land:
Continues
7
PS
Borrow areas for levees
OHB Levee Schedule Summer 2016
WP-43A, -43B, -43D
Construction:
Complete
WP-43C
Construction:
Summer 2016
8
PS
Borrow areas for levees
OHB Levee Schedule Fall 2016
WP-43A, WP-43B,
WP-43C, WP-43D
Construction:
Complete
9
PS
Stormwater Ponds
In-Town Levees Schedule
Land Acquisition to begin in October for known required
properties
Design is being coordinated with the New City Hall
project
10
Supplemental EA Changes
Northern alignment improvements
Western alignment improvements
VE-13 A improvements
More Flow Through Town
Gates on the Diversion Inlet
Protection for Oxbow, Hickson, and Bakke
11
New Map
12
Bridge Reaches
– Back-checking review comments
– Continuing design on CR-20 bridge
OHB Levee
– Geotechnical and Survey work on-going
– Design has begun on the southern section
Cultural
– Planning activities for Phase 1 cultural field work
In-Town levees
– Coordinating with New City Hall project
Continued to support Corps with H&H and other Work-in-Kind 13
September 2013 Highlights - Technical
JPA Amendment #2 finalized
Corps Environmental Assessment signed and released to the
public
Integral Determination Report authorizing Work-In-Kind credit
for the OHB Levee work approved by USACE
Executive Leadership Council and Joint PM Board meeting
conducted with Authority and Corps leadership
14
September 2013 Highlights – Other Activities
October 2013 Priority Areas
Authorization (WRRDA)
OHB Levee
– Geotechnical
– Cultural
– Design
– Permitting
– Land Acquisition
In-Town Levees
– Coordination with New City Hall Project
– Land Acquisition
15